Suppose the City of Athens is considering to build a new amphitheater in a previously undeveloped part of town. A.Given the cost and revenue information below, should the city undertake this project? B. Find the NPV of the project, assuming an interest rate of 10% initial early stage(year 1 Last stage(years 3,4, stage and 2) and 5 cost per year(millions) 150 10 10 Revenue per 0 40 80 year(millions0.