SlideShare a Scribd company logo
1 of 15
BY-
KSHITIJ SHARMA
818/07
MECHANICAL ENGG.
7121113526
SUBMITTED TO:
MECHANICAL DEPT.
INTRODUCTION TO NTPC
Power Development
Although electric power generation in India on a commercial basis is almost a century old, substantial power
development efforts began only after independence. At the launch of the First Five-Year plan in 1951, power
generation was recognized as a major input for the country's economic development and was accorded high
priority. Power sector outlays have been among the highest in successive Five-Year Plans ever since. The first two
Plans focused on hydro power (as component of multi-purpose projects). Subsequent plans emphasized on rapid
installations of thermal power stations. As a result of Plan efforts, India's installed power generation capacity grew
to 16,664 MW in 1974. However, assessment of the planned growth since 1951 indicated that with the uneven
distribution of resources, power development with only States as spatial units, would result in large inter-state
imbalances. This, and the need for quicker and greater capacity addition, led the Government of India to assume a
leading role in large scale power generation as a matter of policy and, through an amendment of the Electricity
(Supply) Act, National Thermal Power Corporation Ltd. (NTPC) and National Hydroelectric Power Corporation Ltd.
(NHPC) were set up in the central sector to supplement the efforts of the States.
Consequently, total installed capacity of power utilities has increased from 1,362 MW in 1947 to 104918 MW in
March 2002. Electricity generation, which was only about 4.1 billion units in 1947, has risen to 515 billion units in
2001-02.
National Thermal Power Corporation Limited (NTPC) is the largest thermal power generating company of India. It was
incorporated in the year 1975 with the objective of planning, promoting and organizing an integrated development of
thermal power in the country. NTPC is a public sector company wholly owned by Govt. of India. Today NTPC has power
generating capacity in all the four major power regions of the country.
OPERATION
BADARPUR THERMAL POWER PLANT:
Approved Capacity: 705 MW
Installed Capacity: 705MW
Location: New Delhi
Coal Source: Jharia Coal Fields
Water Source: Agra Canal
Beneficiary States: Delhi
Unit Sizes:
3X95 MW
2X210 MW
Unit Commissioned:
Unit 95 MW - 1973-74
Unit II- 95 MW 1974-75
Unit III- 95 MW 1974-75
Unit IV - 210 MW 1978-79
Unit V - 210 MW - 1981-82
The Management of the Centrally owned Badarpur Thermal Power Station was handed over to NTPC on April 15, 1978.
Widescreen Pictures
Pictures can also be presented more dramatically in widescreen.
COAL TO ELECTRICITY
Basic Power Plant Cycle
The thermal (steam) power plant uses a dual (vapour + liquid) phase cycle. It is a closed cycle to enable the working fluid
(water) to be used again and again. The cycle used is "Rankine Cycle" modified to include super heating of steam,
regenerative feed water heating and reheating of steam.
On large turbines, it becomes economical to increase the cycle efficiency by using reheat, which is a way of partially
overcoming temperature limitations. By returning partially expanded steam, to a reheat, the average temperature at which
heat is added, is  increased and, by expanding this reheated steam to the remaining stages of the turbine, the exhaust
wetness is considerably less than it would otherwise be conversely, if  the maximum tolerable wetness is allowed, the initial
pressure of the steam can be appreciably increased.
Bleed Steam Extraction. For regenerative system, nos. of non-regulated extractions is taken from HP, IP turbine.
Regenerative heating of the boiler feed water is widely used in modern power plants; the effect being to increase the
average temperature at which heat is added to the cycle, thus improving the cycle efficiency.
BOILER MAINTENANCE DEPARTMENT
MAIN BOILER – BOILER FUNDAMENTALS
BOILERS
A boiler is an enclosed vessel that provides a means for combustion heat to be transferred into water until it becomes
heated water or steam. The hot water or steam under pressure is then usable for transferring the heat to a process.
Water is a useful and cheap medium for transferring heat to a process. When water is boiled into steam its volume
increases about 1,600 times, producing a force that is almost as explosive as gunpowder. This causes the boiler to be
extremely dangerous equipment that must be treated with utmost care. The process of heating a liquid until it reaches
its gaseous state is called evaporation. Heat is transferred from one body to another by means of (1) radiation, which is
the transfer of heat from a hot body to a cold body through a conveying medium without physical contact, (2)
convection, the transfer of heat by a conveying medium, such as air or water and (3) conduction, transfer of heat by
actual physical contact, molecule to molecule. The heating surface is any part of the boiler metal that has hot gases of
combustion on one side and water on the other. Any part of the boiler metal that actually contributes to making steam is
heating surface. The amount of heating surface a boiler is expressed in square meters. The larger the heating surface
a boiler has, the more efficient it becomes. The quantity of the steam produced is indicated in tons of water evaporated
to steam per hour.
Water tube or "water in tube" boilers in which the conditions are reversed with the water passing through the tubes and
the hot gasses passing outside the tubes (see figure 1.3). These boilers can be of single- or multiple-drum type. These boilers
can be built to any steam capacities and pressures, and have higher efficiencies than fire tube boilers.
Boiler structural:
The boiler structural is divided into two parts.
•Supporting Structure.
•Galleries and stair ways.
Supporting Structures:
Boilers supporting structure consists of a systematic arrangement of columns stiffened with horizontal beams and vertical
diagonal bracings and comprise of low carbon steel material. It is composed of 18 main columns and 12 auxiliary
columns. The main columns support the main boiler components viz. drum, water wall membranes, panels,
superheaters, reheaters, economisers, air preheater, burners and galleries at various levels. The auxiliary columns,
supports the boiler platforms and other ducts coming in that region. The total weight of supporting structures is about 970
M.T.
Galleries and stairways:
Galleries and stairways around the combustion and heat recovery areas are provided for proper approach to the boiler.
Stairways on both the side of Boiler are provided. All the floors are covered with floor gratings of required depth for
walkway and are tig welded to the structure. The total weight of Galleries and stairway are 900 M.T.
Boiler Drum:
The function of steam drum is to separate the water from the steam generated in the furnace walls and to reduce the
dissolved solid contents of the steam to below the prescribed limit of 1 ppm. The drum is located on the upper front of
boiler.
Economiser:
The purpose of economiser is to preheat the boiler feed water before it is introduced into the steam drum by recovering
heat from the flue gases leaving the boiler. The economiser is located in the boiler rear gas pass below the rear horizontal
superheater.  The economiser is continuous unfinned loop type and water flows in upward direction and gas in the
downward direction.
Super Heater:
There are three stages of superheater besides the side walls and extended sidewalls. The first stage consists of horizontal
superheater of convection mixed flow type with upper and lower banks located above economiser assembly in the rear
pass. The upper bank terminates into hanger tubes, which are connected to outlet header of the first stage superheter. The
second stage superheater consists of pendant platen which is of radiant parallel flow type. The third stage supherheater
pendant spaced is of convection parallel flow type.
The outlet temperature and pressure of the steam coming out from the superheater is 540°C and 157 Kg/Cm2
respectively
for H.P. units.
Reheater:
The function of reheater is to reheat the steam coming out from high pressure turbine to a temperature of 540°C.
The reheater is composed of two sections.
•The front pendant section.
•Rear pendant section.
The rear pendant section is located above the furnace arc and the rear water wall and front  pendant  section  is
 located  between  the  rear  water  hanger  tubes  and  the superheater platen section.
Burners:
There are total twenty four pulverised coal burners for corner fired C.E. type boilers and twelve oil burners provided
each in between two pulverised fuel burner.
The pulverised coal burners are arranged in such a way that six mills supply the coal the burners at 4 corners, of the
furnace. All the nozzles of the burners are interlinked and can be tilted as a single unit from +30° to -30°C.
The oil burners are fed with heavy fuel oil till boiler load reaches to about 25%.
Plant Auxiliary Maintenance Department
Water Treatment Plant
Water treatment process which is generally made up of two sections:
Pretreatment section
Demineralisation section
Internal Treatment
This final D.M effluent is then either led to hot well of the condenser directly as make up to boilers, or being
stored in D.M. Water storage tanks first and then pumped for make up purpose to boiler feed.
As the D.M. Water has a good affinity to absorb carbon dioxide and oxygen, and both are extremely harmful to
metal surfaces for their destruction like corrosion, these have to be removed before it is fed to boiler. This is
being done in deaerator. Still the residual oxygen which is remaining in the water is neutralized by a suitable
doze of hydrazine, at the point after deaerator. To have further minimum corrosion, the pH of feed water is to be
maintained at around 9.0 for which purpose ammonia in suitable doze is added to this make up water at a point
along with hydrazine as stated above.
TURBINE COMPONENTS
The Turbine
The 210 MW turbine installed in our power stations is predominantly of condensing-tandom -compound, three
cylinder,- horizontal, disc and diaphragm, reheat type with nozzle governing and regenerative system of feed water
heating and is coupled directly with A. C. Generator
The various main components of the turbine are described in the following sections.
Turbine Casings
High Pressure Casing: The high pressure casing is made of creep resisting Chromium Molybdenum -vanadium (Cr-
Mo-V) steel casting. The top and bottom halves of the casing are secured together at the flange joint by heat tightened
studs to ensure an effective seal against steam leakage. Four steam chests, two on top and two on sides are welded to
the nozzle boxes, which in turn are welded to the casing at the middle bearing end. The steam chests accommodate four
control valves to regulate the flow of steam to the turbine according to the load requirement. Nozzle boxes and steam
chests are also made of creep resisting Cr-Mo-V steel castings.
Intermediate Pressure Casing: The intermediate pressure casing of the turbine is made of two parts. The front part is
made of creep resisting Chromium-Molybdenum-Vanadium steel castings and the exhaust part is of steel fabricated
structure. The two parts are connected by a vertical joint. Each part consists of two helves having a horizontal joint. The
horizontal joint is secured with the help of studs and nuts. These nuts and studs are made of creep resisting Cr-Mo-V steel
forgings. The control valves of I.P Turbine are mounted on the casing itself. In the intermediate pressure turbine the nozzle
boxes are cast integral with the casing, the first stage nozzle segment o IPT is a welded construction like other diaphragms
and in mounted directly in the casing. Next two diaphragms are also housed incasing while other 8 diaphragms are housed
in three liners which in turn are mounted in casing. From the intermediate pressure turbine, steam is carried through cross-
over pipes to the double flow low pressure cylinder. Each cross over pipe is provided with a compensator for taking care of
thermal expansion and to ensure that no heavy thrust or turning moments are thrown on to the flanged connections at the
intermediate pressure cylinder exhaust and the low pressure cylinder inlet.
Low Pressure Casing: The L.P. casing consists of three parts i.e. one middle part and two exhaust parts. The three
parts are fabricated from weldable mild steel the exhaust casings are bolted to the middle casings by a vertical flange. The
casings are divided in the horizontal plane through the turbine centre line. The lower half of the L.P. casing has an integral
bearing pedestal.
MAINTENANCE AND PLANNING DIVISION
Not withstanding the ruggedness that is in the machine, a little care at periodic intervals will ensure a trouble
free service and prevent breakdowns, also avoid loss of maintenance and shut down. It is always worthwhile a
log book for each motor, where in various reading are entered daily and details of any major and minor overhaul
listed maintenance schedules could be broadly divided into seven categories:
•Routine maintenance.
•Periodic maintenance.
•Capital maintenance.
•Breakdown maintenance.
•Preventive maintenance.
•Opportunity maintenance.
•Predictive maintenance.
Training Work
 On site demonstration of removal of waste log of wood from the Water Treatment Plant under the
supervision of Head of WTP department, Mr. Pratap Singh.
 Demonstration of the working of steam nozzle illustrating the flow of stream under the supervision
of Head of Boiler Maintenance Department, Mr. Gyanendra Singh
 Annual Maintenance of NTPC plant conducted by the Maintenance and Planning Division Dept.
under the supervision of Head MPD, Mr. Mahindra Singh demonstrating the maintenance of
Condenser walls and Turbine Blades maintained under the Turbine Maintenance Department.

More Related Content

What's hot

SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT Amit Gupta
 
Steam boilers
Steam boilersSteam boilers
Steam boilerssing367
 
Thermal power plants presentation (bathinda)
Thermal power plants presentation (bathinda)Thermal power plants presentation (bathinda)
Thermal power plants presentation (bathinda)Lovesh Singla
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power PlantsDebajyoti Bose
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)sometech
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02arvind singh rathore
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)iimt college meerut
 
thermal power plant
thermal power plant thermal power plant
thermal power plant GOD BRAIN
 
Thermal power station
Thermal power stationThermal power station
Thermal power stationvishal gupta
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeAnshuman Tyagi
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant00veerchauhan
 

What's hot (20)

Steam power plant
Steam power plantSteam power plant
Steam power plant
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Ppe unit 1
Ppe unit 1Ppe unit 1
Ppe unit 1
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
Thermal power plants presentation (bathinda)
Thermal power plants presentation (bathinda)Thermal power plants presentation (bathinda)
Thermal power plants presentation (bathinda)
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power Plants
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)
 
thermal power plant
thermal power plant thermal power plant
thermal power plant
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 
Thermal power station
Thermal power stationThermal power station
Thermal power station
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Thermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to KnowledgeThermal Power Plant Basic to Knowledge
Thermal Power Plant Basic to Knowledge
 
Steam Power Plant and Components
Steam Power Plant and ComponentsSteam Power Plant and Components
Steam Power Plant and Components
 
Bandel training
Bandel trainingBandel training
Bandel training
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
Steam Power Plant
Steam Power PlantSteam Power Plant
Steam Power Plant
 

Viewers also liked

Viewers also liked (8)

Loving heart 20140103
Loving heart 20140103Loving heart 20140103
Loving heart 20140103
 
Presentation1
Presentation1Presentation1
Presentation1
 
Saudi Arabia Companies
Saudi Arabia CompaniesSaudi Arabia Companies
Saudi Arabia Companies
 
Pai 1
Pai 1Pai 1
Pai 1
 
Fgfdsxh
FgfdsxhFgfdsxh
Fgfdsxh
 
Assignment2b2014
Assignment2b2014Assignment2b2014
Assignment2b2014
 
Auger lucien ayudarse a si mismo
Auger lucien   ayudarse a si mismoAuger lucien   ayudarse a si mismo
Auger lucien ayudarse a si mismo
 
Чтение
ЧтениеЧтение
Чтение
 

Similar to NTPC's Badarpur Thermal Power Plant and Operations

National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporationAbhishek Awasthi
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRabi Kumar
 
ptherml power palnt basica nd advancded.pptx
ptherml power palnt basica nd advancded.pptxptherml power palnt basica nd advancded.pptx
ptherml power palnt basica nd advancded.pptxramsao2018com
 
A technical overview of thermal power plant
A technical overview of thermal power plantA technical overview of thermal power plant
A technical overview of thermal power plantMirdul Amin Sarkar
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDPrasant Kumar
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantVinay Garg
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsIbrahim AboKhalil
 
Thermal Power Station
Thermal Power StationThermal Power Station
Thermal Power StationDinesh Sharma
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantViren Patel
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportLovesh Singla
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarRishikesh .
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyShobhan Biswas
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaEesha Gupta
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTPrasant Kumar
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Srikanta Sinha
 

Similar to NTPC's Badarpur Thermal Power Plant and Operations (20)

National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporation
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
ptherml power palnt basica nd advancded.pptx
ptherml power palnt basica nd advancded.pptxptherml power palnt basica nd advancded.pptx
ptherml power palnt basica nd advancded.pptx
 
report final
report finalreport final
report final
 
A technical overview of thermal power plant
A technical overview of thermal power plantA technical overview of thermal power plant
A technical overview of thermal power plant
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Boiler turbe failores
Boiler turbe failoresBoiler turbe failores
Boiler turbe failores
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
 
Thermal Power Station
Thermal Power StationThermal Power Station
Thermal Power Station
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester report
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical only
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, Haryana
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 

NTPC's Badarpur Thermal Power Plant and Operations

  • 2. INTRODUCTION TO NTPC Power Development Although electric power generation in India on a commercial basis is almost a century old, substantial power development efforts began only after independence. At the launch of the First Five-Year plan in 1951, power generation was recognized as a major input for the country's economic development and was accorded high priority. Power sector outlays have been among the highest in successive Five-Year Plans ever since. The first two Plans focused on hydro power (as component of multi-purpose projects). Subsequent plans emphasized on rapid installations of thermal power stations. As a result of Plan efforts, India's installed power generation capacity grew to 16,664 MW in 1974. However, assessment of the planned growth since 1951 indicated that with the uneven distribution of resources, power development with only States as spatial units, would result in large inter-state imbalances. This, and the need for quicker and greater capacity addition, led the Government of India to assume a leading role in large scale power generation as a matter of policy and, through an amendment of the Electricity (Supply) Act, National Thermal Power Corporation Ltd. (NTPC) and National Hydroelectric Power Corporation Ltd. (NHPC) were set up in the central sector to supplement the efforts of the States. Consequently, total installed capacity of power utilities has increased from 1,362 MW in 1947 to 104918 MW in March 2002. Electricity generation, which was only about 4.1 billion units in 1947, has risen to 515 billion units in 2001-02.
  • 3. National Thermal Power Corporation Limited (NTPC) is the largest thermal power generating company of India. It was incorporated in the year 1975 with the objective of planning, promoting and organizing an integrated development of thermal power in the country. NTPC is a public sector company wholly owned by Govt. of India. Today NTPC has power generating capacity in all the four major power regions of the country.
  • 4. OPERATION BADARPUR THERMAL POWER PLANT: Approved Capacity: 705 MW Installed Capacity: 705MW Location: New Delhi Coal Source: Jharia Coal Fields Water Source: Agra Canal Beneficiary States: Delhi Unit Sizes: 3X95 MW 2X210 MW Unit Commissioned: Unit 95 MW - 1973-74 Unit II- 95 MW 1974-75 Unit III- 95 MW 1974-75 Unit IV - 210 MW 1978-79 Unit V - 210 MW - 1981-82 The Management of the Centrally owned Badarpur Thermal Power Station was handed over to NTPC on April 15, 1978.
  • 5. Widescreen Pictures Pictures can also be presented more dramatically in widescreen. COAL TO ELECTRICITY Basic Power Plant Cycle The thermal (steam) power plant uses a dual (vapour + liquid) phase cycle. It is a closed cycle to enable the working fluid (water) to be used again and again. The cycle used is "Rankine Cycle" modified to include super heating of steam, regenerative feed water heating and reheating of steam. On large turbines, it becomes economical to increase the cycle efficiency by using reheat, which is a way of partially overcoming temperature limitations. By returning partially expanded steam, to a reheat, the average temperature at which heat is added, is  increased and, by expanding this reheated steam to the remaining stages of the turbine, the exhaust wetness is considerably less than it would otherwise be conversely, if  the maximum tolerable wetness is allowed, the initial pressure of the steam can be appreciably increased. Bleed Steam Extraction. For regenerative system, nos. of non-regulated extractions is taken from HP, IP turbine. Regenerative heating of the boiler feed water is widely used in modern power plants; the effect being to increase the average temperature at which heat is added to the cycle, thus improving the cycle efficiency.
  • 6. BOILER MAINTENANCE DEPARTMENT MAIN BOILER – BOILER FUNDAMENTALS BOILERS A boiler is an enclosed vessel that provides a means for combustion heat to be transferred into water until it becomes heated water or steam. The hot water or steam under pressure is then usable for transferring the heat to a process. Water is a useful and cheap medium for transferring heat to a process. When water is boiled into steam its volume increases about 1,600 times, producing a force that is almost as explosive as gunpowder. This causes the boiler to be extremely dangerous equipment that must be treated with utmost care. The process of heating a liquid until it reaches its gaseous state is called evaporation. Heat is transferred from one body to another by means of (1) radiation, which is the transfer of heat from a hot body to a cold body through a conveying medium without physical contact, (2) convection, the transfer of heat by a conveying medium, such as air or water and (3) conduction, transfer of heat by actual physical contact, molecule to molecule. The heating surface is any part of the boiler metal that has hot gases of combustion on one side and water on the other. Any part of the boiler metal that actually contributes to making steam is heating surface. The amount of heating surface a boiler is expressed in square meters. The larger the heating surface a boiler has, the more efficient it becomes. The quantity of the steam produced is indicated in tons of water evaporated to steam per hour.
  • 7. Water tube or "water in tube" boilers in which the conditions are reversed with the water passing through the tubes and the hot gasses passing outside the tubes (see figure 1.3). These boilers can be of single- or multiple-drum type. These boilers can be built to any steam capacities and pressures, and have higher efficiencies than fire tube boilers.
  • 8. Boiler structural: The boiler structural is divided into two parts. •Supporting Structure. •Galleries and stair ways. Supporting Structures: Boilers supporting structure consists of a systematic arrangement of columns stiffened with horizontal beams and vertical diagonal bracings and comprise of low carbon steel material. It is composed of 18 main columns and 12 auxiliary columns. The main columns support the main boiler components viz. drum, water wall membranes, panels, superheaters, reheaters, economisers, air preheater, burners and galleries at various levels. The auxiliary columns, supports the boiler platforms and other ducts coming in that region. The total weight of supporting structures is about 970 M.T. Galleries and stairways: Galleries and stairways around the combustion and heat recovery areas are provided for proper approach to the boiler. Stairways on both the side of Boiler are provided. All the floors are covered with floor gratings of required depth for walkway and are tig welded to the structure. The total weight of Galleries and stairway are 900 M.T.
  • 9. Boiler Drum: The function of steam drum is to separate the water from the steam generated in the furnace walls and to reduce the dissolved solid contents of the steam to below the prescribed limit of 1 ppm. The drum is located on the upper front of boiler. Economiser: The purpose of economiser is to preheat the boiler feed water before it is introduced into the steam drum by recovering heat from the flue gases leaving the boiler. The economiser is located in the boiler rear gas pass below the rear horizontal superheater.  The economiser is continuous unfinned loop type and water flows in upward direction and gas in the downward direction. Super Heater: There are three stages of superheater besides the side walls and extended sidewalls. The first stage consists of horizontal superheater of convection mixed flow type with upper and lower banks located above economiser assembly in the rear pass. The upper bank terminates into hanger tubes, which are connected to outlet header of the first stage superheter. The second stage superheater consists of pendant platen which is of radiant parallel flow type. The third stage supherheater pendant spaced is of convection parallel flow type. The outlet temperature and pressure of the steam coming out from the superheater is 540°C and 157 Kg/Cm2 respectively for H.P. units.
  • 10. Reheater: The function of reheater is to reheat the steam coming out from high pressure turbine to a temperature of 540°C. The reheater is composed of two sections. •The front pendant section. •Rear pendant section. The rear pendant section is located above the furnace arc and the rear water wall and front  pendant  section  is  located  between  the  rear  water  hanger  tubes  and  the superheater platen section. Burners: There are total twenty four pulverised coal burners for corner fired C.E. type boilers and twelve oil burners provided each in between two pulverised fuel burner. The pulverised coal burners are arranged in such a way that six mills supply the coal the burners at 4 corners, of the furnace. All the nozzles of the burners are interlinked and can be tilted as a single unit from +30° to -30°C. The oil burners are fed with heavy fuel oil till boiler load reaches to about 25%.
  • 11. Plant Auxiliary Maintenance Department Water Treatment Plant Water treatment process which is generally made up of two sections: Pretreatment section Demineralisation section Internal Treatment This final D.M effluent is then either led to hot well of the condenser directly as make up to boilers, or being stored in D.M. Water storage tanks first and then pumped for make up purpose to boiler feed. As the D.M. Water has a good affinity to absorb carbon dioxide and oxygen, and both are extremely harmful to metal surfaces for their destruction like corrosion, these have to be removed before it is fed to boiler. This is being done in deaerator. Still the residual oxygen which is remaining in the water is neutralized by a suitable doze of hydrazine, at the point after deaerator. To have further minimum corrosion, the pH of feed water is to be maintained at around 9.0 for which purpose ammonia in suitable doze is added to this make up water at a point along with hydrazine as stated above.
  • 12. TURBINE COMPONENTS The Turbine The 210 MW turbine installed in our power stations is predominantly of condensing-tandom -compound, three cylinder,- horizontal, disc and diaphragm, reheat type with nozzle governing and regenerative system of feed water heating and is coupled directly with A. C. Generator The various main components of the turbine are described in the following sections. Turbine Casings High Pressure Casing: The high pressure casing is made of creep resisting Chromium Molybdenum -vanadium (Cr- Mo-V) steel casting. The top and bottom halves of the casing are secured together at the flange joint by heat tightened studs to ensure an effective seal against steam leakage. Four steam chests, two on top and two on sides are welded to the nozzle boxes, which in turn are welded to the casing at the middle bearing end. The steam chests accommodate four control valves to regulate the flow of steam to the turbine according to the load requirement. Nozzle boxes and steam chests are also made of creep resisting Cr-Mo-V steel castings.
  • 13. Intermediate Pressure Casing: The intermediate pressure casing of the turbine is made of two parts. The front part is made of creep resisting Chromium-Molybdenum-Vanadium steel castings and the exhaust part is of steel fabricated structure. The two parts are connected by a vertical joint. Each part consists of two helves having a horizontal joint. The horizontal joint is secured with the help of studs and nuts. These nuts and studs are made of creep resisting Cr-Mo-V steel forgings. The control valves of I.P Turbine are mounted on the casing itself. In the intermediate pressure turbine the nozzle boxes are cast integral with the casing, the first stage nozzle segment o IPT is a welded construction like other diaphragms and in mounted directly in the casing. Next two diaphragms are also housed incasing while other 8 diaphragms are housed in three liners which in turn are mounted in casing. From the intermediate pressure turbine, steam is carried through cross- over pipes to the double flow low pressure cylinder. Each cross over pipe is provided with a compensator for taking care of thermal expansion and to ensure that no heavy thrust or turning moments are thrown on to the flanged connections at the intermediate pressure cylinder exhaust and the low pressure cylinder inlet. Low Pressure Casing: The L.P. casing consists of three parts i.e. one middle part and two exhaust parts. The three parts are fabricated from weldable mild steel the exhaust casings are bolted to the middle casings by a vertical flange. The casings are divided in the horizontal plane through the turbine centre line. The lower half of the L.P. casing has an integral bearing pedestal.
  • 14. MAINTENANCE AND PLANNING DIVISION Not withstanding the ruggedness that is in the machine, a little care at periodic intervals will ensure a trouble free service and prevent breakdowns, also avoid loss of maintenance and shut down. It is always worthwhile a log book for each motor, where in various reading are entered daily and details of any major and minor overhaul listed maintenance schedules could be broadly divided into seven categories: •Routine maintenance. •Periodic maintenance. •Capital maintenance. •Breakdown maintenance. •Preventive maintenance. •Opportunity maintenance. •Predictive maintenance.
  • 15. Training Work  On site demonstration of removal of waste log of wood from the Water Treatment Plant under the supervision of Head of WTP department, Mr. Pratap Singh.  Demonstration of the working of steam nozzle illustrating the flow of stream under the supervision of Head of Boiler Maintenance Department, Mr. Gyanendra Singh  Annual Maintenance of NTPC plant conducted by the Maintenance and Planning Division Dept. under the supervision of Head MPD, Mr. Mahindra Singh demonstrating the maintenance of Condenser walls and Turbine Blades maintained under the Turbine Maintenance Department.