7. You are the project manager for a large technology company. You use agile planning and rolling wave methodology. You are overseeing the completion of the feasibility phase and nearing the start of the development phase. What is this transition period called? A. Transition Project B. Project Initiation Closure C. Phase Gates D. Project Closure.