A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: Using CPM, which activities have slack in this project? Muitiple Choice C. E B, 0 Using CPM, which activities have slack in this project? Multiple Choice C, E B, D A, B, C Only C F, G .