SlideShare a Scribd company logo
1 of 78
Download to read offline
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
 The Power Sector in India has undergone a plethora of reforms in
the last two decades.
 Introduction of competition has been one of the main aims of reform
in the electricity sector in India.
 One of the most important steps taken towards achieving this was
the introduction of open access in the Electricity Act, 2003, where
large consumers have access to the Transmission and Distribution
(T&D) network to obtain electricity from suppliers other than the
local electricity distribution company (DISCOM).
INTRODUCTION
OBJECTIVE
 The objective of open access was to provide opportunity to energy
intensive industry and commercial establishments to source
electricity directly from the market and manage costs to remain
competitive.
 Open Access was to also improve the economic health of the
Distribution Licensees by reducing power procurement at higher
marginal cost so that the non-open access retail consumers of the
Distribution Licensees would not get unduly burdened.
 Electricity Act 2003 (sub-section 2 of section 42) lay down provisions for
a power market and competition wherein electricity consumers now
have the right to procure power from the supplier of their choice other
than their distribution company.
 For example, under open-access a consumer in Telangana has right to
select the source of supply form any generator. This generator may be
generating power in Telangana or any other state in India.
Open Access, as per Electricity Act 2003
 “Non-discriminatory provision for the use of transmission lines or
distribution system or associated facilities with such lines or system by
any licensee or consumer or a person engaged in generation in
accordance with the regulations specified by the Appropriate
Commission”.
 Open Access allows large and heavy users of powers i.e. those with 1
megawatt (MW) and above connected load to buy cheaper power from
the open market.
 The idea is that the customers now able to choose from a number of
competing power companies like GENCOs, CPSU, IPPs, Private.
Licensees, Excess Captive from captive power plants instead of being
forced to buy electricity from their existing electric utility monopoly.
OA WITH EA 2003
1. Competitive Pricing
 Open Access was introduced in the Electricity Act to bring in
competition into the sector, thereby benefitting the end consumer.
 Over the years, it has acted as a catalyst in bringing reforms into the
sector by benefitting the players across the spectrum of value-chain
from generators to suppliers to electricity traders to the end
consumers.
 Open Access will ease the power shortage since a number of power
producers like Solar energy companies can now transmit power from
their solar parks to different load centers.
 Once the consumers are given the choice to purchase power from
the open market, it will automatically lead to competitive pricing of
electricity making electricity cost go down.
2. Regular electricity supply
 It helps the industrial & commercial consumers by ensuring regular
electricity supply at competitive rates.
 It helps large consumers particularly the sick textile, cement and
steel industrial units by ensuring regular supply of electricity at
competitive rates and boost business of power bourses.
PROS AND CONS OF OPEN ACCESS
3. Help Consumers to meet RPOs
 It also enhances the business of power markets as the open access
helps consumers meet their Renewable Purchase Obligations (RPOs) as
well.
4. Exposure to Grid Risks
 In open access, eligible consumer can avail the benefits of cheaper
green solar power by either purchasing through the rooftop solar
installation in its premises or buying from an offsite solar farm.
 While open access does away with limitations of rooftop solar such as
scalability and high capital expenditure, it is often exposed to
unpredictable grid risks.
5. Appropriate utilization of existing infrastructure (T&D)
 Existing Transmission and Distribution Infrastructure can be used to
avail the open access.
 In open access, this will enable number of players utilizing these
infrastructure and transmit power from generation to the load center.
 This will mean utilization of existing infrastructure and easing of power
shortage.
 Trading, now a licensed activity and regulated will also help in
innovative pricing which will lead to competition resulting in lowering of
tariffs.
PROS AND CONS OF OPEN ACCESS
 Open Access, rights governed in India by Electricity Act 2003, can
be classified as under on the basis of location of the purchasing and
selling entities:
Types of Open Access Users
1. Intra State (With in the state)
2. Inter State (State to State)
Intra State Users
1. Short Term (STOA) up to 1 year
2. Medium Term (MTOA) - AP & TS Not Contemplated
3. Long Term (LTOA) 2 years and above
Inter State Users
1. Short Term (STOA) – Maximum one month.
2. Medium Term (MTOA) – 3 months to 5 Years (earlier 3 Years)
3. Long Term (LTOA) – 12 Years to 25 Years
Power Markets- Collective Transactions
1. Indian Energy Exchange Limited – IEX
2. Power Exchange India Limited – PXI
Minimum Open access allowed for 1MW
OPEN ACCESS CLASIFICATION
 When the Purchasing and selling entities belong to same state then
it is called as an Intra-state transaction. In this case, the open
access charges comprising Transmission Losses and Charges
Wheeling losses and Charges (if applicable) and cross-subsidy of
that particular state are applicable.
 In Intra-State Open Access State Electricity Regulatory Commission
(SERC) regulations are followed.
 Wherein purchase rights can be categorized.
 Duration of which depends on the respective state open access
regulations.
Intra State Purchases for DISCOMs
1. Short Term (STPP) up to 1 year
2. Medium Term (MTOA)  AP & TS Not Contemplated
3. Long Term (LTTSA) with GENCO 2 years and above
4. Long Term (LTOA) with Other Generators 2 years and above
Intra State OA Users
1. Short Term (STOA) up to 1 year
2. Medium Term (MTOA) - AP & TS Not Contemplated
3. Long Term (LTOA) 2 years and above
INTRA STATE OPEN ACCESS
 When the Purchasing and selling entities belong to different states
then it is called as an Inter-state transaction.
 In this case, apart from the open access charges applicable in intra-
state transactions, Point-of-Connection (POC) charges and losses of
the regional grids where the buyer and seller are located are also
applicable.
 In Inter State Open Access Central Electricity Regulatory
Commission (CERC) regulations are to be followed
Inter State Open Access
1. Short Term Open Access (STBC): Open Access allowed for the
period of less than one month.
Bilateral: Power Purchase Agreement (PPA) is a contract between
the seller and the consumer. POSOCO is the Coordinator.
Collective: Traded through Power Exchanges by Exchange
Members/Traders.
2. Medium Term Open Access (MTOA): Open Access allowed for a
period of 3 months to 5 years. (earlier 3 Years)
3. Long Term Open Access (LTOA): Open Access allowed for a
period of 12 years to 25 years.
INTER STATE OPEN ACCESS
 Renewable Energy based transactions under intra-state open-
access is more convenient than inter-state open-access.
 in order to promote Renewable Energy, many state provide
various concessional provisions like concessional Wheeling
and Transmission charges, Banking facility benefits,
Electricity Tax / Duty Exemptions, Waiver or Discount in
Cross-Subsidy-Charges etc.
 These concessional provisions reduce the cost of transaction
significantly and allow RE generators to offer better
commercial terms to consumers.
INTRA VS INTER OPEN ACCESS
OPEN ACCESS CHARGES
 Electricity consumers can make use of the existing Transmission and
Distribution infrastructure after paying appropriate charges determined by
their respective State Electricity Regulatory Commissions (SERCs).
 A supportive regulatory regime from the state electricity authorities
combined with better grid stability can make long-term open access projects
viable.
 These changes will facilitate more projects from the renewable energy
companies who are taking huge upfront risks at present and will definitely
upgrade the state of power trading in the country.
 These charges against the usage of Transmission and Distribution
infrastructure can vary from state to state and are lesser in states with
stable grid and favorable regulatory regime.
 In case of solar power, the state-wise open access charges can vary from as
low as Rs. 0.2/KWh to Rs.1.5/KWh.
 There are several charges to be paid by Open Access Consumers to
Distribution Licensee, Transmission Licensees and other related entities,
other than the power purchase cost paid to the generator or supplying
entity.
 Apart from below charges the open access consumers has also to fulfill the
renewable purchase obligation (RPO), in which they have to purchase a part
of their total consumption through electricity generated from renewable
energy.
OPEN ACCESS CHARGES
 Connectivity Charges (at the time of Application)
 Point of Connection (PoC) Charges (CTU)
 Transmission Charges (STU)
 Transmission Losses
 Wheeling Charges (DISCOM)
 Wheeling Losses
 Cross Subsidy Surcharge (DISCOM)
 RLDC Charges (POSOCO)
 SLDC Charges.
 In case of AP & TS  SLDC Charges Bifurcated as
 SLDC Operating Charges
 SLDC Annual Fee.
OPEN ACCESS
 The Buyer and Seller of Electricity can opt for
either Collective or Bilateral Transactions.
 Besides minor changes in the meter installed, Open
Access transactions are essentially managed through
energy accounting at the state level.
 EBC established under Control of SLDC for Energy
Accounting.
 Thus, a Consumer buying Power from Open Access
will see the transaction accounted for in its monthly
bill.
COLLECTIVE TRANSACTIONS
 In case of Collective Transactions the Electricity is
traded through Power Exchanges by Exchange
Members/Traders for a very small margin fixed by
commission.
 Power Exchange transactions are transactions carried
out over an electronic platform.
 Currently India has two operating Power Exchanges
(PXs)
1. Indian Energy Exchange (IEX) and
2. Power Exchange India (PXI).
 At Power Exchanges Consumers can buy/sell electricity
on day-ahead/week-ahead basis or for particular time
period in a day.
 Buyer/Seller will be bidding for electricity cost for
particular time period and for each time period price at
which electricity is determined by market.
BILATERAL TRANSACTIONS
 Power Purchase Agreement (PPA) is a contract
between the Seller and the Consumer for buying
power at mutually agreed tariff for a predetermined
number of years.
 The PPA defines all of the commercial terms for the
sale of electricity between the two parties, including
when the project will begin commercial operation,
schedule for delivery of electricity, penalties for under
delivery, payment terms, and termination clauses.
 A significant quantum of power is still traded through
bilateral transactions.
 Many of the leading solar players under the OPEX
model in India are resorting to bilateral agreements for
tariff determination with commercial and industrial
clients.
BILATERAL VS COLLECTIVE
 Adopting a combination of Bilateral transaction and
Collective transaction may result in cost savings of
sourced energy and long term energy security because
bilateral mode of transaction brings volumetric and
price certainty for a relatively longer duration while
sourcing power from Power Exchanges provides
advantages such as better price discovery, risk
mitigation from counter-party default.
Nodal
Agency
STU SLDC
PGCIL
(CTU)
PGCIL
(CTU)
Exit
RLDC
NLDC
Duration
2 Years
and
above
Up to
1 Year
12 Years
to
25 Years
3 Months
to
5 Years
Max One Month
NOC /
Concurre
nce
NOC by
STU
NOC by
SLDC
Concurr
ence by
SLDC
NOC by
SLDC
Approval
STU
Comml.
SLDC PGCIL PGCIL
Exit
RLDC
NLDC
Agreeme
nt
STU
Comml.
STU
Comml.
PGCIL PGCIL
OA ACTIVITY AUTHORITY
Info
Injection / Entry
Point Voltage
Consumption /
Exit Point Voltage
Transmission
Charges & SLDC
Charges
Wheeling charges
at entry/Exit
Case-1
DISCOM-A or B
EHT Voltage
DISCOM-A or B
EHT Voltage
Applicable NA
Case-2
DISCOM-A
EHT Voltage
DISCOM-A
33KV or 11KV Applicable
DISCOM-A
33KV or 11KV
Entry & Exit Vice-Versa
Case-3
DISCOM-A
EHT Voltage
DISCOM-B
33KV or 11KV
Applicable
DISCOM-B
33KV or 11KV
Case-4
DISCOM-A
33KV or 11KV
DISCOM-B
EHT Voltage
Applicable
DISCOM-A
33KV or 11KV
Case-5
DISCOM-A
33KV Voltage
DISCOM-B
33KV Voltage
Applicable
DISCOM-B
33KV
Case-6
DISCOM-A
11KV Voltage
DISCOM-B
11KV Voltage
Applicable
DISCOM-B
11KV
Case-7
DISCOM-A
33KV Voltage
DISCOM-B
11KV Voltage
Applicable
DISCOM-B
11KV
Case-8
DISCOM-A
11KV Voltage
DISCOM-B
33KV Voltage
Applicable
DISCOM-A
11KV
Case-9
DISCOM-A
33KV or 11KV
DISCOM-A
33KV or 11KV
Only SLDC Charge
(With in DISCOM)
DISCOM-A
33KV or 11KV
(Lower Voltage )
INTRA STATE OA CHARGES (LTOA & STOA)
Info
Entry or exit
Point in State
Voltage
Inter State
Transmission
Charges
Transmission
Charges & SLDC
Charges
Wheeling
charges at
entry/Exit
Case-1
Entry/Injection
at
EHT Voltage
The Inter State
Open Access User
has to Pay the
following Charges
to PGCIL.
1.PoC Injection
Charges of AP
i.e. Rs. Per MW
Per Month in
case of Power
Injection at AP.
2. PoC With drawl
Charges of AP
i.e. Rs. Per MW
Per Month in
case of Power
Withdrawn in
AP.
3. Grid Support
Charges to
POSOCO
Transmission
Charges to
APTRANSCO
i.e Rs. Per KW
per Month as
approved by
APERC from
time to time.
SLDC Charges
to APTRANSCO
i.e. Annual Fee
Rs. Per MW per
Year &
Operating
Charges Rs. Per
MW Per Month
NA
Case-2
Exit/
Withdrawn at
EHT Voltage
NA
Case-3
Entry/Injection
at
33KV or 11KV
Voltage
Particular
DISCOM
33KV or 11KV
wheeling
Charges for exit
or entry
Case-4
Exit/
Withdrawn at
33KV or 11KV
Voltage
INTER STATE OA CHARGES (LTOA & MTOA)
Info
Entry or exit
Point in State
Voltage
Inter State
Transmission
Charges
Transmission
Charges &
SLDC Charges
Wheeling
charges at
entry/Exit
Case-1
Entry/Injection
at
EHT Voltage
The Inter State
Open Access User
has to Pay the
following Charges
to PGCIL.
1.PoC Injection
Charges of AP
i.e. Paisa per
Unit in case of
Power Injection
at AP.
2. PoC With drawl
Charges of AP
i.e. Paisa per
Unit in case of
Power With
drawn in AP.
3. Grid Support
Charges to
POSOCO
Transmission
Charges of AP
i.e Rs. Per
MWH.
SLDC Charges
Rs 1000/- per
day per
Transactions of
OA user.
NA
Case-2
Exit/
Withdrawn
at EHT Voltage
NA
Case-3
Entry/Injection
at
33KV or 11KV
Voltage
Particular
DISCOM
33KV or 11KV
wheeling
Charges for exit
or entry i.e.
Rs. Per MWH.
Case-4
Exit/
Withdrawn at
33KV or 11KV
Voltage
INTER STATE OA CHARGES (STBC)
INTER STATE PoC CHARGES
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
 Transmission of Power From Generator to Consumer
using Utility Network.
 Transmission charges will be collected if Open access
user utilized the Transmission network.
 Wheeling charges will be collected if Open access
user utilized the Distribution network.
 Within DISCOM, Generator & Consumer both at
33KV or 11KV, only wheeling charges applicable &
Transmission Charges not applicable.
 Grid Supporting (SLDC) Charges will be collected for
all open Access Users.
 Regional Network charges will be collected if Open
access user utilized the interstate network.
 As per APERC Guidelines Nodal Organization is
State Transmission Utility (STU-APTRANSCO)
OPEN ACCESS
TRANSMISSION CHARGES (TRC)
Transmission charges as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
65.30 76.66 91.36 95.37 94.44
 Transmission charges will be collected if Open access
user utilized the Transmission network.
 Minimum Capacity Allowed for 1MW for Open Access.
 The same is exempted for Renewable Energy
Generators.
 Transmission Charges are Rs. KW/Month.
 In case of OA Started & end in between a Month
Transmission Charges Applicable for OA Period days
only.
SLDC OPERATION CHARGES (SOC)
SLDC Operating charges as per APERC Rs. /MW/Month
2146.34 2058.18 2086.32 2150.21 2235.65
2378.11 2209.34 2247.62 2300.31 2342.73
 Grid Supporting (SLDC) Charges will be collected for all open
Access Users.
 Minimum Capacity Allowed for 1MW for Open Access.
 Rounding to Next Digit MW in case of Partial MWs.
 SLDC Operating Charges are Rs. MW/Month.
 In case of OA Used  per Hour or per day or per week or per 2
weeks or per 3 weeks or per month, i.e irrespective of no of
Hours/Days in a month, The SLDC Charges will be collected Per
month only.
 In case of Different capacities observed in a month. Highest MW
will be charged for a Particular Month for SLDC Operating Charges.
SLDC ANNUAL FEE (SAF)
SLDC Annual Fee as per APERC Rs. /MW/Year (Annum)
1917.48 2838.01 3792.02 4997.87 6382.27
2535.65 3092.68 3533.18 3995.39 4214.27
 Grid Supporting (SLDC) Charges will be collected for all open
Access Users.
 Minimum Capacity Allowed for 1MW for Open Access.
 Rounding to Next Digit MW in case of Partial MWs.
 SLDC Annual Fee is Rs. MW/Year (Annum).
 In case of OA Started & end in between a Month SLDC Annual Fee
Applicable for OA Period days only.
 This is to be collected for 6 Months in advance.
 These are to be collected in April & October.
 Date Start of OA in between Year, the amount to be collected up to
either up to April or October. Similar case for OA ending period.
TRANSMISSION CHARGES-STAT (TRS)
Transmission charges-Stat as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
65.30 76.66 91.36 95.37 94.44
 Transmission charges will be collected if Open access
user utilized the Transmission network.
 Due to Govt of AP Policy and APERC Tariff,
Transmission Charges are exempted for Wind, Solar
and Mini Hydel Power Plants (Renewable Power Plants
to encourage the business).
 How Much Transmission Charges given exemption is
to be furnished to Govt of AP and APERC. For the
Purpose this condition was created.
EXIT CHARGES (TRE, SOE, SAE)
 The Open Access User can exit or Discontinue the
Open Access Agreement at any time, as per his
convenient for Full Capacity or Partial Capacity.
 In case of LTOA or MTOA Users they have to pay the
Exit Charges as follows:
 25% of Transmission Charges will be applicable for
the Balance period with date of exit Price.
 100% of SLDC Operating Charges will be
applicable for the Balance period with date of exit
Price.
 100% of SLDC Annual Fee will be applicable for
the Balance period with date of exit Price.
 In Case of STOA - 100% of above three Charges will
be applicable for the Balance period with date of exit
Price.
TRANSMISSION CHARGES/DAY (TRD)
 During the Power Crisis, DISCOMs are procuring the
power from various sources to meet the Demand. This
is called Short Term Power Purchases (STPP).
 Monthly Basis for a period of Months in RTC.
 Every Day different capacity for a month.
 Particular Days in a Particular Month for no of
Months in RTC.
 No of Hours in a Day on Particular Dates in
Particular Month for no of Months.
 The Generators are not covered in MYT Tariff.
 The Minimum Transmission Charges will be
applicable on Day basis, irrespective of No of Hours in
a day STPP Agreement is available.
 In case of Monthly Fixed Agreement is there, Monthly
Charges will be applicable.
TRANSMISSION CHARGES/HOUR (TRH)
 Telengana ERC has given directions  if the Short term
Power Purchased from OA Generators, No of Hours in a
Day on Particular Dates in Particular Month for no of
Months, Transmission Charges will be collected per
Hour Basis not on daily or monthly basis.
 This is applicable for DISCOMs and Short Term Power
Purchases (STPP) only to meet the Demand.
 However, during the SAP Development, This provision
also provided for future requirement.
Transmission charges/Hour as per APERC Rs. / MWH
165.67 192.89 214.64 241.38 261.64
90.69 106.47 126.89 132.46 131.17
SLDC ANNUAL FEE/DAY (SAD)
 During the Power Crisis, DISCOMs are procuring the
power from various sources to meet the Demand. This
is called Short Term Power Purchases (STPP).
 Monthly Basis for a period of Months in RTC.
 Every Day different capacity for a month.
 Particular Days in a Particular Month for no of
Months in RTC.
 No of Hours in a Day on Particular Dates in
Particular Month for no of Months.
 The Generators are not covered in MYT Tariff.
 The Minimum SLDC Annual Fee will be applicable on
Day basis, irrespective of No of Hours in a day STPP
Agreement is available.
 In case of Monthly Fixed Agreement is there, Monthly
Charges will be applicable.
TRANSMISSION CHARGES/HOUR (TBC)
 Inter State Short Term Bilateral & Collective (STBC),
the Transmission Charges will be applicable for
Hourly Basis.
 Bilateral Payments will be made by POSOCO.
 Collective Payments will be made by IEX and PXI.
 In case SERC has not determined the transmission
charges, the charges for use of respective state
network shall be payable at the rate of Rs
80.00/MWH
Inter State Transmission charges/Hour Rs. /MWH
165.67 192.89 214.64 241.38 261.64
90.69 106.47 126.89 132.46 131.17
SLDC CHARGES/DAY (SBC)
 Interstate STOA users either bilateral or collective shall
pay SLDC Charges Rs 1000/- per day per Transactions
of OA user.
 Bilateral Payments will be made by POSOCO.
 Collective Payments will be made by IEX and PXI.
 IEX will pay the Charges in one day advance based on
the schedule. Weekly calculation sheets will be mailed.
 POSOCO Weekly Payments and Monthly Calculations
sheets will be mailed.
Inter State SLDC charges/Day Rs. Per Day
CONVERSION PRICES OF OPEN ACCESS
2019-2020
Rs.
Per MWH
165.67
SLDC Charges Rs 1000/- per day per Transactions
of OA user in case of STOA Bilateral (POSOCO) &
Collective (IEX/PXI).
TRANSMISSION
CHARGES FINANCIAL
YEAR
SLDC CHARGES
OPERATING
CHARGES
ANNUAL
FEE
Rs. /KW/Month Rs. MW/Month Rs. MW/Year
65.30 2014-15 2378.11 2535.65
76.66 2015-16 2209.34 3092.78
91.36 2016-17 2247.62 3533.18
95.37 2017-18 2300.31 3995.39
94.44 2018-19 2342.73 4214.27
OPEN ACCESS CHARGES
Transmission charges as per APERC Rs. /KW/Month
65.30 76.66 91.36 95.37 94.44
Transmission charges applicable for Intra/Inter state users per MWH
90.69 106.47 126.89 132.46 131.17
DISCOM WISE – CHARGES APPLICABLE CAPACITY
TRANSMISSION CHARGES APPLICABLE CAPACITY
SLDC OPERATING CHARGES APPLICABLE CAPACITY
SLDC ANNUAL FEE APPLICABLE CAPACITY
APEPDCL APSPDCL
FINANCIAL
YEAR
APCPDCL APNPDCL
3332 4697 2014-15 9714 3347
3707 5225 2015-16 10806 3723
3931 5541 2016-17 11460 3949
4108 5791 2017-18 11977 4127
4284 6038 2018-19 12487 4303
OPEN ACCESS CHARGES (DISCOM)
TRANSMISSION
CHARGES FINANCIAL
YEAR
SLDC CHARGES
OPERATING
CHARGES
ANNUAL
FEE
Rs. /KW/Month Rs. MW/Month Rs. MW/Year
119.28 2019-20 2146.34 1917.48
138.88 2020-21 2058.18 2838.01
154.54 2021-22 2086.32 3792.02
173.79 2022-23 2150.21 4997.87
188.38 2023-24 2235.65 6382.27
OPEN ACCESS CHARGES
Transmission charges as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
Transmission charges applicable for Intra/Inter state users per MWH
165.67 192.89 214.64 241.38 261.64
PEAK
DEMAND
TRANS
MISSION
CHARGES FINANCIAL
YEAR
SLDC CHARGES
Operating
Charges
Annual
Fee
Generation
Capacity
MW
Rs. /KW/
Month
Rs. MW/
Month
Rs. MW/
Year
MW
AP EASTERN POWER DISTRIBUTION COMPANY LIMITED
3792 119.28 2019-20 2146.34 1917.48 6684
4081 138.88 2020-21 2058.18 2838.01 7364
4401 154.54 2021-22 2086.32 3792.02 7627
4755 173.79 2022-23 2150.21 4997.87 7771
5149 188.38 2023-24 2235.65 6382.27 7843
AP SOUTHERN POWER DISTRIBUTION COMPANY LIMITED
7275 119.28 2019-20 2146.34 1917.48 12820
7828 138.88 2020-21 2058.18 2838.01 14123
8442 154.54 2021-22 2086.32 3792.02 14630
9122 173.79 2022-23 2150.21 4997.87 14906
9877 188.38 2023-24 2235.65 6382.27 15043
OPEN ACCESS CHARGES (DISCOM)
PEAK
DEMAND
TRANS
MISSION
CHARGES FINANCIAL
YEAR
Power Allocation between DISCOMs
As per GO MS No13, Dt: 06.04.2020
APEPDCL APSPDCL APCPDCL
MW
Rs. /KW/
Month
34.27% 65.73% -
36.22% 40.44% 23.34%
11067 119.28 2019-20 3793 7274 -
11909 138.88 2020-21 4313 4816 2780
12843 154.54 2021-22 4652 5194 2998
13877 173.79 2022-23 5026 5612 3239
15026 188.38 2023-24 5442 6077 3507
OPEN ACCESS CHARGES (DISCOM)
Transmission charges as per APERC Rs. /KW/Month
119.28 138.88 154.54 173.79 188.38
Transmission charges applicable for Intra/Inter state users per MWH
165.67 192.89 214.64 241.38 261.64
GENERATION
CAPACITY SLDC Charges
FINANCIAL
YEAR
Power Allocation between
DISCOMs
As per GO MS No13, Dt:
06.04.2020
Operating
Charges
Annual
Fee
APEPDCL APSPDCL APCPDCL
MW
Rs. MW/
Month
Rs. MW/
Year
34.27% 65.73% -
36.22% 40.44% 23.34%
19504 2146.34 1917.48 2019-20 6684 12820 -
21487 2058.18 2838.01 2020-21 7783 8689 5015
22257 2086.32 3792.02 2021-22 8061 9001 5195
22677 2150.21 4997.87 2022-23 8214 9171 5293
22886 2235.65 6382.27 2023-24 8289 9255 5342
OPEN ACCESS CHARGES (DISCOM)
INTER STATE CHARGES (STBC)
Transmission charges as per APERC Rs. /KW/Month
65.30 76.66 91.36 95.37 94.44
Transmission charges applicable for Intra/Inter state users per MWH
90.69 106.47 126.89 132.46 131.17
Wheeling charges as per APERC Rs. /KVA/Month for EPDCL
13.46 10.98 11.38 11.80 12.22
240.15 232.39 247.55 262.96 279.50
EPDCL Wheeling charges for inter state users per MWH
19.68 16.05 16.64 17.25 17.87
351.10 339.75 361.92 384.44 408.63
Wheeling charges as per APERC Rs. /KVA/Month for SPDCL
7.66 15.51 15.39 15.11 15.17
164.61 220.82 227.14 232.26 240.68
SPDCL Wheeling charges for inter state users per MWH
11.20 22.68 22.50 22.09 22.18
240.65 322.84 332.07 339.56 351.87
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Long Term Transmission Service Agreement
APERC will issue the Multi Year Tariff along with Generators
list along with capacity, approved capacity for DISCOM wise and
Transmission charges & SLDC Charges.
DISCOMs has to pay the amount according to Contacted
Capacity - Transmission Charges & SLDC Operating Charges
Month Wise and SLDC Annual Fee Half Yearly.
DISCOM has to pay the additional Transmission Charges &
SLDC Charges to APTRANSCO, if they Purchase the Power from
other than approved Generators of approved capacity.
After APERC Multi Year Tariff (MYT) issued, APDISCOMS has to
enter Long Term Transmission Service Agreement with APTRANSCO
for the MYT Period for the approved Generators of approved
Capacities.
STU - Commercial Wing (On behalf of APTRANSCO), Chief
General Manager/Commercial/ DISCOM (on behalf of respective
DISCOM ) will enter Long Term Transmission Service Agreement
(LTTSA) as per APERC approve format.
Long Term Transmission Service Agreement
Executive Director (Finance) (FI Module) will raise the
following invoices every month in consultation with STU
– Commercial Wing to respective DISCOM.
1) invoice for Transmission charges. (Monthly)
(surcharge is not applicable)
2) invoice for SLDC Operating Charges. (Monthly)
due date 10 days. Surcharge will be levied, if due
date exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April
1st & October 1st. Due date 10 days. Surcharge
will be levied, if due date exceeds.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of intra LTOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of LTOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Types of OA Users
1) Captive
2) Group Captive
3) Third Party
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee.
Rs 10,000/- fee shall be payable in favour of
“FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either
through the DD or RTGS.
APTRANSCO Nodal Officer is
STU – CHIEF ENGINEER COMMERCIAL
Field Feasibility Report
Application Received by STU-CE Commercial is the
initiation of Activity.
STU-CE Commercial will address a letter to Generator
Located area of Chief Engineer/Zone & Chief General
Manager / DISCOM and Consumer Located area of Chief
Engineer/Zone & Chief General Manager / DISCOM for
feasibility if Consumer is connected to APTRANSCO
substation at 33KV level and above Voltage level and copy
to respective SE/OMC & SE/ Operations/ DISCOM. if
Consumer connected at 33KV or 11KV at Distribution
network, feasibility was requested the concerned
CGM/DISCOM and SE/Operation/Dist.
Respective SE/OMCs, SE/Operation/DISCOM, Chief
Engineer/ Zones & CGM/DISCOMs will send the feasibility
report to STU-CE Commercial.
Intra LTOA Approval & Agreement Process
STU-CE Commercial will initiate the LTOA approval
and circulate the note to Full APTRANSCO Board based
on the field feasibilities received.
After approval of Board, LTOA approval will be given
to OA user with some conditions & Payments and
request for enter in to agreement as per APERC format.
The OA user has to met the conditions & Payments.
The Generator & Consumer both at 33KV or 11KV
Within DISCOM, LTOA agreement will be done between
DISCOM & OA User.
For others LTOA tripartite agreement will done
between APTRANSCO, DISCOM & OA User.
Intra State LTOA Payment Process
ED/Finance (FI Module) will raise the following invoices
every month in consultation with ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds. ( Not applicable for with in DISCOM)
2) invoice for SLDC Operating Charges. (Monthly) due
date 10 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st
& October 1st. Due date 10 days. Surcharge will be
levied, if due date exceeds.
Terms & Conditions of LTOA approval
1) A Long Term Open Access agreement with APTRANSCO,
DISCOMs (Consumer area) & OA user in the APERC
approved format.
2) The date of commencement of Open Access for the capacity
will be as mentioned in the Agreement.
3) The company shall pay monthly Transmission & SLDC
charges to APTRANSCO, Wheeling charges to Respective
DISCOM as per the Tariff Orders issued by APERC from time
to time irrespective of actual energy injected and also bear
losses in kind.
4) The company shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
5) The company has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of intra STOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of STOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Types of OA Users
1) Captive
2) Group Captive
3) Third Party
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee.
Rs 1000/- fee shall be payable in favour of “SAO/SLDC,
APTRANSCO” Payable at Hyderabad either through RTGS.
APTRANSCO Nodal Officer is
Chief Engineer (SLDC)
Intra STOA Approval & Agreement Process
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission
network is involved.
4. CGM/DISCOM – for feasibility if Distribution Network
involved.
if the CMD capacity is more than the contracted, the Power
system feasibility is to be obtained.
1) The OA User shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
2) The OA User has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
CE/SLDC will issue STOA approval based on the field
feasibilities received & above amounts received.
Intra STOA Approval & Agreement Process
Any deviation of feasibility, Note file will be circulated
to Full Board for approval.
After approval issued by CE/SLDC, the OA User was
requested for enter in to agreement as per APERC
format, and meet the STU – CE Commercial for enter in
to agreement.
The Generator & Consumer both at 33KV or 11KV
Within DISCOM, STOA agreement will be done between
DISCOM & OA User.
DISCOM will Furnish the Agreement to STU-CE
Commercial, CE/SLDC & ED/Finance & SAO/SLDC.
For others STOA tripartite agreement will done
between APTRANSCO, DISCOM & OA User.
Intra State STOA Payment Process
ED/Finance (FI Module) will raise the following invoices
every month in consultation with ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds. ( Not applicable for with in DISCOM)
2) invoice for SLDC Operating Charges. (Monthly) due
date 10 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Monthly
proportionate). Due date 10 days. Surcharge will be
levied, if due date exceeds.
Terms & Conditions of STOA approval
1) A Short Term Open Access agreement with APTRANSCO,
DISCOMs (Consumer area) & OA user in the APERC
approved format.
2) The Period of Open Access for the capacity will be as
mentioned in the SLDC Approval.
3) The company shall pay monthly Transmission & SLDC
charges to APTRANSCO, Wheeling charges to Respective
DISCOM as per the Tariff Orders issued by APERC from time
to time irrespective of actual energy injected and also bear
losses in kind.
4) The company shall pay two months SLDC charges to
APTRANSCO as security deposit before commencement of
Open Access as per APERC Orders and Regulations from
time to time.
5) The company has to open Letter of Credit towards imbalance
in supply and consumption of electricity for a period of 10
days, before commencement of Open Access to DISCOMs.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Short Term Power Purchases (DISCOM)
Andhra Pradesh Power Coordination Committee
(APPCC – Representative of APDISCOMs) will purchase
the Power from the intra State Pvt Generators based on
the requirement of Power for DISCOM on Day /
Monthly/ Quarterly/Half yearly/Yearly basis (Maximum
One Year) to meet the DISCOM demand in Consultation
with SLDC.
The PPA approval Copy will sent to STU-CE
Commercial, CE/SLDC and Executive Director (Finance).
As per the PPA with Generators, The Generator has
to pay the Transmission & SLDC Charges to
APTRANSCO.
Short Term Power Purchases (DISCOM)
ED/Finance (FI Module) will raise the following invoices
every month for the PPA period in consultation with
CE/Commercial/APPCC, CE/SLDC and ED/HRD & Plg.
1) invoice for Transmission charges. (Monthly) if the
Generator having a PPA for differential capacities for
different periods in a month, calculate the proportionate
transmission charges. due date 15 days. Surcharge will
be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) if the
Generator having a PPA for differential capacities for
different periods in a month, the charges will be levied
fully (Whole month) on a Highest capacity of a Particular
month. due date 15 days. Surcharge will be levied, if due
date exceeds. due date 10 days. Surcharge will be
levied, if due date exceeds.
3) Invoice for SLDC Annual Fee. (monthly). Calculation as
per point no1 above (Transmission Charges). Due date
10 days. Surcharge will be levied, if due date exceeds.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of Inter LTOA Application
Either Generator or Consumer (Open Access User) may
eligible for submission of inter state LTOA Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or Multi
Generators.
Inter State LTOA Application
The OA Users has to submit the detailed application
along with necessary Documents along with requisite fee to
Power Grid.
Power Grid will request the concerned STU for NOC.
The OA User has to pay the Prescribed fee in favour of
“FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either
through the DD or RTGS.
APTRANSCO Nodal Officer is STU-CE Commercial
Inter State LTOA Approval Process
The Fee Details as follows
1. Up to 100 MW : Rs 2.00 Lakhs
2. 101 MW to 500 MW : Rs 3.00 Lakhs
3. 501 MW to 1000 MW : Rs 6.00 Lakhs
4. Above 1000MW : Rs 9.00 Lakhs
STU-CE Commercial will address a letter to OA User
Located area of Chief Engineer/Zone and copy to respective
SE/OMC in case of OA user.
Respective SE/OMC & Chief Engineer/ Zones will be
sent the feasibility report to STU-CE Commercial.
STU-CE Commercial will initiate the inter state LTOA
approval and circulate the note to Full APTRANSCO Board
based on the field feasibilities received through CE/PS &
CE/SLDC.
After approval of Board, NOC approval will be given to
PGCIL.
Inter State LTOA Approval & Payment
The Inter state LTOA Approval will be issued by PGCIL
under intimation to APTRANSCO.
STU-CE Commercial, CE/SLDC & SAO/SLDC has to
collect each Interstate LTOA Approvals from PGCIL web Site.
Based on the Inter State LTOA approval, ED/Finance (FI
Module) will raise the following invoices every month in
consultation with STU-CE Commercial,
CE/Commercial/APPCC & CE/SLDC to OA User.
1) invoice for Transmission charges. (Monthly) due date
15 days. Surcharge will be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) due
date 15 days. Surcharge will be levied, if due date
exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st &
October 1st. Due date 10 days. Surcharge will be
levied, if due date exceeds.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of Inter MTOA Application
Either Generator or Consumer (Open Access User)
may eligible for submission of inter state MTOA
Application.
Single Generator can supply to single or Multi
Consumers.
Single Consumer can take supply from single or
Multi Generators.
Inter State MTOA Application
The OA Users has to submit the detailed application
(Format-1 & Format-2) along with necessary Documents
along with requisite fee to Power Grid. Same time the OA
user has to submit the Application to STU along with
requisite fee. The OA User shall furnish the valid PPA for
the application period.
Submission of Inter MTOA Application
The OA User has to pay the Prescribed fee in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS only.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
The Fee Details as follows
1. Up to 100 MW : Rs 1.00 Lakhs
2. 101 MW to 500 MW : Rs 2.00 Lakhs
3. 501 MW to 1000 MW : Rs 3.00 Lakhs
4. Above 1000MW : Rs 4.00 Lakhs
CE/SLDC will address a letter to OA User Located
area of respective CGM/DISCOM & Chief Engineer/Zone
(in case of EHT) for feasibility.
Respective CGM/DISCOM & Chief Engineer/ Zones
will be sent the feasibility report to CE/SLDC.
Inter State MTOA Approval at SLDC
if the CMD capacity is more than the contracted, the Power system
feasibility is to be obtained.
If PPA was not submitted along with the application, the Consent/
Concurrence/NOC will be rejected.
1) The OA User shall pay two months SLDC charges to APTRANSCO
as security deposit before commencement of Open Access as per
APERC Orders and Regulations from time to time.
2) The OA User has to open Letter of Credit towards imbalance in
supply and consumption of electricity for a period of 10 days,
before commencement of Open Access to DISCOMs.
CE/SLDC will initiate the Inter State MTOA approval and circulate
the note to Full APTRANSCO Board based on the field feasibilities
received and amounts received.
After approval of Board, NOC will be issued to PGCIL with
standard format-3 for inter state MTOA.
SLDC shall convey its concurrence to the applicant (New OA User)
With in 10 Working days.
The start date of MTOA shall not be earlier than 5 months and
later than 1 year from the last day of the month in which application
has been made.
Inter State MTOA Approval & Payment
The Inter state MTOA Approval will be issued by PGCIL
under intimation to APTRANSCO.
STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect
each Interstate MTOA Approvals from PGCIL.
Based on the Inter State MTOA approval, ED/Finance (FI
Module) will raise the following invoices every month in
consultation with STU-CE Commercial, CE/Commercial/APPCC
& CE/SLDC to OA User.
1) invoice for Transmission charges. (Monthly) due date 15
days. Surcharge will be levied, if due date exceeds.
2) invoice for SLDC Operating Charges. (Monthly) due date
15 days. Surcharge will be levied, if due date exceeds.
3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st &
October 1st. Due date 10 days. Surcharge will be levied,
if due date exceeds.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of Inter STBC Application
Either Generator or Consumer (Open Access User)
may eligible for submission of Inter State STOA
Application.
Generator / Consumer / Trader Treated as OA User.
The OA Users has to submit the detailed application
(Format-1 & Format-2 of CERC) along with necessary
Documents along with requisite fee.
Rs 5,000/- fee shall be payable in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
INTER STATE STBC APPROVAL PROCESS
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission network is
involved.
4. CGM/DISCOM – for feasibility if Distribution Network involved.
Payments to be done
1) The OA User shall pay two months SLDC charges to APTRANSCO
as security deposit before commencement of Open Access as per
APERC Orders and Regulations from time to time.
2) The OA User has to open Letter of Credit towards imbalance in
supply and consumption of electricity for a period of 10 days,
before commencement of Open Access to DISCOMs.
CE/SLDC will issue Consent/ Concurrence for Inter State STOA
(Bilateral) approval to OA User with Standard Format-3 based on the
field feasibilities received & above amounts received.
As per the CERC Procedure Consent/ Concurrence shall be issued
as for the schedules
1. With in 7 days for New OA User
2. With in 3 days for Already availed OA user.
Inter State STBC Approval & Payment
SRLDC will issue approvals for Inter state STOA (Bilateral).
STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect
each Interstate STOA Approvals (Bilateral) from SRLDC web
Site.
SRLDC Will Pay the Month wise Amounts on 1st of
upcoming month for the last month for Bilateral Approvals to
FA&CCA(R&A).
ED/Finance (FI Module) will Verify the Amounts received
towards each approval regarding Transmission Charges, SLDC
Charges and total amount received from SRLDC, on monthly
basis in consultation with ED/HRD & Plg.
1) Transmission charges based on the MWH Transmitted.
2) SLDC Charges Rs 1000/- per day per Transactions of
OA user.
Any deviation of payments STU-CE Commercial will intimate
for discrepancies to SRLDC under copy to ED/Finance.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984
Submission of Inter STBC Application
Either Generator or Consumer (Open Access User)
may eligible for submission of Inter State LTOA
Application.
Generator / Consumer / Trader Treated as OA User.
The OA Users has to submit the detailed application
(Format-1 & Format-2 of CERC) along with necessary
Documents along with requisite fee.
Rs 5,000/- fee shall be payable in favour of
“SAO/SLDC, APTRANSCO” Payable at Hyderabad
through RTGS.
APTRANSCO Nodal Officer is Chief Engineer (SLDC)
Inter State STBC Approval Process
The Application Directly reach to following Authorities
1. CE/SLDC for Processing of STOA Application
2. SAO/SLDC for payment receipt
3. CE/Zone/APTRANSCO – for feasibility if Transmission
network is involved.
4. CGM/DISCOM – for feasibility if Distribution Network
involved.
if the CMD capacity is more than the contracted, the
Power system feasibility is to be obtained.
CE/SLDC will issue NOC for Inter State STOA
(Collective) approval to OA User with Standard Format-3
based on the field feasibilities received & above amounts
received.
As per the CERC Procedure NOC shall be issued as for
the schedules
1. With in 7 days for New OA User
2. With in 3 days for Already availed OA user.
Inter State STBC Approval & Payment
IEX/PXI will send day wise Transactions on weekly
basis to ED/HRD & Plg through mail for reconciliation.
IEX/PXI Will Pay the Day wise Amounts.
ED/Finance (FI Module) will Verify the Amounts
received towards each Transactions regarding
Transmission Charges, SLDC Charges, Wheeling charges
and total amount received from IEX/PEX, on monthly basis
in consultation with STU - CE Commercial.
1) Transmission charges based on the MWH
Transmitted.
2) SLDC Charges Rs 1000/- per day per Transactions
of OA user.
Any deviation of payments STU-CE Commercial will
intimate for discrepancies to IEX/PEX under copy to
ED/Finance.
GOPALA KRISHNAPALEPU
gkpalepu@gmail.com,
Mobile:9440336984

More Related Content

Similar to 11. Open Access- Intra State, Inter State.pdf

Market Based Criteria for Congestion Management and Transmission Pricing
Market Based Criteria for Congestion Management and Transmission PricingMarket Based Criteria for Congestion Management and Transmission Pricing
Market Based Criteria for Congestion Management and Transmission PricingIJERA Editor
 
bidding strategies in indian restructured power market
bidding strategies in indian restructured power marketbidding strategies in indian restructured power market
bidding strategies in indian restructured power marketKomal Nigam
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaAmitava Nag
 
Analytical review of loss reduction techniques in indian power distribution s...
Analytical review of loss reduction techniques in indian power distribution s...Analytical review of loss reduction techniques in indian power distribution s...
Analytical review of loss reduction techniques in indian power distribution s...eSAT Publishing House
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxmsounak95
 
Energy consumers' rights and the EU legislation
Energy consumers' rights and the EU legislationEnergy consumers' rights and the EU legislation
Energy consumers' rights and the EU legislationenergydialog
 
Electricity Reforms - An_Overview
Electricity Reforms - An_OverviewElectricity Reforms - An_Overview
Electricity Reforms - An_OverviewNzar Mohammad
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
01012010 demand response
01012010 demand response 01012010 demand response
01012010 demand response miguelazo84
 
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptx
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptxRPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptx
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptxPoojaAnupGarg
 
Wind Energy Business Case PowerGenz
Wind Energy Business Case PowerGenzWind Energy Business Case PowerGenz
Wind Energy Business Case PowerGenzJohn Chaimanis
 
Unit_5_Tariff_&_Power_Factor_Improvement.pdf
Unit_5_Tariff_&_Power_Factor_Improvement.pdfUnit_5_Tariff_&_Power_Factor_Improvement.pdf
Unit_5_Tariff_&_Power_Factor_Improvement.pdfhomanathmore
 

Similar to 11. Open Access- Intra State, Inter State.pdf (20)

Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Restructuring
RestructuringRestructuring
Restructuring
 
Prakhar report
Prakhar reportPrakhar report
Prakhar report
 
Market Based Criteria for Congestion Management and Transmission Pricing
Market Based Criteria for Congestion Management and Transmission PricingMarket Based Criteria for Congestion Management and Transmission Pricing
Market Based Criteria for Congestion Management and Transmission Pricing
 
bidding strategies in indian restructured power market
bidding strategies in indian restructured power marketbidding strategies in indian restructured power market
bidding strategies in indian restructured power market
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in India
 
OPEN ACCESS REGULATION
OPEN ACCESS REGULATIONOPEN ACCESS REGULATION
OPEN ACCESS REGULATION
 
Analytical review of loss reduction techniques in indian power distribution s...
Analytical review of loss reduction techniques in indian power distribution s...Analytical review of loss reduction techniques in indian power distribution s...
Analytical review of loss reduction techniques in indian power distribution s...
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptx
 
COMPETITIVE MARKET
COMPETITIVE MARKET COMPETITIVE MARKET
COMPETITIVE MARKET
 
Energy consumers' rights and the EU legislation
Energy consumers' rights and the EU legislationEnergy consumers' rights and the EU legislation
Energy consumers' rights and the EU legislation
 
CAPSTONE FINAL VERSION
CAPSTONE FINAL VERSIONCAPSTONE FINAL VERSION
CAPSTONE FINAL VERSION
 
Electricity Reforms - An_Overview
Electricity Reforms - An_OverviewElectricity Reforms - An_Overview
Electricity Reforms - An_Overview
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
A1070108
A1070108A1070108
A1070108
 
01012010 demand response
01012010 demand response 01012010 demand response
01012010 demand response
 
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptx
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptxRPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptx
RPS PPT UNIT-1ccvbvbbbvbvbvbvbbcvbvc.pptx
 
Wind Energy Business Case PowerGenz
Wind Energy Business Case PowerGenzWind Energy Business Case PowerGenz
Wind Energy Business Case PowerGenz
 
Ai24238246
Ai24238246Ai24238246
Ai24238246
 
Unit_5_Tariff_&_Power_Factor_Improvement.pdf
Unit_5_Tariff_&_Power_Factor_Improvement.pdfUnit_5_Tariff_&_Power_Factor_Improvement.pdf
Unit_5_Tariff_&_Power_Factor_Improvement.pdf
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

11. Open Access- Intra State, Inter State.pdf

  • 2.  The Power Sector in India has undergone a plethora of reforms in the last two decades.  Introduction of competition has been one of the main aims of reform in the electricity sector in India.  One of the most important steps taken towards achieving this was the introduction of open access in the Electricity Act, 2003, where large consumers have access to the Transmission and Distribution (T&D) network to obtain electricity from suppliers other than the local electricity distribution company (DISCOM). INTRODUCTION OBJECTIVE  The objective of open access was to provide opportunity to energy intensive industry and commercial establishments to source electricity directly from the market and manage costs to remain competitive.  Open Access was to also improve the economic health of the Distribution Licensees by reducing power procurement at higher marginal cost so that the non-open access retail consumers of the Distribution Licensees would not get unduly burdened.
  • 3.  Electricity Act 2003 (sub-section 2 of section 42) lay down provisions for a power market and competition wherein electricity consumers now have the right to procure power from the supplier of their choice other than their distribution company.  For example, under open-access a consumer in Telangana has right to select the source of supply form any generator. This generator may be generating power in Telangana or any other state in India. Open Access, as per Electricity Act 2003  “Non-discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the Appropriate Commission”.  Open Access allows large and heavy users of powers i.e. those with 1 megawatt (MW) and above connected load to buy cheaper power from the open market.  The idea is that the customers now able to choose from a number of competing power companies like GENCOs, CPSU, IPPs, Private. Licensees, Excess Captive from captive power plants instead of being forced to buy electricity from their existing electric utility monopoly. OA WITH EA 2003
  • 4. 1. Competitive Pricing  Open Access was introduced in the Electricity Act to bring in competition into the sector, thereby benefitting the end consumer.  Over the years, it has acted as a catalyst in bringing reforms into the sector by benefitting the players across the spectrum of value-chain from generators to suppliers to electricity traders to the end consumers.  Open Access will ease the power shortage since a number of power producers like Solar energy companies can now transmit power from their solar parks to different load centers.  Once the consumers are given the choice to purchase power from the open market, it will automatically lead to competitive pricing of electricity making electricity cost go down. 2. Regular electricity supply  It helps the industrial & commercial consumers by ensuring regular electricity supply at competitive rates.  It helps large consumers particularly the sick textile, cement and steel industrial units by ensuring regular supply of electricity at competitive rates and boost business of power bourses. PROS AND CONS OF OPEN ACCESS
  • 5. 3. Help Consumers to meet RPOs  It also enhances the business of power markets as the open access helps consumers meet their Renewable Purchase Obligations (RPOs) as well. 4. Exposure to Grid Risks  In open access, eligible consumer can avail the benefits of cheaper green solar power by either purchasing through the rooftop solar installation in its premises or buying from an offsite solar farm.  While open access does away with limitations of rooftop solar such as scalability and high capital expenditure, it is often exposed to unpredictable grid risks. 5. Appropriate utilization of existing infrastructure (T&D)  Existing Transmission and Distribution Infrastructure can be used to avail the open access.  In open access, this will enable number of players utilizing these infrastructure and transmit power from generation to the load center.  This will mean utilization of existing infrastructure and easing of power shortage.  Trading, now a licensed activity and regulated will also help in innovative pricing which will lead to competition resulting in lowering of tariffs. PROS AND CONS OF OPEN ACCESS
  • 6.  Open Access, rights governed in India by Electricity Act 2003, can be classified as under on the basis of location of the purchasing and selling entities: Types of Open Access Users 1. Intra State (With in the state) 2. Inter State (State to State) Intra State Users 1. Short Term (STOA) up to 1 year 2. Medium Term (MTOA) - AP & TS Not Contemplated 3. Long Term (LTOA) 2 years and above Inter State Users 1. Short Term (STOA) – Maximum one month. 2. Medium Term (MTOA) – 3 months to 5 Years (earlier 3 Years) 3. Long Term (LTOA) – 12 Years to 25 Years Power Markets- Collective Transactions 1. Indian Energy Exchange Limited – IEX 2. Power Exchange India Limited – PXI Minimum Open access allowed for 1MW OPEN ACCESS CLASIFICATION
  • 7.  When the Purchasing and selling entities belong to same state then it is called as an Intra-state transaction. In this case, the open access charges comprising Transmission Losses and Charges Wheeling losses and Charges (if applicable) and cross-subsidy of that particular state are applicable.  In Intra-State Open Access State Electricity Regulatory Commission (SERC) regulations are followed.  Wherein purchase rights can be categorized.  Duration of which depends on the respective state open access regulations. Intra State Purchases for DISCOMs 1. Short Term (STPP) up to 1 year 2. Medium Term (MTOA)  AP & TS Not Contemplated 3. Long Term (LTTSA) with GENCO 2 years and above 4. Long Term (LTOA) with Other Generators 2 years and above Intra State OA Users 1. Short Term (STOA) up to 1 year 2. Medium Term (MTOA) - AP & TS Not Contemplated 3. Long Term (LTOA) 2 years and above INTRA STATE OPEN ACCESS
  • 8.  When the Purchasing and selling entities belong to different states then it is called as an Inter-state transaction.  In this case, apart from the open access charges applicable in intra- state transactions, Point-of-Connection (POC) charges and losses of the regional grids where the buyer and seller are located are also applicable.  In Inter State Open Access Central Electricity Regulatory Commission (CERC) regulations are to be followed Inter State Open Access 1. Short Term Open Access (STBC): Open Access allowed for the period of less than one month. Bilateral: Power Purchase Agreement (PPA) is a contract between the seller and the consumer. POSOCO is the Coordinator. Collective: Traded through Power Exchanges by Exchange Members/Traders. 2. Medium Term Open Access (MTOA): Open Access allowed for a period of 3 months to 5 years. (earlier 3 Years) 3. Long Term Open Access (LTOA): Open Access allowed for a period of 12 years to 25 years. INTER STATE OPEN ACCESS
  • 9.  Renewable Energy based transactions under intra-state open- access is more convenient than inter-state open-access.  in order to promote Renewable Energy, many state provide various concessional provisions like concessional Wheeling and Transmission charges, Banking facility benefits, Electricity Tax / Duty Exemptions, Waiver or Discount in Cross-Subsidy-Charges etc.  These concessional provisions reduce the cost of transaction significantly and allow RE generators to offer better commercial terms to consumers. INTRA VS INTER OPEN ACCESS
  • 10. OPEN ACCESS CHARGES  Electricity consumers can make use of the existing Transmission and Distribution infrastructure after paying appropriate charges determined by their respective State Electricity Regulatory Commissions (SERCs).  A supportive regulatory regime from the state electricity authorities combined with better grid stability can make long-term open access projects viable.  These changes will facilitate more projects from the renewable energy companies who are taking huge upfront risks at present and will definitely upgrade the state of power trading in the country.  These charges against the usage of Transmission and Distribution infrastructure can vary from state to state and are lesser in states with stable grid and favorable regulatory regime.  In case of solar power, the state-wise open access charges can vary from as low as Rs. 0.2/KWh to Rs.1.5/KWh.  There are several charges to be paid by Open Access Consumers to Distribution Licensee, Transmission Licensees and other related entities, other than the power purchase cost paid to the generator or supplying entity.  Apart from below charges the open access consumers has also to fulfill the renewable purchase obligation (RPO), in which they have to purchase a part of their total consumption through electricity generated from renewable energy.
  • 11. OPEN ACCESS CHARGES  Connectivity Charges (at the time of Application)  Point of Connection (PoC) Charges (CTU)  Transmission Charges (STU)  Transmission Losses  Wheeling Charges (DISCOM)  Wheeling Losses  Cross Subsidy Surcharge (DISCOM)  RLDC Charges (POSOCO)  SLDC Charges.  In case of AP & TS  SLDC Charges Bifurcated as  SLDC Operating Charges  SLDC Annual Fee.
  • 12. OPEN ACCESS  The Buyer and Seller of Electricity can opt for either Collective or Bilateral Transactions.  Besides minor changes in the meter installed, Open Access transactions are essentially managed through energy accounting at the state level.  EBC established under Control of SLDC for Energy Accounting.  Thus, a Consumer buying Power from Open Access will see the transaction accounted for in its monthly bill.
  • 13. COLLECTIVE TRANSACTIONS  In case of Collective Transactions the Electricity is traded through Power Exchanges by Exchange Members/Traders for a very small margin fixed by commission.  Power Exchange transactions are transactions carried out over an electronic platform.  Currently India has two operating Power Exchanges (PXs) 1. Indian Energy Exchange (IEX) and 2. Power Exchange India (PXI).  At Power Exchanges Consumers can buy/sell electricity on day-ahead/week-ahead basis or for particular time period in a day.  Buyer/Seller will be bidding for electricity cost for particular time period and for each time period price at which electricity is determined by market.
  • 14. BILATERAL TRANSACTIONS  Power Purchase Agreement (PPA) is a contract between the Seller and the Consumer for buying power at mutually agreed tariff for a predetermined number of years.  The PPA defines all of the commercial terms for the sale of electricity between the two parties, including when the project will begin commercial operation, schedule for delivery of electricity, penalties for under delivery, payment terms, and termination clauses.  A significant quantum of power is still traded through bilateral transactions.  Many of the leading solar players under the OPEX model in India are resorting to bilateral agreements for tariff determination with commercial and industrial clients.
  • 15. BILATERAL VS COLLECTIVE  Adopting a combination of Bilateral transaction and Collective transaction may result in cost savings of sourced energy and long term energy security because bilateral mode of transaction brings volumetric and price certainty for a relatively longer duration while sourcing power from Power Exchanges provides advantages such as better price discovery, risk mitigation from counter-party default.
  • 16. Nodal Agency STU SLDC PGCIL (CTU) PGCIL (CTU) Exit RLDC NLDC Duration 2 Years and above Up to 1 Year 12 Years to 25 Years 3 Months to 5 Years Max One Month NOC / Concurre nce NOC by STU NOC by SLDC Concurr ence by SLDC NOC by SLDC Approval STU Comml. SLDC PGCIL PGCIL Exit RLDC NLDC Agreeme nt STU Comml. STU Comml. PGCIL PGCIL OA ACTIVITY AUTHORITY
  • 17. Info Injection / Entry Point Voltage Consumption / Exit Point Voltage Transmission Charges & SLDC Charges Wheeling charges at entry/Exit Case-1 DISCOM-A or B EHT Voltage DISCOM-A or B EHT Voltage Applicable NA Case-2 DISCOM-A EHT Voltage DISCOM-A 33KV or 11KV Applicable DISCOM-A 33KV or 11KV Entry & Exit Vice-Versa Case-3 DISCOM-A EHT Voltage DISCOM-B 33KV or 11KV Applicable DISCOM-B 33KV or 11KV Case-4 DISCOM-A 33KV or 11KV DISCOM-B EHT Voltage Applicable DISCOM-A 33KV or 11KV Case-5 DISCOM-A 33KV Voltage DISCOM-B 33KV Voltage Applicable DISCOM-B 33KV Case-6 DISCOM-A 11KV Voltage DISCOM-B 11KV Voltage Applicable DISCOM-B 11KV Case-7 DISCOM-A 33KV Voltage DISCOM-B 11KV Voltage Applicable DISCOM-B 11KV Case-8 DISCOM-A 11KV Voltage DISCOM-B 33KV Voltage Applicable DISCOM-A 11KV Case-9 DISCOM-A 33KV or 11KV DISCOM-A 33KV or 11KV Only SLDC Charge (With in DISCOM) DISCOM-A 33KV or 11KV (Lower Voltage ) INTRA STATE OA CHARGES (LTOA & STOA)
  • 18. Info Entry or exit Point in State Voltage Inter State Transmission Charges Transmission Charges & SLDC Charges Wheeling charges at entry/Exit Case-1 Entry/Injection at EHT Voltage The Inter State Open Access User has to Pay the following Charges to PGCIL. 1.PoC Injection Charges of AP i.e. Rs. Per MW Per Month in case of Power Injection at AP. 2. PoC With drawl Charges of AP i.e. Rs. Per MW Per Month in case of Power Withdrawn in AP. 3. Grid Support Charges to POSOCO Transmission Charges to APTRANSCO i.e Rs. Per KW per Month as approved by APERC from time to time. SLDC Charges to APTRANSCO i.e. Annual Fee Rs. Per MW per Year & Operating Charges Rs. Per MW Per Month NA Case-2 Exit/ Withdrawn at EHT Voltage NA Case-3 Entry/Injection at 33KV or 11KV Voltage Particular DISCOM 33KV or 11KV wheeling Charges for exit or entry Case-4 Exit/ Withdrawn at 33KV or 11KV Voltage INTER STATE OA CHARGES (LTOA & MTOA)
  • 19. Info Entry or exit Point in State Voltage Inter State Transmission Charges Transmission Charges & SLDC Charges Wheeling charges at entry/Exit Case-1 Entry/Injection at EHT Voltage The Inter State Open Access User has to Pay the following Charges to PGCIL. 1.PoC Injection Charges of AP i.e. Paisa per Unit in case of Power Injection at AP. 2. PoC With drawl Charges of AP i.e. Paisa per Unit in case of Power With drawn in AP. 3. Grid Support Charges to POSOCO Transmission Charges of AP i.e Rs. Per MWH. SLDC Charges Rs 1000/- per day per Transactions of OA user. NA Case-2 Exit/ Withdrawn at EHT Voltage NA Case-3 Entry/Injection at 33KV or 11KV Voltage Particular DISCOM 33KV or 11KV wheeling Charges for exit or entry i.e. Rs. Per MWH. Case-4 Exit/ Withdrawn at 33KV or 11KV Voltage INTER STATE OA CHARGES (STBC)
  • 20. INTER STATE PoC CHARGES
  • 22.  Transmission of Power From Generator to Consumer using Utility Network.  Transmission charges will be collected if Open access user utilized the Transmission network.  Wheeling charges will be collected if Open access user utilized the Distribution network.  Within DISCOM, Generator & Consumer both at 33KV or 11KV, only wheeling charges applicable & Transmission Charges not applicable.  Grid Supporting (SLDC) Charges will be collected for all open Access Users.  Regional Network charges will be collected if Open access user utilized the interstate network.  As per APERC Guidelines Nodal Organization is State Transmission Utility (STU-APTRANSCO) OPEN ACCESS
  • 23. TRANSMISSION CHARGES (TRC) Transmission charges as per APERC Rs. /KW/Month 119.28 138.88 154.54 173.79 188.38 65.30 76.66 91.36 95.37 94.44  Transmission charges will be collected if Open access user utilized the Transmission network.  Minimum Capacity Allowed for 1MW for Open Access.  The same is exempted for Renewable Energy Generators.  Transmission Charges are Rs. KW/Month.  In case of OA Started & end in between a Month Transmission Charges Applicable for OA Period days only.
  • 24. SLDC OPERATION CHARGES (SOC) SLDC Operating charges as per APERC Rs. /MW/Month 2146.34 2058.18 2086.32 2150.21 2235.65 2378.11 2209.34 2247.62 2300.31 2342.73  Grid Supporting (SLDC) Charges will be collected for all open Access Users.  Minimum Capacity Allowed for 1MW for Open Access.  Rounding to Next Digit MW in case of Partial MWs.  SLDC Operating Charges are Rs. MW/Month.  In case of OA Used  per Hour or per day or per week or per 2 weeks or per 3 weeks or per month, i.e irrespective of no of Hours/Days in a month, The SLDC Charges will be collected Per month only.  In case of Different capacities observed in a month. Highest MW will be charged for a Particular Month for SLDC Operating Charges.
  • 25. SLDC ANNUAL FEE (SAF) SLDC Annual Fee as per APERC Rs. /MW/Year (Annum) 1917.48 2838.01 3792.02 4997.87 6382.27 2535.65 3092.68 3533.18 3995.39 4214.27  Grid Supporting (SLDC) Charges will be collected for all open Access Users.  Minimum Capacity Allowed for 1MW for Open Access.  Rounding to Next Digit MW in case of Partial MWs.  SLDC Annual Fee is Rs. MW/Year (Annum).  In case of OA Started & end in between a Month SLDC Annual Fee Applicable for OA Period days only.  This is to be collected for 6 Months in advance.  These are to be collected in April & October.  Date Start of OA in between Year, the amount to be collected up to either up to April or October. Similar case for OA ending period.
  • 26. TRANSMISSION CHARGES-STAT (TRS) Transmission charges-Stat as per APERC Rs. /KW/Month 119.28 138.88 154.54 173.79 188.38 65.30 76.66 91.36 95.37 94.44  Transmission charges will be collected if Open access user utilized the Transmission network.  Due to Govt of AP Policy and APERC Tariff, Transmission Charges are exempted for Wind, Solar and Mini Hydel Power Plants (Renewable Power Plants to encourage the business).  How Much Transmission Charges given exemption is to be furnished to Govt of AP and APERC. For the Purpose this condition was created.
  • 27. EXIT CHARGES (TRE, SOE, SAE)  The Open Access User can exit or Discontinue the Open Access Agreement at any time, as per his convenient for Full Capacity or Partial Capacity.  In case of LTOA or MTOA Users they have to pay the Exit Charges as follows:  25% of Transmission Charges will be applicable for the Balance period with date of exit Price.  100% of SLDC Operating Charges will be applicable for the Balance period with date of exit Price.  100% of SLDC Annual Fee will be applicable for the Balance period with date of exit Price.  In Case of STOA - 100% of above three Charges will be applicable for the Balance period with date of exit Price.
  • 28. TRANSMISSION CHARGES/DAY (TRD)  During the Power Crisis, DISCOMs are procuring the power from various sources to meet the Demand. This is called Short Term Power Purchases (STPP).  Monthly Basis for a period of Months in RTC.  Every Day different capacity for a month.  Particular Days in a Particular Month for no of Months in RTC.  No of Hours in a Day on Particular Dates in Particular Month for no of Months.  The Generators are not covered in MYT Tariff.  The Minimum Transmission Charges will be applicable on Day basis, irrespective of No of Hours in a day STPP Agreement is available.  In case of Monthly Fixed Agreement is there, Monthly Charges will be applicable.
  • 29. TRANSMISSION CHARGES/HOUR (TRH)  Telengana ERC has given directions  if the Short term Power Purchased from OA Generators, No of Hours in a Day on Particular Dates in Particular Month for no of Months, Transmission Charges will be collected per Hour Basis not on daily or monthly basis.  This is applicable for DISCOMs and Short Term Power Purchases (STPP) only to meet the Demand.  However, during the SAP Development, This provision also provided for future requirement. Transmission charges/Hour as per APERC Rs. / MWH 165.67 192.89 214.64 241.38 261.64 90.69 106.47 126.89 132.46 131.17
  • 30. SLDC ANNUAL FEE/DAY (SAD)  During the Power Crisis, DISCOMs are procuring the power from various sources to meet the Demand. This is called Short Term Power Purchases (STPP).  Monthly Basis for a period of Months in RTC.  Every Day different capacity for a month.  Particular Days in a Particular Month for no of Months in RTC.  No of Hours in a Day on Particular Dates in Particular Month for no of Months.  The Generators are not covered in MYT Tariff.  The Minimum SLDC Annual Fee will be applicable on Day basis, irrespective of No of Hours in a day STPP Agreement is available.  In case of Monthly Fixed Agreement is there, Monthly Charges will be applicable.
  • 31. TRANSMISSION CHARGES/HOUR (TBC)  Inter State Short Term Bilateral & Collective (STBC), the Transmission Charges will be applicable for Hourly Basis.  Bilateral Payments will be made by POSOCO.  Collective Payments will be made by IEX and PXI.  In case SERC has not determined the transmission charges, the charges for use of respective state network shall be payable at the rate of Rs 80.00/MWH Inter State Transmission charges/Hour Rs. /MWH 165.67 192.89 214.64 241.38 261.64 90.69 106.47 126.89 132.46 131.17
  • 32. SLDC CHARGES/DAY (SBC)  Interstate STOA users either bilateral or collective shall pay SLDC Charges Rs 1000/- per day per Transactions of OA user.  Bilateral Payments will be made by POSOCO.  Collective Payments will be made by IEX and PXI.  IEX will pay the Charges in one day advance based on the schedule. Weekly calculation sheets will be mailed.  POSOCO Weekly Payments and Monthly Calculations sheets will be mailed. Inter State SLDC charges/Day Rs. Per Day
  • 33. CONVERSION PRICES OF OPEN ACCESS 2019-2020 Rs. Per MWH 165.67 SLDC Charges Rs 1000/- per day per Transactions of OA user in case of STOA Bilateral (POSOCO) & Collective (IEX/PXI).
  • 34. TRANSMISSION CHARGES FINANCIAL YEAR SLDC CHARGES OPERATING CHARGES ANNUAL FEE Rs. /KW/Month Rs. MW/Month Rs. MW/Year 65.30 2014-15 2378.11 2535.65 76.66 2015-16 2209.34 3092.78 91.36 2016-17 2247.62 3533.18 95.37 2017-18 2300.31 3995.39 94.44 2018-19 2342.73 4214.27 OPEN ACCESS CHARGES Transmission charges as per APERC Rs. /KW/Month 65.30 76.66 91.36 95.37 94.44 Transmission charges applicable for Intra/Inter state users per MWH 90.69 106.47 126.89 132.46 131.17
  • 35. DISCOM WISE – CHARGES APPLICABLE CAPACITY TRANSMISSION CHARGES APPLICABLE CAPACITY SLDC OPERATING CHARGES APPLICABLE CAPACITY SLDC ANNUAL FEE APPLICABLE CAPACITY APEPDCL APSPDCL FINANCIAL YEAR APCPDCL APNPDCL 3332 4697 2014-15 9714 3347 3707 5225 2015-16 10806 3723 3931 5541 2016-17 11460 3949 4108 5791 2017-18 11977 4127 4284 6038 2018-19 12487 4303 OPEN ACCESS CHARGES (DISCOM)
  • 36. TRANSMISSION CHARGES FINANCIAL YEAR SLDC CHARGES OPERATING CHARGES ANNUAL FEE Rs. /KW/Month Rs. MW/Month Rs. MW/Year 119.28 2019-20 2146.34 1917.48 138.88 2020-21 2058.18 2838.01 154.54 2021-22 2086.32 3792.02 173.79 2022-23 2150.21 4997.87 188.38 2023-24 2235.65 6382.27 OPEN ACCESS CHARGES Transmission charges as per APERC Rs. /KW/Month 119.28 138.88 154.54 173.79 188.38 Transmission charges applicable for Intra/Inter state users per MWH 165.67 192.89 214.64 241.38 261.64
  • 37. PEAK DEMAND TRANS MISSION CHARGES FINANCIAL YEAR SLDC CHARGES Operating Charges Annual Fee Generation Capacity MW Rs. /KW/ Month Rs. MW/ Month Rs. MW/ Year MW AP EASTERN POWER DISTRIBUTION COMPANY LIMITED 3792 119.28 2019-20 2146.34 1917.48 6684 4081 138.88 2020-21 2058.18 2838.01 7364 4401 154.54 2021-22 2086.32 3792.02 7627 4755 173.79 2022-23 2150.21 4997.87 7771 5149 188.38 2023-24 2235.65 6382.27 7843 AP SOUTHERN POWER DISTRIBUTION COMPANY LIMITED 7275 119.28 2019-20 2146.34 1917.48 12820 7828 138.88 2020-21 2058.18 2838.01 14123 8442 154.54 2021-22 2086.32 3792.02 14630 9122 173.79 2022-23 2150.21 4997.87 14906 9877 188.38 2023-24 2235.65 6382.27 15043 OPEN ACCESS CHARGES (DISCOM)
  • 38. PEAK DEMAND TRANS MISSION CHARGES FINANCIAL YEAR Power Allocation between DISCOMs As per GO MS No13, Dt: 06.04.2020 APEPDCL APSPDCL APCPDCL MW Rs. /KW/ Month 34.27% 65.73% - 36.22% 40.44% 23.34% 11067 119.28 2019-20 3793 7274 - 11909 138.88 2020-21 4313 4816 2780 12843 154.54 2021-22 4652 5194 2998 13877 173.79 2022-23 5026 5612 3239 15026 188.38 2023-24 5442 6077 3507 OPEN ACCESS CHARGES (DISCOM) Transmission charges as per APERC Rs. /KW/Month 119.28 138.88 154.54 173.79 188.38 Transmission charges applicable for Intra/Inter state users per MWH 165.67 192.89 214.64 241.38 261.64
  • 39. GENERATION CAPACITY SLDC Charges FINANCIAL YEAR Power Allocation between DISCOMs As per GO MS No13, Dt: 06.04.2020 Operating Charges Annual Fee APEPDCL APSPDCL APCPDCL MW Rs. MW/ Month Rs. MW/ Year 34.27% 65.73% - 36.22% 40.44% 23.34% 19504 2146.34 1917.48 2019-20 6684 12820 - 21487 2058.18 2838.01 2020-21 7783 8689 5015 22257 2086.32 3792.02 2021-22 8061 9001 5195 22677 2150.21 4997.87 2022-23 8214 9171 5293 22886 2235.65 6382.27 2023-24 8289 9255 5342 OPEN ACCESS CHARGES (DISCOM)
  • 40. INTER STATE CHARGES (STBC) Transmission charges as per APERC Rs. /KW/Month 65.30 76.66 91.36 95.37 94.44 Transmission charges applicable for Intra/Inter state users per MWH 90.69 106.47 126.89 132.46 131.17 Wheeling charges as per APERC Rs. /KVA/Month for EPDCL 13.46 10.98 11.38 11.80 12.22 240.15 232.39 247.55 262.96 279.50 EPDCL Wheeling charges for inter state users per MWH 19.68 16.05 16.64 17.25 17.87 351.10 339.75 361.92 384.44 408.63 Wheeling charges as per APERC Rs. /KVA/Month for SPDCL 7.66 15.51 15.39 15.11 15.17 164.61 220.82 227.14 232.26 240.68 SPDCL Wheeling charges for inter state users per MWH 11.20 22.68 22.50 22.09 22.18 240.65 322.84 332.07 339.56 351.87
  • 43. Long Term Transmission Service Agreement APERC will issue the Multi Year Tariff along with Generators list along with capacity, approved capacity for DISCOM wise and Transmission charges & SLDC Charges. DISCOMs has to pay the amount according to Contacted Capacity - Transmission Charges & SLDC Operating Charges Month Wise and SLDC Annual Fee Half Yearly. DISCOM has to pay the additional Transmission Charges & SLDC Charges to APTRANSCO, if they Purchase the Power from other than approved Generators of approved capacity. After APERC Multi Year Tariff (MYT) issued, APDISCOMS has to enter Long Term Transmission Service Agreement with APTRANSCO for the MYT Period for the approved Generators of approved Capacities. STU - Commercial Wing (On behalf of APTRANSCO), Chief General Manager/Commercial/ DISCOM (on behalf of respective DISCOM ) will enter Long Term Transmission Service Agreement (LTTSA) as per APERC approve format.
  • 44. Long Term Transmission Service Agreement Executive Director (Finance) (FI Module) will raise the following invoices every month in consultation with STU – Commercial Wing to respective DISCOM. 1) invoice for Transmission charges. (Monthly) (surcharge is not applicable) 2) invoice for SLDC Operating Charges. (Monthly) due date 10 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st & October 1st. Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 46. Submission of intra LTOA Application Either Generator or Consumer (Open Access User) may eligible for submission of LTOA Application. Single Generator can supply to single or Multi Consumers. Single Consumer can take supply from single or Multi Generators. Types of OA Users 1) Captive 2) Group Captive 3) Third Party The OA Users has to submit the detailed application along with necessary Documents along with requisite fee. Rs 10,000/- fee shall be payable in favour of “FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either through the DD or RTGS. APTRANSCO Nodal Officer is STU – CHIEF ENGINEER COMMERCIAL
  • 47. Field Feasibility Report Application Received by STU-CE Commercial is the initiation of Activity. STU-CE Commercial will address a letter to Generator Located area of Chief Engineer/Zone & Chief General Manager / DISCOM and Consumer Located area of Chief Engineer/Zone & Chief General Manager / DISCOM for feasibility if Consumer is connected to APTRANSCO substation at 33KV level and above Voltage level and copy to respective SE/OMC & SE/ Operations/ DISCOM. if Consumer connected at 33KV or 11KV at Distribution network, feasibility was requested the concerned CGM/DISCOM and SE/Operation/Dist. Respective SE/OMCs, SE/Operation/DISCOM, Chief Engineer/ Zones & CGM/DISCOMs will send the feasibility report to STU-CE Commercial.
  • 48. Intra LTOA Approval & Agreement Process STU-CE Commercial will initiate the LTOA approval and circulate the note to Full APTRANSCO Board based on the field feasibilities received. After approval of Board, LTOA approval will be given to OA user with some conditions & Payments and request for enter in to agreement as per APERC format. The OA user has to met the conditions & Payments. The Generator & Consumer both at 33KV or 11KV Within DISCOM, LTOA agreement will be done between DISCOM & OA User. For others LTOA tripartite agreement will done between APTRANSCO, DISCOM & OA User.
  • 49. Intra State LTOA Payment Process ED/Finance (FI Module) will raise the following invoices every month in consultation with ED/HRD & Plg. 1) invoice for Transmission charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. ( Not applicable for with in DISCOM) 2) invoice for SLDC Operating Charges. (Monthly) due date 10 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st & October 1st. Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 50. Terms & Conditions of LTOA approval 1) A Long Term Open Access agreement with APTRANSCO, DISCOMs (Consumer area) & OA user in the APERC approved format. 2) The date of commencement of Open Access for the capacity will be as mentioned in the Agreement. 3) The company shall pay monthly Transmission & SLDC charges to APTRANSCO, Wheeling charges to Respective DISCOM as per the Tariff Orders issued by APERC from time to time irrespective of actual energy injected and also bear losses in kind. 4) The company shall pay two months SLDC charges to APTRANSCO as security deposit before commencement of Open Access as per APERC Orders and Regulations from time to time. 5) The company has to open Letter of Credit towards imbalance in supply and consumption of electricity for a period of 10 days, before commencement of Open Access to DISCOMs.
  • 52. Submission of intra STOA Application Either Generator or Consumer (Open Access User) may eligible for submission of STOA Application. Single Generator can supply to single or Multi Consumers. Single Consumer can take supply from single or Multi Generators. Types of OA Users 1) Captive 2) Group Captive 3) Third Party The OA Users has to submit the detailed application along with necessary Documents along with requisite fee. Rs 1000/- fee shall be payable in favour of “SAO/SLDC, APTRANSCO” Payable at Hyderabad either through RTGS. APTRANSCO Nodal Officer is Chief Engineer (SLDC)
  • 53. Intra STOA Approval & Agreement Process The Application Directly reach to following Authorities 1. CE/SLDC for Processing of STOA Application 2. SAO/SLDC for payment receipt 3. CE/Zone/APTRANSCO – for feasibility if Transmission network is involved. 4. CGM/DISCOM – for feasibility if Distribution Network involved. if the CMD capacity is more than the contracted, the Power system feasibility is to be obtained. 1) The OA User shall pay two months SLDC charges to APTRANSCO as security deposit before commencement of Open Access as per APERC Orders and Regulations from time to time. 2) The OA User has to open Letter of Credit towards imbalance in supply and consumption of electricity for a period of 10 days, before commencement of Open Access to DISCOMs. CE/SLDC will issue STOA approval based on the field feasibilities received & above amounts received.
  • 54. Intra STOA Approval & Agreement Process Any deviation of feasibility, Note file will be circulated to Full Board for approval. After approval issued by CE/SLDC, the OA User was requested for enter in to agreement as per APERC format, and meet the STU – CE Commercial for enter in to agreement. The Generator & Consumer both at 33KV or 11KV Within DISCOM, STOA agreement will be done between DISCOM & OA User. DISCOM will Furnish the Agreement to STU-CE Commercial, CE/SLDC & ED/Finance & SAO/SLDC. For others STOA tripartite agreement will done between APTRANSCO, DISCOM & OA User.
  • 55. Intra State STOA Payment Process ED/Finance (FI Module) will raise the following invoices every month in consultation with ED/HRD & Plg. 1) invoice for Transmission charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. ( Not applicable for with in DISCOM) 2) invoice for SLDC Operating Charges. (Monthly) due date 10 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (Monthly proportionate). Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 56. Terms & Conditions of STOA approval 1) A Short Term Open Access agreement with APTRANSCO, DISCOMs (Consumer area) & OA user in the APERC approved format. 2) The Period of Open Access for the capacity will be as mentioned in the SLDC Approval. 3) The company shall pay monthly Transmission & SLDC charges to APTRANSCO, Wheeling charges to Respective DISCOM as per the Tariff Orders issued by APERC from time to time irrespective of actual energy injected and also bear losses in kind. 4) The company shall pay two months SLDC charges to APTRANSCO as security deposit before commencement of Open Access as per APERC Orders and Regulations from time to time. 5) The company has to open Letter of Credit towards imbalance in supply and consumption of electricity for a period of 10 days, before commencement of Open Access to DISCOMs.
  • 58. Short Term Power Purchases (DISCOM) Andhra Pradesh Power Coordination Committee (APPCC – Representative of APDISCOMs) will purchase the Power from the intra State Pvt Generators based on the requirement of Power for DISCOM on Day / Monthly/ Quarterly/Half yearly/Yearly basis (Maximum One Year) to meet the DISCOM demand in Consultation with SLDC. The PPA approval Copy will sent to STU-CE Commercial, CE/SLDC and Executive Director (Finance). As per the PPA with Generators, The Generator has to pay the Transmission & SLDC Charges to APTRANSCO.
  • 59. Short Term Power Purchases (DISCOM) ED/Finance (FI Module) will raise the following invoices every month for the PPA period in consultation with CE/Commercial/APPCC, CE/SLDC and ED/HRD & Plg. 1) invoice for Transmission charges. (Monthly) if the Generator having a PPA for differential capacities for different periods in a month, calculate the proportionate transmission charges. due date 15 days. Surcharge will be levied, if due date exceeds. 2) invoice for SLDC Operating Charges. (Monthly) if the Generator having a PPA for differential capacities for different periods in a month, the charges will be levied fully (Whole month) on a Highest capacity of a Particular month. due date 15 days. Surcharge will be levied, if due date exceeds. due date 10 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (monthly). Calculation as per point no1 above (Transmission Charges). Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 62. Submission of Inter LTOA Application Either Generator or Consumer (Open Access User) may eligible for submission of inter state LTOA Application. Single Generator can supply to single or Multi Consumers. Single Consumer can take supply from single or Multi Generators. Inter State LTOA Application The OA Users has to submit the detailed application along with necessary Documents along with requisite fee to Power Grid. Power Grid will request the concerned STU for NOC. The OA User has to pay the Prescribed fee in favour of “FA&CCA(R&A), APTRANSCO” Payable at Hyderabad either through the DD or RTGS. APTRANSCO Nodal Officer is STU-CE Commercial
  • 63. Inter State LTOA Approval Process The Fee Details as follows 1. Up to 100 MW : Rs 2.00 Lakhs 2. 101 MW to 500 MW : Rs 3.00 Lakhs 3. 501 MW to 1000 MW : Rs 6.00 Lakhs 4. Above 1000MW : Rs 9.00 Lakhs STU-CE Commercial will address a letter to OA User Located area of Chief Engineer/Zone and copy to respective SE/OMC in case of OA user. Respective SE/OMC & Chief Engineer/ Zones will be sent the feasibility report to STU-CE Commercial. STU-CE Commercial will initiate the inter state LTOA approval and circulate the note to Full APTRANSCO Board based on the field feasibilities received through CE/PS & CE/SLDC. After approval of Board, NOC approval will be given to PGCIL.
  • 64. Inter State LTOA Approval & Payment The Inter state LTOA Approval will be issued by PGCIL under intimation to APTRANSCO. STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect each Interstate LTOA Approvals from PGCIL web Site. Based on the Inter State LTOA approval, ED/Finance (FI Module) will raise the following invoices every month in consultation with STU-CE Commercial, CE/Commercial/APPCC & CE/SLDC to OA User. 1) invoice for Transmission charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. 2) invoice for SLDC Operating Charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st & October 1st. Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 66. Submission of Inter MTOA Application Either Generator or Consumer (Open Access User) may eligible for submission of inter state MTOA Application. Single Generator can supply to single or Multi Consumers. Single Consumer can take supply from single or Multi Generators. Inter State MTOA Application The OA Users has to submit the detailed application (Format-1 & Format-2) along with necessary Documents along with requisite fee to Power Grid. Same time the OA user has to submit the Application to STU along with requisite fee. The OA User shall furnish the valid PPA for the application period.
  • 67. Submission of Inter MTOA Application The OA User has to pay the Prescribed fee in favour of “SAO/SLDC, APTRANSCO” Payable at Hyderabad through RTGS only. APTRANSCO Nodal Officer is Chief Engineer (SLDC) The Fee Details as follows 1. Up to 100 MW : Rs 1.00 Lakhs 2. 101 MW to 500 MW : Rs 2.00 Lakhs 3. 501 MW to 1000 MW : Rs 3.00 Lakhs 4. Above 1000MW : Rs 4.00 Lakhs CE/SLDC will address a letter to OA User Located area of respective CGM/DISCOM & Chief Engineer/Zone (in case of EHT) for feasibility. Respective CGM/DISCOM & Chief Engineer/ Zones will be sent the feasibility report to CE/SLDC.
  • 68. Inter State MTOA Approval at SLDC if the CMD capacity is more than the contracted, the Power system feasibility is to be obtained. If PPA was not submitted along with the application, the Consent/ Concurrence/NOC will be rejected. 1) The OA User shall pay two months SLDC charges to APTRANSCO as security deposit before commencement of Open Access as per APERC Orders and Regulations from time to time. 2) The OA User has to open Letter of Credit towards imbalance in supply and consumption of electricity for a period of 10 days, before commencement of Open Access to DISCOMs. CE/SLDC will initiate the Inter State MTOA approval and circulate the note to Full APTRANSCO Board based on the field feasibilities received and amounts received. After approval of Board, NOC will be issued to PGCIL with standard format-3 for inter state MTOA. SLDC shall convey its concurrence to the applicant (New OA User) With in 10 Working days. The start date of MTOA shall not be earlier than 5 months and later than 1 year from the last day of the month in which application has been made.
  • 69. Inter State MTOA Approval & Payment The Inter state MTOA Approval will be issued by PGCIL under intimation to APTRANSCO. STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect each Interstate MTOA Approvals from PGCIL. Based on the Inter State MTOA approval, ED/Finance (FI Module) will raise the following invoices every month in consultation with STU-CE Commercial, CE/Commercial/APPCC & CE/SLDC to OA User. 1) invoice for Transmission charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. 2) invoice for SLDC Operating Charges. (Monthly) due date 15 days. Surcharge will be levied, if due date exceeds. 3) Invoice for SLDC Annual Fee. (Half Yearly) April 1st & October 1st. Due date 10 days. Surcharge will be levied, if due date exceeds.
  • 71. Submission of Inter STBC Application Either Generator or Consumer (Open Access User) may eligible for submission of Inter State STOA Application. Generator / Consumer / Trader Treated as OA User. The OA Users has to submit the detailed application (Format-1 & Format-2 of CERC) along with necessary Documents along with requisite fee. Rs 5,000/- fee shall be payable in favour of “SAO/SLDC, APTRANSCO” Payable at Hyderabad through RTGS. APTRANSCO Nodal Officer is Chief Engineer (SLDC)
  • 72. INTER STATE STBC APPROVAL PROCESS The Application Directly reach to following Authorities 1. CE/SLDC for Processing of STOA Application 2. SAO/SLDC for payment receipt 3. CE/Zone/APTRANSCO – for feasibility if Transmission network is involved. 4. CGM/DISCOM – for feasibility if Distribution Network involved. Payments to be done 1) The OA User shall pay two months SLDC charges to APTRANSCO as security deposit before commencement of Open Access as per APERC Orders and Regulations from time to time. 2) The OA User has to open Letter of Credit towards imbalance in supply and consumption of electricity for a period of 10 days, before commencement of Open Access to DISCOMs. CE/SLDC will issue Consent/ Concurrence for Inter State STOA (Bilateral) approval to OA User with Standard Format-3 based on the field feasibilities received & above amounts received. As per the CERC Procedure Consent/ Concurrence shall be issued as for the schedules 1. With in 7 days for New OA User 2. With in 3 days for Already availed OA user.
  • 73. Inter State STBC Approval & Payment SRLDC will issue approvals for Inter state STOA (Bilateral). STU-CE Commercial, CE/SLDC & SAO/SLDC has to collect each Interstate STOA Approvals (Bilateral) from SRLDC web Site. SRLDC Will Pay the Month wise Amounts on 1st of upcoming month for the last month for Bilateral Approvals to FA&CCA(R&A). ED/Finance (FI Module) will Verify the Amounts received towards each approval regarding Transmission Charges, SLDC Charges and total amount received from SRLDC, on monthly basis in consultation with ED/HRD & Plg. 1) Transmission charges based on the MWH Transmitted. 2) SLDC Charges Rs 1000/- per day per Transactions of OA user. Any deviation of payments STU-CE Commercial will intimate for discrepancies to SRLDC under copy to ED/Finance.
  • 75. Submission of Inter STBC Application Either Generator or Consumer (Open Access User) may eligible for submission of Inter State LTOA Application. Generator / Consumer / Trader Treated as OA User. The OA Users has to submit the detailed application (Format-1 & Format-2 of CERC) along with necessary Documents along with requisite fee. Rs 5,000/- fee shall be payable in favour of “SAO/SLDC, APTRANSCO” Payable at Hyderabad through RTGS. APTRANSCO Nodal Officer is Chief Engineer (SLDC)
  • 76. Inter State STBC Approval Process The Application Directly reach to following Authorities 1. CE/SLDC for Processing of STOA Application 2. SAO/SLDC for payment receipt 3. CE/Zone/APTRANSCO – for feasibility if Transmission network is involved. 4. CGM/DISCOM – for feasibility if Distribution Network involved. if the CMD capacity is more than the contracted, the Power system feasibility is to be obtained. CE/SLDC will issue NOC for Inter State STOA (Collective) approval to OA User with Standard Format-3 based on the field feasibilities received & above amounts received. As per the CERC Procedure NOC shall be issued as for the schedules 1. With in 7 days for New OA User 2. With in 3 days for Already availed OA user.
  • 77. Inter State STBC Approval & Payment IEX/PXI will send day wise Transactions on weekly basis to ED/HRD & Plg through mail for reconciliation. IEX/PXI Will Pay the Day wise Amounts. ED/Finance (FI Module) will Verify the Amounts received towards each Transactions regarding Transmission Charges, SLDC Charges, Wheeling charges and total amount received from IEX/PEX, on monthly basis in consultation with STU - CE Commercial. 1) Transmission charges based on the MWH Transmitted. 2) SLDC Charges Rs 1000/- per day per Transactions of OA user. Any deviation of payments STU-CE Commercial will intimate for discrepancies to IEX/PEX under copy to ED/Finance.