BOP Stack Outsource
Customer Focus
Nominee: Jennifer Trawinski
2
GE Title or job number
2/10/2015
Project Description:
Outsourcing two ultra deep water Blow Out Preventer
Stacks. Site Operations Leader for the assembly of
the two stacks and Factory Acceptance Testing using
a vendor who has never seen or built a stack before.
Building these stacks in the open without shelter or
protection from the elements.
Main Customer Concerns (CTQs):
- Schedule/Weather
- FOD (Foreign object damage)
- Vendor Craftsmanship Competency
- GE on site Technical Support
3
GE Title or job number
2/10/2015
Addressing Customer CTQs:
Schedule: Maintain weekly communication of schedule and
milestones; Cohesive coordination of sub vendors for
requirement support equipment
Weather: Site weather & evacuation plan developed and
approved by customer
Foreign Object Damage Prevention: Site FOD plan was
developed, approved by customer and conduct onsite
personnel training
Craftsmanship Competency: GE on site supervision, open
communications with vendor and quality process management
GE Technical Support: Established a GE Project Team to
support outsource vendor during the assembly and FAT
stages
4
GE Title or job number
2/10/2015
Maintaining Customer Focus
- Addressing daily customer concerns with
the highest priority
- Providing outsource vendor with GE
Technical Experts to maintain the level of
quality expected as if it was built in our own
GE MFG Facility.
- 80+ drawing deviations captured for
correction
- Zero HSE incidents
5
GE Title or job number
2/10/2015
Benefits from Outsourcing Stack
- Meeting the Customer’s requirements for
delivery which would not have happened in
2014 due to MFG capacity constraints.
- Expand supply chain capacity
- Ensuring the Businesses Financial Goals
are accomplished
- Recovery of $40 Million in overdue backlog
6
GE Title or job number
2/10/2015
Leading the Team
- Providing weekly updates to Houston on the
project status and Daily updates during Testing
- Maintaining a positive relationship with the onsite
customer and open communication with the main
customer in Houston
- Providing guidance and feedback to all GE
technical support personnel to achieve “One
Team” concept to customer & vendor.
- Most Importantly:
o Maintain GE Quality Standards
o Know & Listen to your Customer
o Lead by example
7
GE Title or job number
2/10/2015
Beginning March 17th 2014
8
GE Title or job number
2/10/2015
May 9th 2014
9
GE Title or job number
2/10/2015
Ending First Stack September 25th
2014

More Related Content

What's hot

PDF | PRINCE2 Foundation Certification Exam | Get Ready to Crack
PDF | PRINCE2 Foundation Certification Exam | Get Ready to CrackPDF | PRINCE2 Foundation Certification Exam | Get Ready to Crack
PDF | PRINCE2 Foundation Certification Exam | Get Ready to CrackMeghna Arora
 
Explosives Basic Training (3,5 days)
Explosives Basic Training (3,5 days)Explosives Basic Training (3,5 days)
Explosives Basic Training (3,5 days)Vadim Grinenko
 
Resume-Isrrael Ibarra(17-5-2016)
Resume-Isrrael Ibarra(17-5-2016)Resume-Isrrael Ibarra(17-5-2016)
Resume-Isrrael Ibarra(17-5-2016)Isrrael Ibarra
 
Google Partners - Certification
Google Partners - CertificationGoogle Partners - Certification
Google Partners - CertificationNeeraj Singh
 
презентация компании вальтер En rev 01
презентация компании вальтер En rev 01презентация компании вальтер En rev 01
презентация компании вальтер En rev 01perewod
 
Display Google Partners - Certification1
Display Google Partners - Certification1Display Google Partners - Certification1
Display Google Partners - Certification1deepak aryan
 
Robert Ginn Resume - 2015
Robert Ginn Resume - 2015Robert Ginn Resume - 2015
Robert Ginn Resume - 2015Robert Ginn
 
Resume of Anil Kumar K R
Resume of Anil Kumar K RResume of Anil Kumar K R
Resume of Anil Kumar K RANIL KUMAR
 
Google Partners - Search Advertising Certification
Google Partners - Search Advertising CertificationGoogle Partners - Search Advertising Certification
Google Partners - Search Advertising CertificationLalit Gangwar
 
Giovanni Whitman resume 2015
Giovanni Whitman resume 2015Giovanni Whitman resume 2015
Giovanni Whitman resume 2015Giovanni Whitman
 
Search Google Partners - Certification3
Search Google Partners - Certification3Search Google Partners - Certification3
Search Google Partners - Certification3deepak aryan
 

What's hot (20)

PDF | PRINCE2 Foundation Certification Exam | Get Ready to Crack
PDF | PRINCE2 Foundation Certification Exam | Get Ready to CrackPDF | PRINCE2 Foundation Certification Exam | Get Ready to Crack
PDF | PRINCE2 Foundation Certification Exam | Get Ready to Crack
 
Resume_geetha
Resume_geethaResume_geetha
Resume_geetha
 
Explosives Basic Training (3,5 days)
Explosives Basic Training (3,5 days)Explosives Basic Training (3,5 days)
Explosives Basic Training (3,5 days)
 
Resume-Isrrael Ibarra(17-5-2016)
Resume-Isrrael Ibarra(17-5-2016)Resume-Isrrael Ibarra(17-5-2016)
Resume-Isrrael Ibarra(17-5-2016)
 
Google Partners - Certification
Google Partners - CertificationGoogle Partners - Certification
Google Partners - Certification
 
AdWords Certification
AdWords Certification AdWords Certification
AdWords Certification
 
презентация компании вальтер En rev 01
презентация компании вальтер En rev 01презентация компании вальтер En rev 01
презентация компании вальтер En rev 01
 
Display Google Partners - Certification1
Display Google Partners - Certification1Display Google Partners - Certification1
Display Google Partners - Certification1
 
sjtcv_2016
sjtcv_2016sjtcv_2016
sjtcv_2016
 
Robert Ginn Resume - 2015
Robert Ginn Resume - 2015Robert Ginn Resume - 2015
Robert Ginn Resume - 2015
 
Resume of Anil Kumar K R
Resume of Anil Kumar K RResume of Anil Kumar K R
Resume of Anil Kumar K R
 
Google Partners - Search Advertising Certification
Google Partners - Search Advertising CertificationGoogle Partners - Search Advertising Certification
Google Partners - Search Advertising Certification
 
Giovanni Whitman resume 2015
Giovanni Whitman resume 2015Giovanni Whitman resume 2015
Giovanni Whitman resume 2015
 
search
searchsearch
search
 
Search Google Partners - Certification3
Search Google Partners - Certification3Search Google Partners - Certification3
Search Google Partners - Certification3
 
JVB_Resume_2016-7-6
JVB_Resume_2016-7-6JVB_Resume_2016-7-6
JVB_Resume_2016-7-6
 
Adwords certfied
Adwords certfiedAdwords certfied
Adwords certfied
 
CV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, AaronCV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, Aaron
 
Franco#12
Franco#12Franco#12
Franco#12
 
vijay cv
vijay cvvijay cv
vijay cv
 

Similar to BOP Stack Outsource

Similar to BOP Stack Outsource (20)

Project management
Project managementProject management
Project management
 
CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23CV_AVINASH B. WADASKAR-2016-08-23
CV_AVINASH B. WADASKAR-2016-08-23
 
JFS_CV-update_09-15[1]
JFS_CV-update_09-15[1]JFS_CV-update_09-15[1]
JFS_CV-update_09-15[1]
 
Husains CV
Husains CVHusains CV
Husains CV
 
MARTY_PATE
MARTY_PATEMARTY_PATE
MARTY_PATE
 
SS_New_Resume_200816
SS_New_Resume_200816SS_New_Resume_200816
SS_New_Resume_200816
 
resume_Celeste_May2015
resume_Celeste_May2015resume_Celeste_May2015
resume_Celeste_May2015
 
Bhavya Pratap_Resume-28-Sep-16
Bhavya Pratap_Resume-28-Sep-16Bhavya Pratap_Resume-28-Sep-16
Bhavya Pratap_Resume-28-Sep-16
 
Glynda Mcdougald resume
Glynda Mcdougald resumeGlynda Mcdougald resume
Glynda Mcdougald resume
 
CT CV (6)
CT CV (6)CT CV (6)
CT CV (6)
 
Samarth_Kumar_Resume_Jul_2016
Samarth_Kumar_Resume_Jul_2016Samarth_Kumar_Resume_Jul_2016
Samarth_Kumar_Resume_Jul_2016
 
Henry P. Agsaullo_Jr_Quality Professional
Henry P. Agsaullo_Jr_Quality ProfessionalHenry P. Agsaullo_Jr_Quality Professional
Henry P. Agsaullo_Jr_Quality Professional
 
R. Venkatraman-Resume
R. Venkatraman-ResumeR. Venkatraman-Resume
R. Venkatraman-Resume
 
Atanu_Sarkar_Resume
Atanu_Sarkar_ResumeAtanu_Sarkar_Resume
Atanu_Sarkar_Resume
 
Raghu cv oct 2015 version 2
Raghu cv oct 2015   version 2Raghu cv oct 2015   version 2
Raghu cv oct 2015 version 2
 
Resume_Development_Quality_Tushar_Karpe.PDF
Resume_Development_Quality_Tushar_Karpe.PDFResume_Development_Quality_Tushar_Karpe.PDF
Resume_Development_Quality_Tushar_Karpe.PDF
 
CV ABHI 06-09 - Copy
CV ABHI 06-09 - CopyCV ABHI 06-09 - Copy
CV ABHI 06-09 - Copy
 
Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
C V
C VC V
C V
 
Daniel Lee
Daniel LeeDaniel Lee
Daniel Lee
 

BOP Stack Outsource

  • 1. BOP Stack Outsource Customer Focus Nominee: Jennifer Trawinski
  • 2. 2 GE Title or job number 2/10/2015 Project Description: Outsourcing two ultra deep water Blow Out Preventer Stacks. Site Operations Leader for the assembly of the two stacks and Factory Acceptance Testing using a vendor who has never seen or built a stack before. Building these stacks in the open without shelter or protection from the elements. Main Customer Concerns (CTQs): - Schedule/Weather - FOD (Foreign object damage) - Vendor Craftsmanship Competency - GE on site Technical Support
  • 3. 3 GE Title or job number 2/10/2015 Addressing Customer CTQs: Schedule: Maintain weekly communication of schedule and milestones; Cohesive coordination of sub vendors for requirement support equipment Weather: Site weather & evacuation plan developed and approved by customer Foreign Object Damage Prevention: Site FOD plan was developed, approved by customer and conduct onsite personnel training Craftsmanship Competency: GE on site supervision, open communications with vendor and quality process management GE Technical Support: Established a GE Project Team to support outsource vendor during the assembly and FAT stages
  • 4. 4 GE Title or job number 2/10/2015 Maintaining Customer Focus - Addressing daily customer concerns with the highest priority - Providing outsource vendor with GE Technical Experts to maintain the level of quality expected as if it was built in our own GE MFG Facility. - 80+ drawing deviations captured for correction - Zero HSE incidents
  • 5. 5 GE Title or job number 2/10/2015 Benefits from Outsourcing Stack - Meeting the Customer’s requirements for delivery which would not have happened in 2014 due to MFG capacity constraints. - Expand supply chain capacity - Ensuring the Businesses Financial Goals are accomplished - Recovery of $40 Million in overdue backlog
  • 6. 6 GE Title or job number 2/10/2015 Leading the Team - Providing weekly updates to Houston on the project status and Daily updates during Testing - Maintaining a positive relationship with the onsite customer and open communication with the main customer in Houston - Providing guidance and feedback to all GE technical support personnel to achieve “One Team” concept to customer & vendor. - Most Importantly: o Maintain GE Quality Standards o Know & Listen to your Customer o Lead by example
  • 7. 7 GE Title or job number 2/10/2015 Beginning March 17th 2014
  • 8. 8 GE Title or job number 2/10/2015 May 9th 2014
  • 9. 9 GE Title or job number 2/10/2015 Ending First Stack September 25th 2014