SlideShare a Scribd company logo
1 of 9
Download to read offline
1
New Construction Retainage Law –
M.G.L. c. 149, Section 29F
Anatoly M. Darov, PE
Burns & Levinson LLP
 Contracting tool used to reduce owner’s risk that
contractor will fail to perform contract obligations
 Retainage = $ amount earned - $ amount paid
 Historically been a flexible tool used by contracting
parties to structure in any number of ways (e.g. flat,
variable, early release, etc.)
 Section 29F imposes new obligations on the project
owner/developer
2
Construction Contract Retainage — The Basics
 Codified as MGL. c. 149, section 29F; effective 11/6/14
 Applies to:
• Private construction contracts of $3 million or more executed on or
after 11/6/14 (prime contracts)
• Residential projects of 1-4 units exempt regardless of cost
 Key provisions:
• Cap of 5 percent retainage on each progress payment
• New timing requirements for substantial completion, punchlists, and
release of retainage
• Statutory form of “notice of substantial completion”
• Limits withholding of retainage after substantial completion
• Limits withholding of retainage from parties not involved in claims
3
Summary of New Retainage Law
— Ch. 276 of the Acts of 2014
New Timing Requirements—Substantial Completion
 Substantial Completion: Date when owner may occupy or
utilize the work for its intended purpose
 14 Days after Substantial Completion: General contractor
submits Notice of Substantial Completion (new form)
 14 Days after Receipt of Notice: Owner must affirmatively
accept or reject or the Notice will be deemed a “final and
binding” acceptance
• A rejection of the Notice of Subst. Completion must state
the factual and contractual basis
 7 Days after Rejection of Notice: Contractor must commence
dispute resolution procedures under the contract
4
New Timing Requirements—Punchlists
 14 Days after acceptance of Notice of Substantial
Completion: Owner must provide punchlist to the contractor
 7 Days after receipt of Punchlist: Contractor must provide
punchlist to all subcontractors
5
New Timing Requirements—Release of Retainage
 60 days after Substantial Completion: Contractor or
subcontractors may apply for release of retainage
 30 days after receipt of Application for Retainage: Owner must
release retainage to contractor
• Contractor has additional 7 days to release retainage to subs
 What amounts can Owner continue to hold?
• For incomplete, incorrect, or missing deliverables: (i) an
agreed amount or (ii) up to 2.5% of the contract value;
• 150% of the cost of incomplete or defective work; and
• Reasonable value of claims, inclusive of atty fees if
permitted by contract
6
7
New Timing Requirements
Contractor
submits Notice of
Subst. Completion
Owner accepts or
rejects Notice of
Subst. Completion
Owner provides
punchlist to
Contractor
Contractor
provides punchlist
to subs
Owner must
release retainage
Contractor/Subcontractors may submit
applications for release of retainage
14 Days 14 Days 7 Days
Punchlist Completion
<25 Days
60 Days 30 Days
Substantial
Completion
achieved
Considerations for Contracting
 Retainage alternatives?
• Letters of credit/escrows
• Surety bonds and subcontract default insurance
 Focus on dispute resolution methods/timing requirements
• Dispute review boards/pre-selected neutrals
 Definition of substantial completion
• Intended use
 New law will make competitive environment for smaller
contractors more challenging
 Does the law apply if no retainage is withheld?
8
Questions?
The Design & Construction Industry Practice at Burns & Levinson LLP focuses on
representation of public, private, and institutional owners and developers requiring the broad
range of legal services necessary to deliver successful development programs. We advise client with
respect to all aspects of project delivery including government relations, permitting, procurement
of design and construction services, project finance, labor/employment, claims mitigation and
strategy, insurance, and dispute resolution.
9
Anatoly M. Darov, P.E.
Chairman, Design & Construction Practice
adarov@burnslev.com
Direct: 617.345.3820

More Related Content

What's hot

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Elan Sector-80, 9911123210,NH-8 Gurgaon
Elan Sector-80, 9911123210,NH-8 GurgaonElan Sector-80, 9911123210,NH-8 Gurgaon
Elan Sector-80, 9911123210,NH-8 Gurgaonrealagentck
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESShivam Sood
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contractsHafizul Mukhlis
 
Blake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake Morgan
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...César del Riego y Fuentes
 

What's hot (20)

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Site possession
Site possessionSite possession
Site possession
 
Elan Sector-80, 9911123210,NH-8 Gurgaon
Elan Sector-80, 9911123210,NH-8 GurgaonElan Sector-80, 9911123210,NH-8 Gurgaon
Elan Sector-80, 9911123210,NH-8 Gurgaon
 
Site Possession
Site PossessionSite Possession
Site Possession
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Eot
EotEot
Eot
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contracts
 
Blake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminarBlake lapthorn new Construction Act seminar
Blake lapthorn new Construction Act seminar
 
UK Construction Act Ammendments: Payment Procedures
UK Construction Act Ammendments: Payment ProceduresUK Construction Act Ammendments: Payment Procedures
UK Construction Act Ammendments: Payment Procedures
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
DUBAI-DIAC Request For Arbitration in Construction Contracts Disputes (Real C...
 

Similar to ACEC Retainage Anatoly Darov February 24, 2015

Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coveragedtownsend
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Industry Changes 060209 Notes Page
Industry Changes 060209 Notes PageIndustry Changes 060209 Notes Page
Industry Changes 060209 Notes Pagedshelor
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Developer's Concerns After Existence of Management Corporation in Malaysia
Developer's Concerns After Existence of Management Corporation in MalaysiaDeveloper's Concerns After Existence of Management Corporation in Malaysia
Developer's Concerns After Existence of Management Corporation in MalaysiaPark Chin Chua
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Tila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesTila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesKaufman & Canoles
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
Lien Law Update
Lien Law UpdateLien Law Update
Lien Law UpdateCallPM
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveSamantha Ip
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Joshua C. Quinter
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 

Similar to ACEC Retainage Anatoly Darov February 24, 2015 (20)

Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coverage
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Industry Changes 060209 Notes Page
Industry Changes 060209 Notes PageIndustry Changes 060209 Notes Page
Industry Changes 060209 Notes Page
 
2016 CRLTO
2016 CRLTO2016 CRLTO
2016 CRLTO
 
2016 Chicago RLTO Summary
2016 Chicago RLTO Summary2016 Chicago RLTO Summary
2016 Chicago RLTO Summary
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Developer's Concerns After Existence of Management Corporation in Malaysia
Developer's Concerns After Existence of Management Corporation in MalaysiaDeveloper's Concerns After Existence of Management Corporation in Malaysia
Developer's Concerns After Existence of Management Corporation in Malaysia
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Tila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decadesTila respa, one of the most expensive changes in decades
Tila respa, one of the most expensive changes in decades
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Lien Law Update
Lien Law UpdateLien Law Update
Lien Law Update
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian Perspective
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
Mechanic's Lien Claims How Recent Changes May Affect Your Right to Assert a M...
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 

ACEC Retainage Anatoly Darov February 24, 2015

  • 1. 1 New Construction Retainage Law – M.G.L. c. 149, Section 29F Anatoly M. Darov, PE Burns & Levinson LLP
  • 2.  Contracting tool used to reduce owner’s risk that contractor will fail to perform contract obligations  Retainage = $ amount earned - $ amount paid  Historically been a flexible tool used by contracting parties to structure in any number of ways (e.g. flat, variable, early release, etc.)  Section 29F imposes new obligations on the project owner/developer 2 Construction Contract Retainage — The Basics
  • 3.  Codified as MGL. c. 149, section 29F; effective 11/6/14  Applies to: • Private construction contracts of $3 million or more executed on or after 11/6/14 (prime contracts) • Residential projects of 1-4 units exempt regardless of cost  Key provisions: • Cap of 5 percent retainage on each progress payment • New timing requirements for substantial completion, punchlists, and release of retainage • Statutory form of “notice of substantial completion” • Limits withholding of retainage after substantial completion • Limits withholding of retainage from parties not involved in claims 3 Summary of New Retainage Law — Ch. 276 of the Acts of 2014
  • 4. New Timing Requirements—Substantial Completion  Substantial Completion: Date when owner may occupy or utilize the work for its intended purpose  14 Days after Substantial Completion: General contractor submits Notice of Substantial Completion (new form)  14 Days after Receipt of Notice: Owner must affirmatively accept or reject or the Notice will be deemed a “final and binding” acceptance • A rejection of the Notice of Subst. Completion must state the factual and contractual basis  7 Days after Rejection of Notice: Contractor must commence dispute resolution procedures under the contract 4
  • 5. New Timing Requirements—Punchlists  14 Days after acceptance of Notice of Substantial Completion: Owner must provide punchlist to the contractor  7 Days after receipt of Punchlist: Contractor must provide punchlist to all subcontractors 5
  • 6. New Timing Requirements—Release of Retainage  60 days after Substantial Completion: Contractor or subcontractors may apply for release of retainage  30 days after receipt of Application for Retainage: Owner must release retainage to contractor • Contractor has additional 7 days to release retainage to subs  What amounts can Owner continue to hold? • For incomplete, incorrect, or missing deliverables: (i) an agreed amount or (ii) up to 2.5% of the contract value; • 150% of the cost of incomplete or defective work; and • Reasonable value of claims, inclusive of atty fees if permitted by contract 6
  • 7. 7 New Timing Requirements Contractor submits Notice of Subst. Completion Owner accepts or rejects Notice of Subst. Completion Owner provides punchlist to Contractor Contractor provides punchlist to subs Owner must release retainage Contractor/Subcontractors may submit applications for release of retainage 14 Days 14 Days 7 Days Punchlist Completion <25 Days 60 Days 30 Days Substantial Completion achieved
  • 8. Considerations for Contracting  Retainage alternatives? • Letters of credit/escrows • Surety bonds and subcontract default insurance  Focus on dispute resolution methods/timing requirements • Dispute review boards/pre-selected neutrals  Definition of substantial completion • Intended use  New law will make competitive environment for smaller contractors more challenging  Does the law apply if no retainage is withheld? 8
  • 9. Questions? The Design & Construction Industry Practice at Burns & Levinson LLP focuses on representation of public, private, and institutional owners and developers requiring the broad range of legal services necessary to deliver successful development programs. We advise client with respect to all aspects of project delivery including government relations, permitting, procurement of design and construction services, project finance, labor/employment, claims mitigation and strategy, insurance, and dispute resolution. 9 Anatoly M. Darov, P.E. Chairman, Design & Construction Practice adarov@burnslev.com Direct: 617.345.3820