Historical TCE releases at a missile launch facility contaminated underlying groundwater. A phased soil gas investigation was used to delineate the soil VOC source. An initial passive soil gas survey identified two hotspots. Follow up active soil gas sampling confirmed results and further delineated impacts. Deep nested soil gas wells profiled vertical contamination and showed one area had a continuous soil source through the vadose zone mass loading groundwater. This approach successfully mapped the soil contamination source.
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Phased Sequential Soil Gas Investigation
1. Phased Sequential Soil Gas Investigations to Delineate a Soil VOC
Source of Underlying Groundwater Contamination
David Springer, P.G., Joachim Eberharter, P.G., Brian Dow, P.G., Harry O’Neill,
and Craig Nathe
Platform Presentation
Historical releases of trichloroethene (TCE) at a former missile launch facility known as Space
Launch Complex 3 West (SLC-3W) at Vandenberg Air Force Base (AFB) have impacted underlying
groundwater and continue to source a contaminant plume estimated to occupy 265 acres. Previous
investigative work suggested the presence of two distinct groundwater source areas centered on
monitoring wells with elevated TCE concentrations. Persistent increasing TCE concentration trends
in several site wells resulted in additional study into the potential presence of a continuing soil source
of contamination.
Due to the depth of groundwater (>200 feet below ground surface [bgs]) and the size of the
investigation area, a conventional approach utilizing deep investigative soil borings was not cost-
effective. Previous negative results from soil samples collected from borings installed in a suspected
source area suggested that an alternative approach may prove more successful. Thus, a phased
investigative approach was devised, which featured an initial shallow passive soil gas (PSG) survey
using an 80-point grid with implants installed at 100-foot spacing to address the area known to overly
TCE groundwater concentrations greater than 1,000 micrograms per liter (µg/L), and which included
all suspected source areas. An active soil gas (ASG) survey was then implemented to confirm
passive results and permit step-out sampling to further delineate TCE presence. Finally, based on
these initial data sets, locations were targeted for installation of deep nested soil vapor monitoring
wells, designed to evaluate vertical contamination profiles and assess the provenance of TCE-
impacted groundwater at various site wells.
The conceptual site model (CSM) and groundwater fate and transport model were revised using these
data sets. A significant savings in project costs and compression of the project schedule was realized
through implementation of this phased soil gas investigation approach, which underscores its applica-
bility and effectiveness in mapping VOC contamination in soil.
David Springer, P.G.
Tetra Tech, Inc., 301 Mentor Drive, Suite A, Santa Barbara, CA 93111, USA, david.springer@tetratech.com,
Telephone: (805) 681-3100, Fax: (805) 681-3108
Joachim Eberharter, P.G.
Tetra Tech, Inc., 301 Mentor Drive, Suite A, Santa Barbara, CA 93111, USA, joa-
chim.eberharter@tetratech.com, Telephone: (805) 681-3100, Fax: (805) 681-3108
Brian Dow, P.G.
Tetra Tech, Inc., 301 Mentor Drive, Suite A, Santa Barbara, CA 93111, USA, brian.dow@tetratech.com, Tele-
phone: (805) 681-3100, Fax: (805) 681-3108
Harry O’Neill
Beacon Environmental Services, Inc., 323 Williams Street, Bel Air, MD 21014, USA harry.oneill@beacon-
usa.com, Telephone: (410) 838-8780, Fax: (410) 838-8740
Craig Nathe
Department of the United States Air Force, 30 CCEVR, 1028 Iceland Avenue, Vandenberg AFB, CA 93437,
USA, Amena.Atta@vandenberg.af.mil, Telephone: (805) 605-7249
Presenting Author: David Springer
2. PHASED SEQUENTIAL SOIL GAS
INVESTIGATIONS TO DELINEATE A SOIL
VOC SOURCE OF UNDERLYING
GROUNDWATER CONTAMINATION,
VANDENBERG AFB, USA
17 March 2011
Joachim Eberharter, P.G.
Tetra Tech, Inc.
David S. Springer, P.G.
Tetra Tech, Inc.
Craig Nathe
U.S. Air Force
Integrity - Service - Excellence
3. Overview
Site Location and Background
Overview of Project Objectives
Rationale Behind Phased Investigative Approach
Scope and Methods / Results
Findings & Conclusions
Questions?
Integrity - Service - Excellence 2
4. General Location Map
Source: Google Earth 2010
Integrity - Service - Excellence 3
5. Background – Site Map
Collectively,
Sites 5, 6, and 7
are referred to as
IRP Site 5 Cluster
Site 7
Bear Creek
Pond
Site 6
SLC-3W Site 5
SLC-3E
Integrity - Service - Excellence 4
6. Background
Typical launch facility infrastructure and operations.
TCE used to clean rocket engines.
Historical release resulted in 90 acre groundwater TCE plume.
Photo: U.S. Air Force
Photo: U.S. Air Force
Integrity - Service - Excellence 5
7. Background
Photo showing SLC-3W, with Building 770, deluge channel, retention
basin, and drilling at location 6-NSG-3B, looking northwest.
Integrity - Service - Excellence 6
10. Objectives of Phased Investigation
Confirm/refute presence of potential persistent soil impacts
sourcing groundwater contamination
Previous investigative work suggested presence of two distinct
groundwater source areas centered on monitoring wells with
elevated TCE concentrations (5-MW-15 and 5-MW-18)
Increasing TCE concentration trends in groundwater monitoring
wells suggested possible persistent soil sources
Delineate and assess soil impacts at source area and at
previously identified groundwater hot spots
Incorporate findings into updated HHERA, CSM, and numerical
groundwater model to support the FS
Integrity - Service - Excellence 9
11. Rationale for Phased Investigation
Considerations included: (1) large investigative area; (2) depth
to groundwater; and (3) negative results from previous soil
sampling in suspected source area
Initial passive soil gas survey designed to focus investigation
early on
Target area approximately 18 acres in size
Follow-up active soil gas investigation designed to confirm or
refute PSG survey results and further delineate TCE impacts
Provide soil gas concentration data
Areas identified during previous surveys targeted for deep
nested soil gas well installations and sampling (two phases)
Create vertical soil gas concentration profiles
Consistent with Triad approach featuring initial high data
density followed by high data quality
Integrity - Service - Excellence 10
12. Passive Soil Gas Survey – Scope and Methods
PSG survey conducted within 18 acre area overlying known
extent of TCE in groundwater >1,000 µg/L
Target area included suspected source area (deluge channel,
retention basin, well 6-MW-3) and wells 5-MW-15 and 5-MW-18
80 passive samplers containing hydrophobic adsorbent
material
100-ft grid spacing
Photo: Beacon Environmental Services, Inc.
Integrity - Service - Excellence 11
13. Passive Soil Gas Survey – Scope and Methods
Integrity - Service - Excellence 12
14. Passive Soil Gas Survey - Results
5-MW-18
Passive samplers used to evaluate
mass flux distribution
Results in units of nanograms
Prominent TCE hotspot centered
at inside elbow of deluge channel
Secondary hotspot identified
approximately 250 ft to the west
Results ruled out significant
contamination in remaining initial
18 acre target area
5-MW-15
6-MW-3
Integrity - Service - Excellence 13
15. Active Soil Gas Survey – Scope and Methods
Confirm/refute results of PSG survey
Assess TCE concentrations at source area and distal locations
Installed 34 double-nested soil gas probes at 17 locations at
nominal depths of 10 and 20 ft bgs using DPT
On-site mobile laboratory provided real-time data
Photo showing active soil gas survey at SLC-3W, looking north.
Integrity - Service - Excellence 14
16. Active Soil Gas Survey – Results
10 ft bgs 20 ft bgs
Integrity - Service - Excellence 15
17. Deep Soil Gas Investigation – Scope and Methods
Advanced four borings through nominally 230 ft of vadose zone
to groundwater using HSA technology
Continuously logged and screened soils (PID), collected soil
samples for environmental and soil physical properties testing,
and collected grab groundwater samples
Installed four quintuple-nested soil gas monitoring arrays (20
probes total) in two phases
6-inch woven stainless steel vapor probe inlets attached to ¼-inch
Nylaflow tubing terminated by Luer valves
Array assembled around central 1” PVC pipe while being lowered
inside augers
Probes carefully emplaced with construction materials (bentonite
hydrated in lifts, sand, etc.) while augers meticulously raised to
prevent formation collapse and ensure proper seal between probes
Minimum 3 system volumes purged days prior to sampling
Integrity - Service - Excellence 16
18. Deep Soil Gas Investigation – Scope and Methods
Samples collected with 50-ml
glass syringe and analyzed
by on-site mobile laboratory
Purge volume tests
Confirmation samples
collected in Summa canisters
for TO-15 analysis
Photo showing system purge
prior to sampling
Integrity - Service - Excellence 17
19. Deep Soil Gas Investigation – Scope and Methods
Photo showing installation of well 6-NSG-1, as tubing is
unspooled and attached onto central PVC pipe, looking northwest.
Integrity - Service - Excellence 18
20. Deep Soil Gas Investigation – Results
Primary purpose of nested arrays was to delineate vertical TCE
impacts in source area and determine provenance of TCE
impacts to groundwater at wells 5-MW-15 and 5-MW-18
Hypothesized three possible profiles, each indicative of a
different scenario explaining cause of soil gas impacts
Off-gassing from
groundwater according
to Henry’s and Fick’s
laws
Shallow soil impacts
coupled with off-gassing
from groundwater
Mass loading from soil
impacts throughout
vertical profile of vadose
zone
Integrity - Service - Excellence 19
21. Deep Soil Gas Investigation – Results
Integrity - Service - Excellence 20
22. Deep Soil Gas Investigation – Results
Investigation found deep perched groundwater zone beneath source
area at deluge channel; high TCE impacts (8,000 µg/L); underlying
groundwater impacts approx. 5,000 µg/L, consistent with
concentrations in wells 5-MW-15 and 5-MW-18
Vertical soil gas profiles at 6-NSG-1 and 6-NSG-4 (collocated with
5-MW-18 and 5-MW-15, respectively) consistent with off-gassing from
groundwater; ruled out as soil source areas; impacted groundwater
from these locations interpreted to have originated from source area
beneath deluge channel (near 6-MW-3)
Vertical soil gas profile at 6-NSG-2 shows mixed source of soil gas
impacts an no mass loading to groundwater from shallow vadose zone
Vertical soil gas profile at 6-NSG-3B (source area) shows continuous
soil source throughout upper vadose zone and mass loading to
underlying perched groundwater; soil impacts to lower vadose zone
(beneath perching clay) likely due to off-gassing from underlying
groundwater
Integrity - Service - Excellence 21
23. Deep Soil Gas Investigation – Results
6-NSG-1 6-NSG-4
Integrity - Service - Excellence 22
24. Deep Soil Gas Investigation – Results
6-NSG-2 6-NSG-3B
Integrity - Service - Excellence 23
25. Deep Soil Gas Investigation – Results
Integrity - Service - Excellence 24
26. Deep Soil Gas Investigation – Results
Integrity - Service - Excellence 25
28. Findings & Conclusions
Initial PSG survey quickly focused investigation, ultimately providing
more robust data set from area of interest
Results of subsequent ASG survey demonstrated viability and utility of
PSG surveys for preliminary screening purposes
Successful installation of 200-ft, quintuple-nested soil gas monitoring
well arrays and resulting informative data set demonstrated feasibility
and utility of this approach to evaluate provenance of groundwater and
extent of soil contamination
Use of soil gas matrix demonstrated as cost-effective alternative to soil
matrix sampling when evaluating soil source area, due to (1) greater
spatial reach with fewer sample locations and (2) repeatability of
sampling regimen
Approach facilitated regulator buy-in, expedited project schedule, and
reduced project costs allowing for bonus SVE pilot study at no extra
cost to the client
Integrity - Service - Excellence 27
29. Questions?
Joachim Eberharter, P.G.
Tetra Tech, Inc.
joachim.eberharter@tetratech.com
David Springer, P.G.
Tetra Tech, Inc.
david.springer@tetratech.com
Integrity - Service - Excellence 28