To work in leading Organization in a Challenging and growth oriented position as a “Lead
Planning & Claim Engineer” where my capabilities, skills and Knowledge can be utilized to an
optimum level and where I can fulfill my thirst for continued knowledge.
Education
2017 | Claims Management and Delay Analysis
Panning Engineer
Construction Claims & EOT Delay Analysis
2012 | Project Management using primavera enterprise (P6 -R8.1)
Collaboration, Management and ControlSolutions(CMCS)
102 Project Management in Primavera P6
106P Advanced Project Management in Primavera P6
106R Resource Management in Primavera P6
2009 | Project Management using primavera enterprise (P6)
Project Management InstituteGulfChapter (PMI-AGC)
Planning & Scheduling with Primavera P6-R6.2.
2007 | Project Management using primavera enterprise (P5)
Promastar Primavera representative(Cairo).
Primavera enterprise P105.
Primavera enterprise P106.
2005 | Professional Program in Project Management (PRMG)
Divisionof GraduateStudies - AmericanUniversityinCairo.
Project Planning and Control Technique.
Management of Project Resources.
Project Budgeting and Financial Control.
Project Feasibility Studies.
Ehab Radwan
+201141144967
+20227093560
ehabrad@gmail.com
skype : pop1167
2. 2
EhabRadwan
Project Bids and Contracts.
Project Primavera Planner P3.
1993 | Bachelor of Architectural Engineering
Facultyof Engineering - CairoUniversity.
Experience
Feb 2015 – Till Now| Senior/Lead Planning and Claim Engineer
MISR SONS DEVELOPMENT (HASSAN ALLAM
SONS)|Cairo,EGYPTwww.allamsons.com
Projects:
South Helwan Supercritical Power Plant 3x650 MW
CONSORTIUM OF CONSOLIDATED CONTRACTORSGroup (S.A.L) (Offshore) &
MISR SONS DEVELOPMENT (HASSAN ALLAM SONS) CCC/HAC.
Responsibilities:
Maintenance and updating the Detailed EPC Baseline Schedule.
Prepare and follow up “Disciplines Schedules” and Reports.
Prepare and follow up “Subcontractors’ Schedules” and Reports.
Prepare and maintain the wall charts/graphic displays with current schedule status.
Monitoring Performance of subcontractors.
Preparing the Weekly and Monthly engineering report for Consultant (PGESCo), Owner (UEEPC)
and JV CCC/HAC.
Attending the Weekly Progress Meeting with Consultant (PGESCo)and owner (UEEPC).
Preparing and manage the internal Weekly Progress Meeting.
May 2014 – Jan 2015| Senior Planning Engineer
Otaishan Consulting Engineers | RIYADH, SAUDI ARABIA. www.otaishan.com.sa
Projects:
Consulting and Follow up 26 Schools for Tatweer Building Company TBC with 3 Contractors.
Responsibilities:
Check and approve of contractors Schedules and S-Curves.
follow up “contractors’ Schedules” and Reports daily, weekly, monthly and submit consultant
reports to the client TBC.
Prepare and follow up weekly and monthly meetings for the three contractors.
Monitoring Performance of contractors.
JULY-2009 – May2014| Senior Planning Engineer
ABV ROCK GROUP LIMITED | RIYADH, SAUDI ARABIA. www.abvrock.com
3. 3
EhabRadwan
Sep-2012 – May 2014 | Senior Planning Engineer for ENDOWMENT
TOWERS PROJECT(endowment.ksu.edu.s a):
Lead Team of 3 Planners to manage all Planning issues related to the UE projects under Saudi Diyar
Consultant as follow:
Projects:
B003 5-Star Hotel Building (48,487 m2 - 1B,GR,10Fl – 176 Mio SAR)
B004 Medical Center Building (39,996 m2 - GR,7Fl - 112 Mio SAR)
B005/006 Residential Suites Building (33,283 m2 – B,GR,13Fl – 162 Mio SAR)
B011 Building Tower No 5 (74,300 m2 - B,GR,MZ,15 Fl – 254 Mio SAR)
B910 Building Tower No 3,4 (63,200 m2 - B,GR,MZ,11Fl - 216 Mio SAR)
B012A Cooling Plant (63,200 m2 - B,GR,RF Fl - 56 Mio SAR)
B013 Office Building (19,812 m2 - B,GR,8Fl - 75 Mio SAR)
Service Tunnel A&B (2,592 lm - 85 Mio SAR)
Refurbishment Tunnel (12,000 lm - 146 Mio SAR)
Responsibilities:
Maintenance and updating the Detailed EPC Baseline Schedule.
Prepare and follow up “Subcontractors’ Schedules” and Reports.
Prepare and maintain the wall charts/graphic displays with current schedule status.
Monitoring Performance of subcontractors.
Preparing the monthly engineering report.
JULY-2009 – Sep-2012 | Senior Planning Engineer for KING SAUD
UNIVERSITY CONTRACT (MEDICAL CITY EXTENSION – ENDOWMENT
TOWERS PROJECTS)
Projects:
034 King Khaled Hospital Extension (84,593 m2 - 2B,GR,5Fl – 695 Mio SAR – 500 Bed)
044 Dental College Extension (39,600 m2 - 2B,GR,10Fl - 197 Mio SAR – 200 Chair)
029 National Diabetic Center (15,400 m2 – B,GR,3Fl – 99 Mio SAR)
011 Building Tower No 5 (74,300 m2 - B,GR,MZ,15 Fl – 254 Mio SAR)
910 Building Tower No 3,4 (63,200 m2 - B,GR,MZ,11Fl - 216 Mio SAR)
Responsibilities:
Maintenance and updating the Detailed EPC Baseline Schedule.
Prepare “Subcontractors’ Schedules”.
Prepare and maintain the wall charts/graphic displays with current schedule status.
Monitoring Performance of subcontractors.
Preparing the monthly engineering report.
NOV-2007 – MAY-2009 | Senior Planning Engineer
Beijing Emirates International Construction | Dubai, UAE.www.becgroup.ae
4. 4
EhabRadwan
Projects:
P270 Offices Tower in Silicon Oasis (3B,GR,25Fl)
P370 Residential Building in Nahda (GR,13Fl)
P252 Residential Tower in Al Khan (GR,28Fl)
P264 Offices Residential Building in Memzar (3B,GR,13 Fl)
P405 A. Omran Hospital in Ras Alkhaima (GR, 2Fl)
Responsibilities:
Maintenance and updating both the Detailed Schedule and the Baseline Schedule.
Prepare “Subcontractors’ Schedules”.
Prepare and maintain the wall charts/graphic displays with current schedule status.
Monitoring Performance of subcontractors.
Preparing the monthly engineering report.
Preparing income cash flow.
JUL-2001 – OCT-2007 | Senior Planning & Estimation Engineer
Siemens Ltd. | Cairo, Egypt.
Projects:
Al Nozha III Exchange.
Luxor I&II Exchange.
90 Village Contract.
Egypt 2000 Package.
Responsibilities:
Bids & offers, B.O.Q Check, Contracts, Subcontractors & Suppliers request (RFQ), Prices
evaluation, Technical comparisons, Customers follow up.
Prepairing preliminary schedules for tenders.
Prepairing Master/General schedule of procurements.
Planning of major milestons in the projects & procurements.
Resources estimation.
NOV-1998 – JUN-2001 | Technical Office Engineer
Morrison Kundsen International | Cairo, Egypt.
Shop Drawings for Design/Build telephone Exchange area outside Plant Facilities (OSPII).
JUL-1995 – OCT-1998 | Architect
Arab Consulting Engineers "Moharram – Bakhoum"| Cairo, Egypt.
Working for conceptual design and work shop drawings for the various projects.
Qatar Embassy in Cairo.
5. 5
EhabRadwan
National Bank of Egypt.
McDonald's Cairo Series:
El Marghani Branch.
El Maadi Branch.
A.U.C Branch.
El Shams Club Branch.
Soliman Basha Branch.
Commercial and Residential Bldg.
Water Supply and Sanitary Auth; Bldg.
El Souqh Station Alex; Underground Subway.
El Hadra Bridge Alex.
Management Bldg. Of Safeer Co.
NOV-1993 – JUN-1995 | Architect
Architecture & Urbanism Group "| Cairo, Egypt.
Working for conceptual design and work shop drawings for the various projects.
Management Bldg; Of Webco Co.
Social Club Of Palma Co.
Interior Design “Villa El Manial”
Villa El Faioum
Petroloap Gas Station “Abou Homos”
Management Blldg; Of palma Co.
Management Bldg; Of Egyptian Drilling Co.
Skills
Computer Skills:
Primavera Project Planning P3.0 & P6 R 8.1.
MS-Projects 2007.
Microsoft Office 2007.
AutoCAD 2009.
Neat User of Internet Dealings and Transactions.
Language Skills:
Fully Conversant With Arabic & English (Reading Writing and Speaking).
Other Skills
Design, Artistic Skills (Freehand Sketching, Perspectives).
PersonalInformation
6. 6
EhabRadwan
Date of Birth
13/11/1967
Nationality
Egyptian
Marital status
Married with four Children.
References
Furnished Upon Request.