SlideShare a Scribd company logo
1 of 1
Contract / Claim Management
in pre-contract, tender and performance stage:
 Legal System (Common and Civil law),
 Conflicts of Law (Pre contractual stage, Tort Law, Compliance Rules),
 International Forms of Contracts (Characteristics, substantial completion, taking
over, liquidated damages, claims, dispute resolution),
 Contract Documents (FiDiC Rainbow, Employer's REQUIREMENTS),
 Development stage (pre-contract, tender, performance), Employer's Duties /
Defaults (1_duty to pay, 2_duty to co-operate in respect of access to site, permits,
delay minimization, making financial arrangements, provide information, estoppel,
and 3_ to compensate),
 Contractor's Duties / Defaults <pre-contractual completion, completion of works,
quality and defects, Time for Compeltion>,
 Design Responsibility <design procedure, design warranties, design updates,
deliverables>,
 Time for Completion < Concurrent delay, disruptions, allocation of risks, Liquidated
Damages),
 Variations / Modifications <change orders, control, consequences, procedures,
avoidance>,
 Tailoring Test Procedures <until completion !, on completion, after completion>,
 Certificates <taking over, payments, valuation, delays, late payment, retention
monies>
 Defect Notification Period <DNP DLP : duty to remedy, removal of defective works,
failure to remedy defects, legal normal and decennial liability,
 Termination <for convenience, with good cause, consequences and termination
agreements> Discharge, Frustration, Force Majeure <risk allocation, normal
discharge, Rebus sic stantibus>, Risks / Insurance < assessment, all risk
insurance, uninsurable risks>
 Bonds <performance, pre-financing, retention>,
 Claims <procedural rules, preparation + review, documentation requirements,
avoidance, Extension of Time, Money Claims (Cost, profit, loss of productivity
claims)
 Dispute Resolution Methods (Amicable Settlement, Conciliation, Dispute
Adjudication Board, DAB / DB - Arbitration with binding effects of DB-decisions on
the parties, Litigation),
 Delay Schedules (failures to notify, defaults of employers and contractors, submit
sureties, programmes / schedules, approvals, claim notices, site visits, design
review period, determinations, notice to inspections, notice of dissatisfaction,
notice of unforeseeable physical conditions, scrutiny of employer’s requirements,
substantiation of a claim, terminations, referral of dispute to DAB /DB ,request to
provide reasonable evidence for financial arrangements and
 Samples / small workshops.

More Related Content

Viewers also liked

E drejta administrative fatmir berisha
E drejta administrative                  fatmir berishaE drejta administrative                  fatmir berisha
E drejta administrative fatmir berisha
fatmir berisha
 
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
Pramod Patil, PMP
 

Viewers also liked (16)

PMP Training Project Scope Management Part 2
PMP Training Project Scope Management Part 2PMP Training Project Scope Management Part 2
PMP Training Project Scope Management Part 2
 
Sky IPv6 Update
Sky IPv6 UpdateSky IPv6 Update
Sky IPv6 Update
 
Tesla World 2015 Herman Konings Cathedral Challenges
Tesla World 2015 Herman Konings Cathedral ChallengesTesla World 2015 Herman Konings Cathedral Challenges
Tesla World 2015 Herman Konings Cathedral Challenges
 
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
TECH START UP TURNED UTILITY – EMPOWERING CUSTOMERS WITH DATA TO TAKE CONTROL...
 
Systems Integration in the Cloud Era with Apache Camel @ ApacheCon Europe 2012
Systems Integration in the Cloud Era with Apache Camel @ ApacheCon Europe 2012Systems Integration in the Cloud Era with Apache Camel @ ApacheCon Europe 2012
Systems Integration in the Cloud Era with Apache Camel @ ApacheCon Europe 2012
 
Gett && Golang
Gett && GolangGett && Golang
Gett && Golang
 
JBoss OneDayTalk 2013: "NoSQL Integration with Apache Camel - MongoDB, CouchD...
JBoss OneDayTalk 2013: "NoSQL Integration with Apache Camel - MongoDB, CouchD...JBoss OneDayTalk 2013: "NoSQL Integration with Apache Camel - MongoDB, CouchD...
JBoss OneDayTalk 2013: "NoSQL Integration with Apache Camel - MongoDB, CouchD...
 
E drejta administrative fatmir berisha
E drejta administrative                  fatmir berishaE drejta administrative                  fatmir berisha
E drejta administrative fatmir berisha
 
Data Warehouse vs. Live Datamart - Comparison and Differences
Data Warehouse vs. Live Datamart - Comparison and DifferencesData Warehouse vs. Live Datamart - Comparison and Differences
Data Warehouse vs. Live Datamart - Comparison and Differences
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Procedura administrative si garanci per mbrojtjen e lirive dhe te drejtave ...
Procedura administrative  si garanci per mbrojtjen  e lirive dhe te drejtave ...Procedura administrative  si garanci per mbrojtjen  e lirive dhe te drejtave ...
Procedura administrative si garanci per mbrojtjen e lirive dhe te drejtave ...
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Enterprise Integration Patterns Revisited (EIP, Apache Camel, Talend ESB)
Enterprise Integration Patterns Revisited (EIP, Apache Camel, Talend ESB)Enterprise Integration Patterns Revisited (EIP, Apache Camel, Talend ESB)
Enterprise Integration Patterns Revisited (EIP, Apache Camel, Talend ESB)
 
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
2812_ASUG_AC_Scope_change_tracking_with_Project_System_Claim_Management
 

Similar to Kenya2015 Contract Claim Management Training

CV_ S Arunkumar -Procurement And Sub Contract
CV_ S  Arunkumar -Procurement And Sub ContractCV_ S  Arunkumar -Procurement And Sub Contract
CV_ S Arunkumar -Procurement And Sub Contract
Arunkumar Shirawalmath
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philip
Farhan Moosa
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013
Weero Koster
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
John Ashton
 

Similar to Kenya2015 Contract Claim Management Training (20)

Homer CV - CA2
Homer CV - CA2Homer CV - CA2
Homer CV - CA2
 
Project insurance claims
Project insurance claimsProject insurance claims
Project insurance claims
 
CV_ S Arunkumar -Procurement And Sub Contract
CV_ S  Arunkumar -Procurement And Sub ContractCV_ S  Arunkumar -Procurement And Sub Contract
CV_ S Arunkumar -Procurement And Sub Contract
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philip
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
U.S. Department of the Navy - Contracting Officer's Technical Representative ...
U.S. Department of the Navy - Contracting Officer's Technical Representative ...U.S. Department of the Navy - Contracting Officer's Technical Representative ...
U.S. Department of the Navy - Contracting Officer's Technical Representative ...
 
Indian Construction Contracts & Covid19 : Way Forward
Indian Construction Contracts & Covid19 : Way ForwardIndian Construction Contracts & Covid19 : Way Forward
Indian Construction Contracts & Covid19 : Way Forward
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Progress billing definition
Progress billing definitionProgress billing definition
Progress billing definition
 
Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013Nat windenergiecongres 16 mei 2013
Nat windenergiecongres 16 mei 2013
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Projects & contracts management, phases & meetings
Projects & contracts management, phases & meetingsProjects & contracts management, phases & meetings
Projects & contracts management, phases & meetings
 
Contracting Process Paper CPMGT_302.docx
Contracting Process Paper CPMGT_302.docxContracting Process Paper CPMGT_302.docx
Contracting Process Paper CPMGT_302.docx
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
APPLICATION OF ZONING VARIANCE
APPLICATION OF ZONING VARIANCEAPPLICATION OF ZONING VARIANCE
APPLICATION OF ZONING VARIANCE
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles project
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
CONTRACT MANAGEMENT.pptx
CONTRACT MANAGEMENT.pptxCONTRACT MANAGEMENT.pptx
CONTRACT MANAGEMENT.pptx
 

Kenya2015 Contract Claim Management Training

  • 1. Contract / Claim Management in pre-contract, tender and performance stage:  Legal System (Common and Civil law),  Conflicts of Law (Pre contractual stage, Tort Law, Compliance Rules),  International Forms of Contracts (Characteristics, substantial completion, taking over, liquidated damages, claims, dispute resolution),  Contract Documents (FiDiC Rainbow, Employer's REQUIREMENTS),  Development stage (pre-contract, tender, performance), Employer's Duties / Defaults (1_duty to pay, 2_duty to co-operate in respect of access to site, permits, delay minimization, making financial arrangements, provide information, estoppel, and 3_ to compensate),  Contractor's Duties / Defaults <pre-contractual completion, completion of works, quality and defects, Time for Compeltion>,  Design Responsibility <design procedure, design warranties, design updates, deliverables>,  Time for Completion < Concurrent delay, disruptions, allocation of risks, Liquidated Damages),  Variations / Modifications <change orders, control, consequences, procedures, avoidance>,  Tailoring Test Procedures <until completion !, on completion, after completion>,  Certificates <taking over, payments, valuation, delays, late payment, retention monies>  Defect Notification Period <DNP DLP : duty to remedy, removal of defective works, failure to remedy defects, legal normal and decennial liability,  Termination <for convenience, with good cause, consequences and termination agreements> Discharge, Frustration, Force Majeure <risk allocation, normal discharge, Rebus sic stantibus>, Risks / Insurance < assessment, all risk insurance, uninsurable risks>  Bonds <performance, pre-financing, retention>,  Claims <procedural rules, preparation + review, documentation requirements, avoidance, Extension of Time, Money Claims (Cost, profit, loss of productivity claims)  Dispute Resolution Methods (Amicable Settlement, Conciliation, Dispute Adjudication Board, DAB / DB - Arbitration with binding effects of DB-decisions on the parties, Litigation),  Delay Schedules (failures to notify, defaults of employers and contractors, submit sureties, programmes / schedules, approvals, claim notices, site visits, design review period, determinations, notice to inspections, notice of dissatisfaction, notice of unforeseeable physical conditions, scrutiny of employer’s requirements, substantiation of a claim, terminations, referral of dispute to DAB /DB ,request to provide reasonable evidence for financial arrangements and  Samples / small workshops.