2. The Power Sector in India has undergone a plethora of reforms in
the last two decades.
Introduction of competition has been one of the main aims of reform
in the electricity sector in India.
One of the most important steps taken towards achieving this was
the introduction of open access in the Electricity Act, 2003, where
large consumers have access to the Transmission and Distribution
(T&D) network to obtain electricity from suppliers other than the
local electricity distribution company (DISCOM).
INTRODUCTION
OBJECTIVE
The objective of open access was to provide opportunity to energy
intensive industry and commercial establishments to source
electricity directly from the market and manage costs to remain
competitive.
Open Access was to also improve the economic health of the
Distribution Licensees by reducing power procurement at higher
marginal cost so that the non-open access retail consumers of the
Distribution Licensees would not get unduly burdened.
3. Electricity Act 2003 (sub-section 2 of section 42) lay down provisions for
a power market and competition wherein electricity consumers now
have the right to procure power from the supplier of their choice other
than their distribution company.
For example, under open-access a consumer in Telangana has right to
select the source of supply form any generator. This generator may be
generating power in Telangana or any other state in India.
Open Access, as per Electricity Act 2003
“Non-discriminatory provision for the use of transmission lines or
distribution system or associated facilities with such lines or system by
any licensee or consumer or a person engaged in generation in
accordance with the regulations specified by the Appropriate
Commission”.
Open Access allows large and heavy users of powers i.e. those with 1
megawatt (MW) and above connected load to buy cheaper power from
the open market.
The idea is that the customers now able to choose from a number of
competing power companies like GENCOs, CPSU, IPPs, Private.
Licensees, Excess Captive from captive power plants instead of being
forced to buy electricity from their existing electric utility monopoly.
OA WITH EA 2003
4. 1. Competitive Pricing
Open Access was introduced in the Electricity Act to bring in
competition into the sector, thereby benefitting the end consumer.
Over the years, it has acted as a catalyst in bringing reforms into the
sector by benefitting the players across the spectrum of value-chain
from generators to suppliers to electricity traders to the end
consumers.
Open Access will ease the power shortage since a number of power
producers like Solar energy companies can now transmit power from
their solar parks to different load centers.
Once the consumers are given the choice to purchase power from
the open market, it will automatically lead to competitive pricing of
electricity making electricity cost go down.
2. Regular electricity supply
It helps the industrial & commercial consumers by ensuring regular
electricity supply at competitive rates.
It helps large consumers particularly the sick textile, cement and
steel industrial units by ensuring regular supply of electricity at
competitive rates and boost business of power bourses.
PROS AND CONS OF OPEN ACCESS
5. 3. Help Consumers to meet RPOs
It also enhances the business of power markets as the open access
helps consumers meet their Renewable Purchase Obligations (RPOs) as
well.
4. Exposure to Grid Risks
In open access, eligible consumer can avail the benefits of cheaper
green solar power by either purchasing through the rooftop solar
installation in its premises or buying from an offsite solar farm.
While open access does away with limitations of rooftop solar such as
scalability and high capital expenditure, it is often exposed to
unpredictable grid risks.
5. Appropriate utilization of existing infrastructure (T&D)
Existing Transmission and Distribution Infrastructure can be used to
avail the open access.
In open access, this will enable number of players utilizing these
infrastructure and transmit power from generation to the load center.
This will mean utilization of existing infrastructure and easing of power
shortage.
Trading, now a licensed activity and regulated will also help in
innovative pricing which will lead to competition resulting in lowering of
tariffs.
PROS AND CONS OF OPEN ACCESS
6. Open Access, rights governed in India by Electricity Act 2003, can
be classified as under on the basis of location of the purchasing and
selling entities:
Types of Open Access Users
1. Intra State (With in the state)
2. Inter State (State to State)
Intra State Users
1. Short Term (STOA) up to 1 year
2. Medium Term (MTOA) - AP & TS Not Contemplated
3. Long Term (LTOA) 2 years and above
Inter State Users
1. Short Term (STOA) – Maximum one month.
2. Medium Term (MTOA) – 3 months to 5 Years (earlier 3 Years)
3. Long Term (LTOA) – 12 Years to 25 Years
Power Markets- Collective Transactions
1. Indian Energy Exchange Limited – IEX
2. Power Exchange India Limited – PXI
Minimum Open access allowed for 1MW
OPEN ACCESS CLASIFICATION
7. When the Purchasing and selling entities belong to same state then
it is called as an Intra-state transaction. In this case, the open
access charges comprising Transmission Losses and Charges
Wheeling losses and Charges (if applicable) and cross-subsidy of
that particular state are applicable.
In Intra-State Open Access State Electricity Regulatory Commission
(SERC) regulations are followed.
Wherein purchase rights can be categorized.
Duration of which depends on the respective state open access
regulations.
Intra State Purchases for DISCOMs
1. Short Term (STPP) up to 1 year
2. Medium Term (MTOA) AP & TS Not Contemplated
3. Long Term (LTTSA) with GENCO 2 years and above
4. Long Term (LTOA) with Other Generators 2 years and above
Intra State OA Users
1. Short Term (STOA) up to 1 year
2. Medium Term (MTOA) - AP & TS Not Contemplated
3. Long Term (LTOA) 2 years and above
INTRA STATE OPEN ACCESS
8. When the Purchasing and selling entities belong to different states
then it is called as an Inter-state transaction.
In this case, apart from the open access charges applicable in intra-
state transactions, Point-of-Connection (POC) charges and losses of
the regional grids where the buyer and seller are located are also
applicable.
In Inter State Open Access Central Electricity Regulatory
Commission (CERC) regulations are to be followed
Inter State Open Access
1. Short Term Open Access (STBC): Open Access allowed for the
period of less than one month.
Bilateral: Power Purchase Agreement (PPA) is a contract between
the seller and the consumer. POSOCO is the Coordinator.
Collective: Traded through Power Exchanges by Exchange
Members/Traders.
2. Medium Term Open Access (MTOA): Open Access allowed for a
period of 3 months to 5 years. (earlier 3 Years)
3. Long Term Open Access (LTOA): Open Access allowed for a
period of 12 years to 25 years.
INTER STATE OPEN ACCESS
9. Renewable Energy based transactions under intra-state open-
access is more convenient than inter-state open-access.
in order to promote Renewable Energy, many state provide
various concessional provisions like concessional Wheeling
and Transmission charges, Banking facility benefits,
Electricity Tax / Duty Exemptions, Waiver or Discount in
Cross-Subsidy-Charges etc.
These concessional provisions reduce the cost of transaction
significantly and allow RE generators to offer better
commercial terms to consumers.
INTRA VS INTER OPEN ACCESS
10. OPEN ACCESS CHARGES
Electricity consumers can make use of the existing Transmission and
Distribution infrastructure after paying appropriate charges determined by
their respective State Electricity Regulatory Commissions (SERCs).
A supportive regulatory regime from the state electricity authorities
combined with better grid stability can make long-term open access projects
viable.
These changes will facilitate more projects from the renewable energy
companies who are taking huge upfront risks at present and will definitely
upgrade the state of power trading in the country.
These charges against the usage of Transmission and Distribution
infrastructure can vary from state to state and are lesser in states with
stable grid and favorable regulatory regime.
In case of solar power, the state-wise open access charges can vary from as
low as Rs. 0.2/KWh to Rs.1.5/KWh.
There are several charges to be paid by Open Access Consumers to
Distribution Licensee, Transmission Licensees and other related entities,
other than the power purchase cost paid to the generator or supplying
entity.
Apart from below charges the open access consumers has also to fulfill the
renewable purchase obligation (RPO), in which they have to purchase a part
of their total consumption through electricity generated from renewable
energy.
11. OPEN ACCESS CHARGES
Connectivity Charges (at the time of Application)
Point of Connection (PoC) Charges (CTU)
Transmission Charges (STU)
Transmission Losses
Wheeling Charges (DISCOM)
Wheeling Losses
Cross Subsidy Surcharge (DISCOM)
RLDC Charges (POSOCO)
SLDC Charges.
In case of AP & TS SLDC Charges Bifurcated as
SLDC Operating Charges
SLDC Annual Fee.
12. OPEN ACCESS
The Buyer and Seller of Electricity can opt for
either Collective or Bilateral Transactions.
Besides minor changes in the meter installed, Open
Access transactions are essentially managed through
energy accounting at the state level.
EBC established under Control of SLDC for Energy
Accounting.
Thus, a Consumer buying Power from Open Access
will see the transaction accounted for in its monthly
bill.
13. COLLECTIVE TRANSACTIONS
In case of Collective Transactions the Electricity is
traded through Power Exchanges by Exchange
Members/Traders for a very small margin fixed by
commission.
Power Exchange transactions are transactions carried
out over an electronic platform.
Currently India has two operating Power Exchanges
(PXs)
1. Indian Energy Exchange (IEX) and
2. Power Exchange India (PXI).
At Power Exchanges Consumers can buy/sell electricity
on day-ahead/week-ahead basis or for particular time
period in a day.
Buyer/Seller will be bidding for electricity cost for
particular time period and for each time period price at
which electricity is determined by market.
14. BILATERAL TRANSACTIONS
Power Purchase Agreement (PPA) is a contract
between the Seller and the Consumer for buying
power at mutually agreed tariff for a predetermined
number of years.
The PPA defines all of the commercial terms for the
sale of electricity between the two parties, including
when the project will begin commercial operation,
schedule for delivery of electricity, penalties for under
delivery, payment terms, and termination clauses.
A significant quantum of power is still traded through
bilateral transactions.
Many of the leading solar players under the OPEX
model in India are resorting to bilateral agreements for
tariff determination with commercial and industrial
clients.
15. BILATERAL VS COLLECTIVE
Adopting a combination of Bilateral transaction and
Collective transaction may result in cost savings of
sourced energy and long term energy security because
bilateral mode of transaction brings volumetric and
price certainty for a relatively longer duration while
sourcing power from Power Exchanges provides
advantages such as better price discovery, risk
mitigation from counter-party default.
17. Info
Injection / Entry
Point Voltage
Consumption /
Exit Point Voltage
Transmission
Charges & SLDC
Charges
Wheeling charges
at entry/Exit
Case-1
DISCOM-A or B
EHT Voltage
DISCOM-A or B
EHT Voltage
Applicable NA
Case-2
DISCOM-A
EHT Voltage
DISCOM-A
33KV or 11KV Applicable
DISCOM-A
33KV or 11KV
Entry & Exit Vice-Versa
Case-3
DISCOM-A
EHT Voltage
DISCOM-B
33KV or 11KV
Applicable
DISCOM-B
33KV or 11KV
Case-4
DISCOM-A
33KV or 11KV
DISCOM-B
EHT Voltage
Applicable
DISCOM-A
33KV or 11KV
Case-5
DISCOM-A
33KV Voltage
DISCOM-B
33KV Voltage
Applicable
DISCOM-B
33KV
Case-6
DISCOM-A
11KV Voltage
DISCOM-B
11KV Voltage
Applicable
DISCOM-B
11KV
Case-7
DISCOM-A
33KV Voltage
DISCOM-B
11KV Voltage
Applicable
DISCOM-B
11KV
Case-8
DISCOM-A
11KV Voltage
DISCOM-B
33KV Voltage
Applicable
DISCOM-A
11KV
Case-9
DISCOM-A
33KV or 11KV
DISCOM-A
33KV or 11KV
Only SLDC Charge
(With in DISCOM)
DISCOM-A
33KV or 11KV
(Lower Voltage )
INTRA STATE OA CHARGES (LTOA & STOA)
18. Info
Entry or exit
Point in State
Voltage
Inter State
Transmission
Charges
Transmission
Charges & SLDC
Charges
Wheeling
charges at
entry/Exit
Case-1
Entry/Injection
at
EHT Voltage
The Inter State
Open Access User
has to Pay the
following Charges
to PGCIL.
1.PoC Injection
Charges of AP
i.e. Rs. Per MW
Per Month in
case of Power
Injection at AP.
2. PoC With drawl
Charges of AP
i.e. Rs. Per MW
Per Month in
case of Power
Withdrawn in
AP.
3. Grid Support
Charges to
POSOCO
Transmission
Charges to
APTRANSCO
i.e Rs. Per KW
per Month as
approved by
APERC from
time to time.
SLDC Charges
to APTRANSCO
i.e. Annual Fee
Rs. Per MW per
Year &
Operating
Charges Rs. Per
MW Per Month
NA
Case-2
Exit/
Withdrawn at
EHT Voltage
NA
Case-3
Entry/Injection
at
33KV or 11KV
Voltage
Particular
DISCOM
33KV or 11KV
wheeling
Charges for exit
or entry
Case-4
Exit/
Withdrawn at
33KV or 11KV
Voltage
INTER STATE OA CHARGES (LTOA & MTOA)
19. Info
Entry or exit
Point in State
Voltage
Inter State
Transmission
Charges
Transmission
Charges &
SLDC Charges
Wheeling
charges at
entry/Exit
Case-1
Entry/Injection
at
EHT Voltage
The Inter State
Open Access User
has to Pay the
following Charges
to PGCIL.
1.PoC Injection
Charges of AP
i.e. Paisa per
Unit in case of
Power Injection
at AP.
2. PoC With drawl
Charges of AP
i.e. Paisa per
Unit in case of
Power With
drawn in AP.
3. Grid Support
Charges to
POSOCO
Transmission
Charges of AP
i.e Rs. Per
MWH.
SLDC Charges
Rs 1000/- per
day per
Transactions of
OA user.
NA
Case-2
Exit/
Withdrawn
at EHT Voltage
NA
Case-3
Entry/Injection
at
33KV or 11KV
Voltage
Particular
DISCOM
33KV or 11KV
wheeling
Charges for exit
or entry i.e.
Rs. Per MWH.
Case-4
Exit/
Withdrawn at
33KV or 11KV
Voltage
INTER STATE OA CHARGES (STBC)
22. Transmission of Power From Generator to Consumer
using Utility Network.
Transmission charges will be collected if Open access
user utilized the Transmission network.
Wheeling charges will be collected if Open access
user utilized the Distribution network.
Within DISCOM, Generator & Consumer both at
33KV or 11KV, only wheeling charges applicable &
Transmission Charges not applicable.
Grid Supporting (SLDC) Charges will be collected for
all open Access Users.
Regional Network charges will be collected if Open
access user utilized the interstate network.
As per APERC Guidelines Nodal Organization is
State Transmission Utility (STU-APTRANSCO)
OPEN ACCESS
23. TRANSMISSION CHARGES (TRC)
Transmission charges as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
65.30 76.66 91.36 95.37 94.44
Transmission charges will be collected if Open access
user utilized the Transmission network.
Minimum Capacity Allowed for 1MW for Open Access.
The same is exempted for Renewable Energy
Generators.
Transmission Charges are Rs. KW/Month.
In case of OA Started & end in between a Month
Transmission Charges Applicable for OA Period days
only.
24. SLDC OPERATION CHARGES (SOC)
SLDC Operating charges as per APERC Rs. /MW/Month
2146.34 2058.18 2086.32 2150.21 2235.65
2378.11 2209.34 2247.62 2300.31 2342.73
Grid Supporting (SLDC) Charges will be collected for all open
Access Users.
Minimum Capacity Allowed for 1MW for Open Access.
Rounding to Next Digit MW in case of Partial MWs.
SLDC Operating Charges are Rs. MW/Month.
In case of OA Used per Hour or per day or per week or per 2
weeks or per 3 weeks or per month, i.e irrespective of no of
Hours/Days in a month, The SLDC Charges will be collected Per
month only.
In case of Different capacities observed in a month. Highest MW
will be charged for a Particular Month for SLDC Operating Charges.
25. SLDC ANNUAL FEE (SAF)
SLDC Annual Fee as per APERC Rs. /MW/Year (Annum)
1917.48 2838.01 3792.02 4997.87 6382.27
2535.65 3092.68 3533.18 3995.39 4214.27
Grid Supporting (SLDC) Charges will be collected for all open
Access Users.
Minimum Capacity Allowed for 1MW for Open Access.
Rounding to Next Digit MW in case of Partial MWs.
SLDC Annual Fee is Rs. MW/Year (Annum).
In case of OA Started & end in between a Month SLDC Annual Fee
Applicable for OA Period days only.
This is to be collected for 6 Months in advance.
These are to be collected in April & October.
Date Start of OA in between Year, the amount to be collected up to
either up to April or October. Similar case for OA ending period.
26. TRANSMISSION CHARGES-STAT (TRS)
Transmission charges-Stat as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
65.30 76.66 91.36 95.37 94.44
Transmission charges will be collected if Open access
user utilized the Transmission network.
Due to Govt of AP Policy and APERC Tariff,
Transmission Charges are exempted for Wind, Solar
and Mini Hydel Power Plants (Renewable Power Plants
to encourage the business).
How Much Transmission Charges given exemption is
to be furnished to Govt of AP and APERC. For the
Purpose this condition was created.
27. EXIT CHARGES (TRE, SOE, SAE)
The Open Access User can exit or Discontinue the
Open Access Agreement at any time, as per his
convenient for Full Capacity or Partial Capacity.
In case of LTOA or MTOA Users they have to pay the
Exit Charges as follows:
25% of Transmission Charges will be applicable for
the Balance period with date of exit Price.
100% of SLDC Operating Charges will be
applicable for the Balance period with date of exit
Price.
100% of SLDC Annual Fee will be applicable for
the Balance period with date of exit Price.
In Case of STOA - 100% of above three Charges will
be applicable for the Balance period with date of exit
Price.
28. TRANSMISSION CHARGES/DAY (TRD)
During the Power Crisis, DISCOMs are procuring the
power from various sources to meet the Demand. This
is called Short Term Power Purchases (STPP).
Monthly Basis for a period of Months in RTC.
Every Day different capacity for a month.
Particular Days in a Particular Month for no of
Months in RTC.
No of Hours in a Day on Particular Dates in
Particular Month for no of Months.
The Generators are not covered in MYT Tariff.
The Minimum Transmission Charges will be
applicable on Day basis, irrespective of No of Hours in
a day STPP Agreement is available.
In case of Monthly Fixed Agreement is there, Monthly
Charges will be applicable.
29. TRANSMISSION CHARGES/HOUR (TRH)
Telengana ERC has given directions if the Short term
Power Purchased from OA Generators, No of Hours in a
Day on Particular Dates in Particular Month for no of
Months, Transmission Charges will be collected per
Hour Basis not on daily or monthly basis.
This is applicable for DISCOMs and Short Term Power
Purchases (STPP) only to meet the Demand.
However, during the SAP Development, This provision
also provided for future requirement.
Transmission charges/Hour as per APERC Rs. / MWH
165.67 192.89 214.64 241.38 261.64
90.69 106.47 126.89 132.46 131.17
30. SLDC ANNUAL FEE/DAY (SAD)
During the Power Crisis, DISCOMs are procuring the
power from various sources to meet the Demand. This
is called Short Term Power Purchases (STPP).
Monthly Basis for a period of Months in RTC.
Every Day different capacity for a month.
Particular Days in a Particular Month for no of
Months in RTC.
No of Hours in a Day on Particular Dates in
Particular Month for no of Months.
The Generators are not covered in MYT Tariff.
The Minimum SLDC Annual Fee will be applicable on
Day basis, irrespective of No of Hours in a day STPP
Agreement is available.
In case of Monthly Fixed Agreement is there, Monthly
Charges will be applicable.
31. TRANSMISSION CHARGES/HOUR (TBC)
Inter State Short Term Bilateral & Collective (STBC),
the Transmission Charges will be applicable for
Hourly Basis.
Bilateral Payments will be made by POSOCO.
Collective Payments will be made by IEX and PXI.
In case SERC has not determined the transmission
charges, the charges for use of respective state
network shall be payable at the rate of Rs
80.00/MWH
Inter State Transmission charges/Hour Rs. /MWH
165.67 192.89 214.64 241.38 261.64
90.69 106.47 126.89 132.46 131.17
32. SLDC CHARGES/DAY (SBC)
Interstate STOA users either bilateral or collective shall
pay SLDC Charges Rs 1000/- per day per Transactions
of OA user.
Bilateral Payments will be made by POSOCO.
Collective Payments will be made by IEX and PXI.
IEX will pay the Charges in one day advance based on
the schedule. Weekly calculation sheets will be mailed.
POSOCO Weekly Payments and Monthly Calculations
sheets will be mailed.
Inter State SLDC charges/Day Rs. Per Day
33. CONVERSION PRICES OF OPEN ACCESS
2019-2020
Rs.
Per MWH
165.67
SLDC Charges Rs 1000/- per day per Transactions
of OA user in case of STOA Bilateral (POSOCO) &
Collective (IEX/PXI).
34. TRANSMISSION
CHARGES FINANCIAL
YEAR
SLDC CHARGES
OPERATING
CHARGES
ANNUAL
FEE
Rs. /KW/Month Rs. MW/Month Rs. MW/Year
65.30 2014-15 2378.11 2535.65
76.66 2015-16 2209.34 3092.78
91.36 2016-17 2247.62 3533.18
95.37 2017-18 2300.31 3995.39
94.44 2018-19 2342.73 4214.27
OPEN ACCESS CHARGES
Transmission charges as per APERC Rs. /KW/Month
65.30 76.66 91.36 95.37 94.44
Transmission charges applicable for Intra/Inter state users per MWH
90.69 106.47 126.89 132.46 131.17
43. Long Term Transmission Service Agreement
APERC will issue the Multi Year Tariff along with Generators
list along with capacity, approved capacity for DISCOM wise and
Transmission charges & SLDC Charges.
DISCOMs has to pay the amount according to Contacted
Capacity - Transmission Charges & SLDC Operating Charges
Month Wise and SLDC Annual Fee Half Yearly.
DISCOM has to pay the additional Transmission Charges &
SLDC Charges to APTRANSCO, if they Purchase the Power from
other than approved Generators of approved capacity.
After APERC Multi Year Tariff (MYT) issued, APDISCOMS has to
enter Long Term Transmission Service Agreement with APTRANSCO
for the MYT Period for the approved Generators of approved
Capacities.
STU - Commercial Wing (On behalf of APTRANSCO), Chief
General Manager/Commercial/ DISCOM (on behalf of respective
DISCOM ) will enter Long Term Transmission Service Agreement
(LTTSA) as per APERC approve format.
44. Long Term Transmission Service Agreement
Executive Director (Finance) (FI Module) will raise the
following invoices every month in consultation with STU
– Commercial Wing to respective DISCOM.
1) invoice for Transmission charges. (Monthly)
(surcharge is not applicable)
2) invoice for SLDC Operating Charges. (Monthly)
due date 10 days. Surcharge will be levied, if due
date exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April
1st & October 1st. Due date 10 days. Surcharge
will be levied, if due date exceeds.
46. Submission of intra LTOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of LTOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Types of OA Users
1) Captive
2) Group Captive
3) Third Party
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee.
Rs 10,000/- fee shall be payable in favour of
“FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either
through the DD or RTGS.
APTRANSCO Nodal Officer is
STU – CHIEF ENGINEER COMMERCIAL
47. Field Feasibility Report
Application Received by STU-CE Commercial is the
initiation of Activity.
STU-CE Commercial will address a letter to Generator
Located area of Chief Engineer/Zone & Chief General
Manager / DISCOM and Consumer Located area of Chief
Engineer/Zone & Chief General Manager / DISCOM for
feasibility if Consumer is connected to APTRANSCO
substation at 33KV level and above Voltage level and copy
to respective SE/OMC & SE/ Operations/ DISCOM. if
Consumer connected at 33KV or 11KV at Distribution
network, feasibility was requested the concerned
CGM/DISCOM and SE/Operation/Dist.
Respective SE/OMCs, SE/Operation/DISCOM, Chief
Engineer/ Zones & CGM/DISCOMs will send the feasibility
report to STU-CE Commercial.
48. Intra LTOA Approval & Agreement Process
STU-CE Commercial will initiate the LTOA approval
and circulate the note to Full APTRANSCO Board based
on the field feasibilities received.
After approval of Board, LTOA approval will be given
to OA user with some conditions & Payments and
request for enter in to agreement as per APERC format.
The OA user has to met the conditions & Payments.
The Generator & Consumer both at 33KV or 11KV
Within DISCOM, LTOA agreement will be done between
DISCOM & OA User.
For others LTOA tripartite agreement will done
between APTRANSCO, DISCOM & OA User.
49. Intra State LTOA Payment Process
ED/Finance (FI Module) will raise the following invoices
every month in consultation with ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds. ( Not applicable for with in DISCOM)
2) invoice for SLDC Operating Charges. (Monthly) due
date 10 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st
& October 1st. Due date 10 days. Surcharge will be
levied, if due date exceeds.
50. Terms & Conditions of LTOA approval
1) A Long Term Open Access agreement with APTRANSCO,
DISCOMs (Consumer area) & OA user in the APERC
approved format.
2) The date of commencement of Open Access for the capacity
will be as mentioned in the Agreement.
3) The company shall pay monthly Transmission & SLDC
charges to APTRANSCO, Wheeling charges to Respective
DISCOM as per the Tariff Orders issued by APERC from time
to time irrespective of actual energy injected and also bear
losses in kind.
4) The company shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
5) The company has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
52. Submission of intra STOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of STOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Types of OA Users
1) Captive
2) Group Captive
3) Third Party
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee.
Rs 1000/- fee shall be payable in favour of “SAO/SLDC,
APTRANSCO” Payable at Hyderabad either through RTGS.
APTRANSCO Nodal Officer is
Chief Engineer (SLDC)
53. Intra STOA Approval & Agreement Process
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission
network is involved.
4. CGM/DISCOM – for feasibility if Distribution Network
involved.
if the CMD capacity is more than the contracted, the Power
system feasibility is to be obtained.
1) The OA User shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
2) The OA User has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
CE/SLDC will issue STOA approval based on the field
feasibilities received & above amounts received.
54. Intra STOA Approval & Agreement Process
Any deviation of feasibility, Note file will be circulated
to Full Board for approval.
After approval issued by CE/SLDC, the OA User was
requested for enter in to agreement as per APERC
format, and meet the STU – CE Commercial for enter in
to agreement.
The Generator & Consumer both at 33KV or 11KV
Within DISCOM, STOA agreement will be done between
DISCOM & OA User.
DISCOM will Furnish the Agreement to STU-CE
Commercial, CE/SLDC & ED/Finance & SAO/SLDC.
For others STOA tripartite agreement will done
between APTRANSCO, DISCOM & OA User.
55. Intra State STOA Payment Process
ED/Finance (FI Module) will raise the following invoices
every month in consultation with ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds. ( Not applicable for with in DISCOM)
2) invoice for SLDC Operating Charges. (Monthly) due
date 10 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Monthly
proportionate). Due date 10 days. Surcharge will be
levied, if due date exceeds.
56. Terms & Conditions of STOA approval
1) A Short Term Open Access agreement with APTRANSCO,
DISCOMs (Consumer area) & OA user in the APERC
approved format.
2) The Period of Open Access for the capacity will be as
mentioned in the SLDC Approval.
3) The company shall pay monthly Transmission & SLDC
charges to APTRANSCO, Wheeling charges to Respective
DISCOM as per the Tariff Orders issued by APERC from time
to time irrespective of actual energy injected and also bear
losses in kind.
4) The company shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
5) The company has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
58. Short Term Power Purchases (DISCOM)
Andhra Pradesh Power Coordination Committee
(APPCC – Representative of APDISCOMs) will purchase
the Power from the intra State Pvt Generators based on
the requirement of Power for DISCOM on Day /
Monthly/ Quarterly/Half yearly/Yearly basis (Maximum
One Year) to meet the DISCOM demand in Consultation
with SLDC.
The PPA approval Copy will sent to STU-CE
Commercial, CE/SLDC and Executive Director (Finance).
As per the PPA with Generators, The Generator has
to pay the Transmission & SLDC Charges to
APTRANSCO.
59. Short Term Power Purchases (DISCOM)
ED/Finance (FI Module) will raise the following invoices
every month for the PPA period in consultation with
CE/Commercial/APPCC, CE/SLDC and ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) if the
Generator having a PPA for differential capacities for
different periods in a month, calculate the proportionate
transmission charges. due date 15 days. Surcharge will
be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) if the
Generator having a PPA for differential capacities for
different periods in a month, the charges will be levied
fully (Whole month) on a Highest capacity of a Particular
month. due date 15 days. Surcharge will be levied, if due
date exceeds. due date 10 days. Surcharge will be
levied, if due date exceeds.
3) Invoice for SLDC Annual Fee. (monthly). Calculation as
per point no1 above (Transmission Charges). Due date
10 days. Surcharge will be levied, if due date exceeds.
62. Submission of Inter LTOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of inter state LTOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Inter State LTOA Application
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee to
Power Grid.
Power Grid will request the concerned STU for NOC.
The OA User has to pay the Prescribed fee in favour of
“FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either
through the DD or RTGS.
APTRANSCO Nodal Officer is STU-CE Commercial
63. Inter State LTOA Approval Process
The Fee Details as follows
1. Up to 100 MW : Rs 2.00 Lakhs
2. 101 MW to 500 MW : Rs 3.00 Lakhs
3. 501 MW to 1000 MW : Rs 6.00 Lakhs
4. Above 1000MW : Rs 9.00 Lakhs
STU-CE Commercial will address a letter to OA User
Located area of Chief Engineer/Zone and copy to respective
SE/OMC in case of OA user.
Respective SE/OMC & Chief Engineer/ Zones will be
sent the feasibility report to STU-CE Commercial.
STU-CE Commercial will initiate the inter state LTOA
approval and circulate the note to Full APTRANSCO Board
based on the field feasibilities received through CE/PS &
CE/SLDC.
After approval of Board, NOC approval will be given to
PGCIL.
64. Inter State LTOA Approval & Payment
The Inter state LTOA Approval will be issued by PGCIL
under intimation to APTRANSCO.
STU-CE Commercial, CE/SLDC & SAO/SLDC has to
collect each Interstate LTOA Approvals from PGCIL web Site.
Based on the Inter State LTOA approval, ED/Finance (FI
Module) will raise the following invoices every month in
consultation with STU-CE Commercial,
CE/Commercial/APPCC & CE/SLDC to OA User.
1) invoice for Transmission charges. (Monthly) due date
15 days. Surcharge will be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st &
October 1st. Due date 10 days. Surcharge will be
levied, if due date exceeds.
66. Submission of Inter MTOA Application
Either Generator or Consumer (Open Access User)
may eligible for submission of inter state MTOA
Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or
Multi Generators.
Inter State MTOA Application
The OA Users has to submit the detailed application
(Format-1 & Format-2) along with necessary Documents
along with requisite fee to Power Grid. Same time the OA
user has to submit the Application to STU along with
requisite fee. The OA User shall furnish the valid PPA for
the application period.
67. Submission of Inter MTOA Application
The OA User has to pay the Prescribed fee in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS only.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
The Fee Details as follows
1. Up to 100 MW : Rs 1.00 Lakhs
2. 101 MW to 500 MW : Rs 2.00 Lakhs
3. 501 MW to 1000 MW : Rs 3.00 Lakhs
4. Above 1000MW : Rs 4.00 Lakhs
CE/SLDC will address a letter to OA User Located
area of respective CGM/DISCOM & Chief Engineer/Zone
(in case of EHT) for feasibility.
Respective CGM/DISCOM & Chief Engineer/ Zones
will be sent the feasibility report to CE/SLDC.
68. Inter State MTOA Approval at SLDC
if the CMD capacity is more than the contracted, the Power system
feasibility is to be obtained.
If PPA was not submitted along with the application, the Consent/
Concurrence/NOC will be rejected.
1) The OA User shall pay two months SLDC charges to APTRANSCO
as security deposit before commencement of Open Access as per
APERC Orders and Regulations from time to time.
2) The OA User has to open Letter of Credit towards imbalance in
supply and consumption of electricity for a period of 10 days,
before commencement of Open Access to DISCOMs.
CE/SLDC will initiate the Inter State MTOA approval and circulate
the note to Full APTRANSCO Board based on the field feasibilities
received and amounts received.
After approval of Board, NOC will be issued to PGCIL with
standard format-3 for inter state MTOA.
SLDC shall convey its concurrence to the applicant (New OA User)
With in 10 Working days.
The start date of MTOA shall not be earlier than 5 months and
later than 1 year from the last day of the month in which application
has been made.
69. Inter State MTOA Approval & Payment
The Inter state MTOA Approval will be issued by PGCIL
under intimation to APTRANSCO.
STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect
each Interstate MTOA Approvals from PGCIL.
Based on the Inter State MTOA approval, ED/Finance (FI
Module) will raise the following invoices every month in
consultation with STU-CE Commercial, CE/Commercial/APPCC
& CE/SLDC to OA User.
1) invoice for Transmission charges. (Monthly) due date 15
days. Surcharge will be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) due date
15 days. Surcharge will be levied, if due date exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st &
October 1st. Due date 10 days. Surcharge will be levied,
if due date exceeds.
71. Submission of Inter STBC Application
Either Generator or Consumer (Open Access User)
may eligible for submission of Inter State STOA
Application.
Generator / Consumer / Trader Treated as OA User.
The OA Users has to submit the detailed application
(Format-1 & Format-2 of CERC) along with necessary
Documents along with requisite fee.
Rs 5,000/- fee shall be payable in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
72. INTER STATE STBC APPROVAL PROCESS
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission network is
involved.
4. CGM/DISCOM – for feasibility if Distribution Network involved.
Payments to be done
1) The OA User shall pay two months SLDC charges to APTRANSCO
as security deposit before commencement of Open Access as per
APERC Orders and Regulations from time to time.
2) The OA User has to open Letter of Credit towards imbalance in
supply and consumption of electricity for a period of 10 days,
before commencement of Open Access to DISCOMs.
CE/SLDC will issue Consent/ Concurrence for Inter State STOA
(Bilateral) approval to OA User with Standard Format-3 based on the
field feasibilities received & above amounts received.
As per the CERC Procedure Consent/ Concurrence shall be issued
as for the schedules
1. With in 7 days for New OA User
2. With in 3 days for Already availed OA user.
73. Inter State STBC Approval & Payment
SRLDC will issue approvals for Inter state STOA (Bilateral).
STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect
each Interstate STOA Approvals (Bilateral) from SRLDC web
Site.
SRLDC Will Pay the Month wise Amounts on 1st of
upcoming month for the last month for Bilateral Approvals to
FA&CCA(R&A).
ED/Finance (FI Module) will Verify the Amounts received
towards each approval regarding Transmission Charges, SLDC
Charges and total amount received from SRLDC, on monthly
basis in consultation with ED/HRD & Plg.
1) Transmission charges based on the MWH Transmitted.
2) SLDC Charges Rs 1000/- per day per Transactions of
OA user.
Any deviation of payments STU-CE Commercial will intimate
for discrepancies to SRLDC under copy to ED/Finance.
75. Submission of Inter STBC Application
Either Generator or Consumer (Open Access User)
may eligible for submission of Inter State LTOA
Application.
Generator / Consumer / Trader Treated as OA User.
The OA Users has to submit the detailed application
(Format-1 & Format-2 of CERC) along with necessary
Documents along with requisite fee.
Rs 5,000/- fee shall be payable in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
76. Inter State STBC Approval Process
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission
network is involved.
4. CGM/DISCOM – for feasibility if Distribution Network
involved.
if the CMD capacity is more than the contracted, the
Power system feasibility is to be obtained.
CE/SLDC will issue NOC for Inter State STOA
(Collective) approval to OA User with Standard Format-3
based on the field feasibilities received & above amounts
received.
As per the CERC Procedure NOC shall be issued as for
the schedules
1. With in 7 days for New OA User
2. With in 3 days for Already availed OA user.
77. Inter State STBC Approval & Payment
IEX/PXI will send day wise Transactions on weekly
basis to ED/HRD & Plg through mail for reconciliation.
IEX/PXI Will Pay the Day wise Amounts.
ED/Finance (FI Module) will Verify the Amounts
received towards each Transactions regarding
Transmission Charges, SLDC Charges, Wheeling charges
and total amount received from IEX/PEX, on monthly basis
in consultation with STU - CE Commercial.
1) Transmission charges based on the MWH
Transmitted.
2) SLDC Charges Rs 1000/- per day per Transactions
of OA user.
Any deviation of payments STU-CE Commercial will
intimate for discrepancies to IEX/PEX under copy to
ED/Finance.