SlideShare a Scribd company logo
1 of 17
Good Neighbourly Relations
Committee
February 6, 2018
Update on work on the Jacques Cartier Bridge
(Montreal sector)
2
Outline
Good Neighbourly Relations
Committee
+ Work on the steel structure
- Work status
- Planning for the coming weeks
- Status of noise management
+ Other updates
+ Discussion period
+ Next meeting
3
Steel work – 2017-2019
4
Work status
+ Contractor: Stellaire Construction
+ Work monitoring: WSC
+ Overall start-up complete
+ Equipment delivered
+ Various types of work related to noise management
Work platform above De
Maisonneuve Boulevard
5
6
Steel work schedule
+ Work planned for the coming weeks
- Installation of scaffolding
- Set up of noise mitigation measures
• Approx. 4 nights of work
• Boom lift, forklift and tracked carrier at the site
- Surface preparation
• Grinding and sandblasting (day)
- Steel repairs
• Removal of rivets during the day (approx. 6
workers)
• Some steel work at night
7
Steel work schedule
+ Work shifts
- One work shift until early March
• 7:00 a.m. to 4:30 p.m. (30 workers)
- Two work shifts starting in early March
• 7:00 a.m. to 4:30 p.m. (12 workers)
• 9:00 p.m. to 5:30 a.m. (18 workers)
- From Monday morning to Friday night
8
Current location of sound level meters
Campion
De Maisonneuve
9
Noise management
Noise management plan – steel work site
+ Ambient noise readings taken before the work
+ Ongoing – Installation of acoustic barriers + noise
screens
+ Strict noise management by the monitoring team
+ Optimization of work schedules (as much noisy work
as possible done during the day)
10
Noise management
Measures have been monitored since start-up
+ Confinement of compressors (shelter made from plywood,
soundproofing panels and soundproofing wool)
+ Sound barrier installed near 2004 De Maisonneuve
+ Low-noise generator
11
Noise management
Measures have been monitored since start-up
+ Optimization of the work area
+ Attention paid to the choice and position of
temporary lighting
+ Contractor's work method
+ Site set up so as to reduce backing up of gangway
delivery truck
+ Boom lift with a white-noise back-up alarm
+ Forklift truck with a white-noise back-up alarm or
flagger used
+ Prebuilt gangway
+ Screws used as much as possible instead of nails
12
Other work – Steel
13
Other work
+ Priority replacement of a strut under the
multipurpose path on the west side between
René-Lévesque and Falardeau until mid-March
- Attention will be paid to the equipment used and
noise management. Guidelines have been given
to the contractor.
- Estimated work schedule: 3 weeks, including
start-up and dismantling.
+ Continued work to replace guard rails on the
multipurpose path and sidewalk
14
Other work
+ Continuation of winter maintenance pilot project
on the multipurpose path
- VéloBus Jacques-Cartier service offered
during peak hours in collaboration with the
RTL
Discussion period
16
Let’s stay connected!
Information and communication tools
+ Notices to residents
+ Work advisories available online and via e-mail alerts
+ Resource people
+ Good Neighbourly Relations Committee
+ Twitter account for the Jacques Cartier Bridge @pontJCBridge
+ www.JacquesCartierChamplain.ca
Questions, complaints or comments?
+ 450-651-8771
+ communications@pjcci.ca
Next meeting TBD (mid-April to mid-May)
Good Neighbourly Relations Commitee - Jacques Cartier Bridge - February 6th 2018

More Related Content

What's hot

Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCrosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Project - WTS Concrete
Project - WTS ConcreteProject - WTS Concrete
Project - WTS ConcreteDamian Brandon
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty CurryRWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty CurryRae Davies
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 

What's hot (20)

Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Hybrid Résumé-PR (2)
Hybrid Résumé-PR (2)Hybrid Résumé-PR (2)
Hybrid Résumé-PR (2)
 
Community Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank StationCommunity Information Meeting of parkette design plan at Fairbank Station
Community Information Meeting of parkette design plan at Fairbank Station
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Project - WTS Concrete
Project - WTS ConcreteProject - WTS Concrete
Project - WTS Concrete
 
Tippo International
Tippo InternationalTippo International
Tippo International
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Russell Noanoa resume for 2015
Russell Noanoa resume for 2015Russell Noanoa resume for 2015
Russell Noanoa resume for 2015
 
Tippo International
Tippo InternationalTippo International
Tippo International
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty CurryRWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Construction Noise Ordinance
Construction Noise OrdinanceConstruction Noise Ordinance
Construction Noise Ordinance
 

Similar to Good Neighbourly Relations Commitee - Jacques Cartier Bridge - February 6th 2018

College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 finalToronto Public Consultation Unit
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Pont Samuel-De Champlain Bridge
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016Pont Samuel-De Champlain Bridge
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Pont Samuel-De Champlain Bridge
 
Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017Pont Samuel-De Champlain Bridge
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Pont Samuel-De Champlain Bridge
 
Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Chris Myers
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Pont Samuel-De Champlain Bridge
 
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...Pont Samuel-De Champlain Bridge
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations CommitteeMeeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations CommitteePont Samuel-De Champlain Bridge
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Crosstown TO
 
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...Pont Samuel-De Champlain Bridge
 

Similar to Good Neighbourly Relations Commitee - Jacques Cartier Bridge - February 6th 2018 (20)

College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects2017 Planning: Presentation of major projects
2017 Planning: Presentation of major projects
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
2018 Planning
2018 Planning2018 Planning
2018 Planning
 
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
Jacques Cartier Bicycle Path Network - Advisory Committee - October 4, 2017
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
 
Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017Good neighbourly relations committee meeting - Brossard - January 25, 2017
Good neighbourly relations committee meeting - Brossard - January 25, 2017
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 
Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction Bathurst St and King St W TTC Track Allowance Reconstruction
Bathurst St and King St W TTC Track Allowance Reconstruction
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016Good neighbourly relations committee City of Brossard - May 4, 2016
Good neighbourly relations committee City of Brossard - May 4, 2016
 
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
 
Review of work in 2016
Review of work in 2016Review of work in 2016
Review of work in 2016
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations CommitteeMeeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee 2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
2018-06-19 - Jacques Cartier Bicycle Path Network - Advisory Committee
 
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
Meeting of the verdun  sud ouest good neighbourly relations committee - febru...Meeting of the verdun  sud ouest good neighbourly relations committee - febru...
Meeting of the verdun sud ouest good neighbourly relations committee - febru...
 

Recently uploaded

Causes of poverty in France presentation.pptx
Causes of poverty in France presentation.pptxCauses of poverty in France presentation.pptx
Causes of poverty in France presentation.pptxCamilleBoulbin1
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Baileyhlharris
 
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...Pooja Nehwal
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubssamaasim06
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Chameera Dedduwage
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatmentnswingard
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lodhisaajjda
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoKayode Fayemi
 
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...Delhi Call girls
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaKayode Fayemi
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxraffaeleoman
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIINhPhngng3
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar TrainingKylaCullinane
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, YardstickSaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, Yardsticksaastr
 
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...amilabibi1
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfSenaatti-kiinteistöt
 

Recently uploaded (20)

Causes of poverty in France presentation.pptx
Causes of poverty in France presentation.pptxCauses of poverty in France presentation.pptx
Causes of poverty in France presentation.pptx
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Bailey
 
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...
Aesthetic Colaba Mumbai Cst Call girls 📞 7738631006 Grant road Call Girls ❤️-...
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatment
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
Busty Desi⚡Call Girls in Sector 51 Noida Escorts >༒8448380779 Escort Service-...
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New Nigeria
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio III
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar Training
 
ICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdfICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdf
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, YardstickSaaStr Workshop Wednesday w/ Lucas Price, Yardstick
SaaStr Workshop Wednesday w/ Lucas Price, Yardstick
 
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 97 Noida Escorts >༒8448380779 Escort Service
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
 

Good Neighbourly Relations Commitee - Jacques Cartier Bridge - February 6th 2018

  • 1. Good Neighbourly Relations Committee February 6, 2018 Update on work on the Jacques Cartier Bridge (Montreal sector)
  • 2. 2 Outline Good Neighbourly Relations Committee + Work on the steel structure - Work status - Planning for the coming weeks - Status of noise management + Other updates + Discussion period + Next meeting
  • 3. 3 Steel work – 2017-2019
  • 4. 4 Work status + Contractor: Stellaire Construction + Work monitoring: WSC + Overall start-up complete + Equipment delivered + Various types of work related to noise management Work platform above De Maisonneuve Boulevard
  • 5. 5
  • 6. 6 Steel work schedule + Work planned for the coming weeks - Installation of scaffolding - Set up of noise mitigation measures • Approx. 4 nights of work • Boom lift, forklift and tracked carrier at the site - Surface preparation • Grinding and sandblasting (day) - Steel repairs • Removal of rivets during the day (approx. 6 workers) • Some steel work at night
  • 7. 7 Steel work schedule + Work shifts - One work shift until early March • 7:00 a.m. to 4:30 p.m. (30 workers) - Two work shifts starting in early March • 7:00 a.m. to 4:30 p.m. (12 workers) • 9:00 p.m. to 5:30 a.m. (18 workers) - From Monday morning to Friday night
  • 8. 8 Current location of sound level meters Campion De Maisonneuve
  • 9. 9 Noise management Noise management plan – steel work site + Ambient noise readings taken before the work + Ongoing – Installation of acoustic barriers + noise screens + Strict noise management by the monitoring team + Optimization of work schedules (as much noisy work as possible done during the day)
  • 10. 10 Noise management Measures have been monitored since start-up + Confinement of compressors (shelter made from plywood, soundproofing panels and soundproofing wool) + Sound barrier installed near 2004 De Maisonneuve + Low-noise generator
  • 11. 11 Noise management Measures have been monitored since start-up + Optimization of the work area + Attention paid to the choice and position of temporary lighting + Contractor's work method + Site set up so as to reduce backing up of gangway delivery truck + Boom lift with a white-noise back-up alarm + Forklift truck with a white-noise back-up alarm or flagger used + Prebuilt gangway + Screws used as much as possible instead of nails
  • 13. 13 Other work + Priority replacement of a strut under the multipurpose path on the west side between René-Lévesque and Falardeau until mid-March - Attention will be paid to the equipment used and noise management. Guidelines have been given to the contractor. - Estimated work schedule: 3 weeks, including start-up and dismantling. + Continued work to replace guard rails on the multipurpose path and sidewalk
  • 14. 14 Other work + Continuation of winter maintenance pilot project on the multipurpose path - VéloBus Jacques-Cartier service offered during peak hours in collaboration with the RTL
  • 16. 16 Let’s stay connected! Information and communication tools + Notices to residents + Work advisories available online and via e-mail alerts + Resource people + Good Neighbourly Relations Committee + Twitter account for the Jacques Cartier Bridge @pontJCBridge + www.JacquesCartierChamplain.ca Questions, complaints or comments? + 450-651-8771 + communications@pjcci.ca Next meeting TBD (mid-April to mid-May)