Microsoft Dynamics GP Year‐End Tips 
 
The end of the year is always a busy and stressful time of year.  Hopefully the following 
steps/guideline will take some of the stress out of the year‐end close of your Dynamics GP 
system. 
 
There is a specific order that Microsoft recommends when performing the year‐end close for 
the different GP modules.  Please see the order as listed below: 
 
1. US Payroll/Canadian Payroll – the payroll module is independent of the other modules 
and is always done at the end of the calendar year. 
2. Inventory Control 
3. Receivables Management 
4. Payables Management 
5. Fixed Assets 
6. Analytical Accounting** 
7. General Ledger 
 
*Note: there is no year‐end close process for Sales Order Processing or Purchase Order 
Processing. 
 
**Note: Analytical Accounting is part of the General Ledger close process. 
 
 
Payroll 
The payroll module is independent of the other modules within Dynamics GP.  The closing of 
the payroll module should be done only after all pay runs for the current year have been 
performed and the year‐end wage file has been created.  Listed below are the steps to closing 
the Dynamics GP Payroll module: 
1. Complete a backup of the database that can be restored back to if necessary 
2. Verify that the latest 2016 tax update has been installed 
3. Complete all pay runs for the current year 
4. Make a backup of the original file 
a. This will be your backup pre‐year‐end close 
5. Install the 2016 year‐end update 
6. Create the year‐end file 
a. Dynamics GP, Tools, Routines, Payroll, Year‐End Closing 
b. In the Year type ‘2016’, and then click process 
7. Make a backup of the new file 
 
  2    
trinsoft.comtrinsoft.com
a. This will be your backup as of year‐end 
8. Verify W‐2 and 1099‐R statement information 
a. W‐2: Dynamics GP, Tools, Routines, Payroll, Edit W‐2s 
b. 1099‐R: Dynamics GP, Tools, Routines, Payroll, Edit 1099‐Rs 
9. Print the W‐2 and the W‐3 Transmittal form 
a. W‐2: Dynamics GP, Tools, Routines, Payroll, Print W‐2s 
i. Print W‐2s for: Normal Year‐End 
b. W‐3 Transmittal Form: Dynamics GP, Tools, Routines, Payroll, Print W‐3s 
i. Print W‐2s for: Normal Year‐End 
ii. Print W‐3 Transmittal Form 
10. Print the 1099‐R and the 1096 Transmittal form 
a. 1099‐R: Dynamics GP, Tools, Routines, Payroll, Print 1099‐Rs 
i. Click 1099‐R Forms, Print 
b. 1096 Transmittal Form: Dynamics GP, Tools, Routines, Payroll, Print 1099‐Rs 
i. Click 1096 Transmittal Form, Print 
11. Create a W‐2 Electronic File (Optional) 
a. Dynamics GP, Tools, Routines, Payroll, W‐2 Electronic File 
12. Archive inactive Employee Human Resources information (Optional) 
a. Dynamics GP, Tools, Utilities, Human resources, Archive Employee 
13. Set up Fiscal Periods for 2017 
a. Dynamics GP, Setup, Company, Fiscal Periods 
14. Close Fiscal Periods for the Payroll Series for 2016 (Optional) 
a. Dynamics GP, Setup, Company, Fiscal Periods 
15. Install the Payroll Tax Update for 2017 
a. DO NOT install the payroll tax update for 2017 until the year‐end file has been 
created for 2016. 
b. Dynamics GP, Maintenance, US Payroll Updates, Check for Tax Updates 
 
Inventory 
The inventory module should be closed at the end of the fiscal year BEFORE posting any 
transactions in the next fiscal year.  When performing the close for inventory GP will transfer all 
summarized current‐year quantities (cost and sales amounts) to last‐year for the items keeping 
summarized Sales History.  The system will also update each items Beginning quantity from the 
quantity on hand at each site.  GP also zeros out the quantity sold field in the Item Quantity 
Maintenance window for each site. The system also give the user the option to remove 
discontinued items, remove sold receipts, remove sold lot attributes, and update items 
standard cost.  Listed below are the steps to closing the Dynamics GP Inventory module: 
1. Post all Transactions for the Year 
a. Including: Invoice transactions, Sales Order Processing transactions, and 
Inventory transactions 
2. Reconcile Inventory Quantities   
a. Dynamics GP, Tools, Utilities, Inventory, Reconcile 
b. If any differences are found the quantities will be adjusted 
3. Complete a Physical Inventory Count, Post any Adjustments 
 
  3    
trinsoft.comtrinsoft.com
a. Instead can print a physical inventory checklist by using the Activity Reports 
window and then perform a physical count of the inventory on hand to make 
sure those amounts are accurate. 
b. Enter any adjustments as needed in the Inventory, Transaction Entry Window 
4. Print Additional Reports 
a. Suggested reports to keep for planning/records include:  
Stock Status Report  Purchase Receipts Report Turnover Report 
Transaction History Report Serial Number List Lot Number List 
5. Make a Backup 
6. Close the year 
a. Dynamics GP, Tools, Routines, Inventory, Year‐End Close 
7. Close the Fiscal Periods for the Inventory Series (Optional) 
a. Dynamics GP, Setup, Company, Fiscal Periods 
8. Make a Final Backup 
a. Gives the user a permanent record of the company’s financial position at the 
time the user closed the year. 
 
Note: there is no Year‐End closing report for Inventory 
 
 
Receivables Management 
The Receivable Management module has both a Calendar and a Fiscal year‐end close.  For both 
options the close should be done prior to any transactions posting for the next calendar year.  
For the Calendar close Dynamics GP will clear the Calendar year‐to‐date finance charges and 
move them to the Last Year Calendar field in the Customer Finance Charge Summary.  For the 
Fiscal close Dynamics GP will transfer all amounts other then Calendar year‐to‐date Finance 
Charges to the Last Year column in Customer Summary using the Amounts Since Last Closed 
View.  Be aware that there is some date sensitivity for SmartLists and Summary Reports with 
this module.  Listed below are the steps to closing the Dynamics GP Receivables Management 
module: 
1. Post all Sales and Receivables Transactions for the Year 
2. Make a Pre‐Year‐End Closing Backup 
3. Close the Year 
a. Dynamics GP, Tools, Routines, Sales, Year‐End Close 
i. Select if closing calendar or fiscal or all. 
4. Close the Fiscal Periods (Optional) 
a. Dynamics GP, Tools, Setup, Company, Fiscal Periods 
5. Close the Tax Year 
a. Follow ONLY after you complete the year‐end closing procedures for all the sales 
and purchasing modules 
b. Dynamics GP, Tools, Routines, Company, Tax Year‐End Close 
i. Select the Close Year, Process 
6. Make a Post‐Year‐End Closing Backup 
 
  4    
trinsoft.comtrinsoft.com
a. Provides a permanent record of the company’s financial position at the end of 
the year. 
 
 
Payables Management 
Like the receivables management module, the payables management series has both a 
Calendar and a Fiscal year‐end close.  With either close no new year transactions should be 
posted until the prior year is closed out.  For the Calendar close Dynamics GP will transfer the 
1099 amount from year‐to‐date to the Last Year column in the Amounts Since Last Close view 
to the Vendor Yearly Summary window.  For the Fiscal close Dynamics GP will transfer all other 
amounts from year‐to‐date to the Last Year column in the Amounts Since Last Close view.  
Listed below are the steps to closing the Dynamics GP Payables Management module: 
1. Post all Transactions for the Year 
2. Print the Aged Trial Balance with Options Report 
a. Reports, Purchasing, Trial Balance 
3. Print the Vendor Period Analysis Report 
a. Reports, Purchasing, Analysis 
4. Install the Payroll Year‐End Update (optional) 
a. If there are compliance changes for Payables Management, such as 1099 form 
changes, install the update. 
5. Make a Backup that is Named “Pre‐1099 Edits” 
6. Verify the 1099 Information and Edit as needed 
a. Dynamics GP, Tools, Routines, Purchasing, Print 1099 
b. To Edit: Transactions, Purchasing, Edit 1099 Transaction Information 
7. Print 1099 Statements 
a. Dynamics GP, Tools, Routines, Purchasing, Print 1099 
8. Make a Backup that is Named “Pre Year‐End” 
9. Close the Year 
a. Dynamics GP, Tools, Routines, Purchasing, Year‐End Close 
i. Select if closing calendar or fiscal or all. 
10. Close the Fiscal Periods 
a. Dynamics GP, Tools, Setup, Company, Fiscal Periods 
11. Make a Backup that is Named “Post Year‐End” 
a. Gives you a permanent record of the company’s financial position at the end of 
the year. 
 
 
Fixed Assets 
The fixed assets module should be closed prior to posting any transactions into the new fiscal 
year.  It should be closed after the payables management module but before the general ledger 
transactions are posted into the new year.  Fixed asset books can be closed separately, 
however, all books must be closed prior to processing the fixed assets for the new year.  When 
the close process is run Dynamics GP will update a few windows and fields.  In the Assets 
General Window, the year‐to‐date maintenance amount is cleared and then quantity is copied 
 
  5    
trinsoft.comtrinsoft.com
o the beginning quantity field.  Within the Asset Book Window, the year‐to‐date depreciation 
amount is cleared, cost basis is copied to the beginning year cost field, life‐to‐date depreciation 
is copied to beginning reserve field, and salvage value is copied to the beginning salvage field.  
Finally, the current fiscal year is increased to the next year.  Listed below are the steps to 
closing the Dynamics GP Fixed Assets module: 
1. Perform all the Year‐End Closing Procedures for Payables Management in Dynamics GP 
a. This guarantees that all outstanding fixed assets transactions are capitalized. 
2. Enter all the Fixed Assets Transactions for the Current Fiscal Year 
3. Depreciate all Assets Through the Last Day of the Current Fiscal Year 
a. Dynamics GP, Tools, Routines, Fixed Assets, Depreciate 
4. Perform the GL Posting (GL Interface) Process (Optional) 
5. Run any Year‐End Reports that you want to keep as part of the Year‐End Financial 
Records 
a. Reports to consider: 
Annual Activity  Additions Retirements
Transfers  Depreciation Ledger Property Ledger
Fixed Assets to GL Reconciliation  Book to Book Reconciliation Book to Book YTD Depreciation Comparison
6. Guarantee that the Fixed Assets Calendar is Built Correctly (Optional) 
a. Dynamics GP, Tools, Utilities, Fixed Assets, Build Calendar 
7. Verify that the Quarters are Setup Correctly for all the Fiscal Years 
a. Dynamics GP, Tools, Utilities, Fixed Assets, Quarter 
8. Create a Backup 
a. Is a permanent record of the company’s financial position at the end of the year 
9. Perform the Fixed Assets Year‐End Closing Routine 
a. Dynamics GP, Tools, Routines, Fixed Assets, Year End 
 
 
General Ledger 
The general ledger closing should be performed only after all other modules have been closed.  
When the GL is closed all Profit & Loss accounts are rolled into retained earnings and all Balance 
Sheet accounts are rolled into the beginning balance for that account.  Inactive accounts with 
no balance and no historical transactions are removed.  Finally, the year that was just closed is 
marked as historical and the fiscal period tables are updated marking the year as historical.  
Listed below are the steps to closing the Dynamics GP General Ledger module: 
1. Complete the Posting Procedures & Closing Procedures for all Other Modules 
2. Post the Final Adjusting Entries in General Ledger 
a. Any correcting entries, journal entries for revenue or expense, etc. 
3. Print an Account List to verify the Posting Type of Each Account 
a. The posting type determines whether an account is closed to retained earnings 
account or whether an account brings a balance forward to the next fiscal year. 
4. Close the Last Period of the Fiscal Year (Optional) 
a. This prevents transactions from being posted to the wrong period or year 
5. Perform File Maintenance on the Finical Series Group of Modules (Optional) 
 
  6    
trinsoft.comtrinsoft.com
a. Run the check links procedure on the Financial series group of modules 
6. Verify the Settings in the General Ledger Setup Window 
a. If desire to keep historical records, then the user must select the Accounts check 
box and the Transactions check box in the Maintain History area of the GL setup 
window. 
7. Make a backup 
8. Print a final Detailed Trial Balance Report 
9. Print the Year‐End Financial Statements 
a. Most common reports include: 
Balance Sheet  Profit & Loss Statement 
Statement of Cash Flow  Statement of Retained Earnings 
10. Setup a New Fiscal year 
a. Use the Fiscal Periods Setup window 
11. Close the Fiscal Year 
a. Dynamics GP, Tools, Routines, Financial, Year‐End Closing 
b. Specify an account in the Retained Earnings Account box 
c. Specify if journal entry numbers should be reset 
d. Click Close Year to start the routine 
12. Close all the Fiscal Periods for all the Series (Optional) 
a. To prevent transactions from being posted into closed periods 
13. Adjust the Budget Figures for the New year, and Then Print the Financial Statements 
14. Make a backup 
a. This backup gives the user a permanent record of the company’s financial 
position at the start of the new year. 
 
 
Finally, take a deep breath as the close is now complete! 

More Related Content

Similar to Microsoft Dynamics GP Year-End Close Process Tips

Webinar Presentation: Microsoft Dynamics 2013 Year End Close
Webinar Presentation: Microsoft Dynamics 2013 Year End Close Webinar Presentation: Microsoft Dynamics 2013 Year End Close
Webinar Presentation: Microsoft Dynamics 2013 Year End Close Emtec Inc.
 
Dynamics GP 2013 Year End Closing Procedures
Dynamics GP 2013 Year End  Closing ProceduresDynamics GP 2013 Year End  Closing Procedures
Dynamics GP 2013 Year End Closing ProceduresACE Microtechnology, Inc.
 
Dynamics GP 10 and 2010 year end closing procedures
Dynamics GP 10 and 2010 year end closing proceduresDynamics GP 10 and 2010 year end closing procedures
Dynamics GP 10 and 2010 year end closing proceduresACE Microtechnology, Inc.
 
2014 Year End Closing for Microsoft Dynamics GP
2014 Year End Closing for Microsoft Dynamics GP2014 Year End Closing for Microsoft Dynamics GP
2014 Year End Closing for Microsoft Dynamics GPTGO Consulting
 
2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End Closing2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End ClosingSociusPartner
 
2016 Year End Close Procedures
2016 Year End Close Procedures2016 Year End Close Procedures
2016 Year End Close ProceduresTGO Consulting
 
Sage MAS 90 Year End Payroll Closing For 2010
Sage MAS 90 Year End Payroll Closing For 2010Sage MAS 90 Year End Payroll Closing For 2010
Sage MAS 90 Year End Payroll Closing For 2010Jeffrey Paulette
 
Webinar - Year-end Processing in Microsoft Dynamics GP
Webinar - Year-end Processing in Microsoft Dynamics GPWebinar - Year-end Processing in Microsoft Dynamics GP
Webinar - Year-end Processing in Microsoft Dynamics GPm-hance
 
sap-fi-bootcamp-training-day2.ppt
sap-fi-bootcamp-training-day2.pptsap-fi-bootcamp-training-day2.ppt
sap-fi-bootcamp-training-day2.pptveysi yi?it
 
Microsoft dynamics gp 2010 training
Microsoft dynamics gp 2010 trainingMicrosoft dynamics gp 2010 training
Microsoft dynamics gp 2010 trainingmagnificdynamics
 
Microsoft dynamics training
Microsoft dynamics trainingMicrosoft dynamics training
Microsoft dynamics trainingmagnificdynamics
 
Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019RKLeSolutions
 
Microsoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingMicrosoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingmagnificdynamics
 
Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018RKLeSolutions
 
Microsoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingMicrosoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingmagnificdynamics
 
Sage Intacct Year-end Processing 2020
Sage Intacct Year-end Processing 2020Sage Intacct Year-end Processing 2020
Sage Intacct Year-end Processing 2020RKLeSolutions
 
Microsoft Dynamics NAV Year-End Processing Checklist
Microsoft Dynamics NAV Year-End Processing ChecklistMicrosoft Dynamics NAV Year-End Processing Checklist
Microsoft Dynamics NAV Year-End Processing ChecklistJohn Stucky
 
Budgeting & Forecasting for High Growth Companies (Updated!)
Budgeting & Forecasting for High Growth Companies (Updated!)Budgeting & Forecasting for High Growth Companies (Updated!)
Budgeting & Forecasting for High Growth Companies (Updated!)Chris Arndt
 
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue Estimation
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue EstimationSmarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue Estimation
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue EstimationJukka Niiranen
 
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...BCS ProSoft
 

Similar to Microsoft Dynamics GP Year-End Close Process Tips (20)

Webinar Presentation: Microsoft Dynamics 2013 Year End Close
Webinar Presentation: Microsoft Dynamics 2013 Year End Close Webinar Presentation: Microsoft Dynamics 2013 Year End Close
Webinar Presentation: Microsoft Dynamics 2013 Year End Close
 
Dynamics GP 2013 Year End Closing Procedures
Dynamics GP 2013 Year End  Closing ProceduresDynamics GP 2013 Year End  Closing Procedures
Dynamics GP 2013 Year End Closing Procedures
 
Dynamics GP 10 and 2010 year end closing procedures
Dynamics GP 10 and 2010 year end closing proceduresDynamics GP 10 and 2010 year end closing procedures
Dynamics GP 10 and 2010 year end closing procedures
 
2014 Year End Closing for Microsoft Dynamics GP
2014 Year End Closing for Microsoft Dynamics GP2014 Year End Closing for Microsoft Dynamics GP
2014 Year End Closing for Microsoft Dynamics GP
 
2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End Closing2012 Microsoft Dynamics GP Year End Closing
2012 Microsoft Dynamics GP Year End Closing
 
2016 Year End Close Procedures
2016 Year End Close Procedures2016 Year End Close Procedures
2016 Year End Close Procedures
 
Sage MAS 90 Year End Payroll Closing For 2010
Sage MAS 90 Year End Payroll Closing For 2010Sage MAS 90 Year End Payroll Closing For 2010
Sage MAS 90 Year End Payroll Closing For 2010
 
Webinar - Year-end Processing in Microsoft Dynamics GP
Webinar - Year-end Processing in Microsoft Dynamics GPWebinar - Year-end Processing in Microsoft Dynamics GP
Webinar - Year-end Processing in Microsoft Dynamics GP
 
sap-fi-bootcamp-training-day2.ppt
sap-fi-bootcamp-training-day2.pptsap-fi-bootcamp-training-day2.ppt
sap-fi-bootcamp-training-day2.ppt
 
Microsoft dynamics gp 2010 training
Microsoft dynamics gp 2010 trainingMicrosoft dynamics gp 2010 training
Microsoft dynamics gp 2010 training
 
Microsoft dynamics training
Microsoft dynamics trainingMicrosoft dynamics training
Microsoft dynamics training
 
Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019Sage 100Cloud Year-end Processing and Payroll Webinar 2019
Sage 100Cloud Year-end Processing and Payroll Webinar 2019
 
Microsoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingMicrosoft dynamics gp 2013 training
Microsoft dynamics gp 2013 training
 
Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018
 
Microsoft dynamics gp 2013 training
Microsoft dynamics gp 2013 trainingMicrosoft dynamics gp 2013 training
Microsoft dynamics gp 2013 training
 
Sage Intacct Year-end Processing 2020
Sage Intacct Year-end Processing 2020Sage Intacct Year-end Processing 2020
Sage Intacct Year-end Processing 2020
 
Microsoft Dynamics NAV Year-End Processing Checklist
Microsoft Dynamics NAV Year-End Processing ChecklistMicrosoft Dynamics NAV Year-End Processing Checklist
Microsoft Dynamics NAV Year-End Processing Checklist
 
Budgeting & Forecasting for High Growth Companies (Updated!)
Budgeting & Forecasting for High Growth Companies (Updated!)Budgeting & Forecasting for High Growth Companies (Updated!)
Budgeting & Forecasting for High Growth Companies (Updated!)
 
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue Estimation
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue EstimationSmarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue Estimation
Smarter Sales Process in Dynamics CRM 2015 - Part 2: Revenue Estimation
 
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...
Year-End Processing with Sage 100 ERP (MAS 90 and MAS 200) | Q4 2014 User Gro...
 

More from Callie Wagner

7 Pitfalls to Avoid When Transitioning Business Software to the Cloud
7 Pitfalls to Avoid When Transitioning Business Software to the Cloud7 Pitfalls to Avoid When Transitioning Business Software to the Cloud
7 Pitfalls to Avoid When Transitioning Business Software to the CloudCallie Wagner
 
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...Callie Wagner
 
What's New in Microsoft Dynamics NAV 2018
What's New in Microsoft Dynamics NAV 2018What's New in Microsoft Dynamics NAV 2018
What's New in Microsoft Dynamics NAV 2018Callie Wagner
 
Microsoft Dynamics NAV Year-End Prep
Microsoft Dynamics NAV Year-End PrepMicrosoft Dynamics NAV Year-End Prep
Microsoft Dynamics NAV Year-End PrepCallie Wagner
 
Microsoft Dynamics User Group Summit 2017 Recap
Microsoft Dynamics User Group Summit 2017 RecapMicrosoft Dynamics User Group Summit 2017 Recap
Microsoft Dynamics User Group Summit 2017 RecapCallie Wagner
 
Moving Microsoft Dynamics to the Cloud
Moving Microsoft Dynamics to the CloudMoving Microsoft Dynamics to the Cloud
Moving Microsoft Dynamics to the CloudCallie Wagner
 
Maximize Your Dynamics User Group Summit 2017 Experience
Maximize Your Dynamics User Group Summit 2017 ExperienceMaximize Your Dynamics User Group Summit 2017 Experience
Maximize Your Dynamics User Group Summit 2017 ExperienceCallie Wagner
 
Year-End Close Process for Microsoft Dynamics GP
Year-End Close Process for Microsoft Dynamics GPYear-End Close Process for Microsoft Dynamics GP
Year-End Close Process for Microsoft Dynamics GPCallie Wagner
 
Microsoft Envision 2016 Recap
Microsoft Envision 2016 RecapMicrosoft Envision 2016 Recap
Microsoft Envision 2016 RecapCallie Wagner
 

More from Callie Wagner (9)

7 Pitfalls to Avoid When Transitioning Business Software to the Cloud
7 Pitfalls to Avoid When Transitioning Business Software to the Cloud7 Pitfalls to Avoid When Transitioning Business Software to the Cloud
7 Pitfalls to Avoid When Transitioning Business Software to the Cloud
 
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...
What is Microsoft Dynamics 365 Business Central & What Does It Mean for My Bu...
 
What's New in Microsoft Dynamics NAV 2018
What's New in Microsoft Dynamics NAV 2018What's New in Microsoft Dynamics NAV 2018
What's New in Microsoft Dynamics NAV 2018
 
Microsoft Dynamics NAV Year-End Prep
Microsoft Dynamics NAV Year-End PrepMicrosoft Dynamics NAV Year-End Prep
Microsoft Dynamics NAV Year-End Prep
 
Microsoft Dynamics User Group Summit 2017 Recap
Microsoft Dynamics User Group Summit 2017 RecapMicrosoft Dynamics User Group Summit 2017 Recap
Microsoft Dynamics User Group Summit 2017 Recap
 
Moving Microsoft Dynamics to the Cloud
Moving Microsoft Dynamics to the CloudMoving Microsoft Dynamics to the Cloud
Moving Microsoft Dynamics to the Cloud
 
Maximize Your Dynamics User Group Summit 2017 Experience
Maximize Your Dynamics User Group Summit 2017 ExperienceMaximize Your Dynamics User Group Summit 2017 Experience
Maximize Your Dynamics User Group Summit 2017 Experience
 
Year-End Close Process for Microsoft Dynamics GP
Year-End Close Process for Microsoft Dynamics GPYear-End Close Process for Microsoft Dynamics GP
Year-End Close Process for Microsoft Dynamics GP
 
Microsoft Envision 2016 Recap
Microsoft Envision 2016 RecapMicrosoft Envision 2016 Recap
Microsoft Envision 2016 Recap
 

Recently uploaded

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 

Recently uploaded (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 

Microsoft Dynamics GP Year-End Close Process Tips

  • 1.       trinsoft.com           Microsoft Dynamics GP Year‐End Tips    The end of the year is always a busy and stressful time of year.  Hopefully the following  steps/guideline will take some of the stress out of the year‐end close of your Dynamics GP  system.    There is a specific order that Microsoft recommends when performing the year‐end close for  the different GP modules.  Please see the order as listed below:    1. US Payroll/Canadian Payroll – the payroll module is independent of the other modules  and is always done at the end of the calendar year.  2. Inventory Control  3. Receivables Management  4. Payables Management  5. Fixed Assets  6. Analytical Accounting**  7. General Ledger    *Note: there is no year‐end close process for Sales Order Processing or Purchase Order  Processing.    **Note: Analytical Accounting is part of the General Ledger close process.      Payroll  The payroll module is independent of the other modules within Dynamics GP.  The closing of  the payroll module should be done only after all pay runs for the current year have been  performed and the year‐end wage file has been created.  Listed below are the steps to closing  the Dynamics GP Payroll module:  1. Complete a backup of the database that can be restored back to if necessary  2. Verify that the latest 2016 tax update has been installed  3. Complete all pay runs for the current year  4. Make a backup of the original file  a. This will be your backup pre‐year‐end close  5. Install the 2016 year‐end update  6. Create the year‐end file  a. Dynamics GP, Tools, Routines, Payroll, Year‐End Closing  b. In the Year type ‘2016’, and then click process  7. Make a backup of the new file 
  • 2.     2     trinsoft.comtrinsoft.com a. This will be your backup as of year‐end  8. Verify W‐2 and 1099‐R statement information  a. W‐2: Dynamics GP, Tools, Routines, Payroll, Edit W‐2s  b. 1099‐R: Dynamics GP, Tools, Routines, Payroll, Edit 1099‐Rs  9. Print the W‐2 and the W‐3 Transmittal form  a. W‐2: Dynamics GP, Tools, Routines, Payroll, Print W‐2s  i. Print W‐2s for: Normal Year‐End  b. W‐3 Transmittal Form: Dynamics GP, Tools, Routines, Payroll, Print W‐3s  i. Print W‐2s for: Normal Year‐End  ii. Print W‐3 Transmittal Form  10. Print the 1099‐R and the 1096 Transmittal form  a. 1099‐R: Dynamics GP, Tools, Routines, Payroll, Print 1099‐Rs  i. Click 1099‐R Forms, Print  b. 1096 Transmittal Form: Dynamics GP, Tools, Routines, Payroll, Print 1099‐Rs  i. Click 1096 Transmittal Form, Print  11. Create a W‐2 Electronic File (Optional)  a. Dynamics GP, Tools, Routines, Payroll, W‐2 Electronic File  12. Archive inactive Employee Human Resources information (Optional)  a. Dynamics GP, Tools, Utilities, Human resources, Archive Employee  13. Set up Fiscal Periods for 2017  a. Dynamics GP, Setup, Company, Fiscal Periods  14. Close Fiscal Periods for the Payroll Series for 2016 (Optional)  a. Dynamics GP, Setup, Company, Fiscal Periods  15. Install the Payroll Tax Update for 2017  a. DO NOT install the payroll tax update for 2017 until the year‐end file has been  created for 2016.  b. Dynamics GP, Maintenance, US Payroll Updates, Check for Tax Updates    Inventory  The inventory module should be closed at the end of the fiscal year BEFORE posting any  transactions in the next fiscal year.  When performing the close for inventory GP will transfer all  summarized current‐year quantities (cost and sales amounts) to last‐year for the items keeping  summarized Sales History.  The system will also update each items Beginning quantity from the  quantity on hand at each site.  GP also zeros out the quantity sold field in the Item Quantity  Maintenance window for each site. The system also give the user the option to remove  discontinued items, remove sold receipts, remove sold lot attributes, and update items  standard cost.  Listed below are the steps to closing the Dynamics GP Inventory module:  1. Post all Transactions for the Year  a. Including: Invoice transactions, Sales Order Processing transactions, and  Inventory transactions  2. Reconcile Inventory Quantities    a. Dynamics GP, Tools, Utilities, Inventory, Reconcile  b. If any differences are found the quantities will be adjusted  3. Complete a Physical Inventory Count, Post any Adjustments 
  • 3.     3     trinsoft.comtrinsoft.com a. Instead can print a physical inventory checklist by using the Activity Reports  window and then perform a physical count of the inventory on hand to make  sure those amounts are accurate.  b. Enter any adjustments as needed in the Inventory, Transaction Entry Window  4. Print Additional Reports  a. Suggested reports to keep for planning/records include:   Stock Status Report  Purchase Receipts Report Turnover Report  Transaction History Report Serial Number List Lot Number List  5. Make a Backup  6. Close the year  a. Dynamics GP, Tools, Routines, Inventory, Year‐End Close  7. Close the Fiscal Periods for the Inventory Series (Optional)  a. Dynamics GP, Setup, Company, Fiscal Periods  8. Make a Final Backup  a. Gives the user a permanent record of the company’s financial position at the  time the user closed the year.    Note: there is no Year‐End closing report for Inventory      Receivables Management  The Receivable Management module has both a Calendar and a Fiscal year‐end close.  For both  options the close should be done prior to any transactions posting for the next calendar year.   For the Calendar close Dynamics GP will clear the Calendar year‐to‐date finance charges and  move them to the Last Year Calendar field in the Customer Finance Charge Summary.  For the  Fiscal close Dynamics GP will transfer all amounts other then Calendar year‐to‐date Finance  Charges to the Last Year column in Customer Summary using the Amounts Since Last Closed  View.  Be aware that there is some date sensitivity for SmartLists and Summary Reports with  this module.  Listed below are the steps to closing the Dynamics GP Receivables Management  module:  1. Post all Sales and Receivables Transactions for the Year  2. Make a Pre‐Year‐End Closing Backup  3. Close the Year  a. Dynamics GP, Tools, Routines, Sales, Year‐End Close  i. Select if closing calendar or fiscal or all.  4. Close the Fiscal Periods (Optional)  a. Dynamics GP, Tools, Setup, Company, Fiscal Periods  5. Close the Tax Year  a. Follow ONLY after you complete the year‐end closing procedures for all the sales  and purchasing modules  b. Dynamics GP, Tools, Routines, Company, Tax Year‐End Close  i. Select the Close Year, Process  6. Make a Post‐Year‐End Closing Backup 
  • 4.     4     trinsoft.comtrinsoft.com a. Provides a permanent record of the company’s financial position at the end of  the year.      Payables Management  Like the receivables management module, the payables management series has both a  Calendar and a Fiscal year‐end close.  With either close no new year transactions should be  posted until the prior year is closed out.  For the Calendar close Dynamics GP will transfer the  1099 amount from year‐to‐date to the Last Year column in the Amounts Since Last Close view  to the Vendor Yearly Summary window.  For the Fiscal close Dynamics GP will transfer all other  amounts from year‐to‐date to the Last Year column in the Amounts Since Last Close view.   Listed below are the steps to closing the Dynamics GP Payables Management module:  1. Post all Transactions for the Year  2. Print the Aged Trial Balance with Options Report  a. Reports, Purchasing, Trial Balance  3. Print the Vendor Period Analysis Report  a. Reports, Purchasing, Analysis  4. Install the Payroll Year‐End Update (optional)  a. If there are compliance changes for Payables Management, such as 1099 form  changes, install the update.  5. Make a Backup that is Named “Pre‐1099 Edits”  6. Verify the 1099 Information and Edit as needed  a. Dynamics GP, Tools, Routines, Purchasing, Print 1099  b. To Edit: Transactions, Purchasing, Edit 1099 Transaction Information  7. Print 1099 Statements  a. Dynamics GP, Tools, Routines, Purchasing, Print 1099  8. Make a Backup that is Named “Pre Year‐End”  9. Close the Year  a. Dynamics GP, Tools, Routines, Purchasing, Year‐End Close  i. Select if closing calendar or fiscal or all.  10. Close the Fiscal Periods  a. Dynamics GP, Tools, Setup, Company, Fiscal Periods  11. Make a Backup that is Named “Post Year‐End”  a. Gives you a permanent record of the company’s financial position at the end of  the year.      Fixed Assets  The fixed assets module should be closed prior to posting any transactions into the new fiscal  year.  It should be closed after the payables management module but before the general ledger  transactions are posted into the new year.  Fixed asset books can be closed separately,  however, all books must be closed prior to processing the fixed assets for the new year.  When  the close process is run Dynamics GP will update a few windows and fields.  In the Assets  General Window, the year‐to‐date maintenance amount is cleared and then quantity is copied 
  • 5.     5     trinsoft.comtrinsoft.com o the beginning quantity field.  Within the Asset Book Window, the year‐to‐date depreciation  amount is cleared, cost basis is copied to the beginning year cost field, life‐to‐date depreciation  is copied to beginning reserve field, and salvage value is copied to the beginning salvage field.   Finally, the current fiscal year is increased to the next year.  Listed below are the steps to  closing the Dynamics GP Fixed Assets module:  1. Perform all the Year‐End Closing Procedures for Payables Management in Dynamics GP  a. This guarantees that all outstanding fixed assets transactions are capitalized.  2. Enter all the Fixed Assets Transactions for the Current Fiscal Year  3. Depreciate all Assets Through the Last Day of the Current Fiscal Year  a. Dynamics GP, Tools, Routines, Fixed Assets, Depreciate  4. Perform the GL Posting (GL Interface) Process (Optional)  5. Run any Year‐End Reports that you want to keep as part of the Year‐End Financial  Records  a. Reports to consider:  Annual Activity  Additions Retirements Transfers  Depreciation Ledger Property Ledger Fixed Assets to GL Reconciliation  Book to Book Reconciliation Book to Book YTD Depreciation Comparison 6. Guarantee that the Fixed Assets Calendar is Built Correctly (Optional)  a. Dynamics GP, Tools, Utilities, Fixed Assets, Build Calendar  7. Verify that the Quarters are Setup Correctly for all the Fiscal Years  a. Dynamics GP, Tools, Utilities, Fixed Assets, Quarter  8. Create a Backup  a. Is a permanent record of the company’s financial position at the end of the year  9. Perform the Fixed Assets Year‐End Closing Routine  a. Dynamics GP, Tools, Routines, Fixed Assets, Year End      General Ledger  The general ledger closing should be performed only after all other modules have been closed.   When the GL is closed all Profit & Loss accounts are rolled into retained earnings and all Balance  Sheet accounts are rolled into the beginning balance for that account.  Inactive accounts with  no balance and no historical transactions are removed.  Finally, the year that was just closed is  marked as historical and the fiscal period tables are updated marking the year as historical.   Listed below are the steps to closing the Dynamics GP General Ledger module:  1. Complete the Posting Procedures & Closing Procedures for all Other Modules  2. Post the Final Adjusting Entries in General Ledger  a. Any correcting entries, journal entries for revenue or expense, etc.  3. Print an Account List to verify the Posting Type of Each Account  a. The posting type determines whether an account is closed to retained earnings  account or whether an account brings a balance forward to the next fiscal year.  4. Close the Last Period of the Fiscal Year (Optional)  a. This prevents transactions from being posted to the wrong period or year  5. Perform File Maintenance on the Finical Series Group of Modules (Optional) 
  • 6.     6     trinsoft.comtrinsoft.com a. Run the check links procedure on the Financial series group of modules  6. Verify the Settings in the General Ledger Setup Window  a. If desire to keep historical records, then the user must select the Accounts check  box and the Transactions check box in the Maintain History area of the GL setup  window.  7. Make a backup  8. Print a final Detailed Trial Balance Report  9. Print the Year‐End Financial Statements  a. Most common reports include:  Balance Sheet  Profit & Loss Statement  Statement of Cash Flow  Statement of Retained Earnings  10. Setup a New Fiscal year  a. Use the Fiscal Periods Setup window  11. Close the Fiscal Year  a. Dynamics GP, Tools, Routines, Financial, Year‐End Closing  b. Specify an account in the Retained Earnings Account box  c. Specify if journal entry numbers should be reset  d. Click Close Year to start the routine  12. Close all the Fiscal Periods for all the Series (Optional)  a. To prevent transactions from being posted into closed periods  13. Adjust the Budget Figures for the New year, and Then Print the Financial Statements  14. Make a backup  a. This backup gives the user a permanent record of the company’s financial  position at the start of the new year.      Finally, take a deep breath as the close is now complete!