SlideShare a Scribd company logo
1 of 2
Download to read offline
Cameron LNG
Liquefaction Project Details
With a total cost of approximately
$10 billion, many benefits—both
locally and globally—will result from
the construction and operation of the
Cameron LNG liquefaction facilities.
PROJECT TIMELINE
November 2011 Commencement of Front End Engineering Design
January 2012 Cameron LNG received approval from the DOE to export up to
12 MTPA of domestically produced LNG from the Cameron LNG
facility to all current and future Free Trade Agreement (FTA)
countries.
April 2012 Submitted request to FERC to initiate pre-filing review process
December 2012 Filed permit application with FERC
April 2014 Final Environmental Impact Statement issued by FERC
June 2014 Received authorization from FERC to build facilities
August 2014 Final Investment Decision by Partners
September 2014 Received Final Non-FTA authorization from DOE
October 2014 Full construction begins
2019 First full year of commercial operation on all three trains
Artist’s rendering of Cameron Liquefaction Project
Cameron LNG is developing natural gas liquefaction and export facilities next
to its existing liquefied natural gas (LNG) receipt terminal in Hackberry,
Louisiana. It has obtained approval from the U.S. Department of Energy (DOE)
to export up to 12 million tonnes per annum (Mtpa), or approximately 1.7 billion
cubic feet (bcf) per day, of LNG to all Free Trade Agreement (FTA) countries, and
on September 2014 received final authorization to export to non-FTA countries.
Cameron LNG received notice in April 2014 that the Federal Energy Regulatory
Commission (FERC) issued the final environmental impact statement (EIS) to
construct and operate the liquefaction facilities, and in June 2014, FERC issued
authorization to site, construct and operate the project.
CAMERON LNG
Project Description
Cameron LNG’s existing receipt
terminal is situated along the
Calcasieu Ship Channel near
Hackberry, Louisiana. It is located
18 miles from the Gulf of Mexico
and connected to major interstate
pipelines via the Cameron Interstate
Pipeline.
The proposed liquefaction project will
use Cameron LNG’s existing facilities,
including two marine berths capable
of accommodating Q-Flex sized LNG
ships, three LNG storage tanks with
a combined storage capacity of
480,000 cubic meters, and vaporization
capability for regasification services
of 1.5 Bcf per day.
The completed liquefaction project
is expected to be comprised of three
liquefaction trains with a nameplate
of 4.5 Mtpa of capacity each.
Once the facilities are operational,
Cameron LNG will have the
capability to:
• liquefy domestically-produced
natural gas for export,
• import LNG and regasify it for
delivery to domestic markets, or
• re-export foreign-sourced LNG.
Commercial
Development Agreements
Affiliates of Sempra Energy, GDF
SUEZ S.A., Mitsubishi Corporation
(through a related company jointly
established with Nippon Yusen
Kabushiki Kaisha) and Mitsui & Co.,
Ltd. signed a joint venture agreement
to support the development, financing
and construction of the liquefaction
facility.
Cameron LNG signed 20-year tolling
agreements with GDF SUEZ S.A. and
affiliates of Mitsubishi Corporation
and Mitsui & Co., Ltd. for the facility’s
liquefaction capacity.
Economic Benefits
With a total cost of approximately
$10 billion, many benefits—both
locally and globally—will result from
the construction and operation of the
Cameron LNG liquefaction facilities,
including:
• Exports by our customers of
approximately $8.6 billion of
LNG per year and an average of
$2.2 billion of natural gas liquids
production, averaging total trade
balance benefits of $10.8 billion
per year based on 2011 dollars.
• Approximately 140 new full-time
jobs at Cameron LNG and an
•
additional 45 new jobs at the
headquarters in Houston, Tx.
The design, engineering and
construction of the project will
Responsible
Community Partners
Community Investment: We are
committed to the community where
we live and work. We invest time,
talent and financial resources to
help improve the quality of life for
our customers, neighbors and
employees. By partnering with local
organizations, we maintain a commit-
Cameron LNG is strategically located near a major pipeline
hub that can deliver domestic natural gas to the project.
©2014 Cameron LNG. All copyright and trademark rights reserved, 11845 10/16/14 AB
Engineering & Construction
Cameron LNG awarded the engineering
services contract to Foster Wheeler;
Cameron LNG
301 Main Street
Hackberry, LA 70645
Tel: 1-337-680-4677
Media: 1-866-257-1298
info@CameronLNG.com
www.CameronLNG.com
result in the creation of approxi-
mately 3,000 on-site jobs in
Southwest Louisiana.
ment to making a positive difference
in our community.
Marshland creation: Construction of
the liquefaction facilities will result
in the creation of beneficial marsh
wetlands in Cameron Parish.
and the engineering, procurement
and construction (EPC) contract to
CCJV, a joint venture between CB&I
and Chiyoda.

More Related Content

What's hot

Gary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningGary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningInforma Australia
 
The Prize and Pitfalls of the Global LNG Business - Betsey Spomer
The Prize and Pitfalls of the Global LNG Business - Betsey SpomerThe Prize and Pitfalls of the Global LNG Business - Betsey Spomer
The Prize and Pitfalls of the Global LNG Business - Betsey SpomerEnergy Intelligence
 
Gas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionGas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionBrandon Shin
 
130718 ditmeyer natural gas locomotives - trb
130718 ditmeyer   natural gas locomotives - trb 130718 ditmeyer   natural gas locomotives - trb
130718 ditmeyer natural gas locomotives - trb Stephanie Camay
 
LNG in Transportation Executive Summary
LNG in Transportation Executive SummaryLNG in Transportation Executive Summary
LNG in Transportation Executive SummaryPaul Cassar
 
Combine coal transshipment project report
Combine coal transshipment project reportCombine coal transshipment project report
Combine coal transshipment project reportshehri_cbe
 
Eagle LNG Terminal and Pipeline - Efficient solutions for the Balkans
Eagle LNG Terminal and Pipeline - Efficient solutions for the BalkansEagle LNG Terminal and Pipeline - Efficient solutions for the Balkans
Eagle LNG Terminal and Pipeline - Efficient solutions for the BalkansAlbania Energy Association
 
Peter O'Sullivan - Gladstone Port Corporation
Peter O'Sullivan - Gladstone Port CorporationPeter O'Sullivan - Gladstone Port Corporation
Peter O'Sullivan - Gladstone Port CorporationInforma Australia
 
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood MackenzieAlaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood Mackenzieallalaskagasline
 
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016Brad Keithley
 
Teekay LNG Partners Fourth Quarter and 2014 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2014 Earnings PresentationTeekay LNG Partners Fourth Quarter and 2014 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2014 Earnings PresentationTeekay LNG Partners L.P.
 
Teekay LNG Partners Fourth Quarter and 2012 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2012 Earnings PresentationTeekay LNG Partners Fourth Quarter and 2012 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2012 Earnings PresentationTeekay LNG Partners L.P.
 
Poyry - How can small-scale LNG help grow the European gas market? - Point of...
Poyry - How can small-scale LNG help grow the European gas market? - Point of...Poyry - How can small-scale LNG help grow the European gas market? - Point of...
Poyry - How can small-scale LNG help grow the European gas market? - Point of...Pöyry
 
Asia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionAsia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionInnovation Norway
 

What's hot (20)

Gary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningGary Cochrane - Bounty Mining
Gary Cochrane - Bounty Mining
 
The Prize and Pitfalls of the Global LNG Business - Betsey Spomer
The Prize and Pitfalls of the Global LNG Business - Betsey SpomerThe Prize and Pitfalls of the Global LNG Business - Betsey Spomer
The Prize and Pitfalls of the Global LNG Business - Betsey Spomer
 
Poten and partners
Poten and partnersPoten and partners
Poten and partners
 
Gas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionGas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distribution
 
PETROBRAS LNG PROJECT
PETROBRAS LNG PROJECTPETROBRAS LNG PROJECT
PETROBRAS LNG PROJECT
 
130718 ditmeyer natural gas locomotives - trb
130718 ditmeyer   natural gas locomotives - trb 130718 ditmeyer   natural gas locomotives - trb
130718 ditmeyer natural gas locomotives - trb
 
LNG in Transportation Executive Summary
LNG in Transportation Executive SummaryLNG in Transportation Executive Summary
LNG in Transportation Executive Summary
 
Combine coal transshipment project report
Combine coal transshipment project reportCombine coal transshipment project report
Combine coal transshipment project report
 
Eagle LNG Terminal and Pipeline - Efficient solutions for the Balkans
Eagle LNG Terminal and Pipeline - Efficient solutions for the BalkansEagle LNG Terminal and Pipeline - Efficient solutions for the Balkans
Eagle LNG Terminal and Pipeline - Efficient solutions for the Balkans
 
Peter O'Sullivan - Gladstone Port Corporation
Peter O'Sullivan - Gladstone Port CorporationPeter O'Sullivan - Gladstone Port Corporation
Peter O'Sullivan - Gladstone Port Corporation
 
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood MackenzieAlaskan LNG Exports Competitiveness Study by Wood Mackenzie
Alaskan LNG Exports Competitiveness Study by Wood Mackenzie
 
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016Wood MacKenzie Alaska LNG Competitiveness Study   Aug 2016
Wood MacKenzie Alaska LNG Competitiveness Study Aug 2016
 
Teekay LNG Partners Fourth Quarter and 2014 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2014 Earnings PresentationTeekay LNG Partners Fourth Quarter and 2014 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2014 Earnings Presentation
 
FERC_LNG
FERC_LNGFERC_LNG
FERC_LNG
 
Nusantra regas
Nusantra regasNusantra regas
Nusantra regas
 
Albania Oil and Gas & Energy 2015 Summit
Albania Oil and Gas & Energy 2015 SummitAlbania Oil and Gas & Energy 2015 Summit
Albania Oil and Gas & Energy 2015 Summit
 
Teekay LNG Partners Fourth Quarter and 2012 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2012 Earnings PresentationTeekay LNG Partners Fourth Quarter and 2012 Earnings Presentation
Teekay LNG Partners Fourth Quarter and 2012 Earnings Presentation
 
Poyry - How can small-scale LNG help grow the European gas market? - Point of...
Poyry - How can small-scale LNG help grow the European gas market? - Point of...Poyry - How can small-scale LNG help grow the European gas market? - Point of...
Poyry - How can small-scale LNG help grow the European gas market? - Point of...
 
Asia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionAsia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distribution
 
Eric Thorpe - IHS Markit
Eric Thorpe - IHS MarkitEric Thorpe - IHS Markit
Eric Thorpe - IHS Markit
 

Similar to 11337 CameronFctShts_LiquefactionProject

Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG Project
Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG ProjectLiquefied Natural Gas Limited Bear Head, Nova Scotia LNG Project
Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG ProjectMarcellus Drilling News
 
Investor deck september - final
Investor deck september - finalInvestor deck september - final
Investor deck september - finalDorianLPG2016
 
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...LOWaterkeeper
 
Cequence energy announces_operations_update_feb_20161
Cequence energy announces_operations_update_feb_20161Cequence energy announces_operations_update_feb_20161
Cequence energy announces_operations_update_feb_20161Julian Majic
 
New base 06 february 2021 energy news issue 1403 by khaled al awadi
New base 06 february  2021 energy news issue   1403  by khaled al awadiNew base 06 february  2021 energy news issue   1403  by khaled al awadi
New base 06 february 2021 energy news issue 1403 by khaled al awadiKhaled Al Awadi
 
New base special 16 april 2014
New base special  16  april 2014New base special  16  april 2014
New base special 16 april 2014Khaled Al Awadi
 
Teekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationTeekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationAltera Infrastructure
 
New base energy news issue 951 dated 20 november 2016
New base energy news issue  951 dated 20 november 2016New base energy news issue  951 dated 20 november 2016
New base energy news issue 951 dated 20 november 2016Khaled Al Awadi
 
ET_Q1_2022_Earnings_Presentation_Final_R.pdf
ET_Q1_2022_Earnings_Presentation_Final_R.pdfET_Q1_2022_Earnings_Presentation_Final_R.pdf
ET_Q1_2022_Earnings_Presentation_Final_R.pdfssuser6f254f1
 
February 2018 Presentation – Dorian LPG
February 2018 Presentation – Dorian LPGFebruary 2018 Presentation – Dorian LPG
February 2018 Presentation – Dorian LPGDorianLPG2016
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith
 
Dorian lpg june 2017
Dorian lpg   june 2017Dorian lpg   june 2017
Dorian lpg june 2017DorianLPG2016
 
focus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globefocus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globeKlaus Gohra
 
September ir deck final
September ir deck finalSeptember ir deck final
September ir deck finalDorianLPG2016
 

Similar to 11337 CameronFctShts_LiquefactionProject (20)

Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG Project
Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG ProjectLiquefied Natural Gas Limited Bear Head, Nova Scotia LNG Project
Liquefied Natural Gas Limited Bear Head, Nova Scotia LNG Project
 
Investor deck september - final
Investor deck september - finalInvestor deck september - final
Investor deck september - final
 
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
Grangemouth CCS project, Stephen Kerr, Summit Power - UKCCSRC Strathclyde Bia...
 
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...
 
Overview
 Overview Overview
Overview
 
Global cs ltr
Global cs ltrGlobal cs ltr
Global cs ltr
 
Global cs ltr
Global cs ltrGlobal cs ltr
Global cs ltr
 
PNG LNG
PNG LNGPNG LNG
PNG LNG
 
Cequence energy announces_operations_update_feb_20161
Cequence energy announces_operations_update_feb_20161Cequence energy announces_operations_update_feb_20161
Cequence energy announces_operations_update_feb_20161
 
New base 06 february 2021 energy news issue 1403 by khaled al awadi
New base 06 february  2021 energy news issue   1403  by khaled al awadiNew base 06 february  2021 energy news issue   1403  by khaled al awadi
New base 06 february 2021 energy news issue 1403 by khaled al awadi
 
New base special 16 april 2014
New base special  16  april 2014New base special  16  april 2014
New base special 16 april 2014
 
Teekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings PresentationTeekay Offshore Partners Q4-2016 Earnings Presentation
Teekay Offshore Partners Q4-2016 Earnings Presentation
 
New base energy news issue 951 dated 20 november 2016
New base energy news issue  951 dated 20 november 2016New base energy news issue  951 dated 20 november 2016
New base energy news issue 951 dated 20 november 2016
 
Clough CH-IV Brochure
Clough CH-IV BrochureClough CH-IV Brochure
Clough CH-IV Brochure
 
ET_Q1_2022_Earnings_Presentation_Final_R.pdf
ET_Q1_2022_Earnings_Presentation_Final_R.pdfET_Q1_2022_Earnings_Presentation_Final_R.pdf
ET_Q1_2022_Earnings_Presentation_Final_R.pdf
 
February 2018 Presentation – Dorian LPG
February 2018 Presentation – Dorian LPGFebruary 2018 Presentation – Dorian LPG
February 2018 Presentation – Dorian LPG
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-history
 
Dorian lpg june 2017
Dorian lpg   june 2017Dorian lpg   june 2017
Dorian lpg june 2017
 
focus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globefocus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globe
 
September ir deck final
September ir deck finalSeptember ir deck final
September ir deck final
 

11337 CameronFctShts_LiquefactionProject

  • 1. Cameron LNG Liquefaction Project Details With a total cost of approximately $10 billion, many benefits—both locally and globally—will result from the construction and operation of the Cameron LNG liquefaction facilities. PROJECT TIMELINE November 2011 Commencement of Front End Engineering Design January 2012 Cameron LNG received approval from the DOE to export up to 12 MTPA of domestically produced LNG from the Cameron LNG facility to all current and future Free Trade Agreement (FTA) countries. April 2012 Submitted request to FERC to initiate pre-filing review process December 2012 Filed permit application with FERC April 2014 Final Environmental Impact Statement issued by FERC June 2014 Received authorization from FERC to build facilities August 2014 Final Investment Decision by Partners September 2014 Received Final Non-FTA authorization from DOE October 2014 Full construction begins 2019 First full year of commercial operation on all three trains Artist’s rendering of Cameron Liquefaction Project Cameron LNG is developing natural gas liquefaction and export facilities next to its existing liquefied natural gas (LNG) receipt terminal in Hackberry, Louisiana. It has obtained approval from the U.S. Department of Energy (DOE) to export up to 12 million tonnes per annum (Mtpa), or approximately 1.7 billion cubic feet (bcf) per day, of LNG to all Free Trade Agreement (FTA) countries, and on September 2014 received final authorization to export to non-FTA countries. Cameron LNG received notice in April 2014 that the Federal Energy Regulatory Commission (FERC) issued the final environmental impact statement (EIS) to construct and operate the liquefaction facilities, and in June 2014, FERC issued authorization to site, construct and operate the project. CAMERON LNG
  • 2. Project Description Cameron LNG’s existing receipt terminal is situated along the Calcasieu Ship Channel near Hackberry, Louisiana. It is located 18 miles from the Gulf of Mexico and connected to major interstate pipelines via the Cameron Interstate Pipeline. The proposed liquefaction project will use Cameron LNG’s existing facilities, including two marine berths capable of accommodating Q-Flex sized LNG ships, three LNG storage tanks with a combined storage capacity of 480,000 cubic meters, and vaporization capability for regasification services of 1.5 Bcf per day. The completed liquefaction project is expected to be comprised of three liquefaction trains with a nameplate of 4.5 Mtpa of capacity each. Once the facilities are operational, Cameron LNG will have the capability to: • liquefy domestically-produced natural gas for export, • import LNG and regasify it for delivery to domestic markets, or • re-export foreign-sourced LNG. Commercial Development Agreements Affiliates of Sempra Energy, GDF SUEZ S.A., Mitsubishi Corporation (through a related company jointly established with Nippon Yusen Kabushiki Kaisha) and Mitsui & Co., Ltd. signed a joint venture agreement to support the development, financing and construction of the liquefaction facility. Cameron LNG signed 20-year tolling agreements with GDF SUEZ S.A. and affiliates of Mitsubishi Corporation and Mitsui & Co., Ltd. for the facility’s liquefaction capacity. Economic Benefits With a total cost of approximately $10 billion, many benefits—both locally and globally—will result from the construction and operation of the Cameron LNG liquefaction facilities, including: • Exports by our customers of approximately $8.6 billion of LNG per year and an average of $2.2 billion of natural gas liquids production, averaging total trade balance benefits of $10.8 billion per year based on 2011 dollars. • Approximately 140 new full-time jobs at Cameron LNG and an • additional 45 new jobs at the headquarters in Houston, Tx. The design, engineering and construction of the project will Responsible Community Partners Community Investment: We are committed to the community where we live and work. We invest time, talent and financial resources to help improve the quality of life for our customers, neighbors and employees. By partnering with local organizations, we maintain a commit- Cameron LNG is strategically located near a major pipeline hub that can deliver domestic natural gas to the project. ©2014 Cameron LNG. All copyright and trademark rights reserved, 11845 10/16/14 AB Engineering & Construction Cameron LNG awarded the engineering services contract to Foster Wheeler; Cameron LNG 301 Main Street Hackberry, LA 70645 Tel: 1-337-680-4677 Media: 1-866-257-1298 info@CameronLNG.com www.CameronLNG.com result in the creation of approxi- mately 3,000 on-site jobs in Southwest Louisiana. ment to making a positive difference in our community. Marshland creation: Construction of the liquefaction facilities will result in the creation of beneficial marsh wetlands in Cameron Parish. and the engineering, procurement and construction (EPC) contract to CCJV, a joint venture between CB&I and Chiyoda.