SlideShare a Scribd company logo
1 of 33
By Farhad Khazaeli
Fall 2014
Australasian society for trenchless technology (astt)
 Pipe bursting is trenchless methods used to replace existing
pipelines in the same alignment without physically removing
the existing pipeline.
 Pipe bursting was first developed in the United Kingdom in
the late 1970s by D. J. Ryan & Sons
 This method was patented in the United Kingdom in 1981
and in the United States in 1986; but expired in April 2005.
Najafi, 2010
 Pipe bursting typically involves insertion of a cone-shaped
bursting head into an existing
 The base of the cone is larger than the inside diameter of the
existing pipe and slightly larger than the outside diameter
 The back end of the bursting head is connected to the new pipe
and the front end is attached to a cable or pulling rod
 The new pipe and bursting head are launched from the insertion
shaft and the cable or pulling rod is pulled from the pulling shaft
Najafi, 2010
 Pipe bursting is too widely used to replace deteriorated
pipes with new pipes of the same or larger diameter
 Currently, pipe bursting is used to replace waterlines,
gas lines, and sewer lines throughout the world
Najafi, 2010
 pulling cable or rod (static method)
 hydraulic source (hydraulic method)
 air compressor (pneumatic method)
Najafi, 2010
 The most common pipe-bursting method is the pneumatic system.
 The bursting tool is a soil displacement hammer driven by
compressed air
 The hammer operated at a rate of 180 to 580 blows per minute.
 It is similar to a pile-driving operation, but in a horizontal
orientation.
Najafi, 2010
http://budgetsewer.com/
Movie
1. The head is attached to the new pipe,
2. The winch cable is inserted through the existing pipe and attached to the head
3. The air compressor and the winch are set at constant pressure and tension
values.
4. The process continues with operator supervision until the head reaches the
pulling shaft at which point it is separated from the new pipe and retrieved
Najafi, 2010
Najafi, 2010
the old pipe is burst in two steps:
1. The bursting head is pulled into the existing pipe with a
winch cable, which is inserted from the reception pit
2. The head is expanded laterally to break that pipe. An axially
mounted hydraulic piston drives the lateral expansion head
This method of pipe bursting is not common
Najafi, 2010
Najafi, 2010
 The cone transfers the horizontal pulling force into a radial force
 The steel rods, each about 4 ft in length, are inserted into the
existing pipe from the pulling shaft.
 A hydraulic unit in the pulling shaft pulls the rods
 The tensile force of a cable compared to a rod section is limited
Najafi, 2010
 A form of static pipe-bursting method
 The method for breaking and replacing cast-iron or ductile iron pipes by
longitudinal slitting.
 A splitting wheel or cutting knives, slit the pipe longitudinally at two
more lines along the side of the pipe
 A new pipe of the same or larger diameter may be drawn behind the
splitting tool
Najafi, 2010
http://plasticpipe.org/
Australasian society for trenchless technology (astt)
This method excavates the existing pipe in very fine particles and
Removes the existing pipe rather than displaces them into the
surrounding ground like:
HDD, MTBM, or HAB methods
Najafi, 2010
Pipe removal is further divided into several methods:
1. Pipe reaming and impactor methods
2. Pipe eating
3. Pipe ejection or pipe extraction
Najafi, 2010
• Pipe reaming is a pipe replacement technique that uses an HDD
machine with minor modifications.
• Removal of the existing pipe is accomplished by mixing the
ground material with the drilling fluid and transferring it to an exit
point
Najafi, 2010
Najafi, 2010
1. The patented impactor method is a system that combines the
HDD method with pipe bursting
2. The bursting head (impactor) receives air through the HDD drill
rod
3. The drill rod is pushed through existing pipe to the next manhole
or exit pit
Najafi, 2010
4. The impactor device, after it is attached to the drill stem and to
the new pipe, is activated and pulled into the existing pipe
5. The impactor system bursts the existing pipe by combined action
of pulling using the HDD rig and hammering with the impactor
device breaking the existing pipe and replacing it with the new
pipe
Najafi, 2010
Najafi, 2010
This method pushes or jacks a new pipe into the existing deteriorated
Pipe
Pipe extraction can remove existing pipes for disposal and replace
them with new high density polyurethane (HDPE) or polyurethane
(PE) pipes
Najafi, 2010
1. The lead a heavy steel guide pipe which maintains the alignment within
the center of the existing pipe
2. The cracker which fractures the existing pipe
3. The cone expander which radially expands the fractured line into the
surrounding soil
4. The front jack, a hydraulic cylinder, which provides axial thrust to the
penetration/compaction pieces
5. The pipe adapter, which provides mating surfaces, linking the new pipe
to the front jack
Najafi, 2010
Najafi, 2010
http://www.unitracc.com/
 The process can potentially be executed by horizontal auger
boring
 Excavates the existing pipe and surrounding soil by using a
rotating cutting head attached to an auger
 Other potential methods of pipe eating are using a modified
version of the MTBM or using pipe ramming equipment
Najafi, 2010
youtub
Movie
 High and medium-density polyethylene (HDPE or MDPE)
 The main advantages of PE pipes are
 Continuity
 Flexibility
 Versatility
 Smooth interior surface
 Smooth exterior surface
Najafi, 2010
 Pipe bursting is most cost advantageous compared to the lining
techniques when:
 There are few lateral connections to be reconnected within a replacement
section
 The existing pipe is structurally deteriorated
 Additional capacity is needed
Najafi, 2010
 Much faster
 More efficient
 Often less expensive than open-cut, especially in sewer
applications due to the large depths
 Specific studies in the United States have shown that pipe
bursting cost savings are as high as 44% , with an average
savings of 25 % , compared to open-cut (Fraser et al., 1992)
Najafi, 2010
 Insertion and pulling shafts are required, especially for larger bursts
 Excavation for service lateral connections is required
 Expansive soils may cause difficulties
 A collapsed (existing) pipe segment may require excavation at that point
to allow the insertion of pulling cable or rod and to repair pipe sag
 Point repairs with ductile material can interfere with the bursting and
replacement process
Najafi, 2010

More Related Content

Similar to Pipe Replacement Method

BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326Danny Flett
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Western Pipeway
 
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerVarun Patel
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and applianceHarsha Singh
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 
introduction to molecular oriented polyvinyl chloride pvco pipe
introduction to molecular oriented polyvinyl chloride pvco pipeintroduction to molecular oriented polyvinyl chloride pvco pipe
introduction to molecular oriented polyvinyl chloride pvco pipeManishPatel169454
 
Aqua_Pump_Pro and pro plus_Guidelines
Aqua_Pump_Pro and pro plus_GuidelinesAqua_Pump_Pro and pro plus_Guidelines
Aqua_Pump_Pro and pro plus_GuidelinesJohn Malcolm Cook
 
Ch. no. 4 flow measurement
Ch. no. 4 flow measurementCh. no. 4 flow measurement
Ch. no. 4 flow measurementAmol Kokare
 
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...Abhishekyadav196663
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY MD AMANULLAH
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdfpawankumar491710
 
Wastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsWastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsAreej Al-Azzawi
 
Case Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBCase Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBStefanie Straubert
 
EJ Roe and Michael Watson-Deep Sea Soil Collector
EJ Roe and Michael Watson-Deep Sea Soil CollectorEJ Roe and Michael Watson-Deep Sea Soil Collector
EJ Roe and Michael Watson-Deep Sea Soil CollectorEvan (E.J.) Roe
 
Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 finaliampichu
 
Review_of_casing_while_drilling_technology.pdf
Review_of_casing_while_drilling_technology.pdfReview_of_casing_while_drilling_technology.pdf
Review_of_casing_while_drilling_technology.pdfJooPauloFiori1
 

Similar to Pipe Replacement Method (20)

ENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIOENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIO
 
BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326
 
Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)Stripping of liners from pipes using hdd technology (2007)
Stripping of liners from pipes using hdd technology (2007)
 
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
 
Trenchless Technologies
Trenchless TechnologiesTrenchless Technologies
Trenchless Technologies
 
Coring chapter 5
Coring   chapter 5Coring   chapter 5
Coring chapter 5
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliance
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 
introduction to molecular oriented polyvinyl chloride pvco pipe
introduction to molecular oriented polyvinyl chloride pvco pipeintroduction to molecular oriented polyvinyl chloride pvco pipe
introduction to molecular oriented polyvinyl chloride pvco pipe
 
Aqua_Pump_Pro and pro plus_Guidelines
Aqua_Pump_Pro and pro plus_GuidelinesAqua_Pump_Pro and pro plus_Guidelines
Aqua_Pump_Pro and pro plus_Guidelines
 
Ch. no. 4 flow measurement
Ch. no. 4 flow measurementCh. no. 4 flow measurement
Ch. no. 4 flow measurement
 
Driconeq
DriconeqDriconeq
Driconeq
 
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...
Modification in air brake pipes & its fittings in LHB Coaches dated 24.06.201...
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
 
Wastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsWastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutions
 
Case Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBCase Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GB
 
EJ Roe and Michael Watson-Deep Sea Soil Collector
EJ Roe and Michael Watson-Deep Sea Soil CollectorEJ Roe and Michael Watson-Deep Sea Soil Collector
EJ Roe and Michael Watson-Deep Sea Soil Collector
 
Unit 5 final
Unit 5 finalUnit 5 final
Unit 5 final
 
Review_of_casing_while_drilling_technology.pdf
Review_of_casing_while_drilling_technology.pdfReview_of_casing_while_drilling_technology.pdf
Review_of_casing_while_drilling_technology.pdf
 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Pipe Replacement Method

  • 2. Australasian society for trenchless technology (astt)
  • 3.  Pipe bursting is trenchless methods used to replace existing pipelines in the same alignment without physically removing the existing pipeline.  Pipe bursting was first developed in the United Kingdom in the late 1970s by D. J. Ryan & Sons  This method was patented in the United Kingdom in 1981 and in the United States in 1986; but expired in April 2005. Najafi, 2010
  • 4.  Pipe bursting typically involves insertion of a cone-shaped bursting head into an existing  The base of the cone is larger than the inside diameter of the existing pipe and slightly larger than the outside diameter  The back end of the bursting head is connected to the new pipe and the front end is attached to a cable or pulling rod  The new pipe and bursting head are launched from the insertion shaft and the cable or pulling rod is pulled from the pulling shaft Najafi, 2010
  • 5.  Pipe bursting is too widely used to replace deteriorated pipes with new pipes of the same or larger diameter  Currently, pipe bursting is used to replace waterlines, gas lines, and sewer lines throughout the world Najafi, 2010
  • 6.  pulling cable or rod (static method)  hydraulic source (hydraulic method)  air compressor (pneumatic method) Najafi, 2010
  • 7.  The most common pipe-bursting method is the pneumatic system.  The bursting tool is a soil displacement hammer driven by compressed air  The hammer operated at a rate of 180 to 580 blows per minute.  It is similar to a pile-driving operation, but in a horizontal orientation. Najafi, 2010
  • 9. 1. The head is attached to the new pipe, 2. The winch cable is inserted through the existing pipe and attached to the head 3. The air compressor and the winch are set at constant pressure and tension values. 4. The process continues with operator supervision until the head reaches the pulling shaft at which point it is separated from the new pipe and retrieved Najafi, 2010
  • 11. the old pipe is burst in two steps: 1. The bursting head is pulled into the existing pipe with a winch cable, which is inserted from the reception pit 2. The head is expanded laterally to break that pipe. An axially mounted hydraulic piston drives the lateral expansion head This method of pipe bursting is not common Najafi, 2010
  • 13.  The cone transfers the horizontal pulling force into a radial force  The steel rods, each about 4 ft in length, are inserted into the existing pipe from the pulling shaft.  A hydraulic unit in the pulling shaft pulls the rods  The tensile force of a cable compared to a rod section is limited Najafi, 2010
  • 14.  A form of static pipe-bursting method  The method for breaking and replacing cast-iron or ductile iron pipes by longitudinal slitting.  A splitting wheel or cutting knives, slit the pipe longitudinally at two more lines along the side of the pipe  A new pipe of the same or larger diameter may be drawn behind the splitting tool Najafi, 2010
  • 16. Australasian society for trenchless technology (astt)
  • 17. This method excavates the existing pipe in very fine particles and Removes the existing pipe rather than displaces them into the surrounding ground like: HDD, MTBM, or HAB methods Najafi, 2010
  • 18. Pipe removal is further divided into several methods: 1. Pipe reaming and impactor methods 2. Pipe eating 3. Pipe ejection or pipe extraction Najafi, 2010
  • 19. • Pipe reaming is a pipe replacement technique that uses an HDD machine with minor modifications. • Removal of the existing pipe is accomplished by mixing the ground material with the drilling fluid and transferring it to an exit point Najafi, 2010
  • 21. 1. The patented impactor method is a system that combines the HDD method with pipe bursting 2. The bursting head (impactor) receives air through the HDD drill rod 3. The drill rod is pushed through existing pipe to the next manhole or exit pit Najafi, 2010
  • 22. 4. The impactor device, after it is attached to the drill stem and to the new pipe, is activated and pulled into the existing pipe 5. The impactor system bursts the existing pipe by combined action of pulling using the HDD rig and hammering with the impactor device breaking the existing pipe and replacing it with the new pipe Najafi, 2010
  • 24. This method pushes or jacks a new pipe into the existing deteriorated Pipe Pipe extraction can remove existing pipes for disposal and replace them with new high density polyurethane (HDPE) or polyurethane (PE) pipes Najafi, 2010
  • 25. 1. The lead a heavy steel guide pipe which maintains the alignment within the center of the existing pipe 2. The cracker which fractures the existing pipe 3. The cone expander which radially expands the fractured line into the surrounding soil 4. The front jack, a hydraulic cylinder, which provides axial thrust to the penetration/compaction pieces 5. The pipe adapter, which provides mating surfaces, linking the new pipe to the front jack Najafi, 2010
  • 28.  The process can potentially be executed by horizontal auger boring  Excavates the existing pipe and surrounding soil by using a rotating cutting head attached to an auger  Other potential methods of pipe eating are using a modified version of the MTBM or using pipe ramming equipment Najafi, 2010
  • 30.  High and medium-density polyethylene (HDPE or MDPE)  The main advantages of PE pipes are  Continuity  Flexibility  Versatility  Smooth interior surface  Smooth exterior surface Najafi, 2010
  • 31.  Pipe bursting is most cost advantageous compared to the lining techniques when:  There are few lateral connections to be reconnected within a replacement section  The existing pipe is structurally deteriorated  Additional capacity is needed Najafi, 2010
  • 32.  Much faster  More efficient  Often less expensive than open-cut, especially in sewer applications due to the large depths  Specific studies in the United States have shown that pipe bursting cost savings are as high as 44% , with an average savings of 25 % , compared to open-cut (Fraser et al., 1992) Najafi, 2010
  • 33.  Insertion and pulling shafts are required, especially for larger bursts  Excavation for service lateral connections is required  Expansive soils may cause difficulties  A collapsed (existing) pipe segment may require excavation at that point to allow the insertion of pulling cable or rod and to repair pipe sag  Point repairs with ductile material can interfere with the bursting and replacement process Najafi, 2010

Editor's Notes

  1. As the drill rig rotates the drill rod string and simultaneously pulls it back, the existing pipe is pulverized and replaced by the new pipe