SlideShare a Scribd company logo
1 of 2
Download to read offline
Project Overview
S
ince the oil industry replaced agriculture as the biggest user of diesel
in North Dakota, diesel fuel consumption in the state has risen by
51% to approximately 53,000 barrels per day, with about two-thirds
of the state’s diesel fuel imported.
In 2012, MDU Resources, a regional utility company, and Calumet Specialty
Products commissioned Ventech to develop a technical study for a new
refinery that would help the state of North Dakota meet its demand for diesel
using locally produced Bakken crudes while reducing its dependency on out-
of-state imports.
Based on its study recommendations, Ventech was awarded a contract in June
2013 to provide the refinery technology and primary equipment for the Dakota
Prairie Refinery, a 20,000 BPSD refinery and the first greenfield refinery to be
built in the U.S. since 1976.
DakotaPrairieRefining
20,000BPSDCrudeOilRefinery
Dickinson,NorthDakota
Client: MDU Resources Group, Inc. and Calumet Specialty Products Partners, L.P.
Scope: Lump Sum Engineering, Procurement, Fabrication and coordinating transport of modules to site
Status: Completed May, 2015
20,000
20,000 BPSD
capacity (exceeded
performance
expectations)
13 months to
fabricate and deliver
modules (22 months
to fabricate, deliver
and install)
13
42
42 modules
total
6
6 different
process units
designed and
fabricated
1976
The first
greenfield refinery
built in the U.S.
since 1976
Ventech Engineers
International LLC
713-477-0201
sales@ventech-eng.com
www.ventech-eng.com
As one of the leading designer/fabricators of modularized
processing facilities, Ventech brought a unique perspective
to the project. In addition to its experience in executing both
modular and stick-built facilities, the company is also in the
surplus equipment industry buying, selling, valuing and
moving complete refinery systems and surplus process
units.
This combination of knowledge enables Ventech to not only
design and engineer facilities that process a wide variety
of feedstocks to maximize high-value products, but to also
deliver the most efficient and cost-effective facility to meet
the client’s fast-track schedule and derive the greatest value
from the capital budget.
Proven Design, Custom Tailored Maximizing Value to the Last Drop
TherefineryVentechdesignedforCalumetandMDUResources
is based on its proven 20,000 BPSD design customized for the
client’s product specifications and the locally sourced Bakken
crude oil.
In addition to 7,000 BPSD of ultra-low-sulfur diesel fuel
destined for North Dakota-based customers, the production
slate includes 6,500 BPSD stabilized naphtha, 6,000 BPSD
atmospheric bottoms and approximately 300 BPSD of mixed
LPG’s trucked to a nearby natural gas processing facility
owned by WBI Energy, Inc., a subsidiary of MDU Resources.
Wastewater is pre-treated at the refinery site and then piped
to a municipal water treatment plant and sold to fracking
operations.
To meet the client’s “quicker to production” and budget
objectives, the refinery design uses a combination of stick-
built, modularized and refurbished units, including:
•	 20,000 BPSD Crude Distillation Unit – 11 modules 	
	 & 1 burner management skid (BMS)
•	 7,000 BPSD Naphtha Stabilizer Unit – 2 modules
•	 8,000 BPSD Mid-Distillates Hydrotreater – 11 		
	 modules & 2 BMS
•	 Sour Water Stripper Unit – 3 modules
•	 Refurbished Hydrogen Unit – 8 modules & 1 BMS
•	 Amine regeneration unit – 6 modules
•	 Sulfur recovery unit – 1 module
•	 All supporting utilities
The amine regeneration unit and the sulfur recovery unit
modules were designed and supplied by a third party.
An Integrated EPF Solution
Working from a lump-sum, fixed-price contract and
using an integrated schedule for project contractors and
subcontractors, Ventech began fabrication of the refinery’s
modules and skids at its Pasadena indoor fabrication
facility, located just 30 minutes from the Port of Houston.
To support the fast-track schedule, module fabrication
started early in the project and continued in parallel with
engineering. Key pieces of equipment and materials were
competitively sourced from vendors in the USA, Canada,
Mexico, Spain and Taiwan.
The unprecedented boom in the oil and gas industry and
the shortage of materials and manpower inevitably led to
schedule challenges that had to be managed on a daily
basis. Ventech’s procurement organization worked closely
with third-party vendors and transport companies to
expedite deliveries and develop workarounds.
Through close coordination with the owners and other
contractors, the Dakota Prairie Refinery was completed
safely in one of the fastest grassroots – refinery builds ever
(less than three years from technical studies to production).
Project Highlights
•	 Ventech’sscopeexecutedforafixedlump-sumprice,versusothercontractors’T&M/reimbursable
contracts.
•	 One of the fastest ever builds of a greenfield refinery.
•	 First greenfield refinery project in the United States since the 1970s.
•	 Combined design solution of modular (42 total modules + 4 burner management skids), stick
built and refurbished units to optimize build time and lower costs.
•	 Used proven Ventech 20,000 BPSD refinery design customized to feedstock and client product
specifications.
•	 Currently performing as designed, has acheived higher than nameplate design performance.

More Related Content

What's hot

MARS Meeting Summer 2015-North American Energy Revolution-Implications for Rail
MARS Meeting Summer 2015-North American Energy Revolution-Implications for RailMARS Meeting Summer 2015-North American Energy Revolution-Implications for Rail
MARS Meeting Summer 2015-North American Energy Revolution-Implications for RailPLG Consulting
 
Decree release india
Decree release indiaDecree release india
Decree release indiaIFFCO Canada
 
Plg robinson petrochemical engineering & contstruction 2015 final
Plg robinson   petrochemical engineering & contstruction 2015 finalPlg robinson   petrochemical engineering & contstruction 2015 final
Plg robinson petrochemical engineering & contstruction 2015 finalPLG Consulting
 
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, Kenya
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, KenyaB4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, Kenya
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, KenyaIceland Geothermal
 
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceTeekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceAltera Infrastructure
 
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceTeekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceTeekay LNG Partners L.P.
 
Novello GTL Intro Deck Feb 2016 for Social Media-print
Novello GTL Intro Deck Feb 2016 for Social Media-printNovello GTL Intro Deck Feb 2016 for Social Media-print
Novello GTL Intro Deck Feb 2016 for Social Media-printpicajachoo
 
PLG Consulting Appalachian logistics League May 5, 2015
PLG Consulting Appalachian logistics League May 5, 2015PLG Consulting Appalachian logistics League May 5, 2015
PLG Consulting Appalachian logistics League May 5, 2015PLG Consulting
 
Plg rail summit 2015 04-30
Plg rail summit 2015 04-30Plg rail summit 2015 04-30
Plg rail summit 2015 04-30PLG Consulting
 
Xebec Biogas 2010 Presentation
Xebec Biogas 2010 PresentationXebec Biogas 2010 Presentation
Xebec Biogas 2010 Presentationsorschak
 
All of these Mega Projects require vast amounts of Construction aggregate
All of these Mega Projects require vast amounts of Construction aggregateAll of these Mega Projects require vast amounts of Construction aggregate
All of these Mega Projects require vast amounts of Construction aggregateFollow me on Twitter @Stockshaman
 
Technology in BP - Factsheet
Technology in BP - FactsheetTechnology in BP - Factsheet
Technology in BP - Factsheetbp
 
Plg refc presentation 2015 v gb 16 9 aspect final 030115
Plg refc presentation 2015 v gb 16 9 aspect final 030115Plg refc presentation 2015 v gb 16 9 aspect final 030115
Plg refc presentation 2015 v gb 16 9 aspect final 030115PLG Consulting
 
Le 05 Liquefied Natural Gas (LNG) Business
Le 05 Liquefied Natural Gas (LNG) BusinessLe 05 Liquefied Natural Gas (LNG) Business
Le 05 Liquefied Natural Gas (LNG) BusinessNsulangi Paul
 
Le 02 natural gas exploration and production
Le 02 natural gas exploration and productionLe 02 natural gas exploration and production
Le 02 natural gas exploration and productionNsulangi Paul
 
Elamathi Panneerselvam CV
Elamathi Panneerselvam CVElamathi Panneerselvam CV
Elamathi Panneerselvam CVzetiengg
 

What's hot (20)

MARS Meeting Summer 2015-North American Energy Revolution-Implications for Rail
MARS Meeting Summer 2015-North American Energy Revolution-Implications for RailMARS Meeting Summer 2015-North American Energy Revolution-Implications for Rail
MARS Meeting Summer 2015-North American Energy Revolution-Implications for Rail
 
Decree release india
Decree release indiaDecree release india
Decree release india
 
Plg robinson petrochemical engineering & contstruction 2015 final
Plg robinson   petrochemical engineering & contstruction 2015 finalPlg robinson   petrochemical engineering & contstruction 2015 final
Plg robinson petrochemical engineering & contstruction 2015 final
 
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, Kenya
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, KenyaB4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, Kenya
B4 - Quantum Power - Menengai 35MW Geothermal Project Nakuru County, Kenya
 
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceTeekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
 
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream ConferenceTeekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
Teekay Group presents at the 2013 Citi One-on-One MLP / Midstream Conference
 
Novello GTL Intro Deck Feb 2016 for Social Media-print
Novello GTL Intro Deck Feb 2016 for Social Media-printNovello GTL Intro Deck Feb 2016 for Social Media-print
Novello GTL Intro Deck Feb 2016 for Social Media-print
 
Ranjith cv
Ranjith cvRanjith cv
Ranjith cv
 
Turnkey CNG Station Construction
Turnkey CNG Station ConstructionTurnkey CNG Station Construction
Turnkey CNG Station Construction
 
PLG Consulting Appalachian logistics League May 5, 2015
PLG Consulting Appalachian logistics League May 5, 2015PLG Consulting Appalachian logistics League May 5, 2015
PLG Consulting Appalachian logistics League May 5, 2015
 
Plg rail summit 2015 04-30
Plg rail summit 2015 04-30Plg rail summit 2015 04-30
Plg rail summit 2015 04-30
 
Xebec Biogas 2010 Presentation
Xebec Biogas 2010 PresentationXebec Biogas 2010 Presentation
Xebec Biogas 2010 Presentation
 
Gangopadhaya Shekhar CV
Gangopadhaya Shekhar CVGangopadhaya Shekhar CV
Gangopadhaya Shekhar CV
 
All of these Mega Projects require vast amounts of Construction aggregate
All of these Mega Projects require vast amounts of Construction aggregateAll of these Mega Projects require vast amounts of Construction aggregate
All of these Mega Projects require vast amounts of Construction aggregate
 
Technology in BP - Factsheet
Technology in BP - FactsheetTechnology in BP - Factsheet
Technology in BP - Factsheet
 
Plg refc presentation 2015 v gb 16 9 aspect final 030115
Plg refc presentation 2015 v gb 16 9 aspect final 030115Plg refc presentation 2015 v gb 16 9 aspect final 030115
Plg refc presentation 2015 v gb 16 9 aspect final 030115
 
Hbk.nr dec.1.16
Hbk.nr dec.1.16Hbk.nr dec.1.16
Hbk.nr dec.1.16
 
Le 05 Liquefied Natural Gas (LNG) Business
Le 05 Liquefied Natural Gas (LNG) BusinessLe 05 Liquefied Natural Gas (LNG) Business
Le 05 Liquefied Natural Gas (LNG) Business
 
Le 02 natural gas exploration and production
Le 02 natural gas exploration and productionLe 02 natural gas exploration and production
Le 02 natural gas exploration and production
 
Elamathi Panneerselvam CV
Elamathi Panneerselvam CVElamathi Panneerselvam CV
Elamathi Panneerselvam CV
 

Similar to DPR Project Profile FINAL

A1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdfA1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdfDaniel Donatelli
 
Curriculum vitae of qasir abbas
Curriculum vitae of qasir abbasCurriculum vitae of qasir abbas
Curriculum vitae of qasir abbasQASIR ABBAS
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09arosental
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016Mujahid Ali Akhtar
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering ResumeStephen Davidson
 
curriculum vitae- koshyvarghese dec2015
curriculum vitae- koshyvarghese dec2015curriculum vitae- koshyvarghese dec2015
curriculum vitae- koshyvarghese dec2015KOSHY VARGHESE KOSHY
 
Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand Dhawan
 
Mission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NCMission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NCMcKenney's Inc
 
DSEC Article on ACABIO - Biofuels Nov-Dec_2013
DSEC Article on ACABIO - Biofuels Nov-Dec_2013DSEC Article on ACABIO - Biofuels Nov-Dec_2013
DSEC Article on ACABIO - Biofuels Nov-Dec_2013Pierre Jacquy
 
Ahmed Khalil CV & Resume
Ahmed Khalil CV & ResumeAhmed Khalil CV & Resume
Ahmed Khalil CV & ResumeAhmed Khalil
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantabhishekthakur309
 
PV projects for sale in Mexico
PV projects for sale in MexicoPV projects for sale in Mexico
PV projects for sale in MexicoSabine Christiaens
 
LinkedIn Profile Sumit Deb Nath
LinkedIn Profile Sumit Deb NathLinkedIn Profile Sumit Deb Nath
LinkedIn Profile Sumit Deb NathSumit Debnath
 
Mineworx Corporate Presentation August 2021
Mineworx Corporate Presentation August 2021Mineworx Corporate Presentation August 2021
Mineworx Corporate Presentation August 2021The Howard Group Inc.
 

Similar to DPR Project Profile FINAL (20)

A1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdfA1 Company Profile Secure Supplies 1.pdf
A1 Company Profile Secure Supplies 1.pdf
 
Curriculum vitae of qasir abbas
Curriculum vitae of qasir abbasCurriculum vitae of qasir abbas
Curriculum vitae of qasir abbas
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
Corporate Profile
Corporate ProfileCorporate Profile
Corporate Profile
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering Resume
 
projects
projectsprojects
projects
 
curriculum vitae- koshyvarghese dec2015
curriculum vitae- koshyvarghese dec2015curriculum vitae- koshyvarghese dec2015
curriculum vitae- koshyvarghese dec2015
 
01_HVAC-R5_Tecni
01_HVAC-R5_Tecni01_HVAC-R5_Tecni
01_HVAC-R5_Tecni
 
Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)Anand CV (latest Nov 2016)
Anand CV (latest Nov 2016)
 
N c group presentation
N c group presentationN c group presentation
N c group presentation
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
FoGB assignment
FoGB assignmentFoGB assignment
FoGB assignment
 
Mission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NCMission Critical Data Center Retrofit Project - Catawaba County, NC
Mission Critical Data Center Retrofit Project - Catawaba County, NC
 
DSEC Article on ACABIO - Biofuels Nov-Dec_2013
DSEC Article on ACABIO - Biofuels Nov-Dec_2013DSEC Article on ACABIO - Biofuels Nov-Dec_2013
DSEC Article on ACABIO - Biofuels Nov-Dec_2013
 
Ahmed Khalil CV & Resume
Ahmed Khalil CV & ResumeAhmed Khalil CV & Resume
Ahmed Khalil CV & Resume
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
 
PV projects for sale in Mexico
PV projects for sale in MexicoPV projects for sale in Mexico
PV projects for sale in Mexico
 
LinkedIn Profile Sumit Deb Nath
LinkedIn Profile Sumit Deb NathLinkedIn Profile Sumit Deb Nath
LinkedIn Profile Sumit Deb Nath
 
Mineworx Corporate Presentation August 2021
Mineworx Corporate Presentation August 2021Mineworx Corporate Presentation August 2021
Mineworx Corporate Presentation August 2021
 

DPR Project Profile FINAL

  • 1. Project Overview S ince the oil industry replaced agriculture as the biggest user of diesel in North Dakota, diesel fuel consumption in the state has risen by 51% to approximately 53,000 barrels per day, with about two-thirds of the state’s diesel fuel imported. In 2012, MDU Resources, a regional utility company, and Calumet Specialty Products commissioned Ventech to develop a technical study for a new refinery that would help the state of North Dakota meet its demand for diesel using locally produced Bakken crudes while reducing its dependency on out- of-state imports. Based on its study recommendations, Ventech was awarded a contract in June 2013 to provide the refinery technology and primary equipment for the Dakota Prairie Refinery, a 20,000 BPSD refinery and the first greenfield refinery to be built in the U.S. since 1976. DakotaPrairieRefining 20,000BPSDCrudeOilRefinery Dickinson,NorthDakota Client: MDU Resources Group, Inc. and Calumet Specialty Products Partners, L.P. Scope: Lump Sum Engineering, Procurement, Fabrication and coordinating transport of modules to site Status: Completed May, 2015 20,000 20,000 BPSD capacity (exceeded performance expectations) 13 months to fabricate and deliver modules (22 months to fabricate, deliver and install) 13 42 42 modules total 6 6 different process units designed and fabricated 1976 The first greenfield refinery built in the U.S. since 1976 Ventech Engineers International LLC 713-477-0201 sales@ventech-eng.com www.ventech-eng.com
  • 2. As one of the leading designer/fabricators of modularized processing facilities, Ventech brought a unique perspective to the project. In addition to its experience in executing both modular and stick-built facilities, the company is also in the surplus equipment industry buying, selling, valuing and moving complete refinery systems and surplus process units. This combination of knowledge enables Ventech to not only design and engineer facilities that process a wide variety of feedstocks to maximize high-value products, but to also deliver the most efficient and cost-effective facility to meet the client’s fast-track schedule and derive the greatest value from the capital budget. Proven Design, Custom Tailored Maximizing Value to the Last Drop TherefineryVentechdesignedforCalumetandMDUResources is based on its proven 20,000 BPSD design customized for the client’s product specifications and the locally sourced Bakken crude oil. In addition to 7,000 BPSD of ultra-low-sulfur diesel fuel destined for North Dakota-based customers, the production slate includes 6,500 BPSD stabilized naphtha, 6,000 BPSD atmospheric bottoms and approximately 300 BPSD of mixed LPG’s trucked to a nearby natural gas processing facility owned by WBI Energy, Inc., a subsidiary of MDU Resources. Wastewater is pre-treated at the refinery site and then piped to a municipal water treatment plant and sold to fracking operations. To meet the client’s “quicker to production” and budget objectives, the refinery design uses a combination of stick- built, modularized and refurbished units, including: • 20,000 BPSD Crude Distillation Unit – 11 modules & 1 burner management skid (BMS) • 7,000 BPSD Naphtha Stabilizer Unit – 2 modules • 8,000 BPSD Mid-Distillates Hydrotreater – 11 modules & 2 BMS • Sour Water Stripper Unit – 3 modules • Refurbished Hydrogen Unit – 8 modules & 1 BMS • Amine regeneration unit – 6 modules • Sulfur recovery unit – 1 module • All supporting utilities The amine regeneration unit and the sulfur recovery unit modules were designed and supplied by a third party. An Integrated EPF Solution Working from a lump-sum, fixed-price contract and using an integrated schedule for project contractors and subcontractors, Ventech began fabrication of the refinery’s modules and skids at its Pasadena indoor fabrication facility, located just 30 minutes from the Port of Houston. To support the fast-track schedule, module fabrication started early in the project and continued in parallel with engineering. Key pieces of equipment and materials were competitively sourced from vendors in the USA, Canada, Mexico, Spain and Taiwan. The unprecedented boom in the oil and gas industry and the shortage of materials and manpower inevitably led to schedule challenges that had to be managed on a daily basis. Ventech’s procurement organization worked closely with third-party vendors and transport companies to expedite deliveries and develop workarounds. Through close coordination with the owners and other contractors, the Dakota Prairie Refinery was completed safely in one of the fastest grassroots – refinery builds ever (less than three years from technical studies to production). Project Highlights • Ventech’sscopeexecutedforafixedlump-sumprice,versusothercontractors’T&M/reimbursable contracts. • One of the fastest ever builds of a greenfield refinery. • First greenfield refinery project in the United States since the 1970s. • Combined design solution of modular (42 total modules + 4 burner management skids), stick built and refurbished units to optimize build time and lower costs. • Used proven Ventech 20,000 BPSD refinery design customized to feedstock and client product specifications. • Currently performing as designed, has acheived higher than nameplate design performance.