Dr. Engr. Tajudeen Humble Sikiru Presentation at Power Nigeria 2018.
Designing Mini-grid Systems.
How to design a mini-grid system. Where to look for the necessary data during the planing stage. How to use financial model to determine tariff. Impact of smart meters to revenue generation in mini-grids.
2018 power nigeria conference workshop slides mini grid
1. Designing Mini-grid Systems
POWER NIGERIA 2018
Engr. Tajudeen Humble Sikiru (PhD)
Electrical Engineering Department, Ahmadu Bello University, Zaria.
Rana World Tech Engineering Limited, Kaduna, Nigeria
1
2. 24-Sep-18 2
A mini-gridis a distributed network with a power source serving a load between1 kW and 1 MW.
The Power source could be Fossil fuel or Renewable(Solar, Wind, SmallHydro or Biomass)
Generallya typical Mini-gridmay be a combination of fossil fuel and Renewablesource
Mini-grids could be grid connectedor off-grid
Systemdesigncomplexityisa function of the load to be served
Mini-gridsare fast to deploy and set up compared to grid expansion
Mini-grid is best for servingrural and semi-urban communitieswheregrid expansion is expensive
Power Nigeria2018
3. 24-Sep-18 3
A power Source (Fossil or Renewable) + A distributed grid = Independent or national grid connected
Power Nigeria2018
4. 24-Sep-18 4
Understanding Government Policies and Framework on Mini-grid
Site Identification
Good Technical Design
Mini-grid Tariff Calculation using Financial Modelling
Power Nigeria2018
5. 24-Sep-18 5
Understanding Government policies and framework on Mini-grid
Mini-grids 1 kW to 100 kW : no permit required before operation
Mini-grids 100 kW to 1 MW : permit required before operation
How to Benefit from Government grant (REA-Rural Electrification
fund)/other Donor agencies
Site Identification
Proximity of national grid (working with DISCO or from DISCO)
Aggregating loads
Commercial viability of a community
Exclusivity agreement
Power Nigeria2018
6. 24-Sep-18 6
Good Technical Design
How to predict the size of a mini-grid
Where to find the necessary data in the planning stage
How to design an entire system
Mini-grid Tariff Calculation and Financial Modelling
Using Financial Modelling to determine Tariff and to select the best
Techno-Economic model
Power Nigeria2018
10. 24-Sep-18 10
Site Assessment Framework
What is the current Energy Access Level in this Community?
What is the current and Future Energy Demand Level for this
Community ?
What is the Potential User Profiles (Household, Commercial &
Productive)?
What is the history of Socio-Political Factors within this Community?
Which of the Regulatory Factor Applies to this Community (NERC
policies and the Distance to the grid, is there possibility of grid arrival
soon?)
What Economic Factor may lead to better Productivity in this
Community ?
Power Nigeria2018
11. Keys to Profitability:
• Select communities with large number of commercial
users
• Select communities whose activities depend on
electricityor can expand with the arrival of electricity
• Ensure that the community is willing to pay for the
electricity
• Involve State and Local Government during site
identification
• Avoid selecting sites based on politics expect State
Government is the off taker
• The most profitable Mini-grid operators are
those serving Underserved communities !!!
• Work with DISCO if possible to provide power
to semi urban communities
24-Sep-18
Power Nigeria2018
11
12. 24-Sep-18 12
Understand that the mini-grid business model is far different
from the telecommunication model in Nigeria
Tariff rate without grants could be as high as N 250 /kWh and between
N 110 – N 170 / kWh with grant
Your Source of financing is critical in determining the payback period
( Loan Versus Equity)
Foreign loan versus Local loan (Could Hedge Financing Help?)
Understand the technology to be deployed ( Renewable or fossil)
Understand the right Design concept: AC coupled or DC coupled
Systems
Power Nigeria2018
13. Survey: Location and Load parameters
• Know your solar installation location
• Accurately determine the load size
24-Sep-18 13
Source: REA Nigeria Mini-grid investment brief
Power Nigeria2018
14. Survey: Technique to Predict Load Size
• Current Load
• Future Load growth
Current Load
• Use survey questioner
• Divide users into two broad categories: Residential
and Commercials
• Model Residential loads
• Model Commercial loads
• Combine the load forecast of Residential and
Commercial Loads
• Use curve fitting techniques and Binomial and
Poisson Distribution to determine load duration curve
• Use Fuzzy time series technique
24-Sep-18 Power Nigeria 2017 14
Source: REA Nigeria Mini-grid investment brief
Power Nigeria2018
15. Technique to Predict Load Size
Load Forecasting Keys Indices to Consider:
Demand Factor = Max. Demand / Connected load
Load Factor = Avg. Demand / Max. Demand
Diversity Factor = sum of individual max. demands /
max. demand of mini-grid power station
Utilization Factor = Max. demand of mini-grid power
station/ Rated capacity of mini-grid power station
The goal is have the utilization factor to be very high
25-Sep-18 15
Source: REA Nigeria Mini-grid investment brief
Power Nigeria2018
16. Let Use Solar Power Station as an Example
We will use a community in Mokoloki ( see load curve on
the right)
Max. Peak Load 120 kW
Avg. Peak Load 98 kW ( 14.00 – 20.00 hrs)
Day time Avg. Load 50 kW ( 7.00 – 20.00 hrs)
Night time Avg. Load 8 kW (20.00 – 6.00 hrs)
What should be the optimal best size of the solar panels?
What should be the best sizing for the battery bank?
What is the right size of Generator?
The right Business Sense Questions to ask:
How many hours of power supply should the mini-grid
provide?
What percentage of consumption would be met by the
Diesel generator ?
What is the impact of battery bank on the tariff cost?
25-Sep-18 16
Source: REA Nigeria Mini-grid investment brief
Peak load
Avg. peak
Avg. load
Power Nigeria2018
17. Energy Consumption Analysis
Step 1: Minimum energy supply per day
50 kW * 14 hrs (6.00 – 20.00 hrs) = 700 kWh
8 kW * 10 hrs (20.00 – 6.00 hrs) = 80 kWh
Total Minimum consumption = 780 kWh
Low Sun / Night time energy consumption = 8 kW *10 hr +
50*6hr = 380 kwh
Minimum night load on battery 8 kW* 10 hrs = 80 kWh
Step 2: Design for Battery Capacity
Option 1: Minimum Battery capacity = 160 kWh @ 50% DOD of
minimum night load
Option 2: Maximum battery capacity = 460 kWh @ 80% DOD of
low sun/night consumption
Because of high capex for batteries we select battery capacity
between 160 kWh and 288 kWh when we do the economic
analysis
25-Sep-18 17
Source: REA Nigeria Mini-grid investment brief
Peak load
Avg. peak
Avg. load
Best Harvest
Power Nigeria2018
18. Energy Consumption Analysis
Step 2: Design for Selecting of PV capacity
Location of Mokoloki: OGUN STATE
1 kWp solar installation will yield = 3.2 kWh/day
Solar capacity =Total Minimum consumption (780 kWh) /
3.2 kWh (energy per day from 1 kWp installation)
= 240 kWp (ideal solar size)
25-Sep-18 18
Peak load
Avg. peak
Avg. load
Best Harvest
Mokoloki
204 kW (peak PV generation)
150 kVA Generator
(3 hours max. per day)
BatteryBank
suppliespower
Power Nigeria2018
19. Energy Consumption Analysis
Step 3: Adjusting PV capacity
Because Diesel generator will run daily due to the time of
night of the peak load, scaling down the PV capacity may be
considered !!
However, this requires a lot of considerations (will
cumulative cost of diesel fuel over 10 years + outweigh PV
cost?)
PV can be scaled down to 150 kWp minimum! If PV
capacity is too low tariff increases due to high fuel
consumption
25-Sep-18 19
204 kW (peak PV generation)
150 kVA Generator
(3 hours max. per day)
BatteryBank
suppliespower Fuel consumptionperiod 7 hours per day
156 kW
Power Nigeria2018
20. 25-Sep-18 20
Modelling the load duration Curve using Odyssey Software
Example of the softwaremodelling is shown below:
Power Nigeria2018
21. 25-Sep-18 21
Modelling the load duration Curve using Odyssey Software
Example of the softwaremodelling is shown below:
Power Nigeria2018
22. 25-Sep-18 22
Modelling the mini-grid system using HOMER Software
Example of the softwaremodelling is shown below:
Power Nigeria2018
23. 25-Sep-18 23
Selecting the right technology (AC Versus DC Coupled Systems)
Good for small mini-grids
With less loadsduring the daytime
Good for large mini-grids
With more loads during the daytime
Power Nigeria2018
24. 25-Sep-18 24
Design of internal
distribution Network
Should conform to National
grid standards, if
compensation must be
provided when grid arrives
Distribution network could
be single or three phase
depending on the load type
and size being served
Wooden or concrete poles?
20-33 meters span between
poles
Power Nigeria2018
25. 25-Sep-18 Power Nigeria 2017 25
Tariff Collection
(smart metering)
and Project
Monitoring
Daily energy
production should
be monitored (faults
and increasing loads
could easily be
identified)
Mobile money
payment is preferred
Pre-paid payment
model is most
suitable for cash
flow analysis
Power Nigeria2018
26. 25-Sep-18 Power Nigeria 2017 26
Summary page:
Enter company info
only
Other data in the
Summary page are
auto generated if all
the entries are
correct
Power Nigeria2018
27. 25-Sep-18 27
Input page:
Enter all fields in
colouredwith
GREEN
e.g. Diesel cost
Exchange rate
Tariff for 1 phase
user
Tariff for 3 phase
users
Percentage of
projectcost to be
coveredby grant
Power Nigeria2018
28. 25-Sep-18 28
Input page:
Enter all fields in
colouredwith
GREEN relatedto
Cash flow and
Project
Development
e.g. Income tax
cost of feasibility
Costof EIA
Staff salaries
Travel and vehicle
cost
Power Nigeria2018
29. 25-Sep-18 29
Input page:
Enter all fields in
colouredwith
GREEN relatedto
REVENUES
e.g. nos of 1
phase and 3
phase users
Total energy sold
to these users
Costof new
connections
Power Nigeria2018
30. 25-Sep-18 30
Must be positive
The higher the better
Zero if no debt funding
Break even cost
Average tariff with grant
Earning before tax and otherdeductions
Very important
Power Nigeria2018