2. INSTALLATION WORKPACK FOR A
WORKOVER SCENARIO
THIS TOPIC IS FOR YOU ENGINEERING BUFFS
DRILLING HIERARCHY LETS ENGINEERING KNOW THE
INTENT OF THE WORKOVER 12-24 WEEKS UPFRONT.
ENGINEERING WORKPACKS ARE PREPARED, MATERIAL
PROCURED AND ALL SET!
4 WEEKS GOING INTO THE WORKOVER, THE INTENT HAS
BEEN CHANGED BY DRILLING – BACK TO THE DRAWING
BOARD.
HIGH IMPACT ON COST, SCHEDULE, MATERIALS,
RESOURCES.
I DEVISED A LEGO-TYPE METHOD TO BE USED FOR THE
ENGINEERING WORKPACK IN MY RECENT WORKPLACE
THAT INCREASES THE ENGINEERING COST INITIALLY BUT
KNOCKS OUT IMPACT ON SCHEDULE AND RE-WORK - NO
MATTER WHAT CHANGES CAME FROM DRILLING