1. CURRICULM VITAE
SUMMARY DATA
NAME: James O’Dowd
POSITION SOUGHT: Site Supervisor
QUALIFICATIONS: SSSTS Reg No 1443858, CSCS
PTS AC/DCCR Sentinal No: 455541
CPCS 360 10 above and below, Tracked and
Wheeled, Telehandeler full reach, Dumper,
City & Gills Bricklaying (intermediate)
EMPLOYERS: Buckinghams
Vinchi
Terrawise
Macalpines
Clancydocwra
Gamble
First Engineering
Quattro
Readypower
Carrilion
PREFERRED LOCATION: South Yorkshire
AVAILABILTY: 1 Week
SUMMARY:
From an early age I have enjoyed working manually. My father’s building firm was a
good forum for basic skills. I then developed my interperson and communicative
skills dealing with the public during a short career in corperate communication.
Missing the creative and satisfaction I got from the building trade I soon went back.
Working as a Groundworker and Plant operative within civils construction and rail
civils. Both directly and more recently freelance through agencies. I work well within
a committed team structure. Strive to meet targets and deadlines with a very good
knowledge base. For 6 years my coss ticket gave me a strong understanding of
railway safty. Also 7 years of RRV op’s has varied the scope on other railway works.
I am always keen to learn and adapt well. Working freelance I have developed a good
relationship with many companys both large and small.
_____________________________________________________________________
2. EMPLOYMENT HISTORY
Oct 14-Present. Buckingham group/ SCP
POSITION: Supervisor/Machine operator
PROJECT: Earthworks and structures at MOD section of the Bicester to
Oxford Carillion joint venture for East West Rail, Chilton Rail
and Network rail.
DUTIES: Supervising, briefing implementation of POWRA. Operating
Excavator cutting embankment, Bunt, rabit netting instalment
and top soiling batter. Day to day running of 6 man gang in
section.
Jan 14-Oct-14 Vinchi/Venesky-Brown
POSITION: Supervisor
PROJECT: Nottingham Trams
DUTIES: Day to day running of small group. Liaising with GF
paperwork, keeping Principle contractor and
Clients safey file upto date. Daily POWRA, SSOW, Plant logs,
Havs, Permits to dig, spike, hot works. And help implement
when lifting PUWER, LOLER. Distrobution and records of
PPE
Mar 13-Jan 14 Terrawise/Randstad
POSITION: Ganger/ 360 Operator
PROJECT: Retford to Gainsborough re-signelng contract.
DUTIES: Daily briefing and signing of task brief and method statement.
plant logs, Permits and coss forms. Extraction of earth for
concrete base. Liaise and assist with shuttery joiner. Install
steal detail and cable ducts. Poar and easy float PSB base. Plus
2 other smaller REB bases. At different locations.
Instalation of FTP posts and LOC bases,boxes. Timber with
ballest board surrounds with hand rails. Drivers walk ways.
Rod and roping, Brick and ballest board re-enforcement.
3. Feb 12-Mar 13 Carillion civils north/Coyle
POSITION: Plant operator
PROJECT: Atherton rail bridge renewal.
DUTIES: 360, Telehandeler and Cherry picker op’s. Site set up and
service road. Bridge road strip down to under plates, Steel fix,
shutter and concrete cloak of existing brick stantions. Mass
pour of disused right and left void. Removal of old steel
structure. Assist sub-contract company with lift and placement
of new bridge.
June 11-Feb 13 Clancydocwra
POSITION: 360 Operator
PROJECT: Orban Railway station drainage installation
DUTIES: Trench, installation of drainage ducting. Gravel & tram rap.
Back fill and fit catch pits.
Jan 10-June 11 Gamble/Telent
POSITION: Supervisor/COSS
PROJECT: Peterbrough to Great Yarmouth Crossing re-signaling
and platform security cameras.
DUTIES: Daily briefs and signing of risk assessment, method statement
Oversee 2 gangs installing FTP, LOC boxes, rod and roping of
Manholes at crossing.
Construction of concrete top hat bases for security cameras on
platforms.
4. 8.10 QUATTRO & READYPOWER
POSSITION: RRV Operator
PROJECT: Various nationwide. Hire operator
8.10 J O’DOWD PLANT OP’S UK LTD
POSSITION: Director/Sole trader
PROJECT: Domestic driveway, Landscaping, General ground work’s, etc
DUTIES: Mini digger and mini dumper for hire.
7.8 MACALPINES/COYLE
POSSITION: Plant operator
PROJECT: Hunters lane Rugby railway walk over bridge.
DUTIES: Site set up. Service road, Block built fuel storage, relocation of
services, piles and bridge base. Bridge expansion, crash barrier,
crane pads, Embankment expansion, Haymaking, dumper
wagon loading. Block paving, kerb laying, batters.
Feb 06-Jan 07 OAKFIELD CONSTRUCTION
POSSITION: 360 Operator/Groundworker
PROJECT: Lindholm prison immigration wing
DUTIES: Foundations, foul drainage, manholes and benching. Re-route
of services. Fiber optic ducting. Floor sawing of old runway.
Street lamps and ducting 6 12 way.
_____________________________________________________________________
5. 0.6 FIRST ENGINEERING
POSITION: Railway civils labourer/COSS/Plant operator
PROJECT: Various nationwide
DUTIES: Troughing( extraction, installation , distribution)
UTX crossings( drum and brick)
LOC box bases
Drivers walk ways
Access steps
REB bases
PSB bases
Camera
Cable pulling
Stantion bases
Ballast board fencing
Retainer walls
Bank re-enforcement
Telehandeler and 360 ops
CONTACT: TEL/WATS APP: 07860551545
EMAIL: jamesodowd88@gmail.com
6. 0.6 FIRST ENGINEERING
POSITION: Railway civils labourer/COSS/Plant operator
PROJECT: Various nationwide
DUTIES: Troughing( extraction, installation , distribution)
UTX crossings( drum and brick)
LOC box bases
Drivers walk ways
Access steps
REB bases
PSB bases
Camera
Cable pulling
Stantion bases
Ballast board fencing
Retainer walls
Bank re-enforcement
Telehandeler and 360 ops
CONTACT: TEL/WATS APP: 07860551545
EMAIL: jamesodowd88@gmail.com