SlideShare a Scribd company logo
1 of 109
58th Webinar on Grouting Technology
for Civil Engineering Applications
11th December,2020
Organised by
IGS – Guntur Chapter
IGS – Student Chapter
GUDLAVALLERU ENGINEERING COLLEGE
1
Thanks to IGS – Guntur Chapter
Good Morning
VARIOUS GROUND IMPROVEMENT TECHNIQUES
TREATMENT SHALLOW
LAYERS
TREATMENT OF DEEP
LAYERS
 Compaction
 Stabilization
 Freezing & Heating
 Geotextile
 Reinforced Earth
 CNS Layer
 Dynamic compaction and
consolidation
 Vibroflotation
 Compaction pile
 Blasting
 Heavy tamping
 Pre-compression – Vertical
drain
 Electro Osmosis
 Lime piles and columns
 Stone columns
 Grouting
Dr. D.L.SHAH
Professor (Retd.), M S University of Baroda.
Senior Consultant, GEO DYNAMICS
Chairman, Indian Geotechnical Society – Baroda Chapter
Consultant to SSNNL, Govt of Guj.
dr_dlshah@yahoo.com
Grouting Technology for Civil
Engineering Applications
Definition
Grouting is a process of injection of setting fluids in to
the voids of the alluvium, or into the fissures of the
rock either to reduce permeability or to increase
strength or both.
Injected fluid (grout) will solidify by physico-chemical
or by chemical action with the passage of time and
thereby increases the strength and reduces the
permeability.
The success of the grouting is mainly dependent on
selection and type of grout materials and suitable
grouting techniques.
FUNCTIONS OF GROUTING
Permeation Compaction
Jet Grouting
Civil Engineering Applications of Grouting
 Alluvial Grouting of Earth Dam Foundations
 Alluvial Grouting of Building Foundations
 Rock Grouting of Masonry and Concrete Dam foundations
 Grouting During Pipe Jacking Operation
 Grouting of Foundation Soils of Existing Machine Foundations.
 Grouted Anchors.
 Grouted Mattress for Seepage and Leakage Control in Perennial
Canal
 Microfine Cement Grouting in Tunnelling and other
Applications
 Crack Grouting for Rehabilitation of Building and Dams
 Jet Grouting for Deep Foundations & Tunnels
Alluvial Grouting for Earth Dam Foundation
Concrete Gravity Dam with Intersecting Fault Zone
Concrete rch Dam
Resist Unstable
Movements
Soil Stabilization, Tunnel Construction
Vibration Isolation for Machine Foundation
Cement/Chemical injection of foundation media is a recent
innovation in decreasing vibration. Such injection results in
increased rigidity of the base and consequently increased natural
vibration of the foundation. Increased rigidity increases the
difference between the frequency of natural vibration and the
frequency of the machine. Consequently the amplitudes of
foundation vibration are decreased.
The injection method has the special advantages of non-interruption
of work of the machine during the treatment.
Compaction & Jet Grouting
Controlled Lifting with
Compaction Grouting
Correction of Structural
Settlement
(a) from the top down
(b) from the bottom up
Compaction Grouting For Increasing End Bearing And Friction
Jet Grouting
Execution Phases
Jet Grouting
• A relatively new and one of the most successful techniques
• A speed jet of water released from a 1 to 2 mm nozzle at the
end of a grout pipe at a pressure of 200 to 5000 kg/cm2 cuts
through the soil or soft rock.
• When the slot has been formed, a chemical solution grout is
substituted for the water and stabilizes in place as a solid
mass.
• The grout pipe is lifted from bottom of the hole as process
continues.
Various Applications of Jet grouting
Consolidation & Underpinning for deep
excavation close to existing buildings
Underpinning of Existing Buildings
foundations of viaduct piles
Building Foundation improvement
Dam Grouting
An outline of Grouting from beginning
to end
•Investigation
•Decide whether grouting necessary or not
•Design
•Site preparation
•Equipment
•Drilling
•Water testing
•Hook-up
•Commencing grouting
•Looking for trouble
•Review of mix
•Completion
•Assessment
•Long term performance
POSITIONING OF GROUT
CURTAIN
Rock Grouting
WHEN IS GROUTING WARRANTED??
The Lugeon Test
The Lugeon Test The most commonly in-situ test
used to estimate hydraulic conductivity of rock
masses is the Lugeon test – also called the packer
test. The test, which derives its name from
Maurice Lugeon (1933), is a constant head type
test that takes place in an isolated portion of a
borehole. Water at constant pressure is injected into
the rock mass through a slotted pipe bounded by
pneumatic packers. A pneumatic packer is an inflatable
rubber sleeve that expands radially to seal the annulus
space between the drill rods and the boring walls.
One Lugeon value, which is empirically defined
as flow rate of 1 liter/minute per meter of test
hole under a reference water pressure equal to 1
MPa
Lugeon Test Configuration
Use of Automated Data Acquisition System
Automated data acquisition systems capable of
measuring, displaying and recording Lugeon test
and grouting data in Real Time have become
available over the last years. This equipment
measures flow rate and pressure at regular
intervals of time and displays the information on
an LCD display.
• To give a sense of proportion for the
unit:
• 1 lugeon unit is the type of permeability
where grouting is hardly necessary.
• 10 lugeons warrants grouting for most
seepage reduction jobs.
• 100 lugeons is the type of permeability met
in heavily jointed sites with relatively open
joints or in sparsely cracked foundations
where joints are very wide open.
Geological Investigation
Adapting Grouting to Suit the Geology
Features that can influence grouting design and construction
include:
• 1. Spacing of Joints
• 2. Joint Widths and Continuity
• 3. Joint Inclination
• 4. Uniformity of the Site
• 5. Rock Soundness
• 6. Strength
• 7. Piping
1. Spacing of Joints
As far as cement grouting
is concerned, it is the
open, groutable joints
that are of interest. If
they are widely spaced,
the grouting is usually
easier than if closely
spaced where troubles
such as frequent surface
leaks, collapsing holes
and patchy penetrations
can happen. These make
for more expensive grouting,
perhaps requiring special
surface treatment.
2. Joint Width and Continuity
The easiest joints to grout
have widths in the range
between about 0.250 in [6
mm] and 0.020 in [0.5 mm].
Continuity of open jointing
systems affects penetration:
lack of continuity means
that more grout holes will
be needed than if grout can
travel appreciable distances
through the systems.
3. Joint Inclination
Where dipping is mainly between 20° and about 60°, vertical grout
holes may give optimum interception. These are the easiest to drill
and are preferable. Steeper jointing usually requires use of
inclined holes.
4. Uniformity of Site
Uniformity of jointing permits a regular layout
of grout holes, whereas irregular jointing,
dykes, disconformities, and so on may
require placement of holes at various
inclinations and spacing . Weaknesses may
need to be treated intensively.
7. Piping
Where material in
joints can be removed
by seepage, either by
taking the material
into solution or by
eroding it, the
grouting will need to
be more intensive than
otherwise in order to
ensure that seepage
through such joints is
virtually eliminated.
Starting Mix Decided on:
• The recommended water:cement ratio is 2 : 1
for starting many of the grouting jobs. This is
two parts of water to one part of cement,
measured by volume.
• However, if the majority of cracks are known
to be relatively FINE such as 0.75mm or finer ,
starting with 3 : 1 could be better.
At the other extreme, If cracks are fairly
WIDE such as 1.25mm, it is usually wise to
start with 1 : 1. (W:C ratio by volume)
•
Fast Grout take
If the hole takes grout very rapidly, use
of a thicker mix can be warranted,
except in the special case where large
voids are present; the water test before
grouting should have indicated
whether such voids are present.
Usually, a fast take with minimal pressure buildup indicates that the
cracks will probably accept a thicker mix without blocking. Therefore
the grout should be thickened by one step and injected into the hole so
as to use the thickest practicable grout and thereby gain maximum
durability.
Further thickening of the mix might be warranted if grout behaviour
warrants this.
STANDARD MIXES and THICKENING STEPS
There is no need to use any other mixes than
5 : 1 by volume
4 : 1
3 : 1
2 : 1
1 : 1
0.8 : 1
0.6 : 1
0.5 : 1
When thickening the mix during grouting,
proceed down the list one mix at a time - never
jump a mix. For instance, if thickening from 3 : 1,
go to 2 : 1 for a while and then to 1 : 1 and
perhaps on.
Never go straight from 3 : 1 down to 1 : 1 or else
the too sudden thickening is liable to
prematurely block cracks in the job.
Procedure and Monitoring of
Grouting Operation
ROCK GROUT CLOSURE WHEN DOING CEMENT GROUTING
Closure grouting is the process of drilling and grouting the first holes
in an area fairly widely apart, then drilling and grouting a hole midway
between them, then putting holes midway in the remaining gaps, and
so on, continuing this process of halving centres until enough grouting
has been done.
The first holes are usually called
PRIMARY.
The holes midway between them usually
are given the name SECONDARY.
The Concept of Closure
The Concept of Closure
When grout holes are longer than about 30
ft [10 m], it is usually best to divide them
into shorter lengths, called stages, and
grout each of these stages separately.
DOWNSTAGE WITHOUT PACKER
DOWNSTAGE WITH PACKER
UPSTAGE
PATTERN OF GROUT HOLES FOR CURTAIN
GROUTING AND CONSOLIDATION ROCK GROUTING
JET
S
104
software
-
GROUTING
As per IS : 6066
STAND PIPE FITTINGS
UPHEAVAL
GAUGE FOR
EARTHEN DAM
UPHEAVAL
GAUGE FOR
MASONARY /
CONRETE
DAM
Assessment during grouting
High take of grout
TPC Diagrams for behaviour of
grout hole
Refusal Criteria
Each grout operation should continue until refusal is reached.
Refusal is considered to have been reached when
intact grout at the desired limiting pressure is less
than 2 lit/min averaged over a period of 10 minutes
and the pressure greater than 3.5kg/cm2, or 1 lit/min
when the pressure is below 3.5kg/cm2.
Alluvial Grouting
GRAVEL SAND COARSE SILT SILT (NON PLASTIC)
FINE COARSE MEDIUM FINE
CEMENT
BENTONITE
POLYURETHANE AND POLYACRYLAMIDE
SILICATES – HIGH CONCENTRATION
SILICATES – LOW CONCENTRATION
AMINOPLAST
PHENOPLASTS
MICRO FINE
CEMENT
GROUT
ACRYLAMIDE
ACRYLATES
PENETRABILITY OF GROUTS
Grout Materials
Neat Cement Grouts
Cement Grouts with Bentonite
Cement Grout with Flyash
Cement Grout with Chemical Admixtures
Sand Cement Grouts
Chemical Grouts
Sodium Silicate
Lignosulphonate
Aminoplast
Phenoplast
Acrylamide
Polyurethane
Epoxy
 CEMENT BENTONITE GROUTS
Clay H.G.
Bentonite
Cement Water +Peptizing
agent
- - 0.5 8 -
0.8 0.2 0.6 6 0.1 to 2%
- 0.4 1 5 2%
- 0.7 1 5 2%
0.4 0.6 0.6 6 2%
- 1 0 8 Sodium silicate
Monosodium
phosphate
- 1 0.5 8 S/ P = 1
=1
Marsh Cone – Oriffice Type Viscometer
Horizontal Flow Meter for
Flow measurement of Sand Cement Grout
Bleeding Test for Bleeding
Potential Mearuement
Water Retentivity Testing Set Up
Penetrability and Washout Test Set Up for
Seepage Study through Grouted sample
Grout Injection Mould for
Strength Measurement
Chemical Grouting
Penetrability
Gel time control
Sensitivity
Permanence
Strength
Toxicity
Economic factor
The basic material should be as follows:
A powder readily soluble in water.
Inexpensive & derive in abundant supply.
Non toxic
Non corrosive
Non explosive
The grout solution should have:
A low viscosity solution
Stable under all normal temperature
Non toxic, non corrosive, non explosive
Catalyzed with common inexpensive chemicals
Insensitive to salts normally found in ground water
Of stable pH
Readily controlled for varying gel times
Able to withstand appreciable dilution with ground water.
The end product should be:
Permanent gel
Unaffected by chemicals normally found in ground water
Non toxic, non corrosive, non explosive
High strength
Since about 1970, silicate and acrylamide-based grouts share a
market percentage between 85% and 90%, with the remaining
portion of the market divided among other products. Chemical
grouts fall into the following categories:
Silicate formulations
Acrylics (includes acrylamide and acrylate grouts)
Lignosulfonates
Phenoplasts
Aminoplasts
Other materials
Chemical Grout Types
ELECTROKINETIC GROUTING
• Electrokinetic grouting may be applied towards solidification of soil, reducing
its permeability and thereby increasing the strength of the soil.
– Definition: When a DC current is applied across a sandy soil mass or any
fine grained soil, sodium silicate (Na2SiO3) in the cathode compartment
and the reactants like calcium chloride (CaCl2) as a hardener in the anode
compartment migrate. The anionic silicate will migrate toward the anode
due to electro-migration and cationic metal ions will migrate toward the
cathode. When these charged ions meet within the soil, the pH of sodium
silicate will be reduced and thereby form a gel within the soil and grout
the soil mass. In silty soil where electroosmosis (pore water flow from
anode to cathode) occurs due to application of D.C. electric field, it is
expected that water-soluble sodium silicate grout will be carried away by
electroosmotic flow from the anode towards the cathode. When the pH of
this grout is reduced by the H+, generated and migrated (Electromigration)
from the anode, the sodium silicate grout will form a gel and stabilize the
soil.
• Electrokinetic Grouting may also be used to trap or immobilize the
contaminants within their host soil medium instead of removing
them through chemical or physical treatment; simultaneously while
densifying the soil.
SOIL TREATED BY ELECTROKINETIC GROUTING
• This method, an application of electrokinetic remediation
technique, was used to improve the geotechnical properties
of the soil mass by using a chemical grout. Soil was
compacted in model by hand compaction.
• At anode concentration used was made using 2% calcium
chloride (CaCl2) powder dissolved in tap water, whereas
at the cathode 20%, 25% and 30% sodium silicate
(Na2SiO3) dissolved in tap water was used for different
tests.
• These solutions were used as two different components of
a most commonly used chemical grout.
• Carbon electrodes were then placed and connected to an
AC- DC converter unit.
Model No. L (cm) H (cm) W (cm) Fill Height (cm)
o/p 1 8.3 19.8 10.2 15
o/p 2 18.2 19.5 15.5 15
o/p 3 25 19.8 20 15
o/p 4 41 22 30 15
 Different size of open model
98
Comparison of initial and final UCS of soil at different
locations
0.000
0.200
0.400
0.600
0.800
1.000
1.200
1.400
Anode Middle Cathode
UCS
in
kg/
cm
2
Before Electrokinetic Grouting
After Electrokinetic Grouting
Case Study
Work at KAKRAPAR Canals in Gujarat
At the instructions of the Government of Gujarat, a Study has been taken
up by Cemindia, Bombay under World Bank Credit for adopting the
method of Grouted Mattress in India. For this purpose pilot testing have
been taken up at two sections of Kakrapar Canal system near Surat. The
canal has a maximum flow of about 250 cusecs and water depth of about
1.8 meters, having bed of about 6.6 wide and side slopes are 1 vertical to
1.5 horizontal.
Grouted Geotextile Mattress
Preamble
As a consequence of research and development jointly
by the Applied Mechanics Department & Textile
Engineering Department of Faculty of Technology &
Engineering and indigenous technique of GROUTED
GEOTEXTILE MATTRESS for canal lining under
flowing water condition was devised by R & D
Division of Cemindia. Model and field studies have
revealed that the strength of material in lining attained
at 28 days is about 180 kg/cm2 and the permeability and
rugosity co-efficient of lined canal are within the limit
of code of practice.
Technique
The technique involves use
of and mattress cove made
with two layers of a specially
woven synthetic fabric (Fig.)
Strip or threaded spacers are
provided in the dual walled
fabric which give the mat its
characteristics “cobbled”
effect.
The woven fabric is positioned on the prepared slope or surface
and subsequently filled with fine grained sand-cement grout mix.
The completed mat provides a slab of nominal 100 mm thickness.
Construction of the concrete matting starts with the positioning
and securing of the mattress on the ground profile.
Special pipes are then
inserted to the bottom of the
frame work. Colloidal sand
cement mix is then pumped
into position as the pipes are
gradually with drawn to the
surface. (Fig.) Pumping in
this way under low pressure
ensures continuity and
uniformity of the filter and as
the concrete mat is casted, it
adapts itself to the ground
profile. The mix is normally
used for pumping consists of
sand, cement and water.
Mattress fabric cover with spacer
A typical fabric developed for this purpose which involves special
three dimensional weaving technique. The fabric is a double layered
one and the two layers can be separated by a predetermined amount
with the help of spacer yarns. The spacer yarn ensures the continuity
of the two layers of the fabric shell as well as the thickness of the
lining without any hindrance to the fluid flow of the grout mix
during its application.
The length and distribution of the spacers yarn in total fabric matrix
can be manipulated to suit the specific requirements of the lining
thickness and grout pressure. To resist the pressure it is essential that
fabric shell possess sufficient tensile and bursting strength as also
low value of elongation at all levels of loading. The fabric is resistant
to acids, alkalis and other common chemical as also to weathering
and exposure to sunlight.
CHARACTERISTICS OF DOUBLE LAYER GEOTEXTILE88
1) Warp – Nylon yarn – Count – 1120 Deniers , Breaking load
– 7.36 Kgs. At 10 cms gauge length
2) Weft – Polypropylene flat Tape – Count – 1038 Deniers
Breaking load – 3.66 Kgs at 10 cms gauge length
%age Elongation – 41.83 %
3) Space Yarn –Nylon woven ape – Count – 7160 Deniers
Breaking load – 41.42 Kgs.
%age Elongation – 45.10 %
No. of ends and picks per inch 22
Two spacer yarns are used.
The Canal perimeter was cleared of vegetation and trimmed to provide a
reasonably working surface. A canal perimeter is about 14.7 m. The mattress
length of about 15 m was laid, in the flowing water conditions, on the bed and
side slopes of the canal. It was properly secured along the edges. The next
length of the mattress was joined to the first 15 m length after completion of
the in-filling of the mattress. The joining of bed lengths was carried out in the
flowing canal. The mattress was filled up with a pumpable mix of cement-
sand – water and additives by the help of screw type pump. The nominal
thickness of the lining as achieved in about 11 cm. Tests carried out on
samples from the lining itself showed that the strength of the materials
attained at 28 days is about 180 kg/cm2.
Concluding remarks
It is essential to have good understanding of the
geologic conditions being treated by grouting. The
grouting program should be designed to address
those conditions and maintain sufficient flexibility
to accommodate new information obtained
following implementation. “Cook Book
Programme” will not suffice. The geologic,
grouting and permeability should be continuously
monitored so that appropriate changes in the
design can be made, and so that the impact of the
inevitable geological surprise can be minimized.
dr_dlshah@yahoo.com

More Related Content

What's hot

IS Classification of Soils
IS Classification of SoilsIS Classification of Soils
IS Classification of SoilsVijai Krishnan V
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
CANAL REGULATIONS
CANAL REGULATIONSCANAL REGULATIONS
CANAL REGULATIONSKarthick MK
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concreteKaran Patel
 
Under water concreting
Under water concretingUnder water concreting
Under water concretingAgnesh Shetty
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADkumawat123
 
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B KBk Imran
 
Soil improvement report final
Soil improvement report finalSoil improvement report final
Soil improvement report finalMohd Usama
 
Aggregate - Concrete Technology
Aggregate - Concrete TechnologyAggregate - Concrete Technology
Aggregate - Concrete TechnologyDavid Grubba
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test pptsayan sarkar
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 
Various types of pressure pipes
Various types of pressure pipes Various types of pressure pipes
Various types of pressure pipes Lavanya Singh
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement TechniquesLokeswar
 

What's hot (20)

Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
IS Classification of Soils
IS Classification of SoilsIS Classification of Soils
IS Classification of Soils
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
CANAL REGULATIONS
CANAL REGULATIONSCANAL REGULATIONS
CANAL REGULATIONS
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Plain sedimentation
Plain sedimentationPlain sedimentation
Plain sedimentation
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROAD
 
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
 
Soil improvement report final
Soil improvement report finalSoil improvement report final
Soil improvement report final
 
Aggregate - Concrete Technology
Aggregate - Concrete TechnologyAggregate - Concrete Technology
Aggregate - Concrete Technology
 
Methods of boring ppt
Methods of boring  pptMethods of boring  ppt
Methods of boring ppt
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
Coarse Aggregate
Coarse AggregateCoarse Aggregate
Coarse Aggregate
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Various types of pressure pipes
Various types of pressure pipes Various types of pressure pipes
Various types of pressure pipes
 
Reinforced earth & its application
Reinforced earth & its applicationReinforced earth & its application
Reinforced earth & its application
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 

Similar to Grouting Technology - Guntur Chapter.ppt

5.8 remedial measures at foundation by methods of grouting
5.8 remedial measures at foundation by methods of grouting5.8 remedial measures at foundation by methods of grouting
5.8 remedial measures at foundation by methods of groutingDr.Anil Deshpande
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concreteErankajKumar
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresUjwal Ujwal
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concreteErankajKumar
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement techniqueSatish Kambaliya
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresKumarS250747
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance inKulbir Singh gill
 
Grouting PPT by OM.ppt
Grouting PPT by OM.pptGrouting PPT by OM.ppt
Grouting PPT by OM.pptOMVIRSINGH44
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundationashishcivil098
 

Similar to Grouting Technology - Guntur Chapter.ppt (20)

Grouting n gunintung
Grouting n gunintungGrouting n gunintung
Grouting n gunintung
 
6.1 Grouting.pptx
6.1 Grouting.pptx6.1 Grouting.pptx
6.1 Grouting.pptx
 
5.8 remedial measures at foundation by methods of grouting
5.8 remedial measures at foundation by methods of grouting5.8 remedial measures at foundation by methods of grouting
5.8 remedial measures at foundation by methods of grouting
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 
Permeation grouting for remediation of dam cores
Permeation grouting for remediation of dam coresPermeation grouting for remediation of dam cores
Permeation grouting for remediation of dam cores
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Methodes of reparing cracks
Methodes of reparing cracksMethodes of reparing cracks
Methodes of reparing cracks
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
 
pile wall
pile wallpile wall
pile wall
 
1.9 GROUTING.ppt
1.9 GROUTING.ppt1.9 GROUTING.ppt
1.9 GROUTING.ppt
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Grout curtain
Grout curtainGrout curtain
Grout curtain
 
9487 (1).ppt
9487 (1).ppt9487 (1).ppt
9487 (1).ppt
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structures
 
Presentation edited final
Presentation edited finalPresentation edited final
Presentation edited final
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance in
 
Grouting PPT by OM.ppt
Grouting PPT by OM.pptGrouting PPT by OM.ppt
Grouting PPT by OM.ppt
 
Presentation on surface investigation techniques for foundation
Presentation on surface investigation techniques  for foundationPresentation on surface investigation techniques  for foundation
Presentation on surface investigation techniques for foundation
 

Recently uploaded

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 

Recently uploaded (20)

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 

Grouting Technology - Guntur Chapter.ppt

  • 1. 58th Webinar on Grouting Technology for Civil Engineering Applications 11th December,2020 Organised by IGS – Guntur Chapter IGS – Student Chapter GUDLAVALLERU ENGINEERING COLLEGE 1
  • 2. Thanks to IGS – Guntur Chapter Good Morning
  • 3.
  • 4.
  • 5.
  • 6.
  • 7. VARIOUS GROUND IMPROVEMENT TECHNIQUES TREATMENT SHALLOW LAYERS TREATMENT OF DEEP LAYERS  Compaction  Stabilization  Freezing & Heating  Geotextile  Reinforced Earth  CNS Layer  Dynamic compaction and consolidation  Vibroflotation  Compaction pile  Blasting  Heavy tamping  Pre-compression – Vertical drain  Electro Osmosis  Lime piles and columns  Stone columns  Grouting
  • 8.
  • 9. Dr. D.L.SHAH Professor (Retd.), M S University of Baroda. Senior Consultant, GEO DYNAMICS Chairman, Indian Geotechnical Society – Baroda Chapter Consultant to SSNNL, Govt of Guj. dr_dlshah@yahoo.com Grouting Technology for Civil Engineering Applications
  • 10.
  • 11. Definition Grouting is a process of injection of setting fluids in to the voids of the alluvium, or into the fissures of the rock either to reduce permeability or to increase strength or both. Injected fluid (grout) will solidify by physico-chemical or by chemical action with the passage of time and thereby increases the strength and reduces the permeability. The success of the grouting is mainly dependent on selection and type of grout materials and suitable grouting techniques.
  • 12. FUNCTIONS OF GROUTING Permeation Compaction Jet Grouting
  • 13.
  • 14. Civil Engineering Applications of Grouting  Alluvial Grouting of Earth Dam Foundations  Alluvial Grouting of Building Foundations  Rock Grouting of Masonry and Concrete Dam foundations  Grouting During Pipe Jacking Operation  Grouting of Foundation Soils of Existing Machine Foundations.  Grouted Anchors.  Grouted Mattress for Seepage and Leakage Control in Perennial Canal  Microfine Cement Grouting in Tunnelling and other Applications  Crack Grouting for Rehabilitation of Building and Dams  Jet Grouting for Deep Foundations & Tunnels
  • 15. Alluvial Grouting for Earth Dam Foundation Concrete Gravity Dam with Intersecting Fault Zone Concrete rch Dam Resist Unstable Movements
  • 17. Vibration Isolation for Machine Foundation Cement/Chemical injection of foundation media is a recent innovation in decreasing vibration. Such injection results in increased rigidity of the base and consequently increased natural vibration of the foundation. Increased rigidity increases the difference between the frequency of natural vibration and the frequency of the machine. Consequently the amplitudes of foundation vibration are decreased. The injection method has the special advantages of non-interruption of work of the machine during the treatment.
  • 18. Compaction & Jet Grouting
  • 19.
  • 20.
  • 21.
  • 22. Controlled Lifting with Compaction Grouting Correction of Structural Settlement (a) from the top down (b) from the bottom up
  • 23.
  • 24. Compaction Grouting For Increasing End Bearing And Friction
  • 27. Jet Grouting • A relatively new and one of the most successful techniques • A speed jet of water released from a 1 to 2 mm nozzle at the end of a grout pipe at a pressure of 200 to 5000 kg/cm2 cuts through the soil or soft rock. • When the slot has been formed, a chemical solution grout is substituted for the water and stabilizes in place as a solid mass. • The grout pipe is lifted from bottom of the hole as process continues.
  • 28. Various Applications of Jet grouting
  • 29. Consolidation & Underpinning for deep excavation close to existing buildings Underpinning of Existing Buildings
  • 30. foundations of viaduct piles Building Foundation improvement
  • 31.
  • 33. An outline of Grouting from beginning to end •Investigation •Decide whether grouting necessary or not •Design •Site preparation •Equipment •Drilling •Water testing •Hook-up •Commencing grouting •Looking for trouble •Review of mix •Completion •Assessment •Long term performance
  • 34.
  • 35.
  • 37.
  • 39. WHEN IS GROUTING WARRANTED??
  • 40.
  • 41. The Lugeon Test The Lugeon Test The most commonly in-situ test used to estimate hydraulic conductivity of rock masses is the Lugeon test – also called the packer test. The test, which derives its name from Maurice Lugeon (1933), is a constant head type test that takes place in an isolated portion of a borehole. Water at constant pressure is injected into the rock mass through a slotted pipe bounded by pneumatic packers. A pneumatic packer is an inflatable rubber sleeve that expands radially to seal the annulus space between the drill rods and the boring walls.
  • 42. One Lugeon value, which is empirically defined as flow rate of 1 liter/minute per meter of test hole under a reference water pressure equal to 1 MPa
  • 44.
  • 45.
  • 46. Use of Automated Data Acquisition System Automated data acquisition systems capable of measuring, displaying and recording Lugeon test and grouting data in Real Time have become available over the last years. This equipment measures flow rate and pressure at regular intervals of time and displays the information on an LCD display.
  • 47. • To give a sense of proportion for the unit: • 1 lugeon unit is the type of permeability where grouting is hardly necessary. • 10 lugeons warrants grouting for most seepage reduction jobs. • 100 lugeons is the type of permeability met in heavily jointed sites with relatively open joints or in sparsely cracked foundations where joints are very wide open.
  • 49. Adapting Grouting to Suit the Geology Features that can influence grouting design and construction include: • 1. Spacing of Joints • 2. Joint Widths and Continuity • 3. Joint Inclination • 4. Uniformity of the Site • 5. Rock Soundness • 6. Strength • 7. Piping
  • 50. 1. Spacing of Joints As far as cement grouting is concerned, it is the open, groutable joints that are of interest. If they are widely spaced, the grouting is usually easier than if closely spaced where troubles such as frequent surface leaks, collapsing holes and patchy penetrations can happen. These make for more expensive grouting, perhaps requiring special surface treatment.
  • 51. 2. Joint Width and Continuity The easiest joints to grout have widths in the range between about 0.250 in [6 mm] and 0.020 in [0.5 mm]. Continuity of open jointing systems affects penetration: lack of continuity means that more grout holes will be needed than if grout can travel appreciable distances through the systems.
  • 52. 3. Joint Inclination Where dipping is mainly between 20° and about 60°, vertical grout holes may give optimum interception. These are the easiest to drill and are preferable. Steeper jointing usually requires use of inclined holes.
  • 53. 4. Uniformity of Site Uniformity of jointing permits a regular layout of grout holes, whereas irregular jointing, dykes, disconformities, and so on may require placement of holes at various inclinations and spacing . Weaknesses may need to be treated intensively.
  • 54. 7. Piping Where material in joints can be removed by seepage, either by taking the material into solution or by eroding it, the grouting will need to be more intensive than otherwise in order to ensure that seepage through such joints is virtually eliminated.
  • 55. Starting Mix Decided on: • The recommended water:cement ratio is 2 : 1 for starting many of the grouting jobs. This is two parts of water to one part of cement, measured by volume. • However, if the majority of cracks are known to be relatively FINE such as 0.75mm or finer , starting with 3 : 1 could be better. At the other extreme, If cracks are fairly WIDE such as 1.25mm, it is usually wise to start with 1 : 1. (W:C ratio by volume) •
  • 56. Fast Grout take If the hole takes grout very rapidly, use of a thicker mix can be warranted, except in the special case where large voids are present; the water test before grouting should have indicated whether such voids are present. Usually, a fast take with minimal pressure buildup indicates that the cracks will probably accept a thicker mix without blocking. Therefore the grout should be thickened by one step and injected into the hole so as to use the thickest practicable grout and thereby gain maximum durability. Further thickening of the mix might be warranted if grout behaviour warrants this.
  • 57. STANDARD MIXES and THICKENING STEPS There is no need to use any other mixes than 5 : 1 by volume 4 : 1 3 : 1 2 : 1 1 : 1 0.8 : 1 0.6 : 1 0.5 : 1
  • 58. When thickening the mix during grouting, proceed down the list one mix at a time - never jump a mix. For instance, if thickening from 3 : 1, go to 2 : 1 for a while and then to 1 : 1 and perhaps on. Never go straight from 3 : 1 down to 1 : 1 or else the too sudden thickening is liable to prematurely block cracks in the job.
  • 59. Procedure and Monitoring of Grouting Operation
  • 60. ROCK GROUT CLOSURE WHEN DOING CEMENT GROUTING Closure grouting is the process of drilling and grouting the first holes in an area fairly widely apart, then drilling and grouting a hole midway between them, then putting holes midway in the remaining gaps, and so on, continuing this process of halving centres until enough grouting has been done. The first holes are usually called PRIMARY. The holes midway between them usually are given the name SECONDARY.
  • 61. The Concept of Closure
  • 62. The Concept of Closure
  • 63. When grout holes are longer than about 30 ft [10 m], it is usually best to divide them into shorter lengths, called stages, and grout each of these stages separately.
  • 67. PATTERN OF GROUT HOLES FOR CURTAIN GROUTING AND CONSOLIDATION ROCK GROUTING
  • 68.
  • 69.
  • 70.
  • 72. As per IS : 6066
  • 73. STAND PIPE FITTINGS UPHEAVAL GAUGE FOR EARTHEN DAM UPHEAVAL GAUGE FOR MASONARY / CONRETE DAM
  • 75. High take of grout
  • 76. TPC Diagrams for behaviour of grout hole
  • 77. Refusal Criteria Each grout operation should continue until refusal is reached. Refusal is considered to have been reached when intact grout at the desired limiting pressure is less than 2 lit/min averaged over a period of 10 minutes and the pressure greater than 3.5kg/cm2, or 1 lit/min when the pressure is below 3.5kg/cm2.
  • 79. GRAVEL SAND COARSE SILT SILT (NON PLASTIC) FINE COARSE MEDIUM FINE CEMENT BENTONITE POLYURETHANE AND POLYACRYLAMIDE SILICATES – HIGH CONCENTRATION SILICATES – LOW CONCENTRATION AMINOPLAST PHENOPLASTS MICRO FINE CEMENT GROUT ACRYLAMIDE ACRYLATES PENETRABILITY OF GROUTS
  • 80. Grout Materials Neat Cement Grouts Cement Grouts with Bentonite Cement Grout with Flyash Cement Grout with Chemical Admixtures Sand Cement Grouts Chemical Grouts Sodium Silicate Lignosulphonate Aminoplast Phenoplast Acrylamide Polyurethane Epoxy
  • 81.  CEMENT BENTONITE GROUTS Clay H.G. Bentonite Cement Water +Peptizing agent - - 0.5 8 - 0.8 0.2 0.6 6 0.1 to 2% - 0.4 1 5 2% - 0.7 1 5 2% 0.4 0.6 0.6 6 2% - 1 0 8 Sodium silicate Monosodium phosphate - 1 0.5 8 S/ P = 1 =1
  • 82. Marsh Cone – Oriffice Type Viscometer Horizontal Flow Meter for Flow measurement of Sand Cement Grout Bleeding Test for Bleeding Potential Mearuement Water Retentivity Testing Set Up
  • 83. Penetrability and Washout Test Set Up for Seepage Study through Grouted sample Grout Injection Mould for Strength Measurement
  • 86. The basic material should be as follows: A powder readily soluble in water. Inexpensive & derive in abundant supply. Non toxic Non corrosive Non explosive The grout solution should have: A low viscosity solution Stable under all normal temperature Non toxic, non corrosive, non explosive Catalyzed with common inexpensive chemicals Insensitive to salts normally found in ground water Of stable pH Readily controlled for varying gel times Able to withstand appreciable dilution with ground water.
  • 87. The end product should be: Permanent gel Unaffected by chemicals normally found in ground water Non toxic, non corrosive, non explosive High strength
  • 88. Since about 1970, silicate and acrylamide-based grouts share a market percentage between 85% and 90%, with the remaining portion of the market divided among other products. Chemical grouts fall into the following categories: Silicate formulations Acrylics (includes acrylamide and acrylate grouts) Lignosulfonates Phenoplasts Aminoplasts Other materials Chemical Grout Types
  • 89.
  • 90. ELECTROKINETIC GROUTING • Electrokinetic grouting may be applied towards solidification of soil, reducing its permeability and thereby increasing the strength of the soil. – Definition: When a DC current is applied across a sandy soil mass or any fine grained soil, sodium silicate (Na2SiO3) in the cathode compartment and the reactants like calcium chloride (CaCl2) as a hardener in the anode compartment migrate. The anionic silicate will migrate toward the anode due to electro-migration and cationic metal ions will migrate toward the cathode. When these charged ions meet within the soil, the pH of sodium silicate will be reduced and thereby form a gel within the soil and grout the soil mass. In silty soil where electroosmosis (pore water flow from anode to cathode) occurs due to application of D.C. electric field, it is expected that water-soluble sodium silicate grout will be carried away by electroosmotic flow from the anode towards the cathode. When the pH of this grout is reduced by the H+, generated and migrated (Electromigration) from the anode, the sodium silicate grout will form a gel and stabilize the soil.
  • 91.
  • 92.
  • 93. • Electrokinetic Grouting may also be used to trap or immobilize the contaminants within their host soil medium instead of removing them through chemical or physical treatment; simultaneously while densifying the soil.
  • 94. SOIL TREATED BY ELECTROKINETIC GROUTING • This method, an application of electrokinetic remediation technique, was used to improve the geotechnical properties of the soil mass by using a chemical grout. Soil was compacted in model by hand compaction. • At anode concentration used was made using 2% calcium chloride (CaCl2) powder dissolved in tap water, whereas at the cathode 20%, 25% and 30% sodium silicate (Na2SiO3) dissolved in tap water was used for different tests. • These solutions were used as two different components of a most commonly used chemical grout. • Carbon electrodes were then placed and connected to an AC- DC converter unit.
  • 95. Model No. L (cm) H (cm) W (cm) Fill Height (cm) o/p 1 8.3 19.8 10.2 15 o/p 2 18.2 19.5 15.5 15 o/p 3 25 19.8 20 15 o/p 4 41 22 30 15  Different size of open model
  • 96. 98 Comparison of initial and final UCS of soil at different locations 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 Anode Middle Cathode UCS in kg/ cm 2 Before Electrokinetic Grouting After Electrokinetic Grouting
  • 98. Work at KAKRAPAR Canals in Gujarat At the instructions of the Government of Gujarat, a Study has been taken up by Cemindia, Bombay under World Bank Credit for adopting the method of Grouted Mattress in India. For this purpose pilot testing have been taken up at two sections of Kakrapar Canal system near Surat. The canal has a maximum flow of about 250 cusecs and water depth of about 1.8 meters, having bed of about 6.6 wide and side slopes are 1 vertical to 1.5 horizontal.
  • 99. Grouted Geotextile Mattress Preamble As a consequence of research and development jointly by the Applied Mechanics Department & Textile Engineering Department of Faculty of Technology & Engineering and indigenous technique of GROUTED GEOTEXTILE MATTRESS for canal lining under flowing water condition was devised by R & D Division of Cemindia. Model and field studies have revealed that the strength of material in lining attained at 28 days is about 180 kg/cm2 and the permeability and rugosity co-efficient of lined canal are within the limit of code of practice.
  • 100. Technique The technique involves use of and mattress cove made with two layers of a specially woven synthetic fabric (Fig.) Strip or threaded spacers are provided in the dual walled fabric which give the mat its characteristics “cobbled” effect. The woven fabric is positioned on the prepared slope or surface and subsequently filled with fine grained sand-cement grout mix. The completed mat provides a slab of nominal 100 mm thickness. Construction of the concrete matting starts with the positioning and securing of the mattress on the ground profile.
  • 101. Special pipes are then inserted to the bottom of the frame work. Colloidal sand cement mix is then pumped into position as the pipes are gradually with drawn to the surface. (Fig.) Pumping in this way under low pressure ensures continuity and uniformity of the filter and as the concrete mat is casted, it adapts itself to the ground profile. The mix is normally used for pumping consists of sand, cement and water.
  • 102. Mattress fabric cover with spacer A typical fabric developed for this purpose which involves special three dimensional weaving technique. The fabric is a double layered one and the two layers can be separated by a predetermined amount with the help of spacer yarns. The spacer yarn ensures the continuity of the two layers of the fabric shell as well as the thickness of the lining without any hindrance to the fluid flow of the grout mix during its application. The length and distribution of the spacers yarn in total fabric matrix can be manipulated to suit the specific requirements of the lining thickness and grout pressure. To resist the pressure it is essential that fabric shell possess sufficient tensile and bursting strength as also low value of elongation at all levels of loading. The fabric is resistant to acids, alkalis and other common chemical as also to weathering and exposure to sunlight.
  • 103. CHARACTERISTICS OF DOUBLE LAYER GEOTEXTILE88 1) Warp – Nylon yarn – Count – 1120 Deniers , Breaking load – 7.36 Kgs. At 10 cms gauge length 2) Weft – Polypropylene flat Tape – Count – 1038 Deniers Breaking load – 3.66 Kgs at 10 cms gauge length %age Elongation – 41.83 % 3) Space Yarn –Nylon woven ape – Count – 7160 Deniers Breaking load – 41.42 Kgs. %age Elongation – 45.10 % No. of ends and picks per inch 22 Two spacer yarns are used.
  • 104.
  • 105. The Canal perimeter was cleared of vegetation and trimmed to provide a reasonably working surface. A canal perimeter is about 14.7 m. The mattress length of about 15 m was laid, in the flowing water conditions, on the bed and side slopes of the canal. It was properly secured along the edges. The next length of the mattress was joined to the first 15 m length after completion of the in-filling of the mattress. The joining of bed lengths was carried out in the flowing canal. The mattress was filled up with a pumpable mix of cement- sand – water and additives by the help of screw type pump. The nominal thickness of the lining as achieved in about 11 cm. Tests carried out on samples from the lining itself showed that the strength of the materials attained at 28 days is about 180 kg/cm2.
  • 106.
  • 107.
  • 108. Concluding remarks It is essential to have good understanding of the geologic conditions being treated by grouting. The grouting program should be designed to address those conditions and maintain sufficient flexibility to accommodate new information obtained following implementation. “Cook Book Programme” will not suffice. The geologic, grouting and permeability should be continuously monitored so that appropriate changes in the design can be made, and so that the impact of the inevitable geological surprise can be minimized.