2. Programme Update - ITS
For Period : Mon 29th February – Friday 11th March
- Completed SFS (Steel Framing System) works to internal structure
- Commenced Bauder roofing to new build and re-commenced works to existing roof
- Commence works to form new dormer within roof
- Commenced external brick cleaning works to building façade
- Completed installation of underfloor heating works to all floors
- Completed refurbishment of windows within existing building
8. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete new dormer within roof
- Continue Bauder roofing to new build structure and works to existing re-roof
- Continue external brickwork to new-build structure
- Complete floor screed pour to all floors
- Complete construction of internal lift shift
- Commence internal partitions within new and existing buildings