8. TSR(P) BY PQRS
In Division, TSR (P) by 3 PQRS machine is in progress at 3 locations i.e. between PBN-MMR,
MUE-NED & PBN-PRLI sections. During the year total 50.0 Kms has been completed upto
15th Oct’2019 as against total target of 121 Kms.
9. DEEP SCREENING OF PLAIN TRACK AND POINTS & CROSSING BY BCM
MACHINE.
30 Kms plain track as against prop. target of 30 Kms and 20 P&Cs as against prop. target of
20 have been deep screened by BCM machine during the year up to 15th Oct’2019.
10. THROUGH FITTING RENEWAL
As a measure to enhance track condition, TFR along with Distressing is in progress
between MMR-PBN, MUE-PMKT & HNL-PAU sections. During the year 47.0 Kms is
completed upto 15th Oct’2019 as against total target of 90 Kms.
11. ELIMINATION OF LEVEL CROSSINGS
During the year 27 Manned LCs have been targeted for elimination by LHS. As on date
RCC Boxes have been inserted at 03 Manned Level crossings. Works are in progress at
balance LCs
12. THROUGH WELD RENEWAL
In order to enhance the safety of track, Through Weld Renewal by Mobile Flash Butt
Welding is commenced between MMR-PBN section. As on date 11.00 kms is
completed and further work is in progress
Reason for shortfall: Less progress due to deployment of one MFBWP machine by
ITC, Kanpur. A letter was addressed to ITC for arranging second MFBWP Machine
early to expedite progress
13. NI Work at WDN YARD
PQRS siding is commenced in WDN yard, where remodeling of yard is done duly
replacing 1 in 8.5 52kg old Turnout with new Turnout of 1 in 8.5 60kg and connected with
main line.
14. Road Over Bridge (ROB)
Road Over Bridge (ROB) of 4 lane & span 45.5m is sanctioned under deposit between
CTH-KMV section at Km 135/7-8. The work is executed by Maharashtra Industrial
Development Corpn, Mumbai. During the month, traffic block of 2.30hrs is availed for
four days for launching of twelve girders. Other track renewal works have been taken
under the shadow of this ROB block
15. REBUILDING OF BRIDGES
One Old Stone Culvert Bridge (STC) bridge has been rebuilded with RCC Box in
Manmad-Mudkhed Section.
16. TREE PLANTATION
In order to improve greenery, Mass Tree plantation about 1,40,000 no’s has been done in the
entire division upto 15th Oct’ 2019 as against target of 1,75,000 during the year.
17. NURSERY AT HINGOLI, JALNA & ADILABAD
To commemorate 150th Birth Anniversary of Mahatma Gandhi Nurseries at 3 stations in
Division i.e. Hingoli, Adilabad and Jalna stations adjacent to Railway track has been
developed.
18. 100 Ft Monumental flag
100 ft Monumental Flag has been commissioned in circulating area of Nanded Station.
19. Rain Water Harvesting Pits
Rain harvesting pits and ponds were made at maximum locations over the division to
improve ground water levels. Thus total 347 no’s have been made against total target of
300 no’s
RWH PIT AT NAGARSOL STATION RWH PIT AT SHIVNI SHIVPUR STATION
20. Roof Top Rain Water Harvesting
Roof Top rain water harvesting structure is made in the division office building. In this
storm water collected on Roof Top of the building passes through three chamber for
filtration, after which this water is let into bore well pipes. This process have shown
improvement in recharging ground water.
21. Major Works
SN Description Unit
Target
FY 2019-20
Progress as
on
15.10.19
1 CAPACITY ENHANCEMENT Nos. 27 3
i) Un Manned LC by Manning Nos. 0 0
ii) Un Manned LC by RUB/ LHS Nos. 0 0
iii) Manned LC’s by RUB/LHS Nos. 27 3
2 TRACK WORKS
i)Through Rail Renewal (TRR) In Km 6.34 6.00
ii)Through Sleeper Renewal (TSR) In Km 121.0 50.0
iii) Through Weld Renewal (TWR) In Km 137.83 11.0
iv) Through Fitting Renewal(TFR) In km 90.0 47.0
3 RELAXATION OF PSR Nos. 1 1
4 REBUILDING OF BRIDGES Nos. 0 1
5 SUNDRY EARNINGS, in Cr Rs. 5.0 2.38
25. Seminar on Implementation of C.S. 149 & 150 of IRPWM and
Derailment Investigation
Seminar on Implementation of C.S. 149 & 150 of IRPWM and Derailment Investigation was
conducted on dt:26.09.2019 at DTC/PAU. Sr.DSO/NED, ADENs, SSEs/Pway(incharge)
along with APWIs have attended the seminar to refresh the knowledge. Sri Chandrasekhar
SSE/P.Way/SC has delivered lecture on derailment investigation with case studies.
27. Passenger Amenities (SOFT UPGRADATION) Works
Item no. 724
SN
Sanction
Year
Name of work Alloc.
Current Cost
(000)
Remarks
1 2018-19
Purna~~Nanded Division: Ground
Level Reservoir (GLR) of capacity
4,00,000 Liter along with Well at
Purna Station.
CAP 10000
Work is in
progress. TDC:
31.12.2019
2 2018-19
Jalna~~Nanded Division: Provision of
Hydrant Line at Jalna Station..
CAP 10000
Work is in
progress. TDC:
28.2.2020
28. SN
Sanction
Year
Name of work Alloc.
Curren
t Cost
(000)
Remarks
3 2018-19
Redevelopment of Front elevation, Station
Parking etc. at Nanded Railway Station. (SW-I:-
Nanded Station:- Construction of Main Central
Entry with Portico with Dome. SW-II:- Nanded
Station:- Main Station four wheeler parking
and café area in Railway Concept. SW-III:-
Nanded Station:- Structure for Elevation at
Second Floor & FRP domes at Main station and
Gokul Nagar Side Station. SW-IV:- Nanded
Station:- Main Station Building Elevation &
Rear Side Station Building elevation . SW-V:-
Nanded Station:- Entrance kaman in front of
main & rear side station building. SW-VI:-
Nanded Station:- Gokul Nagar Side Entry and
Exit Road. SW-VII:- Nanded Station:- Gokul
Nagar Side Parking Area.)
DF-I 45137
Sanctioned under
UMBRELLA Works
PB 2018-19. After
obtaining DRM
approval & finance
vetting, it will be
submitted to HQs
for further process
ITEM NO. 724 (Contd…)
(contd…) Item no. 724
29. Passenger amenities works sanctioned under
umbrella type works item no. 725
S.N
o
Sanction
Year
Name of work Alloc.
Current
Cost
(000)
TDC
1 2018-19
Aurangabad~~provision of new fob
(6m span) at AWB station
RRSK 50000 30.03.2020
2 2018-19
Adilabad~~Provision of additional
FOB at ADB Station
RRSK 15000 30.10.2019
3 2018-19
Badnapur~~provision of foot over
bridge and high level platform (550
m length ) at BDU station
RRSK 20000 30.09.2019
4 2018-19
Kodi~~Provision of foot over bridge
and high level platform (550 m
length ) at KODI station
RRSK 16000 30.10.2019
Passenger Amenities (FOB & HL PF) Works
Item no. 725
30. S
N
Sanction
Year
Name of work Alloc.
Current
Cost (000)
TDC
5 2018-19
Mudkhed jn~~Provision of
additional FOB at Mudkhed (MUE)
Station.
RRSK 12000 15.10.2019
6 2018-19
Satuna~~Provision of foot over
bridge and high level platform (550
m length) at SCO station
RRSK 16000 30.11.2019
7 2018-19
Manmad~~Mudkhed jn~~Provision
of high level platform (550 m
length ) at TR,CTH,KMV Station
RRSK 15000 28.02.2020
8 2018-19
Provision of RL platform (550 m
length) with VDC and RCC at BMF
station and High level platform at
BHBK Station
RRSK 10000 31.01.2020
ITEM NO. 725 (Contd…)
(contd…) Item no. 725
31. S.N
o
Sanction
Year
Name of work Alloc.
Current
Cost
(000)
TDC
9 2018-19
Parsoda~~Provision of foot over
bridge and high level platform (550
m length ) at PSD station
RRSK 16000 31.01.2020
10 2018-19
Pergaon~~Provision of FOB at PG
station.
RRSK 10000 30.01.2020
11 2018-19
Sahasrakhund~~Provision of FOB at
SHSK station
RRSK 15000 30.12.2019
12 2018-19
Provision of additional FOB at
Manwat road Station
RRSK 12000 30.12.2019
ITEM NO. 725 (Contd…)
(contd…) Item no. 725
32. SN
Sanction
Year
Name of work Alloc.
Current
Cost
(000)
TDC
13 2018-19
Himayatnagar(deccan)~~Provision
of FOB at HEM station
RRSK 10000 30.12.2019
14 2018-19
Parbhani~~Parbhani~~Provision of
new FOB (6m Span) with ramp at
PBN station
RRSK 52500 30.12.2019
15 2018-19
Purna~~Provision of additional FOB
at PAU Station
RRSK 35000 30.03.2020
16 2018-19
Raising of Platform at Wanegaon
(WNG) Station.
RRSK 15000 28.02.2020
ITEM NO. 725 (Contd…)
(contd…) Item no. 725
33. SN
Sanction
Year
Name of work Alloc.
Current
Cost (000)
TDC
17 2018-19
Proposed construction of High level
platform (550m length) at POZ,
KAJG, DGPP
RRSK 24000 30.11.2019
18 2018-19
Proposed construction of High level
platform (550m length) at UPR, PTU,
PDG stations
RRSK 20000 30.11.2019
19 2018-19
Mukundwadi ~~Mukundawadi :-
Widening/extension of High level
platform at Mukundawadi stations.
RRSK 9000 31.01.2020
20 2018-19
Proposed construction of High level
platform (550m length) at AMW,
BSQ, JLG Station
RRSK 20000 30.12.2019
ITEM NO. 725 (Contd…)
(contd…) Item no. 725
34. SN
Sanction
Year
Name of work Alloc
Current
Cost (000)
TDC
21 2018-19
Limbagoan~~Mudkhed jn~~Raising
of Platform at Limbgaon (LBG)
Station.
RRSK 20000 30.01.2020
22 2018-19
Proposed construction of High level
platform (550m length) at SVD,RNE,
PG stations
RRSK 22000 30.01.2020
23 2018-19
Proposed construction of High level
platform (550m length) at CWI,
NDPR, SIF Station
RRSK 20000 30.12.2019
24 2018-19
Jalna~~Proposed construction of
additional FOB at Jalna (J) stations.
RRSK 10000 31.01.2020
25 2018-19
Proposed construction of new FOB
4m span with connecting circulating
area at Hingoli (HNL)stations..
RRSK 25000 28.02.2020
ITEM NO. 725 (Contd…)
(contd…) Item no. 725
35. Pink Book Works PH-5300
S.N
o
Sanction
Year
Name of work Alloc
Current
Cost (000)
TDC
1 2016-17
Jalna & Selu - Provision of cover over
platform
DF-I 31224 Jan-20
2 2017-18
Aurangabad - Cover over platform (200
m) (platform No.1, 2 & 3) and Nagarsol
- Addl foot over bridge to connect
platform No.1 & 2 and cover over
platform (300 m)
DF-I & RRSK 74533 Jan-20
3 2012-13
Aurangabad, Hyderabad, Nanded &
Tirupati - Joint development of
stations in association with Ministry of
Tourism
DF-I & PPP 460000
AWB-Dec’19
NED-Dec’19
45. • Improvement to Façade & Platform Surface at NAGARSOL(NSL) Station.
46. OTHER IMPORTANT WORKS IN PIPE LINE
1. PIT LINE EXTENSION AT NED STATION
Extension of 3rd Pitline from 20 to 26 coach capacity at NED station. TDC:
DEC’2019.
PIT LINE EXTENSION @NED
47. CONSTRUCTION OF NEW FOBs
15 FOBs have been sanctioned in the year 2018-19, out of which 10 nos have been
targeted for completion during the current year in the Division. As on date work is
nearing completion at NED and works are in progress at 4 Stations.
FOB (6 M WIDTH) @ NED STATION FOB (6 M WIDTH) @ PBN STATION
FOB @ KMV STATION FOB @ HNL STATION
48. CONSTRUCTION OF HIGH LEVEL PLATFORMS
27 HLPFs have been sanctioned in the year 2018-19, out of which 20 no’s have been
targetted for completion during the current year in the Division. As on date works are
in progress at various stations
HLPF WORK @ BDU STATION
HLPF WORK @ PG STATION
50. 1600 - Traffic Facilities
SN
Year of
Sanction
Item Alloc.
Current
Cost
(000)
Present Status TDC
1 2005-06
Maltekdi -
Crossing station
in lieu of
sanctioned work
at Pathrad
CAP 95301
Work physically
completed.
Completion report
is under
preparation.
Dec-19
2 2008-09
Tarur, Peragaon,
Selu, Kodi &
Satuna - Addl
loops
CAP 176776
FCC under
preparation.
Oct-19
3 2018-19
Provision of two
(02) additional
loop line at
Nagarsol (NSL)
Station in AWB-
MMR Section.
CAP 123417
ESP under approval
at HQ. Estimate
Sanctioned. Tender
is invited, will be
opened on
5.4.2019.
Mar-20
52. 5200 - Staff Amenities
SN
Year of
Sanction
Item Alloc.
Current
Cost
(000)
Present Status
Sanctioned
Under
1 2017-18
Provision of Mini
Stadium in
Divisional Office
complex,
Nanded.
DF-2 1500 Under way. LSWP
2 2018-19
Nanded Division:-
Improvements of
Staff Quarters
(100 Units).
CAP 24000
Estimate Under
Preparation
PB, Umbrella
53. DIVISION KPI’s (UPTO JULY-19)
S.No
Key performance
indicators
Max Marks Marks obtained
Marks obtained as
per actual Target
1 Safety 15 9.22 10.91
2
Business and financial
performance
20 12.16 14.16
3
Mobility, Throughput and
Capacity Utilization
16 6.4 6.4
4 Data Reliability 15 12.4 12.4
5 Punctuality 10 7 7
Total (marks obtained) 76 47.18 50.87
% marks 62.08 66.93