1. Topic:- Qualification of Dry Powder Mixer
Subject Name :- Pharmaceutical Validation
Subject Code:- MQA204T
Department of Pharmaceutical Quality Assurance
Smt. B. N. B. Swaminarayan Pharmacy College, Salvav–vapi
Presented by:-
Machhi Dhruvi A.
2nd sem M.Pharm.
3. Dry Powder Mixer
Powder mixing may be regarded as an operation in which two or more than two
solid substances in particulate form intermingled in mixer by continuous
movement of particles.
It is an example of neutral mixture & is one the most common operation
employed during preparation of different formulation like powder, tablets,
capsules etc.
21-05-2022
Dhruvi Anilkumar Machhi
3
5. Qualification of Dry Powder Mixer
It is defined as the action of proving & documenting that the Dry powder mixer is
properly installed, work correctly & leads to expected result.
Need of Qualification of Dry Powder Mixer:
Mixing of API & excipients is the critical step in the solid dosage form
preparation that affects the content uniformity at great extent.
21-05-2022
Dhruvi Anilkumar Machhi
5
7. Design Qualification
Design Qualification of Dry powder mixer includes:
Equipment name, made by & model number shall be noted down
Location for the installation of equipment shall be checked
Utilities required shall be listed down
Required capacity of the mixer, type of materials to be mixed & mixing time also
should be taken into consideration
Any deviation observed while following above procedure shall be informed for
corrective action.
21-05-2022
Dhruvi Anilkumar Machhi
7
8. Installation Qualification
The IQ process is intended to demonstrate that the Dry Powder Mixer
Meet all specification
Installed properly &
Supporting program like SOP, Maintenance sheet are in place
After checking all the specifications as mentioned in the selection criteria, service
engineer shall commission the equipment.
Authorized validation team shall carry out installation checks as per the
specification criteria.
21-05-2022
Dhruvi Anilkumar Machhi
8
9. IQ checks :
Manufacturer name & address shall be checked
Equipment name & model no. shall be noted down
Check Gear Box, Control Panel, Buttons & Driving Motor
21-05-2022
Dhruvi Anilkumar Machhi
9
Installation Qualification
10. Operational Qualification
After completion of IQ, initiate the actual operation, to ensure that machine is
operating within the specification.
Check the operation qualification parameters against their specifications.
It includes following checks :
On/ off Switch
Gross Capacity
RPM
After that, document the deviation details.
The quality head & the department head shall decide whether the deviation is
acceptable or not. 21-05-2022
Dhruvi Anilkumar Machhi
10
11. Performance Qualification
Load the material into the mixer
Start the mixer & rotate it for the time as mentioned in the BMR
After completion of mixing switch off the mixer & separate out material
Collect the sample as per sampling procedure
Send the samples to QC department for content uniformity, bulk density & site analysis
21-05-2022
Dhruvi Anilkumar Machhi
11
Utilities = facilities required by the equipment like electricity, drainage
Deviation = departing from standard
Utilities – facilities required by the equipment ex.. electricity
Comission – give instruction or command