Getting Acquainted
1-2
Unit 4 Themes
• Understanding and reinforcing the rights and
responsibilities of each party involved in a
project.
• Understanding and reinforcing the rights and
responsibilities of the construction supervisor.
• Solving problems and resolving issues.
• Creating a win-win situation for all parties.
1-3
Unit 4 Objectives
• Understand critical information about contract documents
and construction law to help recognize the various roles and
responsibilities of all contracting parties.
• Understand how contract documents and construction law
can be helpful to solve problems, resolve issues and remedy
conflicts.
• Know how to develop jobsite processes that are consistent
with contract documents and construction law to maintain
positive relationships among contractors, architects,
engineers, and owners.
• Know how to create a productive, respectful environment on
the jobsite.
1-4
Session 1: Learning Objectives
• Describe the importance of contract documents
and construction law as they apply to
construction supervisors.
• Define key legal terms associated with contracts
and contract documents.
• Describe common contract documents.
• Describe how a contract is formed and define
basic legal terms used in construction
documents.
• Describe the contractual relationships among
various parties to a construction contract.
1-5
Contract Documents: Drawings
• Drawings graphically provide:
– Arrangements
– Materials
– Dimensions
– Configurations
– Other
1-6
Contract Documents:
Specifications
• Specifications provide:
– Written instructions that detail project
requirements.
– Information that is not easily shown on drawings.
1-7
Contract Documents:
Other Key Documents
• Other key documents:
– Contract
– Subcontract
– General conditions
– Supplemental conditions
– Addenda and change orders
– Purchase orders
– Request for information (RFI)
1-8
Elements of Contract Documents
• Common elements of a contract include:
– Mutual consent
– Offer and acceptance
– Exchanging something of value
– Operating in good faith
– Delivering and performing
– No violations of public policy
1-9
Using on the Job What You Learned
Today
• Summary: first key concept
– Recognize various contract documents, how they
relate to each other, and their importance in
providing information pertinent to successful job
completion.
1-10
Using on the Job What You Learned
Today
• Summary: second key concept
– Define a contract, understand terms common to
construction contracts, and recognize the
importance of following contractual obligations.
1-11
Using on the Job What You Learned
Today
• Summary: third key concept
– Understand the various roles contractual parties
have, how they interact, and the importance of
cultivating positive relationships between
contractual parties.
1-12
Review the Jobsite Assignment
2-2
Learning Objectives
• Differentiate between various contractual
relationships.
• Describe the roles and responsibilities of
contractual parties.
• Explain the supervisor’s role in different
contractual relationships.
• Describe potential dispute situations.
• Describe positive practices for dispute avoidance.
• Explain the Alternative Dispute Resolution (ADR)
process.
2-3
Types of Construction Contracts
• Lump-Sum (Fixed-Price) Contract
• Unit-Price Contract
• Negotiated Contract
2-4
Contractual Relationships
• Owner and Architect/Engineer
• Owner and General Contractor/Subcontractor
• Owner and Prime Contractor
• Owner and Construction Manager (CM)
• Owner and Design/Build
2-5
Roles and Responsibilities
• Search ConsensusDocs 200 for your answers.
• Next to each answer, write the article and
section number where you found the answer.
2-6
The Supervisor’s Role in
Contractual Relationships
• The construction supervisor represents the
contractor.
• Knowing relationships, roles, and
responsibilities will help you avoid disputes
and create a positive team process.
2-7
Nested Documents
2-8
All contract documents are related.
Alternative Dispute Resolution
2-9
Using on the Job What
You Learned Today
• Summary: first key concept
–Understand the importance of creating and
maintaining a positive workplace.
2-10
Using on the Job What
You Learned Today
• Summary: second key concept
–Recognize the benefits of building trust between
contractual parties.
2-11
Using on the Job What
You Learned Today
• Summary: third key concept
–Understand how good communication practices help
to avoid disputes.
2-12
Review the Jobsite Assignment
3-2
Learning Objectives
• Identify forms and documents commonly used by
professional associations and governmental
agencies.
• Describe design/build, construction management,
and subcontractor contracts.
• Explain federal, state, and local regulatory issues
concerning human resources, the environment, and
safety.
• Describe liens, bonds, and insurance requirements.
3-3
Standard Forms, Contracts,
and Documents
Standardized forms are prepared by:
–AGC
–AIA
–EJCDC
–CSI
–Federal Government
3-4
Standardized Contracts: a
Worksheet
Use the following ConsensusDocs:
200
500
280
415
420
3-5
Government Regulatory Issues
• AGC Principle 1
–Readily identified and well-defined classes of people
in our society have systematically been excluded from
full participation in the benefits of our society.
3-6
Government Regulatory Issues
• AGC Principle 2
–All persons in our society have an equal right to
employment, which is fundamentally a social right in
itself.
3-7
Government Regulatory Issues
• AGC Principle 3
–The “system” is obligated to correct discrimination
and requires affirmative action to overcome the
effects of past discriminations as well as to modify
future employment patterns.
3-8
Worksheet:
Liens, Bonds, and Insurance
Identify the type of insurance that probably
would cover the loss indicated by each situation.
Write the answer in the space provided.
3-9
Using on the Job What
You Learned Today
• Summary: first key concept
–Identify the common standard form contracts and
documents developed by various agencies; realize
these documents impact various supervisory
activities.
3-10
Using on the Job What
You Learned Today
• Summary: second key concept
–Recognize your role as defined in design/build,
construction management, and subcontractor
agreements.
3-11
Using on the Job What
You Learned Today
• Summary: third key concept
–Develop practices and attitudes that ensure equal
opportunity, protect the environment and produce
safe work conditions.
3-12
Using on the Job What
You Learned Today
• Summary: fourth key concept
–Recognize that liens, bonds, and insurance
requirements can affect successful completion of a
project.
3-13
Review the Jobsite Assignment
4-2
Learning Objectives
• Locate the articles that affect the important
aspects of managing general conditions.
• Recognize the roles and responsibilities
identified by the contract.
• Determine levels of decision-making authority.
• Evaluate the supervisor’s role and
responsibilities as an agent of the contractor.
• Describe project close-out procedures.
4-3
The General Conditions Contract
The General Conditions:
–Establish a common basis for relationships on a
project.
–Classify and clarify duties.
–Help to avoid disputes.
–Guide contractors in the execution of the project.
4-4
Terms of the General Conditions
Using ConsensusDocs 200, find the article and
section numbers that affect aspects of managing
general conditions.
4-5
Supplementary Conditions
Supplementary Conditions:
–Provide information that is specific to a project.
–Immediately follow the General Conditions.
–Are also referred to as Special Conditions.
–Should be reviewed and discussed prior to starting a
project.
4-6
Responsibilities
Using ConsensusDocs 200, read the information
contained in your assigned article.
Briefly list and describe the responsibilities as
determined by the article subparagraph.
4-7
Using General Conditions
Documents for Making Decisions
Determine the basis of authority for:
• The Owner
• The Architect/Engineer
• The Contractor
• The Subcontractor
4-8
The Supervisor as Agent of the
Contractor
• Authority
• Responsibility
• Personnel relations
• The public image
• Dealing with the owner
• Dealing with subcontractors
• Keeping records
4-9
Closing Out the Job
Closing out a job is like selling it to a
satisfied customer.
4-10
Using on the Job What
You Learned Today
• Summary: first key concept
–The General Conditions contract identifies the roles
and responsibilities of the parties involved in a
construction project.
4-11
Using on the Job What
You Learned Today
• Summary: second key concept
–The supervisor can use the contract documents to
determine the levels of decision-making authority.
4-12
Using on the Job What
You Learned Today
• Summary: third key concept
–Use a closing out control program to close out a
project.
4-13
Role Play Exercise
Cast of characters
Mike – the superintendent
Earl – a laborer
Inspector
Tom – the carpenter foreman
2 laborers
Mike’s assistant
5-2
Learning Objectives
• Describe the importance and necessity of
documentation.
• Manage a documentation system.
• Identify various types of documentation practices.
• Develop a model for a sound documentation system.
• Develop a win-win environment.
5-3
Review Jobsite Assignment
5-4
What is Field Documentation?
Documentation includes:
–A complete record of the project.
–All contract documents.
–Records of circumstances.
–Daily reports.
–Meeting minutes.
5-5
Documentation Systems
Documentation is:
–A systematic process for keeping regular, accurate,
complete and legible records of daily activities, actual
circumstances, and unusual events on a project.
5-6
Why Documentation is
So Important
Good documentation can:
–Identify issues
–Resolve conflicts
–Settle disputes
–Avoid litigation
–Provide tangible proof
5-7
Good Documentation Practices
Good documentation must be:
–Accurate
–Objective
–Complete
–Uniform
–Credible
–Timely
5-8
How to Document
Documentation Tools
–Computers
–Photographs
–Video cameras
–Audio recorders
–Written reports
–Daily logs
5-9
Meetings: a Simulation
5-10
Job Diary vs. Job Log
• Job diary: a personal account of all significant
events that occur on a jobsite.
• Job log: a record that tracks reports and forms
that are created, sent or received at a jobsite.
5-11
Role Play Review:
Writing the Report
5-12
Using on the Job What
You Learned Today
• Summary: first key concept
–Develop a documentation system that keeps
regular, accurate, complete and legible records of
daily events, actual circumstances, and unusual
activities on the project.
5-13
• Summary: second key concept
–Understand the various record keeping methods,
including cameras, camcorders, tape recorders,
company written forms, logs, diaries, etc.
Using on the Job What
You Learned Today
5-14
• Summary: third key concept
–It is important to record information in an
accurate and timely fashion.
Using on the Job What
You Learned Today
5-15
Review Jobsite Assignment
6-2
Learning Objectives
• Describe the three major causes of cost overruns.
• Explain the importance of the Changes Provision.
• List and define different types of changes.
• Identify notice and other contract requirements to
recover for changes.
• Explain how to handle differing site conditions
change requests.
6-3
Cost Overruns
• Common factors of cost overruns
–Inaccurate estimates
–Differing site conditions
–Inadequate supervision or management
6-4
The Changes Clause
...allows both the owner and the contractor
to make changes in the scope of a project
without having to negotiate a new contract.
6-5
Revisions to Contract Documents
A supervisor should never:
–Proceed with work that differs from requirements
stated in the contract documents.
–Implement any change to any contract requirements
without first obtaining a properly signed change
order.
6-6
Change Orders, Field Orders, and
Change Directives
Categories requiring change orders
–Owner’s requested change
–Designer’s requested change
–Contractor’s requested change
–Recommendations by subcontractors or material
suppliers
–Requirements by building inspectors or fire marshal
6-7
Using on the Job What
You Learned Today
• Summary: first key concept
–Know the three major causes of cost overruns and
identify how they can be avoided.
6-8
Using on the Job What
You Learned Today
• Summary: second key concept
–Identify different types of changes and know how
they should be handled.
6-9
Using on the Job What
You Learned Today
• Summary: third key concept
–Understand ways that time impacts can affect a
project, and which of them can be recovered
according to the contract documents.
6-10
Review Jobsite Assignment
7-2
Learning Objectives
• Find and identify time-related references in the
contract documents.
• Identify consequences of accelerations, delays,
suspensions and disruptions.
• Describe a process for managing requested
extensions.
• Analyze the effects of time-related issues on the
construction project.
7-3
Construction Schedules
Time impacts include:
–Accelerations — speed up the current process of
work.
–Delays — delays to the progress; can be excusable or
non-excusable.
–Suspensions — interruptions resulting in work
stoppage.
–Disruptions — interruptions causing delays.
7-4
Time Impacts
• Accelerations
• Delays
– Non-excusable
– Excusable
7-5
Excusable Delays
• Compensable
• Non-compensable
7-6
Types of Delays
7-7
Time Impacts
7-8
Consequences of Time-Related Issues
• Principal types of damage claims
–Liquidated damages
–Compensatory damages
–Delay damages
–Claims for latent defects
7-9
Using on the Job What
You Learned Today
• Summary: first key concept
–Various time impacts on the work can result in
compensable or non-compensable claims.
7-10
Using on the Job What
You Learned Today
• Summary: second key concept
–Contract documents provide a process for requesting
extensions of time.
7-11
Review Jobsite Assignment
8-2
Learning Objectives
• Identify the steps in the dispute resolution process.
• Describe the financial impacts of going to court.
• Explain the supervisor’s role in the dispute resolution
process.
• Describe how to obtain final resolution to disputes
that are win-win solutions.
• Summarize the key concepts learned in this course.
8-3
Dispute Resolution Process
Steps in Dispute Resolution:
–Prevention and negotiation
–Mediation
–Arbitration
–Dispute Boards
–Litigation
8-4
Dispute Resolution Process
8-5
Using on the Job What
You Learned Today
• Summary: first key concept
–Understand the ADR process and recognize that the
supervisor is critical to early resolution of problems.
8-6
Using on the Job What
You Learned Today
• Summary: second key concept
–Use partnering, direct negotiations, careful
documentation and cooperative attitudes to create a
win-win solution to potential disputes and claims.
8-7
Using on the Job What
You Learned Today
• Summary: third key concept
–Legal services are important to the project and the
contractor.
8-8
Using on the Job What
You Learned Today
• Summary: fourth key concept
–Rely on company attorneys to provide clear
explanations of contract language and advice on
resolution processes.
8-9
Closing Activities
• Registration and Evaluation
–Register course completion for the STP and
database
–Provide feedback
•Action Plan
–How you will apply what you have learned?
•Award Certificates
8-9

More Related Content

Similar to AGC_STP_PPT_Unit 4_Refresh_0.pptx

Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementGodfrey James
 
Dear students get fully solved assignments Send your semester & Specializatio...
Dear students get fully solved assignments Send your semester & Specializatio...Dear students get fully solved assignments Send your semester & Specializatio...
Dear students get fully solved assignments Send your semester & Specializatio...smumbahelp
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpmKaila Turla
 
Pm0012 – project finance and budgeting
Pm0012 – project finance and budgetingPm0012 – project finance and budgeting
Pm0012 – project finance and budgetingsmumbahelp
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxssuserc0bf9b
 
Mr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxMr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxssusercdf134
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction ProjectIRJET Journal
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
 
3303 Week 01
3303 Week 013303 Week 01
3303 Week 01ajr121
 
GP2-presentation (1).pptx
GP2-presentation (1).pptxGP2-presentation (1).pptx
GP2-presentation (1).pptxSuman Jain
 
Pob stage 2 lecture 15 slides intro to contract
Pob stage 2 lecture 15 slides intro to contractPob stage 2 lecture 15 slides intro to contract
Pob stage 2 lecture 15 slides intro to contractmoduledesign
 
Professional_practice_coa
Professional_practice_coaProfessional_practice_coa
Professional_practice_coaYogesh Bhardwaj
 
Professional_practice_I.pptx
Professional_practice_I.pptxProfessional_practice_I.pptx
Professional_practice_I.pptxYogesh Bhardwaj
 

Similar to AGC_STP_PPT_Unit 4_Refresh_0.pptx (20)

Practitioner class 4 Preparing the contract 04 july13
Practitioner class 4 Preparing the contract 04 july13Practitioner class 4 Preparing the contract 04 july13
Practitioner class 4 Preparing the contract 04 july13
 
Master's project viva zam
Master's project viva   zamMaster's project viva   zam
Master's project viva zam
 
IPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdfIPD-Whitepaper_2018-2.pdf
IPD-Whitepaper_2018-2.pdf
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Dear students get fully solved assignments Send your semester & Specializatio...
Dear students get fully solved assignments Send your semester & Specializatio...Dear students get fully solved assignments Send your semester & Specializatio...
Dear students get fully solved assignments Send your semester & Specializatio...
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpm
 
Pm0012 – project finance and budgeting
Pm0012 – project finance and budgetingPm0012 – project finance and budgeting
Pm0012 – project finance and budgeting
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Mr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptxMr Bolaji Johnson Paper.pptx
Mr Bolaji Johnson Paper.pptx
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
3303 Week 01
3303 Week 013303 Week 01
3303 Week 01
 
GP2-presentation (1).pptx
GP2-presentation (1).pptxGP2-presentation (1).pptx
GP2-presentation (1).pptx
 
Collaborative working
Collaborative workingCollaborative working
Collaborative working
 
professional practic
professional practicprofessional practic
professional practic
 
Pob stage 2 lecture 15 slides intro to contract
Pob stage 2 lecture 15 slides intro to contractPob stage 2 lecture 15 slides intro to contract
Pob stage 2 lecture 15 slides intro to contract
 
Professional_practice_coa
Professional_practice_coaProfessional_practice_coa
Professional_practice_coa
 
Professional_practice_I.pptx
Professional_practice_I.pptxProfessional_practice_I.pptx
Professional_practice_I.pptx
 

Recently uploaded

Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideDesign Studio UI UX
 
Software Architecture - Architecture Styles and Patterns-1.pdf
Software Architecture - Architecture Styles and Patterns-1.pdfSoftware Architecture - Architecture Styles and Patterns-1.pdf
Software Architecture - Architecture Styles and Patterns-1.pdfjordantsagmo
 
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement 210303105569
 
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样yhavx
 
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...Payal Garg #K09
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design1508 A/S
 
Spring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisSpring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisPeclers Paris
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Websitemark11275
 
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in RiyadhIn Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadhahmedjiabur940
 
Spring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisSpring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisPeclers Paris
 
Solutions For Social Media App Development (1).pptx
Solutions For Social Media App Development (1).pptxSolutions For Social Media App Development (1).pptx
Solutions For Social Media App Development (1).pptxBrain Inventory
 
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdf
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdfECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdf
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdfSarbjit Bahga
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...samsungultra782445
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky
 
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证ugzga
 
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证ugzga
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahimamgadibrahim92
 

Recently uploaded (20)

Essential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive GuideEssential UI/UX Design Principles: A Comprehensive Guide
Essential UI/UX Design Principles: A Comprehensive Guide
 
Software Architecture - Architecture Styles and Patterns-1.pdf
Software Architecture - Architecture Styles and Patterns-1.pdfSoftware Architecture - Architecture Styles and Patterns-1.pdf
Software Architecture - Architecture Styles and Patterns-1.pdf
 
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(RUG毕业证书)格罗宁根大学毕业证成绩单本科硕士学位证留信学历认证
 
Resume all my skills and educations and achievement
Resume all my skills and educations and  achievement Resume all my skills and educations and  achievement
Resume all my skills and educations and achievement
 
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UW毕业证书)华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
 
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UMN毕业证书)明尼苏达大学毕业证成绩单本科硕士学位证留信学历认证
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
 
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...
18+ Young ℂall Girls Vadodara Book Esha 7427069034 Top Class ℂall Girl Serviℂ...
 
Morgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity DesignMorgenbooster: Storytelling in Identity Design
Morgenbooster: Storytelling in Identity Design
 
Spring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers ParisSpring Summer 26 Colors Trend Book Peclers Paris
Spring Summer 26 Colors Trend Book Peclers Paris
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Website
 
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in RiyadhIn Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
In Saudi Arabia Jeddah (+918761049707)) Buy Abortion Pills For Sale in Riyadh
 
Spring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers ParisSpring Summer 2026 Inspirations trend book Peclers Paris
Spring Summer 2026 Inspirations trend book Peclers Paris
 
Solutions For Social Media App Development (1).pptx
Solutions For Social Media App Development (1).pptxSolutions For Social Media App Development (1).pptx
Solutions For Social Media App Development (1).pptx
 
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdf
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdfECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdf
ECHOES OF GENIUS - A Tribute to Nari Gandhi's Architectural Legacy. .pdf
 
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
Abortion pills in Riyadh +966572737505 <> buy cytotec <> unwanted kit Saudi A...
 
Edward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to PrintingEdward Boginsky's Trailblazing Contributions to Printing
Edward Boginsky's Trailblazing Contributions to Printing
 
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(UoB毕业证书)伯明翰大学毕业证成绩单本科硕士学位证留信学历认证
 
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证
如何办理(Birmingham毕业证书)伯明翰大学学院毕业证成绩单本科硕士学位证留信学历认证
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahim
 

AGC_STP_PPT_Unit 4_Refresh_0.pptx

  • 1.
  • 3. Unit 4 Themes • Understanding and reinforcing the rights and responsibilities of each party involved in a project. • Understanding and reinforcing the rights and responsibilities of the construction supervisor. • Solving problems and resolving issues. • Creating a win-win situation for all parties. 1-3
  • 4. Unit 4 Objectives • Understand critical information about contract documents and construction law to help recognize the various roles and responsibilities of all contracting parties. • Understand how contract documents and construction law can be helpful to solve problems, resolve issues and remedy conflicts. • Know how to develop jobsite processes that are consistent with contract documents and construction law to maintain positive relationships among contractors, architects, engineers, and owners. • Know how to create a productive, respectful environment on the jobsite. 1-4
  • 5. Session 1: Learning Objectives • Describe the importance of contract documents and construction law as they apply to construction supervisors. • Define key legal terms associated with contracts and contract documents. • Describe common contract documents. • Describe how a contract is formed and define basic legal terms used in construction documents. • Describe the contractual relationships among various parties to a construction contract. 1-5
  • 6. Contract Documents: Drawings • Drawings graphically provide: – Arrangements – Materials – Dimensions – Configurations – Other 1-6
  • 7. Contract Documents: Specifications • Specifications provide: – Written instructions that detail project requirements. – Information that is not easily shown on drawings. 1-7
  • 8. Contract Documents: Other Key Documents • Other key documents: – Contract – Subcontract – General conditions – Supplemental conditions – Addenda and change orders – Purchase orders – Request for information (RFI) 1-8
  • 9. Elements of Contract Documents • Common elements of a contract include: – Mutual consent – Offer and acceptance – Exchanging something of value – Operating in good faith – Delivering and performing – No violations of public policy 1-9
  • 10. Using on the Job What You Learned Today • Summary: first key concept – Recognize various contract documents, how they relate to each other, and their importance in providing information pertinent to successful job completion. 1-10
  • 11. Using on the Job What You Learned Today • Summary: second key concept – Define a contract, understand terms common to construction contracts, and recognize the importance of following contractual obligations. 1-11
  • 12. Using on the Job What You Learned Today • Summary: third key concept – Understand the various roles contractual parties have, how they interact, and the importance of cultivating positive relationships between contractual parties. 1-12
  • 13.
  • 14. Review the Jobsite Assignment 2-2
  • 15. Learning Objectives • Differentiate between various contractual relationships. • Describe the roles and responsibilities of contractual parties. • Explain the supervisor’s role in different contractual relationships. • Describe potential dispute situations. • Describe positive practices for dispute avoidance. • Explain the Alternative Dispute Resolution (ADR) process. 2-3
  • 16. Types of Construction Contracts • Lump-Sum (Fixed-Price) Contract • Unit-Price Contract • Negotiated Contract 2-4
  • 17. Contractual Relationships • Owner and Architect/Engineer • Owner and General Contractor/Subcontractor • Owner and Prime Contractor • Owner and Construction Manager (CM) • Owner and Design/Build 2-5
  • 18. Roles and Responsibilities • Search ConsensusDocs 200 for your answers. • Next to each answer, write the article and section number where you found the answer. 2-6
  • 19. The Supervisor’s Role in Contractual Relationships • The construction supervisor represents the contractor. • Knowing relationships, roles, and responsibilities will help you avoid disputes and create a positive team process. 2-7
  • 20. Nested Documents 2-8 All contract documents are related.
  • 22. Using on the Job What You Learned Today • Summary: first key concept –Understand the importance of creating and maintaining a positive workplace. 2-10
  • 23. Using on the Job What You Learned Today • Summary: second key concept –Recognize the benefits of building trust between contractual parties. 2-11
  • 24. Using on the Job What You Learned Today • Summary: third key concept –Understand how good communication practices help to avoid disputes. 2-12
  • 25.
  • 26. Review the Jobsite Assignment 3-2
  • 27. Learning Objectives • Identify forms and documents commonly used by professional associations and governmental agencies. • Describe design/build, construction management, and subcontractor contracts. • Explain federal, state, and local regulatory issues concerning human resources, the environment, and safety. • Describe liens, bonds, and insurance requirements. 3-3
  • 28. Standard Forms, Contracts, and Documents Standardized forms are prepared by: –AGC –AIA –EJCDC –CSI –Federal Government 3-4
  • 29. Standardized Contracts: a Worksheet Use the following ConsensusDocs: 200 500 280 415 420 3-5
  • 30. Government Regulatory Issues • AGC Principle 1 –Readily identified and well-defined classes of people in our society have systematically been excluded from full participation in the benefits of our society. 3-6
  • 31. Government Regulatory Issues • AGC Principle 2 –All persons in our society have an equal right to employment, which is fundamentally a social right in itself. 3-7
  • 32. Government Regulatory Issues • AGC Principle 3 –The “system” is obligated to correct discrimination and requires affirmative action to overcome the effects of past discriminations as well as to modify future employment patterns. 3-8
  • 33. Worksheet: Liens, Bonds, and Insurance Identify the type of insurance that probably would cover the loss indicated by each situation. Write the answer in the space provided. 3-9
  • 34. Using on the Job What You Learned Today • Summary: first key concept –Identify the common standard form contracts and documents developed by various agencies; realize these documents impact various supervisory activities. 3-10
  • 35. Using on the Job What You Learned Today • Summary: second key concept –Recognize your role as defined in design/build, construction management, and subcontractor agreements. 3-11
  • 36. Using on the Job What You Learned Today • Summary: third key concept –Develop practices and attitudes that ensure equal opportunity, protect the environment and produce safe work conditions. 3-12
  • 37. Using on the Job What You Learned Today • Summary: fourth key concept –Recognize that liens, bonds, and insurance requirements can affect successful completion of a project. 3-13
  • 38.
  • 39. Review the Jobsite Assignment 4-2
  • 40. Learning Objectives • Locate the articles that affect the important aspects of managing general conditions. • Recognize the roles and responsibilities identified by the contract. • Determine levels of decision-making authority. • Evaluate the supervisor’s role and responsibilities as an agent of the contractor. • Describe project close-out procedures. 4-3
  • 41. The General Conditions Contract The General Conditions: –Establish a common basis for relationships on a project. –Classify and clarify duties. –Help to avoid disputes. –Guide contractors in the execution of the project. 4-4
  • 42. Terms of the General Conditions Using ConsensusDocs 200, find the article and section numbers that affect aspects of managing general conditions. 4-5
  • 43. Supplementary Conditions Supplementary Conditions: –Provide information that is specific to a project. –Immediately follow the General Conditions. –Are also referred to as Special Conditions. –Should be reviewed and discussed prior to starting a project. 4-6
  • 44. Responsibilities Using ConsensusDocs 200, read the information contained in your assigned article. Briefly list and describe the responsibilities as determined by the article subparagraph. 4-7
  • 45. Using General Conditions Documents for Making Decisions Determine the basis of authority for: • The Owner • The Architect/Engineer • The Contractor • The Subcontractor 4-8
  • 46. The Supervisor as Agent of the Contractor • Authority • Responsibility • Personnel relations • The public image • Dealing with the owner • Dealing with subcontractors • Keeping records 4-9
  • 47. Closing Out the Job Closing out a job is like selling it to a satisfied customer. 4-10
  • 48. Using on the Job What You Learned Today • Summary: first key concept –The General Conditions contract identifies the roles and responsibilities of the parties involved in a construction project. 4-11
  • 49. Using on the Job What You Learned Today • Summary: second key concept –The supervisor can use the contract documents to determine the levels of decision-making authority. 4-12
  • 50. Using on the Job What You Learned Today • Summary: third key concept –Use a closing out control program to close out a project. 4-13
  • 51.
  • 52. Role Play Exercise Cast of characters Mike – the superintendent Earl – a laborer Inspector Tom – the carpenter foreman 2 laborers Mike’s assistant 5-2
  • 53. Learning Objectives • Describe the importance and necessity of documentation. • Manage a documentation system. • Identify various types of documentation practices. • Develop a model for a sound documentation system. • Develop a win-win environment. 5-3
  • 55. What is Field Documentation? Documentation includes: –A complete record of the project. –All contract documents. –Records of circumstances. –Daily reports. –Meeting minutes. 5-5
  • 56. Documentation Systems Documentation is: –A systematic process for keeping regular, accurate, complete and legible records of daily activities, actual circumstances, and unusual events on a project. 5-6
  • 57. Why Documentation is So Important Good documentation can: –Identify issues –Resolve conflicts –Settle disputes –Avoid litigation –Provide tangible proof 5-7
  • 58. Good Documentation Practices Good documentation must be: –Accurate –Objective –Complete –Uniform –Credible –Timely 5-8
  • 59. How to Document Documentation Tools –Computers –Photographs –Video cameras –Audio recorders –Written reports –Daily logs 5-9
  • 61. Job Diary vs. Job Log • Job diary: a personal account of all significant events that occur on a jobsite. • Job log: a record that tracks reports and forms that are created, sent or received at a jobsite. 5-11
  • 62. Role Play Review: Writing the Report 5-12
  • 63. Using on the Job What You Learned Today • Summary: first key concept –Develop a documentation system that keeps regular, accurate, complete and legible records of daily events, actual circumstances, and unusual activities on the project. 5-13
  • 64. • Summary: second key concept –Understand the various record keeping methods, including cameras, camcorders, tape recorders, company written forms, logs, diaries, etc. Using on the Job What You Learned Today 5-14
  • 65. • Summary: third key concept –It is important to record information in an accurate and timely fashion. Using on the Job What You Learned Today 5-15
  • 66.
  • 68. Learning Objectives • Describe the three major causes of cost overruns. • Explain the importance of the Changes Provision. • List and define different types of changes. • Identify notice and other contract requirements to recover for changes. • Explain how to handle differing site conditions change requests. 6-3
  • 69. Cost Overruns • Common factors of cost overruns –Inaccurate estimates –Differing site conditions –Inadequate supervision or management 6-4
  • 70. The Changes Clause ...allows both the owner and the contractor to make changes in the scope of a project without having to negotiate a new contract. 6-5
  • 71. Revisions to Contract Documents A supervisor should never: –Proceed with work that differs from requirements stated in the contract documents. –Implement any change to any contract requirements without first obtaining a properly signed change order. 6-6
  • 72. Change Orders, Field Orders, and Change Directives Categories requiring change orders –Owner’s requested change –Designer’s requested change –Contractor’s requested change –Recommendations by subcontractors or material suppliers –Requirements by building inspectors or fire marshal 6-7
  • 73. Using on the Job What You Learned Today • Summary: first key concept –Know the three major causes of cost overruns and identify how they can be avoided. 6-8
  • 74. Using on the Job What You Learned Today • Summary: second key concept –Identify different types of changes and know how they should be handled. 6-9
  • 75. Using on the Job What You Learned Today • Summary: third key concept –Understand ways that time impacts can affect a project, and which of them can be recovered according to the contract documents. 6-10
  • 76.
  • 78. Learning Objectives • Find and identify time-related references in the contract documents. • Identify consequences of accelerations, delays, suspensions and disruptions. • Describe a process for managing requested extensions. • Analyze the effects of time-related issues on the construction project. 7-3
  • 79. Construction Schedules Time impacts include: –Accelerations — speed up the current process of work. –Delays — delays to the progress; can be excusable or non-excusable. –Suspensions — interruptions resulting in work stoppage. –Disruptions — interruptions causing delays. 7-4
  • 80. Time Impacts • Accelerations • Delays – Non-excusable – Excusable 7-5
  • 84. Consequences of Time-Related Issues • Principal types of damage claims –Liquidated damages –Compensatory damages –Delay damages –Claims for latent defects 7-9
  • 85. Using on the Job What You Learned Today • Summary: first key concept –Various time impacts on the work can result in compensable or non-compensable claims. 7-10
  • 86. Using on the Job What You Learned Today • Summary: second key concept –Contract documents provide a process for requesting extensions of time. 7-11
  • 87.
  • 89. Learning Objectives • Identify the steps in the dispute resolution process. • Describe the financial impacts of going to court. • Explain the supervisor’s role in the dispute resolution process. • Describe how to obtain final resolution to disputes that are win-win solutions. • Summarize the key concepts learned in this course. 8-3
  • 90. Dispute Resolution Process Steps in Dispute Resolution: –Prevention and negotiation –Mediation –Arbitration –Dispute Boards –Litigation 8-4
  • 92. Using on the Job What You Learned Today • Summary: first key concept –Understand the ADR process and recognize that the supervisor is critical to early resolution of problems. 8-6
  • 93. Using on the Job What You Learned Today • Summary: second key concept –Use partnering, direct negotiations, careful documentation and cooperative attitudes to create a win-win solution to potential disputes and claims. 8-7
  • 94. Using on the Job What You Learned Today • Summary: third key concept –Legal services are important to the project and the contractor. 8-8
  • 95. Using on the Job What You Learned Today • Summary: fourth key concept –Rely on company attorneys to provide clear explanations of contract language and advice on resolution processes. 8-9
  • 96. Closing Activities • Registration and Evaluation –Register course completion for the STP and database –Provide feedback •Action Plan –How you will apply what you have learned? •Award Certificates 8-9