SlideShare a Scribd company logo
1 of 7
Download to read offline
The following article was published in ASHRAE Journal, June, 2002. © Copyright 2002 American Society of Heating, Refrigerating and Air- 
Conditioning Engineers, Inc. It is presented for educational purposes only. This article may not be copied and/or distributed electronically or in 
paper form without permission of ASHRAE. 
Series–Series Counterflow for 
Central Chilled Water Plants 
By Steve Groenke, Associate Member ASHRAE, and Mick Schwedler, P.E., Member ASHRAE 
with the dry bulb, but is internally 
driven. Wet-bulb temperature deter-mines 
cooling-tower energy consump-tion 
at a given load.), 
• Discount rate, 
• 20-year service life, 
• Installed, operating, and mainte-nance 
costs for chillers, pumps, 
and cooling tower fans (The method of 
accounting for pumping energy costs 
is discussed elsewhere in this 
article.), and 
• A specific electric utility rate for 
the plant. 
Fixed Parameters 
As in most central chilled water plants, 
the initial costs for distributing the 
chilled water (pumps, piping) were con-sidered 
critical. Using a larger-than-con-ventional 
difference between the 
entering and leaving chilled water tem-peratures 
permits a lower flow rate. 
Smaller pipes and pumps can then be 
used to satisfy the same capacity.2,3 Based 
on that premise, the plant owner estab-lished 
these non-negotiable design pa-rameters 
for the chilled water system: 
• Entering-chiller water temperature: 
55°F (12.8°C), ‡ 
• Leaving-chiller water temperature: 
†As can be the case when a third party per- 37°F (2.8°C), and 
forms an economic analysis, few details (in-cluding 
About the Authors 
W 
Steve Groenke is the new equipment sales man-ager 
with Trane in Timonium, Md. Mick 
Schwedler, P.E., is a senior principal applications 
engineer with Trane in La Crosse, Wis. 
hen a project is large enough to justify the evaluation of several 
prospective designs, engineers are more willing to explore new 
solutions to familiar challenges. Setting aside convention enables ideas 
to flow freely. The viability of prospective solutions can then be gauged 
using criteria such as life-cycle cost, simplicity, and first cost. The scale 
of a new central cooling plant located in Washington, D.C. was large 
enough to warrant this type of innovative engineering. Given the mag-nitude 
of the project, the owner elected to outsource the design, con-struction, 
and operation of the 10,500-ton (36 900 kW) chilled water 
plant to an energy service company. 
Life-Cycle Cost 
To ensure that the chilled water plant 
provided the owner with the best possible 
value, lowest life-cycle cost was chosen 
as the determining criterion for the plant’s 
design. An independent financial con-sultant 
performed a cost analysis of each 
alternative to ensure an equitable com-parison. 
Each of these analyses was based 
on a load profile specific to the plant. 
The profile was developed from the ex-pected 
loads of the customer who had 
signed the contract to purchase chilled 
water. The primary cooling loads are from 
a convention center. In addition to sig-nificant 
weekday cooling loads, the 
center’s meeting areas often are used on 
weekends. The loads are year-round. 
However, airside economizers reduce the 
need for mechanical cooling during 
many months of the year.† 
The consultant developed a detailed 
spreadsheet to examine the life-cycle 
costs for the chillers, chilled water 
pumps, condenser water pumps, and 
cooling tower fans in each proposed de-sign. 
The spreadsheet accounted for: 
• Load profile, 
• Ambient dry-bulb and wet-bulb 
conditions (Load does not vary directly 
the actual plant load profile) were 
made available to the authors. Readers may 
find this frustrating—so did the authors. Al-though 
third-party analyses can ensure greater 
objectivity and “fair play” by the principals, full 
disclosure of the original data is necessary to 
verify the results and offer recommendations 
that might benefit the plant owner. 
‡It may have been possible to achieve a 
higher entering chiller temperature, but do-ing 
so was not within the plant owner’s direct 
control. 
ASHRAE Journal|June 2002 23
Arrangement Chillers# Evaporator Condenser Cooling Towers System 
Evaporator Condenser 
Units / 
Modules 
Compresor 
Efficiency, 
kW/ton 
Flow, 
gpm 
ΔP, ft 
of 
Water 
Number 
of 
Pumps 
Power 
per 
Pump 
kW 
Flow, 
gpm 
ΔP, ft 
of 
Water 
Number 
of 
Pumps 
Parallel Parallel 5/5 0.649 2,800 3.26 5 2.18 4,200 3.66 5 3.67 8 60 7324 18,836,302 
Parallel Parallel 6/6 0.618 2,333 4.18 6 2.33 3,500 3.53 6 2.95 8 60 7001 18,076,391 
Series 
Series 
Counter- 
flow (1.5 
gpm/ton) 
6/3 0.560 4,667 17.96 3 19.99 5,250 14.8 3 18.54 8 48 6379 16,819,167 
Series 
Series 
Counter- 
flow (2.0 
gpm/ton) 
6/3 0.535 4,667 17.96 3 19.99 7,000 25.2 3 42.08 8 60 6284 16,656,947 
Series 
Parallel 
(2.0 
gpm/ton) 
6/3 0.555 4,667 17.96 3 19.99 3,500 3.53 6 2.95 8 60 6385 16,888,493 
# The chillers represented in this table all have two refrigerant circuits. The full analysis included single refrigerant circuit chillers at various 
flow rates and efficiencies. 
Table 1: Comparison of projected life-cycle costs for central chilled water plant.* 
• Flow rate/capacity: 1.33 gpm/ton (0.024 mL/J). 
Certainly, supplying 37°F (2.8°C) rather than 40°F or 42°F 
(4.4°C or 5.6°C) chilled water would require more power from 
the chillers. Therefore, it was expected that the cost savings 
associated with reduced pumping power and pipe installa-tion 
would offset any increase in chiller power. Historically, 
producing 37°F (2.8°C) water might have prompted concern 
that the low refrigerant suction temperatures would freeze the 
evaporator tubes. Experience shows that the advent of fast, 
accurate chiller controls and algorithms can safely accom-modate 
temperatures as low as 34°F (1.1°C) without the addi-tion 
of antifreeze. 
Selected Design 
Various combinations of absorption chillers, electric chill-ers, 
and engine-driven generator/chillers were considered dur-ing 
the conceptual phase of design. The final evaluation 
examined 11 combinations of plant configurations and flow 
rates. Chillers with single compressors and dual compressors 
were examined, and manufacturers were allowed to submit 
cost and performance information for any configuration. Plant 
configurations ranged from four to nine chillers, and included 
proposals with: 
• Both evaporators and condensers in parallel; 
• Evaporators in series and condensers in parallel; and 
• Both evaporators and condensers in series. 
Table 1 shows five of the combinations that were exam-ined. 
The system with the lowest life-cycle cost consisted of 
six electric centrifugal chillers with dual refrigeration cir-cuits, 
that used 2 gpm (0.0358 mL/J) of condenser water per 
ton of cooling, and was piped in a “series evaporator–series 
condenser” arrangement. 
As Table 1 indicates, arranging the chiller evaporators in se-ries 
reduced life-cycle costs by more than $1.4 million when 
compared with parallel arrangements. Series arrangements of 
Power 
per 
Pump 
kW 
Number 
of Cells 
Power 
per 
Cell 
kW 
Total 
Power, 
kW 
Figure 1: Series–series counterflow arrangement. 
Life-Cycle 
Cost, $ 
USD 
chiller evaporators have been used, when prudent, in many ap-plications. 
7, 16 However, the chilled-water plant design that was 
selected for this project not only arranges the evaporators in 
series, but also arranges the condensers in series using a 
counterflow configuration (see Figure 1). At design conditions: 
• Chilled water enters the upstream chiller at 55°F (12.8°C) 
and exits at 45.1°F (7.3°C). 
• Chilled water enters the downstream chiller at 45.1°F 
(7.3°C) and exits at 37°F (2.8°C). 
Condenser water flows in the opposite direction of the chilled 
water, thus the term “counterflow:” 
• Condenser water enters the downstream chiller at 85°F 
(29.4°C) and exits at 91.3°F (32.9°C). 
• Condenser water enters the upstream chiller at 91.3°F 
(32.9°C) and exits at 98.9°F (37.2°C). 
Chiller Energy Consumption 
A chiller’s power demand reflects the amount of lift provided 
by the compressor. “Lift” describes the difference between evapo- 
* gpm × 0.0631 = L/s; gpm/ton × 0.0179 = mL/J; ft of water × 2.99 = kPa 
24 June 2002|ASHRAE Journal
Chillers 
rator pressure and condenser pressure: 
Evap. Refrigerant Temperature = Lvg. 
Chilled Water 
Temperature – Evap. Approach Tem-perature 
Cond. Refrigerant Temperature = Lvg. 
Cond. Water 
Temperature + Cond. Approach 
Temperature 
At saturation, these temperatures re-late 
directly to the refrigerant pressures 
in the evaporator and condenser. 
It is clear from Table 1 that the series– 
series counterflow arrangement yields 
the lowest full-load chiller power (about 
14% lower than the parallel–parallel 
configuration). The dramatic reduction in chiller power oc-curs 
Figure 2: Conceptualization of reduced lift. 
because the upstream chiller in the series–series 
counterflow arrangement operates at a higher chilled water 
temperature, which means that the refrigerant temperature 
and refrigerant pressure in the evaporator are also higher in 
the upstream machine. Similarly, the downstream chiller 
“sees” a lower condenser leaving water temperature— 
and therefore has a lower condenser refrigerant pressure— 
than it would in a plant with the chiller condensers arranged 
in parallel. 
Figure 2 illustrates the concept of reduced lift using the 
design parameters for this chilled water plant. Although lift is 
the difference between the refrigerant pressures in the evapo-rator 
and condenser, its magnitude can be approximated using 
the difference between the water temperatures leaving the 
evaporator and condenser. Chiller power can be reduced by 
decreasing compressor “lift.” In this case, the difference in 
average lift at design is approximately 13%: 
1 –{[(54.3 + 53.8)/2]/61.9} = 0.126 
The reduction in lift provided by the series–series 
counterflow arrangement also occurs at part-load conditions. 
Why? The temperature of the water leaving the evaporator of 
the upstream chiller is always warmer than the system water, 
and the temperature of the water leaving the condenser of the 
downstream chiller is always cooler than the system water. 
Because each of the chillers in this design has two refrigera-tion 
circuits (Figure 1), the reduced lift effect is multiplied. 
Instead of two lifts, there are four (Figure 2). Therefore, the 
difference in average lift at design for the system with four 
independent refrigeration circuits in a series–series 
counterflow arrangement exceeds 19%: 
1 – {[(51.1 + 50.3 + 50.0 + 48.9)/4]/61.9} = 0.191 
The upstream chiller need not be equally loaded at all 
times; the anticipated savings come from that chiller’s abil-ity 
to produce chilled water at an elevated temperature. 
(When this article was written, the plant had not operated 
through an entire cooling season.) How the plant should re-spond 
to varying system conditions was discussed with the 
design engineer, plant owner, and plant operators. For ex-ample, 
if the entering chiller water temperature did not reach 
design conditions, the operators could: 
• Increase pump speed or the number of active pumps 
to increase flow rates through, and fully load, the active 
chillers. 
• Reset the setpoints of the upstream chillers to 55% of the 
total temperature difference. Lowering the setpoint of the up-stream 
chillers as the result of a drop in entering-chiller water 
temperature lessens the benefit of reduced lift. However, the 
upstream chillers will always run at a higher evaporator 
pressure than the downstream chillers, which saves energy 
consumption and costs. 
Chiller sequencing was also discussed. It was determined 
that the most cost-effective startup strategy would fully load 
one chiller module, and then activate the remaining chillers in 
modules (pairs). Activating the upstream chiller and operating 
it at the higher water temperature would take advantage of all 
of the available heat-transfer surface area without increasing 
the energy consumed by ancillary equipment. 
At the design conditions defined for the system, chiller per-formance 
is well below the 6.10 COP (0.576 kW/ton) require-ment 
set by ANSI/ASHRAE/IESNA Standard 90.1-2001, Energy 
Standard for Buildings Except Low-Rise Residential Build-ings. 
At standard ARI rating conditions, each chiller module 
would operate with an efficiency of 0.445 kW/ton.† The per-formance 
conditions for this application, however, were care-fully 
selected to optimize the overall energy consumption of 
the entire chilled water plant.1 
† Standard ARI rating conditions are 44°F, 2.4 gpm/ton (6.7°C, 
0.043 L/s per kW) for the evaporator and 85°F, 3 gpm/ton (29.4°C, 
0.054 L/s per kW) for the condenser. 
ASHRAE Journal|June 2002 25
Figure 3: Comparison of evaporator layouts. Figure 4: Comparison of counterflow condenser layouts. 
Focus on the System 
The reduction in chiller power comes at the expense of 
increased pumping energy. With the utility meter measuring 
the consumption of the entire plant—not the chillers alone— 
the ultimate goal must be to reduce plant power. Would the 
series–series counterflow arrangement reduce the compres-sor 
power enough to make up for the increase in pump power? 
Table 2 compares the overall power consumption for the 
chilled water plant based 
on three different arrange-ments 
of six chillers. In 
each case, the condenser-water 
flow rate is 2 
gpm/ton (0.0358 mL/J). 
Chilled Water Pumps. 
The f ive chilled water 
pumps in this design are 
piped in a manifold ar-rangement; 
one of the 
Arrangement Pumps 
Evaporator Condenser Chillers Chilled 
Parallel Parallel 6,489 14 18 480 7,001 
Series Parallel 5,827 60 18 480 6,385 
Series 
Series 
Counter-flow 
5,618 60 126 480 6,284 
Table 2: Comparison of power requirements (kW) at identical 
rates of condenser water flow. 
pumps is redundant. 
Doubling the water flow through the evaporators created a 
water pressure drop that was significantly higher for the se-ries 
arrangements than for the parallel configurations (Table 
1). To minimize this “penalty” as much as possible, single-pass 
tube bundles were used in the series evaporators. Other-wise, 
the pressure drop and resultant pump power would have 
been even higher. Despite the high water pressure drop, re-ducing 
compressor lift by arranging the evaporators in series 
yielded chiller power savings that dwarfed the additional 
pump power needed at full load. 
To further offset the economic impact of larger chilled wa-ter 
pumps, the plant design also varies primary flow through 
the chiller evaporators in response to system load. The “pump 
penalty” still exists at full load. However, it is significantly 
less at part load/partial flow because the differences in evapo-rator 
pressure drop and chilled water pumping power decrease 
rapidly as the flow rate slows. Combining variable primary 
flow and a series arrangement of evaporators circulates twice 
as much water through the evaporator of each chiller. 
This combination also creates a second advantage: each 
chiller can accommodate 
a much greater reduction 
in water flow, which post-pones 
the need for a sys-tem 
bypass. (Use of 
variable primary-flow 
systems is increasingly 
common and well docu-mented.) 
4–6,9,11–12,14–15,17 
Condenser Water 
Pumps. The condenser 
water pumps are piped in 
Cooling 
Tower 
Total 
Plant 
Water 
Condenser 
Water 
a manifold arrangement. In the selected plant configuration, 
one active pump is provided per chiller module. Redundancy 
is provided by two smaller pumps, which enables one of the 
pumps to operate during low-load conditions and reduce 
pumping energy consumption. This is described later. 
Basing an economic comparison of design alternatives on 
life-cycle costs requires an overall summation of the total costs 
for power (demand) and energy (consumption). Therefore, al-though 
the total power for the series–series counterflow plant 
was lowest (Table 2), it was also necessary to account for the 
costs related to energy consumption. 
Water flow rates and configurations for the chiller con- 
26 June 2002|ASHRAE Journal
Chillers 
densers were evaluated in a manner similar to that used for 
the chilled water loop. When the results were compared, the 
life-cycle cost analysis (Table 1) pointed to a system design 
that combined a series arrangement of the chiller condensers 
with a condenser water flow rate of 2 gpm/ton (0.0358 mL/J). 
Choosing this design permitted a smaller cooling tower and 
reduced the size of the condenser piping. It also reduced the 
initial and operating costs of the cooling tower fans and con-denser 
water pumps.8,10 As Table 1 reveals, arranging the con-densers 
in series significantly increased the pressure drop 
and required pumping power. Yet, the savings in chiller (com-pressor) 
power and energy offset this penalty, too. 
A further reduction in flow rate to 1.5 gpm/ton (0.268 mL/J) 
was also examined and would provide an even greater reduc-tion 
in tower fan power, but the plant owner did not allow any 
pipe cost for flow rates below 2 gpm/ton (0.0358 mL/J). Nor 
did the owner account for pump savings due to cooling tower 
height and static lift requirements. Although the effects of vari-able 
condenser water flow were considered, the owner decided 
that constant flow would simplify plant operation.‡ 
Space Considerations. The selected design for the chilled 
water plant provided one chilled water pump and one con-denser 
water pump for each chiller module. Two redundant 
pumps were provided as well: one for the chilled water loop 
and one for the condenser water loop. Collectively, these 
components occupy less space than a comparable primary– 
secondary system. Some variable primary-flow systems use 
fewer pumps than chillers to further reduce the space required 
for piping connections, variable speed drives, and electrical 
service for the pumps. 
Clarifying the Economics 
During the design phase, the owner sought to better under-stand 
the relationship between the operating characteristics of 
the series–series counterflow arrangement and the projected 
savings in life-cycle costs. Several questions of particular rel-evance 
are paraphrased here, along with their answers: 
Q: Won’t piping the chiller condensers in series, rather than 
in parallel, result in a significantly higher operating cost? 
A: Arranging the condensers in series does increase the pump-ing 
power per chiller module by 36 kW at full load, given the 
increased condenser pressure drop of 22 ft (66 kPa). However, 
the compressor power reduction per module is 69 kW, which 
far exceeds the 36 kW increase in pumping power. Remember, 
too, that the series–series counterflow arrangement always re-duces 
the required amount of compressor “lift,” even when the 
plant operates at part load. Sequencing the constant-volume 
‡The authors of this article speculate that the decisions made by the 
plant owner represented a “comfortable” compromise between the 
series–series counterflow arrangement, which was economically sen-sible 
but unfamiliar, and other more conventional (and familiar) as-pects 
of chilled water plant design. 
Advertisement in the print edition formerly in this space. 
ASHRAE Journal|June 2002 27
condenser pumps makes it possible to reduce flow to the mod-ules 
as the load decreases. This control strategy significantly 
reduces pumping energy consumption when the plant oper-ates 
at less than 50% of full-load capacity. 
Q: Because the chillers are started in pairs, the series– 
series counterflow arrangement of this design requires two, 
four, or six chillers at load conditions while a parallel–paral-lel 
configuration would only require one, three, or five 
chillers. Did the analysis account for this difference in pump-ing 
energy? 
A: Deciding to minimize the number of condenser water 
pumps used when three chiller modules operate led to the 
use of three large condenser pumps for this plant. All pumps 
operate whether the condensers were piped in parallel or in 
series. To save pumping energy when only one chiller mod-ule 
operates (that is, during “winter” load hours), the system 
is designed to supply only 3,500 gpm (220 L/s) of condenser 
water. Supplying two smaller pumps (rather than one large 
pump) for redundancy allowed this. In low-load conditions, 
only one of the smaller pumps is run. The manufacturer con-firmed 
that the chillers would operate properly at half of the 
design condenser water flow. 
Q: Compared with a parallel configuration, won’t the se-ries– 
series counterflow arrangement of chillers require awk-ward 
and more costly bypass piping and valves around each 
condenser and evaporator? 
A: Operating chillers in pairs is a concept. As such, the se-ries– 
series counterflow arrangement can be implemented by 
piping both loops, condenser and chilled water, in a similar 
manner to the more familiar parallel system. Such arrange-ments 
(Figure 3, Figure 4) provide virtually the same service-ability 
and redundancy, regardless of whether the chillers are 
piped in parallel or in series, unless all of the upstream chillers 
are simultaneously off-line for service. 
With either arrangement (series or parallel), the system will 
run out of capacity at peak load if one chiller is not in service. 
Flow through the operating chillers can be increased until the 
pumps no longer have enough power. However, after system 
load exceeds chiller capacity, the chilled water setpoint will 
not be maintained. 
Conclusions 
The series–series counterflow (series evaporators–series 
condensers) design required discussion and resolution of po-tential 
drawbacks, however, an independent analysis of life-cycle 
costs demonstrated that the series–series counterflow 
Advertisement in the print edition formerly in this space. 
28 June 2002|ASHRAE Journal
Chillers 
arrangement was the most cost-effective solution for this cen-tral 
chilled water plant. 
Since this project was awarded, at least two other chilled 
water plants have adopted similar configurations. The appli-cation 
discussed here was large (more than 10,000 tons [35 
170 kW] of mechanical refrigeration), but the series–series 
counterflow concept can be, and has been, successfully 
applied to much smaller jobs. The same design challenges 
will be encountered and can be overcome when it makes 
economic sense. 
In all cases, remember that the utility meter is on the build-ing. 
The building owner pays the costs (demand plus con-sumption) 
of installing, maintaining, and operating the entire 
system—chillers, chilled water pumps, condenser water pumps, 
cooling tower fans, and controls. Analyze the actual load pro-file 
at ambient conditions to determine which design yields 
the lowest life-cycle cost. 
References 
1. ARI Standard 550/590–1998, Standard for Water Chilling Pack-ages 
Using the Vapor Compressor Cycle (Arlington, VA: Air-Condi-tioning 
and Refrigeration Institute). 
2. 2000 ASHRAE Handbook—HVAC Systems and Equipment. Chapter 
11, “District Heating and Cooling.” 
3. 2000 ASHRAE Handbook—HVAC Systems and Equipment Hand-book. 
Chapter 12, “Hydronic Heating and Cooling System Design.” 
4. Avery, G. 2001. “Improving the efficiency of chilled water plants.” 
ASHRAE Journal 43(5):14–18. 
5. Avery, G. 1998. “Controlling chillers in variable flow systems.” 
ASHRAE Journal 40(2):42–45. 
6. Bahnfleth, W.P., E. Peyer. 2001. “Comparative analysis of variable 
and constant primary-flow chilled-water-plant performance.” HPAC 
Engineering, April, p. 50. 
7. Coad, William J. 1998. “A fundamental perspective on chilled 
water systems.” Heating/Piping/Air Conditioning, August, pp. 59–66. 
8. Demirchian, G.H., M.A. Maragareci. 1997. “The benefits of higher 
condenser water ΔT at Logan International Airport central chilled water 
plant.” IDEA 88th Annual Conference Proceedings, pp. 291–300. 
9. Hartman, T. 2001. “All-variable speed centrifugal chiller plants.” 
ASHRAE Journal, September. 
10. Kelly, D.W., T. Chan. 1999. “Optimizing chilled water plants.” 
Heating/Piping/Air Conditioning, January, pp. 145–147. 
11. Kirsner, W. 1996. “The demise of the primary-secondary pump-ing 
paradigm for chilled water plant design.” Heating/Piping/Air Con-ditioning, 
November. 
12. Luther, K. 1998. “Applying variable volume pumping.” Heat-ing/ 
Piping/Air Conditioning, October, pp. 53–58. 
13. Rishel, J.B. 1996. HVAC Pump Handbook, pp. 109–112. 
14. Schwedler, M., B. Bradley. 2000. “Variable-primary-flow sys-tems: 
An idea for chilled-water plants the time of which has come.” 
Heating/Piping/Air Conditioning, April, pp. 41–44. 
15. Taylor, S. 2002. “Primary-only vs. primary-secondary variable-flow 
chilled water systems.” ASHRAE Journal 44(2):25–29. 
16. Trane. 2001. Multiple-Chiller-System Design and Control, pp. 
58–59. 
17. Waltz, J.P. 1997. “Don’t ignore variable flow.” Contracting Busi-ness 
July:133–144. 
Advertisement in the print edition formerly in this space. 
ASHRAE Journal|June 2002 29

More Related Content

What's hot (20)

Airconditioning ppt
Airconditioning pptAirconditioning ppt
Airconditioning ppt
 
Hvac for beginners
Hvac for beginnersHvac for beginners
Hvac for beginners
 
Hvac basics
Hvac basicsHvac basics
Hvac basics
 
AIR CONDITIONING
AIR CONDITIONINGAIR CONDITIONING
AIR CONDITIONING
 
HVAC Basics
HVAC BasicsHVAC Basics
HVAC Basics
 
Blue star package units
Blue star package unitsBlue star package units
Blue star package units
 
Chilled water systems
Chilled water systemsChilled water systems
Chilled water systems
 
chiller system by Mr.Seng Sunhor
chiller system by Mr.Seng Sunhorchiller system by Mr.Seng Sunhor
chiller system by Mr.Seng Sunhor
 
VARIABLE REFRIGERANT FLOW(VRF) ppt
VARIABLE REFRIGERANT FLOW(VRF)  pptVARIABLE REFRIGERANT FLOW(VRF)  ppt
VARIABLE REFRIGERANT FLOW(VRF) ppt
 
Air conditioning
Air conditioningAir conditioning
Air conditioning
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 
Module (1.3) types of ac units-hvac-apex
Module (1.3) types of ac units-hvac-apexModule (1.3) types of ac units-hvac-apex
Module (1.3) types of ac units-hvac-apex
 
Air Conditioning system and types
Air Conditioning system and typesAir Conditioning system and types
Air Conditioning system and types
 
Project on HVACR
Project on HVACRProject on HVACR
Project on HVACR
 
Calderas horizontales
Calderas horizontalesCalderas horizontales
Calderas horizontales
 
Condensers and cooling towers
Condensers and cooling towersCondensers and cooling towers
Condensers and cooling towers
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
 
Building air con. system
Building air con. systemBuilding air con. system
Building air con. system
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 

Similar to Ashrae chillers inseries

STUDY_HongKongPoly_pre-cool(1)
STUDY_HongKongPoly_pre-cool(1)STUDY_HongKongPoly_pre-cool(1)
STUDY_HongKongPoly_pre-cool(1)Blue Energy Europe
 
Trane eng newsletter heat recovery
Trane eng newsletter heat recoveryTrane eng newsletter heat recovery
Trane eng newsletter heat recoveryMikeLemmon4
 
Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towersAbdelrahim Ramadan
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemesMazhar Sheikh
 
Coefficient of Performance Enhancement of Refrigeration Cycles
Coefficient of Performance Enhancement of Refrigeration CyclesCoefficient of Performance Enhancement of Refrigeration Cycles
Coefficient of Performance Enhancement of Refrigeration CyclesIJERA Editor
 
EXH2200 Cooling Tower Design Guidelines.pdf
EXH2200 Cooling Tower Design Guidelines.pdfEXH2200 Cooling Tower Design Guidelines.pdf
EXH2200 Cooling Tower Design Guidelines.pdfZeeshanAlam90
 
Development of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental ApparatusDevelopment of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental ApparatusCSCJournals
 
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...Associate Professor in VSB Coimbatore
 
Experimental investigation of waste heat recovery system for domestic refrige...
Experimental investigation of waste heat recovery system for domestic refrige...Experimental investigation of waste heat recovery system for domestic refrige...
Experimental investigation of waste heat recovery system for domestic refrige...IAEME Publication
 
"Replacement of vapor compression system of domestic refrigerator by an eject...
"Replacement of vapor compression system of domestic refrigerator by an eject..."Replacement of vapor compression system of domestic refrigerator by an eject...
"Replacement of vapor compression system of domestic refrigerator by an eject...IRJET Journal
 
Cep plate and_frame_hx
Cep plate and_frame_hxCep plate and_frame_hx
Cep plate and_frame_hxHsien Yu Wang
 
Design plate heat exchangers
Design plate heat exchangersDesign plate heat exchangers
Design plate heat exchangersXuan Tung
 
Plate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingPlate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingSyed Waqas Haider
 
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...IAEME Publication
 
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET Journal
 

Similar to Ashrae chillers inseries (20)

Adm apn045-en 0912
Adm apn045-en 0912Adm apn045-en 0912
Adm apn045-en 0912
 
D046041925
D046041925D046041925
D046041925
 
STUDY_HongKongPoly_pre-cool(1)
STUDY_HongKongPoly_pre-cool(1)STUDY_HongKongPoly_pre-cool(1)
STUDY_HongKongPoly_pre-cool(1)
 
Trane eng newsletter heat recovery
Trane eng newsletter heat recoveryTrane eng newsletter heat recovery
Trane eng newsletter heat recovery
 
IJET-V2I6P2
IJET-V2I6P2IJET-V2I6P2
IJET-V2I6P2
 
Saving energy with cooling towers
Saving energy with cooling towersSaving energy with cooling towers
Saving energy with cooling towers
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemes
 
Coefficient of Performance Enhancement of Refrigeration Cycles
Coefficient of Performance Enhancement of Refrigeration CyclesCoefficient of Performance Enhancement of Refrigeration Cycles
Coefficient of Performance Enhancement of Refrigeration Cycles
 
EXH2200 Cooling Tower Design Guidelines.pdf
EXH2200 Cooling Tower Design Guidelines.pdfEXH2200 Cooling Tower Design Guidelines.pdf
EXH2200 Cooling Tower Design Guidelines.pdf
 
Development of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental ApparatusDevelopment of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
Development of a Bench-Top Air-to-Water Heat Pump Experimental Apparatus
 
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...
Development and Performance Evaluation of a Two-Stage Cascade Refrigeration S...
 
Allen Nicholas
Allen NicholasAllen Nicholas
Allen Nicholas
 
Experimental investigation of waste heat recovery system for domestic refrige...
Experimental investigation of waste heat recovery system for domestic refrige...Experimental investigation of waste heat recovery system for domestic refrige...
Experimental investigation of waste heat recovery system for domestic refrige...
 
Condenser performance test
Condenser performance testCondenser performance test
Condenser performance test
 
"Replacement of vapor compression system of domestic refrigerator by an eject...
"Replacement of vapor compression system of domestic refrigerator by an eject..."Replacement of vapor compression system of domestic refrigerator by an eject...
"Replacement of vapor compression system of domestic refrigerator by an eject...
 
Cep plate and_frame_hx
Cep plate and_frame_hxCep plate and_frame_hx
Cep plate and_frame_hx
 
Design plate heat exchangers
Design plate heat exchangersDesign plate heat exchangers
Design plate heat exchangers
 
Plate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger SizingPlate and frame Heat Exchanger Sizing
Plate and frame Heat Exchanger Sizing
 
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...
EXPERIMENTAL INVESTIGATION OF WASTE HEAT RECOVERY SYSTEM FOR DOMESTIC REFRIGE...
 
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
IRJET- Design and Development of a Waste Heat Recovery Unit for Household Ref...
 

Recently uploaded

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

Ashrae chillers inseries

  • 1. The following article was published in ASHRAE Journal, June, 2002. © Copyright 2002 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational purposes only. This article may not be copied and/or distributed electronically or in paper form without permission of ASHRAE. Series–Series Counterflow for Central Chilled Water Plants By Steve Groenke, Associate Member ASHRAE, and Mick Schwedler, P.E., Member ASHRAE with the dry bulb, but is internally driven. Wet-bulb temperature deter-mines cooling-tower energy consump-tion at a given load.), • Discount rate, • 20-year service life, • Installed, operating, and mainte-nance costs for chillers, pumps, and cooling tower fans (The method of accounting for pumping energy costs is discussed elsewhere in this article.), and • A specific electric utility rate for the plant. Fixed Parameters As in most central chilled water plants, the initial costs for distributing the chilled water (pumps, piping) were con-sidered critical. Using a larger-than-con-ventional difference between the entering and leaving chilled water tem-peratures permits a lower flow rate. Smaller pipes and pumps can then be used to satisfy the same capacity.2,3 Based on that premise, the plant owner estab-lished these non-negotiable design pa-rameters for the chilled water system: • Entering-chiller water temperature: 55°F (12.8°C), ‡ • Leaving-chiller water temperature: †As can be the case when a third party per- 37°F (2.8°C), and forms an economic analysis, few details (in-cluding About the Authors W Steve Groenke is the new equipment sales man-ager with Trane in Timonium, Md. Mick Schwedler, P.E., is a senior principal applications engineer with Trane in La Crosse, Wis. hen a project is large enough to justify the evaluation of several prospective designs, engineers are more willing to explore new solutions to familiar challenges. Setting aside convention enables ideas to flow freely. The viability of prospective solutions can then be gauged using criteria such as life-cycle cost, simplicity, and first cost. The scale of a new central cooling plant located in Washington, D.C. was large enough to warrant this type of innovative engineering. Given the mag-nitude of the project, the owner elected to outsource the design, con-struction, and operation of the 10,500-ton (36 900 kW) chilled water plant to an energy service company. Life-Cycle Cost To ensure that the chilled water plant provided the owner with the best possible value, lowest life-cycle cost was chosen as the determining criterion for the plant’s design. An independent financial con-sultant performed a cost analysis of each alternative to ensure an equitable com-parison. Each of these analyses was based on a load profile specific to the plant. The profile was developed from the ex-pected loads of the customer who had signed the contract to purchase chilled water. The primary cooling loads are from a convention center. In addition to sig-nificant weekday cooling loads, the center’s meeting areas often are used on weekends. The loads are year-round. However, airside economizers reduce the need for mechanical cooling during many months of the year.† The consultant developed a detailed spreadsheet to examine the life-cycle costs for the chillers, chilled water pumps, condenser water pumps, and cooling tower fans in each proposed de-sign. The spreadsheet accounted for: • Load profile, • Ambient dry-bulb and wet-bulb conditions (Load does not vary directly the actual plant load profile) were made available to the authors. Readers may find this frustrating—so did the authors. Al-though third-party analyses can ensure greater objectivity and “fair play” by the principals, full disclosure of the original data is necessary to verify the results and offer recommendations that might benefit the plant owner. ‡It may have been possible to achieve a higher entering chiller temperature, but do-ing so was not within the plant owner’s direct control. ASHRAE Journal|June 2002 23
  • 2. Arrangement Chillers# Evaporator Condenser Cooling Towers System Evaporator Condenser Units / Modules Compresor Efficiency, kW/ton Flow, gpm ΔP, ft of Water Number of Pumps Power per Pump kW Flow, gpm ΔP, ft of Water Number of Pumps Parallel Parallel 5/5 0.649 2,800 3.26 5 2.18 4,200 3.66 5 3.67 8 60 7324 18,836,302 Parallel Parallel 6/6 0.618 2,333 4.18 6 2.33 3,500 3.53 6 2.95 8 60 7001 18,076,391 Series Series Counter- flow (1.5 gpm/ton) 6/3 0.560 4,667 17.96 3 19.99 5,250 14.8 3 18.54 8 48 6379 16,819,167 Series Series Counter- flow (2.0 gpm/ton) 6/3 0.535 4,667 17.96 3 19.99 7,000 25.2 3 42.08 8 60 6284 16,656,947 Series Parallel (2.0 gpm/ton) 6/3 0.555 4,667 17.96 3 19.99 3,500 3.53 6 2.95 8 60 6385 16,888,493 # The chillers represented in this table all have two refrigerant circuits. The full analysis included single refrigerant circuit chillers at various flow rates and efficiencies. Table 1: Comparison of projected life-cycle costs for central chilled water plant.* • Flow rate/capacity: 1.33 gpm/ton (0.024 mL/J). Certainly, supplying 37°F (2.8°C) rather than 40°F or 42°F (4.4°C or 5.6°C) chilled water would require more power from the chillers. Therefore, it was expected that the cost savings associated with reduced pumping power and pipe installa-tion would offset any increase in chiller power. Historically, producing 37°F (2.8°C) water might have prompted concern that the low refrigerant suction temperatures would freeze the evaporator tubes. Experience shows that the advent of fast, accurate chiller controls and algorithms can safely accom-modate temperatures as low as 34°F (1.1°C) without the addi-tion of antifreeze. Selected Design Various combinations of absorption chillers, electric chill-ers, and engine-driven generator/chillers were considered dur-ing the conceptual phase of design. The final evaluation examined 11 combinations of plant configurations and flow rates. Chillers with single compressors and dual compressors were examined, and manufacturers were allowed to submit cost and performance information for any configuration. Plant configurations ranged from four to nine chillers, and included proposals with: • Both evaporators and condensers in parallel; • Evaporators in series and condensers in parallel; and • Both evaporators and condensers in series. Table 1 shows five of the combinations that were exam-ined. The system with the lowest life-cycle cost consisted of six electric centrifugal chillers with dual refrigeration cir-cuits, that used 2 gpm (0.0358 mL/J) of condenser water per ton of cooling, and was piped in a “series evaporator–series condenser” arrangement. As Table 1 indicates, arranging the chiller evaporators in se-ries reduced life-cycle costs by more than $1.4 million when compared with parallel arrangements. Series arrangements of Power per Pump kW Number of Cells Power per Cell kW Total Power, kW Figure 1: Series–series counterflow arrangement. Life-Cycle Cost, $ USD chiller evaporators have been used, when prudent, in many ap-plications. 7, 16 However, the chilled-water plant design that was selected for this project not only arranges the evaporators in series, but also arranges the condensers in series using a counterflow configuration (see Figure 1). At design conditions: • Chilled water enters the upstream chiller at 55°F (12.8°C) and exits at 45.1°F (7.3°C). • Chilled water enters the downstream chiller at 45.1°F (7.3°C) and exits at 37°F (2.8°C). Condenser water flows in the opposite direction of the chilled water, thus the term “counterflow:” • Condenser water enters the downstream chiller at 85°F (29.4°C) and exits at 91.3°F (32.9°C). • Condenser water enters the upstream chiller at 91.3°F (32.9°C) and exits at 98.9°F (37.2°C). Chiller Energy Consumption A chiller’s power demand reflects the amount of lift provided by the compressor. “Lift” describes the difference between evapo- * gpm × 0.0631 = L/s; gpm/ton × 0.0179 = mL/J; ft of water × 2.99 = kPa 24 June 2002|ASHRAE Journal
  • 3. Chillers rator pressure and condenser pressure: Evap. Refrigerant Temperature = Lvg. Chilled Water Temperature – Evap. Approach Tem-perature Cond. Refrigerant Temperature = Lvg. Cond. Water Temperature + Cond. Approach Temperature At saturation, these temperatures re-late directly to the refrigerant pressures in the evaporator and condenser. It is clear from Table 1 that the series– series counterflow arrangement yields the lowest full-load chiller power (about 14% lower than the parallel–parallel configuration). The dramatic reduction in chiller power oc-curs Figure 2: Conceptualization of reduced lift. because the upstream chiller in the series–series counterflow arrangement operates at a higher chilled water temperature, which means that the refrigerant temperature and refrigerant pressure in the evaporator are also higher in the upstream machine. Similarly, the downstream chiller “sees” a lower condenser leaving water temperature— and therefore has a lower condenser refrigerant pressure— than it would in a plant with the chiller condensers arranged in parallel. Figure 2 illustrates the concept of reduced lift using the design parameters for this chilled water plant. Although lift is the difference between the refrigerant pressures in the evapo-rator and condenser, its magnitude can be approximated using the difference between the water temperatures leaving the evaporator and condenser. Chiller power can be reduced by decreasing compressor “lift.” In this case, the difference in average lift at design is approximately 13%: 1 –{[(54.3 + 53.8)/2]/61.9} = 0.126 The reduction in lift provided by the series–series counterflow arrangement also occurs at part-load conditions. Why? The temperature of the water leaving the evaporator of the upstream chiller is always warmer than the system water, and the temperature of the water leaving the condenser of the downstream chiller is always cooler than the system water. Because each of the chillers in this design has two refrigera-tion circuits (Figure 1), the reduced lift effect is multiplied. Instead of two lifts, there are four (Figure 2). Therefore, the difference in average lift at design for the system with four independent refrigeration circuits in a series–series counterflow arrangement exceeds 19%: 1 – {[(51.1 + 50.3 + 50.0 + 48.9)/4]/61.9} = 0.191 The upstream chiller need not be equally loaded at all times; the anticipated savings come from that chiller’s abil-ity to produce chilled water at an elevated temperature. (When this article was written, the plant had not operated through an entire cooling season.) How the plant should re-spond to varying system conditions was discussed with the design engineer, plant owner, and plant operators. For ex-ample, if the entering chiller water temperature did not reach design conditions, the operators could: • Increase pump speed or the number of active pumps to increase flow rates through, and fully load, the active chillers. • Reset the setpoints of the upstream chillers to 55% of the total temperature difference. Lowering the setpoint of the up-stream chillers as the result of a drop in entering-chiller water temperature lessens the benefit of reduced lift. However, the upstream chillers will always run at a higher evaporator pressure than the downstream chillers, which saves energy consumption and costs. Chiller sequencing was also discussed. It was determined that the most cost-effective startup strategy would fully load one chiller module, and then activate the remaining chillers in modules (pairs). Activating the upstream chiller and operating it at the higher water temperature would take advantage of all of the available heat-transfer surface area without increasing the energy consumed by ancillary equipment. At the design conditions defined for the system, chiller per-formance is well below the 6.10 COP (0.576 kW/ton) require-ment set by ANSI/ASHRAE/IESNA Standard 90.1-2001, Energy Standard for Buildings Except Low-Rise Residential Build-ings. At standard ARI rating conditions, each chiller module would operate with an efficiency of 0.445 kW/ton.† The per-formance conditions for this application, however, were care-fully selected to optimize the overall energy consumption of the entire chilled water plant.1 † Standard ARI rating conditions are 44°F, 2.4 gpm/ton (6.7°C, 0.043 L/s per kW) for the evaporator and 85°F, 3 gpm/ton (29.4°C, 0.054 L/s per kW) for the condenser. ASHRAE Journal|June 2002 25
  • 4. Figure 3: Comparison of evaporator layouts. Figure 4: Comparison of counterflow condenser layouts. Focus on the System The reduction in chiller power comes at the expense of increased pumping energy. With the utility meter measuring the consumption of the entire plant—not the chillers alone— the ultimate goal must be to reduce plant power. Would the series–series counterflow arrangement reduce the compres-sor power enough to make up for the increase in pump power? Table 2 compares the overall power consumption for the chilled water plant based on three different arrange-ments of six chillers. In each case, the condenser-water flow rate is 2 gpm/ton (0.0358 mL/J). Chilled Water Pumps. The f ive chilled water pumps in this design are piped in a manifold ar-rangement; one of the Arrangement Pumps Evaporator Condenser Chillers Chilled Parallel Parallel 6,489 14 18 480 7,001 Series Parallel 5,827 60 18 480 6,385 Series Series Counter-flow 5,618 60 126 480 6,284 Table 2: Comparison of power requirements (kW) at identical rates of condenser water flow. pumps is redundant. Doubling the water flow through the evaporators created a water pressure drop that was significantly higher for the se-ries arrangements than for the parallel configurations (Table 1). To minimize this “penalty” as much as possible, single-pass tube bundles were used in the series evaporators. Other-wise, the pressure drop and resultant pump power would have been even higher. Despite the high water pressure drop, re-ducing compressor lift by arranging the evaporators in series yielded chiller power savings that dwarfed the additional pump power needed at full load. To further offset the economic impact of larger chilled wa-ter pumps, the plant design also varies primary flow through the chiller evaporators in response to system load. The “pump penalty” still exists at full load. However, it is significantly less at part load/partial flow because the differences in evapo-rator pressure drop and chilled water pumping power decrease rapidly as the flow rate slows. Combining variable primary flow and a series arrangement of evaporators circulates twice as much water through the evaporator of each chiller. This combination also creates a second advantage: each chiller can accommodate a much greater reduction in water flow, which post-pones the need for a sys-tem bypass. (Use of variable primary-flow systems is increasingly common and well docu-mented.) 4–6,9,11–12,14–15,17 Condenser Water Pumps. The condenser water pumps are piped in Cooling Tower Total Plant Water Condenser Water a manifold arrangement. In the selected plant configuration, one active pump is provided per chiller module. Redundancy is provided by two smaller pumps, which enables one of the pumps to operate during low-load conditions and reduce pumping energy consumption. This is described later. Basing an economic comparison of design alternatives on life-cycle costs requires an overall summation of the total costs for power (demand) and energy (consumption). Therefore, al-though the total power for the series–series counterflow plant was lowest (Table 2), it was also necessary to account for the costs related to energy consumption. Water flow rates and configurations for the chiller con- 26 June 2002|ASHRAE Journal
  • 5. Chillers densers were evaluated in a manner similar to that used for the chilled water loop. When the results were compared, the life-cycle cost analysis (Table 1) pointed to a system design that combined a series arrangement of the chiller condensers with a condenser water flow rate of 2 gpm/ton (0.0358 mL/J). Choosing this design permitted a smaller cooling tower and reduced the size of the condenser piping. It also reduced the initial and operating costs of the cooling tower fans and con-denser water pumps.8,10 As Table 1 reveals, arranging the con-densers in series significantly increased the pressure drop and required pumping power. Yet, the savings in chiller (com-pressor) power and energy offset this penalty, too. A further reduction in flow rate to 1.5 gpm/ton (0.268 mL/J) was also examined and would provide an even greater reduc-tion in tower fan power, but the plant owner did not allow any pipe cost for flow rates below 2 gpm/ton (0.0358 mL/J). Nor did the owner account for pump savings due to cooling tower height and static lift requirements. Although the effects of vari-able condenser water flow were considered, the owner decided that constant flow would simplify plant operation.‡ Space Considerations. The selected design for the chilled water plant provided one chilled water pump and one con-denser water pump for each chiller module. Two redundant pumps were provided as well: one for the chilled water loop and one for the condenser water loop. Collectively, these components occupy less space than a comparable primary– secondary system. Some variable primary-flow systems use fewer pumps than chillers to further reduce the space required for piping connections, variable speed drives, and electrical service for the pumps. Clarifying the Economics During the design phase, the owner sought to better under-stand the relationship between the operating characteristics of the series–series counterflow arrangement and the projected savings in life-cycle costs. Several questions of particular rel-evance are paraphrased here, along with their answers: Q: Won’t piping the chiller condensers in series, rather than in parallel, result in a significantly higher operating cost? A: Arranging the condensers in series does increase the pump-ing power per chiller module by 36 kW at full load, given the increased condenser pressure drop of 22 ft (66 kPa). However, the compressor power reduction per module is 69 kW, which far exceeds the 36 kW increase in pumping power. Remember, too, that the series–series counterflow arrangement always re-duces the required amount of compressor “lift,” even when the plant operates at part load. Sequencing the constant-volume ‡The authors of this article speculate that the decisions made by the plant owner represented a “comfortable” compromise between the series–series counterflow arrangement, which was economically sen-sible but unfamiliar, and other more conventional (and familiar) as-pects of chilled water plant design. Advertisement in the print edition formerly in this space. ASHRAE Journal|June 2002 27
  • 6. condenser pumps makes it possible to reduce flow to the mod-ules as the load decreases. This control strategy significantly reduces pumping energy consumption when the plant oper-ates at less than 50% of full-load capacity. Q: Because the chillers are started in pairs, the series– series counterflow arrangement of this design requires two, four, or six chillers at load conditions while a parallel–paral-lel configuration would only require one, three, or five chillers. Did the analysis account for this difference in pump-ing energy? A: Deciding to minimize the number of condenser water pumps used when three chiller modules operate led to the use of three large condenser pumps for this plant. All pumps operate whether the condensers were piped in parallel or in series. To save pumping energy when only one chiller mod-ule operates (that is, during “winter” load hours), the system is designed to supply only 3,500 gpm (220 L/s) of condenser water. Supplying two smaller pumps (rather than one large pump) for redundancy allowed this. In low-load conditions, only one of the smaller pumps is run. The manufacturer con-firmed that the chillers would operate properly at half of the design condenser water flow. Q: Compared with a parallel configuration, won’t the se-ries– series counterflow arrangement of chillers require awk-ward and more costly bypass piping and valves around each condenser and evaporator? A: Operating chillers in pairs is a concept. As such, the se-ries– series counterflow arrangement can be implemented by piping both loops, condenser and chilled water, in a similar manner to the more familiar parallel system. Such arrange-ments (Figure 3, Figure 4) provide virtually the same service-ability and redundancy, regardless of whether the chillers are piped in parallel or in series, unless all of the upstream chillers are simultaneously off-line for service. With either arrangement (series or parallel), the system will run out of capacity at peak load if one chiller is not in service. Flow through the operating chillers can be increased until the pumps no longer have enough power. However, after system load exceeds chiller capacity, the chilled water setpoint will not be maintained. Conclusions The series–series counterflow (series evaporators–series condensers) design required discussion and resolution of po-tential drawbacks, however, an independent analysis of life-cycle costs demonstrated that the series–series counterflow Advertisement in the print edition formerly in this space. 28 June 2002|ASHRAE Journal
  • 7. Chillers arrangement was the most cost-effective solution for this cen-tral chilled water plant. Since this project was awarded, at least two other chilled water plants have adopted similar configurations. The appli-cation discussed here was large (more than 10,000 tons [35 170 kW] of mechanical refrigeration), but the series–series counterflow concept can be, and has been, successfully applied to much smaller jobs. The same design challenges will be encountered and can be overcome when it makes economic sense. In all cases, remember that the utility meter is on the build-ing. The building owner pays the costs (demand plus con-sumption) of installing, maintaining, and operating the entire system—chillers, chilled water pumps, condenser water pumps, cooling tower fans, and controls. Analyze the actual load pro-file at ambient conditions to determine which design yields the lowest life-cycle cost. References 1. ARI Standard 550/590–1998, Standard for Water Chilling Pack-ages Using the Vapor Compressor Cycle (Arlington, VA: Air-Condi-tioning and Refrigeration Institute). 2. 2000 ASHRAE Handbook—HVAC Systems and Equipment. Chapter 11, “District Heating and Cooling.” 3. 2000 ASHRAE Handbook—HVAC Systems and Equipment Hand-book. Chapter 12, “Hydronic Heating and Cooling System Design.” 4. Avery, G. 2001. “Improving the efficiency of chilled water plants.” ASHRAE Journal 43(5):14–18. 5. Avery, G. 1998. “Controlling chillers in variable flow systems.” ASHRAE Journal 40(2):42–45. 6. Bahnfleth, W.P., E. Peyer. 2001. “Comparative analysis of variable and constant primary-flow chilled-water-plant performance.” HPAC Engineering, April, p. 50. 7. Coad, William J. 1998. “A fundamental perspective on chilled water systems.” Heating/Piping/Air Conditioning, August, pp. 59–66. 8. Demirchian, G.H., M.A. Maragareci. 1997. “The benefits of higher condenser water ΔT at Logan International Airport central chilled water plant.” IDEA 88th Annual Conference Proceedings, pp. 291–300. 9. Hartman, T. 2001. “All-variable speed centrifugal chiller plants.” ASHRAE Journal, September. 10. Kelly, D.W., T. Chan. 1999. “Optimizing chilled water plants.” Heating/Piping/Air Conditioning, January, pp. 145–147. 11. Kirsner, W. 1996. “The demise of the primary-secondary pump-ing paradigm for chilled water plant design.” Heating/Piping/Air Con-ditioning, November. 12. Luther, K. 1998. “Applying variable volume pumping.” Heat-ing/ Piping/Air Conditioning, October, pp. 53–58. 13. Rishel, J.B. 1996. HVAC Pump Handbook, pp. 109–112. 14. Schwedler, M., B. Bradley. 2000. “Variable-primary-flow sys-tems: An idea for chilled-water plants the time of which has come.” Heating/Piping/Air Conditioning, April, pp. 41–44. 15. Taylor, S. 2002. “Primary-only vs. primary-secondary variable-flow chilled water systems.” ASHRAE Journal 44(2):25–29. 16. Trane. 2001. Multiple-Chiller-System Design and Control, pp. 58–59. 17. Waltz, J.P. 1997. “Don’t ignore variable flow.” Contracting Busi-ness July:133–144. Advertisement in the print edition formerly in this space. ASHRAE Journal|June 2002 29