White Paper - Data center solutions
Category - EPC Projects
________________________________________________________________________________________
Data center downtime due to the malfunctioning of backup
power system… whom do you blame?
CONTEXT
Demand for data in India is soaring and hence the number of data centers are increasing manifolds.
The new hyperscale facilities are much more power hungry and designed with tier IV levels of
uptime assurance.
Unfortunately, the grid power in the country has not been keeping pace in terms of the capacity,
reliability and the quality of power supplied. As a result, more than 95% of data centers in India
are practically dependent on frequent use of the DG backup power system. But at times even this
backup fails? Whom do you blame? How to have backup power solutions for data center.
© copyright : Neptunus Power Plant
Services
CHALLENGE
There could be no room for downtime in the data center design. In the event of a grid power
outage, the emergency backup power of Diesel Gensets should start in less than 25 seconds to
avoid interruptions in operations. However, at times these gensets may just refuse to respond as
expected, causing the worst nightmare for the data center operating team. The standard design
practice of n+1 redundancy also can’t avoid this possibility.
SOLUTION
The delay in start-up or scaling-up is not due to the DG set itself, but is often a result of inadequate
‘fuel management system’. Unfortunately, this aspect may get ignored or underplayed during the
project design and execution where the focus remains on high-side and high cost elements like
the DG set itself.
This paper discusses the fuel management system in detail including its objectives, components,
design and value in avoiding costly downtime. It can also be retrofitted in an existing data center
facility.
Power supply architecture & utilities for data centers
Figure 1 below shows a power supply system schematic for a typical data center.
The primary source of power at the data center is typically the local power grid. In case of a grid
power interruption (which is not so uncommon in India), a provision of backup power source is
mandatory. This is fulfilled through a DG power plant set-up within the data center premises. This
also includes on-site storage and handling of fuel (diesel) with underground tanks and network of
pipelines connected to the DG room.
© copyright : Neptunus Power Plant
Services
In the event of grid outage, an automatic switching mechanism is provided to seamlessly switch the
connectivity from grid power to DG power. An intermediate emergency power backup is provided
with battery operated UPS system for IT load. But no direct backup is available for the CRAH and
chillers units in server room, hence the DG backup power needs to start and ramp-up at the earliest
so as to take over the entire load.
Need for fuel management system
The malfunctioning of DG sets by way of failure to start or to synchronize quickly can be traced to
an inadequately designed fuel management system. By nature, diesel deteriorates over time, and
the longer it is kept idle either in storage tank or inside the diesel generator, the rate of degradation
is faster. If such diesel is fed into the DG set, it will lead to sludge formation, clogging of filters and
several other problems.
In many markets including India, there is a trend towards the use of ‘clean fuel’ which has lesser
sulphur content, is sometimes blended with biodiesel and other additives to ensure clean burning
and less harmful emissions. While it’s a good move in general, it is also a cause of potential trouble
because, compared to earlier grade, this cleaner grade of diesel is prone to faster decomposition
and sedimentation when stored for a longer time in the tank.
Other factors that drive the need for the fuel management system are critical controls involved at
various stages of fuel handling, right from the intake at the tanker unloading bay to intermediate
movement between the storage tanks, supply through a network of pipelines, day tank and final
supply into the DG set. Leaving this handling operations to manual judgement can be prone to
errors. The automated measurement, and control of fuel quality & transfers help in enhancing
efficiency, reliability and cost optimization.
Can it be retrofitted into the existing data center?
For all new generation data centers with hyperscale capacities and tier IV reliability, use of full
fledged Fuel Management System is mandatory. But even for the older data centers, it is a worthy
upgrade to consider so as to stay competitive and avoid costly downtime in the future. Some of the
reasons why older data center should go for the upgraded fuel management system are listed
below;
1. For the data centers which have been in operation for some years now pollutants and
impurities would have got collected in the fuel tank and can be a cause of DG set failure in
future.
2. Older manually operated systems are prone to errors in terms of valve operations & safety
lapses. Also these will not detect the fuel leaks leading to fuel wastage and higher
operational costs
© copyright : Neptunus Power Plant
Services
3. Older systems only provided for one direct connection between fuel tank yard and DG set.
This has the single point failure risk, that can be avoided with the upgraded fuel management
system
4. Inadequate fuel management system can be a hindrance for the future capacity expansion
and getting uptime certification etc.
Design considerations of the fuel management system
Fuel management at the data center site involves management of:
● Quality:
Maintaining the right quality is crucial across the life cycle of diesel from the moment it
enters the storage tank till its consumed in the DG set.
● Capacity:
This largely depends upon factors like how long the DG backup power is required to run and
the overall space available.
● Other Factors:
There are also some regulatory guidelines (example CCoE, CPCB etc.) that govern the
design. Other key factors include; automation for monitoring the fuel levels, detection of
leak and theft, measurement of fuel consumption and providing real time insights of the
same
Points to ponder upon while designing the Fuel Management System
1. Ensuring availability of clean filtered fuel throughout the system, from storage tank to the day
tanks is one of the key objectives of the fuel management system. This is achieved by the
fuel polishing unit that helps filter out impurities like solid particles, water ingrace, sludge,
sedimentation etc. It not only clean the fuel at the intake/ entry point but also during
circulation of fuel across the tanks. The key benefits of using the Fuel Polishing System are
as follows;
• Reduction in DG maintenance expenses
• Less likelihood of failure of fuel injectors
• Lesser buildup of sludge (sediment, rust, water, etc...)
• Reduced noise and smoke during DG set operations
2. Sometimes, additional fine filtration system between day tank and engine is included in
the fuel management system to prevent injectors of DG set from choking
3. By design, the fuel management system provides for redundancy in fuel supply piping
network between the storage tank and day tank in the DG room. Two routes of piping
ensures that there is no single point of failure. Automation is incorporated to switch the
alternate route in case the primary one can’t be used.
4. Diesel is a costly fuel and any pilferage can be quite costly. The fuel management
system incorporates multiple check-points and metering to maintain an accurate
accounting of fuel consumption. This is also helpful in measuring the efficiency of DG sets
© copyright : Neptunus Power Plant
Services
if required.
5. By design the storage tank holds upto 48 hours of running stock of diesel. However,
anticipating situations where this storage may not suffice, the fuel management system
has provision for the rapid bunkering of the tanks in case of prolonged shutdowns.
6. From the safety viewpoint, the fuel management system incorporates technologies like
fusible link valves that help in quicker evacuation of the day tanks in case of fire in the DG
Power House. Fitment of spillage tank arrangement under the pipe trench inside DG room
will avoid the fire incidence.
7. Provision of a leak detection system across the fuel pipeline helps detect oil pilferage.
It can be connected to the central Building Management System (BMS) to raise alarms.
8. Finally, the fuel management system is also required to provide adequate security and
protection of the sensitive fuel storage and handling areas through fencing and secured
access control.
Key components of the fuel management system
FIGURE 2 : Fuel Management System Layout & Key Components
1) Tank Yard
a) Underground tanks preferred due to better safety
b) Tank capacity (std. 90kL - IS10978 std or usage requirement/ space constraint)
c) Tank size 13-14 m length x 3.15-3.45 m height
d) Tanks redundancy N+1
© copyright : Neptunus Power Plant
Services
e) Space considerations
i) Provide for turning radius of the oil tanker
ii) Provision of “dike wall” around each tank
f) Fire protection & fighting system
g) Proper earthing system to provide to the underground tanks
2) Fuel polishing unit
i) 1 running 1 standby : (n+n)
ii) Pump + filter assembly
3) Fuel transfer pump
i) n+n or n+1 redundancy
ii) Canopy with Electrical panel
b) Fuel input flow meter
c) Instrumentation + earthing needed for each tank in the DG room
d) Leak detection system - High resistance leak detection to give alarm
4) Related to the DG Room
a) Spillage/settling tank fitted in DG room
b) Fuel transfer pump - from storage tank to day tank
c) Max limit for the day tank is 990 L / DG set as per the CCoE norms
d) Automation - valves, instrumentation - connected to fuel automation system
e) Panels + PLC for control purpose
5) Fuel Fire safety system
a) Piping design
b) Tank isolation / Dike walls between two tanks
c) Fire hydrant system for tank yard
d) Fire alarm system and sprinkler system
e) Fire cortons between bays inside DG room
f) Explosion proof electrical equipment inside tank yard - Light. Switches
g) Minimise downtime
© copyright : Neptunus Power Plant
Services
CONCLUSION
Cost of a downtime is far more expensive in a data center than in any other industry. The DG
backup power system is prone to failure if it is not shielded with an adequate and automated fuel
management system. Sedimentation, impurities, decomposition as well as water ingrace are the
main factors causing degradation of diesel that can cause malfunctioning of diesel generators. This
was experienced in the USA. During the Hurricane’s Sandy and Katrina, there were numerous
instances of downtime reported by the data centers and other infrastructure due to failure of backup
power to kick-off when needed.
A robust and well designed Fuel Management System ensures that the DG backup power solution
will be able to operate with very high reliability, responsiveness and at a lower operating cost. This
not only applies to new projects, but can also be retrofitted into existing data center facilities.
Domain experts such as the Uptime Institute and The Society of Automotive Engineers (SAE) place
a high degree of importance on fuel cleaning and polishing to ensure reliable operation of the DG
set. From fuel capacity planning & automation perspective as well there are norms that guide
designing of an efficient, reliable and intelligent Fuel Management System.
Data center establishments spend millions of dollars in erecting the sophisticated backup power
infrastructure for ensuring power reliability and this investment can be justified by caring for the fuel
that goes inside by incorporating fuel management system.
© copyright : Neptunus Power Plant Services
Neptunus combines 23+ years of experience in engines and generators to design and deliver solutions that work. We serve customers from 25
countries in marine, oil & gas, industrial and data center segments. We offer reliable solutions in “advanced predictive maintenance” and “turnkey
project engineering”. We undertake a complete EPC package comprising of the backup power plant, associated fuel storage & management, HVAC,
MEP and the Fire Protection System.
Website: www.neptunus-power.com, Email: info@neptunus-power.com
About the authors
Author : Uday Purohit, Founder and Managing
Director Tel: +91 98200 75933; Email:
uday@neptunus-power.com
Co-author : Satish Kane, Sr. Manager - Project Management
Tel: +91 98894 77269; Email: satish.kane@neptunus-power.com

More Related Content

Similar to White Paper - Data center solutions

Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingSchneider Electric
 
Review on Boiler Control Automation for Sugar Industries
Review on Boiler Control Automation for Sugar IndustriesReview on Boiler Control Automation for Sugar Industries
Review on Boiler Control Automation for Sugar IndustriesIRJET Journal
 
Generator Maintenance Scheduling Of Power System Using Hybrid Technique
Generator Maintenance Scheduling Of Power System Using Hybrid TechniqueGenerator Maintenance Scheduling Of Power System Using Hybrid Technique
Generator Maintenance Scheduling Of Power System Using Hybrid TechniqueIRJET Journal
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Power System Operation
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Power System Operation
 
2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5Victor Sauers
 
Fuel Supply Management Solutions | Kuwait Petroleum International (Q8) Case...
Fuel Supply Management Solutions  |  Kuwait Petroleum International (Q8) Case...Fuel Supply Management Solutions  |  Kuwait Petroleum International (Q8) Case...
Fuel Supply Management Solutions | Kuwait Petroleum International (Q8) Case...Schneider Electric
 
Generator set design parameters
Generator set design parametersGenerator set design parameters
Generator set design parametersBruno De Wachter
 
Condition-based Maintenance for High-speed Fleet
Condition-based Maintenance for High-speed FleetCondition-based Maintenance for High-speed Fleet
Condition-based Maintenance for High-speed FleetGopalakrishna Palem
 
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESCOMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESKamran Hassan
 
Dual fuel System
Dual fuel SystemDual fuel System
Dual fuel SystemBhone Thant
 
Smart Manufacturing Suite for Power Industry
Smart Manufacturing Suite for Power IndustrySmart Manufacturing Suite for Power Industry
Smart Manufacturing Suite for Power IndustryA.T.E. Private Limited
 
Fleet Management of Lifecycle Costs
Fleet Management of Lifecycle Costs Fleet Management of Lifecycle Costs
Fleet Management of Lifecycle Costs Russell Hrdy
 
Understanding ROI for Network Change & Configuration Management
Understanding ROI for Network Change & Configuration ManagementUnderstanding ROI for Network Change & Configuration Management
Understanding ROI for Network Change & Configuration ManagementSolarWinds
 
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...IRJET Journal
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsOptima Control Solutions
 
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...cscpconf
 

Similar to White Paper - Data center solutions (20)

Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handling
 
Review on Boiler Control Automation for Sugar Industries
Review on Boiler Control Automation for Sugar IndustriesReview on Boiler Control Automation for Sugar Industries
Review on Boiler Control Automation for Sugar Industries
 
Generator Maintenance Scheduling Of Power System Using Hybrid Technique
Generator Maintenance Scheduling Of Power System Using Hybrid TechniqueGenerator Maintenance Scheduling Of Power System Using Hybrid Technique
Generator Maintenance Scheduling Of Power System Using Hybrid Technique
 
Power Generation: Coal-Fired
Power Generation: Coal-FiredPower Generation: Coal-Fired
Power Generation: Coal-Fired
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
 
2 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev52 PCCE White_Paper-Rev5
2 PCCE White_Paper-Rev5
 
Fuel Supply Management Solutions | Kuwait Petroleum International (Q8) Case...
Fuel Supply Management Solutions  |  Kuwait Petroleum International (Q8) Case...Fuel Supply Management Solutions  |  Kuwait Petroleum International (Q8) Case...
Fuel Supply Management Solutions | Kuwait Petroleum International (Q8) Case...
 
Generator set design parameters
Generator set design parametersGenerator set design parameters
Generator set design parameters
 
Condition-based Maintenance for High-speed Fleet
Condition-based Maintenance for High-speed FleetCondition-based Maintenance for High-speed Fleet
Condition-based Maintenance for High-speed Fleet
 
Eficiencia Data Center
Eficiencia Data CenterEficiencia Data Center
Eficiencia Data Center
 
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRESCOMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
COMMON PROBLEMS AND CHALLENGES IN DATA CENTRES
 
Dual fuel System
Dual fuel SystemDual fuel System
Dual fuel System
 
Smart Manufacturing Suite for Power Industry
Smart Manufacturing Suite for Power IndustrySmart Manufacturing Suite for Power Industry
Smart Manufacturing Suite for Power Industry
 
Solutions for LNG facilities
Solutions for LNG facilitiesSolutions for LNG facilities
Solutions for LNG facilities
 
Fleet Management of Lifecycle Costs
Fleet Management of Lifecycle Costs Fleet Management of Lifecycle Costs
Fleet Management of Lifecycle Costs
 
Understanding ROI for Network Change & Configuration Management
Understanding ROI for Network Change & Configuration ManagementUnderstanding ROI for Network Change & Configuration Management
Understanding ROI for Network Change & Configuration Management
 
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...
Conversion of an I.C. engine powertrain to Electric powertrain of an All- Ter...
 
Driving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System MigrationsDriving Forces and Key Benefits of Control System Migrations
Driving Forces and Key Benefits of Control System Migrations
 
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...
A SURVEY ON DYNAMIC ENERGY MANAGEMENT AT VIRTUALIZATION LEVEL IN CLOUD DATA C...
 

More from AkhilMurthy1

3 Management Lessons We Can Learn From COVID - VAMS Global .docx
3 Management Lessons We Can Learn From COVID - VAMS Global .docx3 Management Lessons We Can Learn From COVID - VAMS Global .docx
3 Management Lessons We Can Learn From COVID - VAMS Global .docxAkhilMurthy1
 
Chain lubrication
Chain lubrication Chain lubrication
Chain lubrication AkhilMurthy1
 
2020 07-metal industries- asset reliability used cases
 2020 07-metal industries- asset reliability used cases 2020 07-metal industries- asset reliability used cases
2020 07-metal industries- asset reliability used casesAkhilMurthy1
 
Atlanta Case study basicOps
Atlanta Case study basicOpsAtlanta Case study basicOps
Atlanta Case study basicOpsAkhilMurthy1
 
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?AkhilMurthy1
 
Advanced Predictive Diagnostic Tool for Engines and critical rotating equip...
Advanced Predictive Diagnostic Tool for Engines  and critical rotating  equip...Advanced Predictive Diagnostic Tool for Engines  and critical rotating  equip...
Advanced Predictive Diagnostic Tool for Engines and critical rotating equip...AkhilMurthy1
 
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...AkhilMurthy1
 

More from AkhilMurthy1 (7)

3 Management Lessons We Can Learn From COVID - VAMS Global .docx
3 Management Lessons We Can Learn From COVID - VAMS Global .docx3 Management Lessons We Can Learn From COVID - VAMS Global .docx
3 Management Lessons We Can Learn From COVID - VAMS Global .docx
 
Chain lubrication
Chain lubrication Chain lubrication
Chain lubrication
 
2020 07-metal industries- asset reliability used cases
 2020 07-metal industries- asset reliability used cases 2020 07-metal industries- asset reliability used cases
2020 07-metal industries- asset reliability used cases
 
Atlanta Case study basicOps
Atlanta Case study basicOpsAtlanta Case study basicOps
Atlanta Case study basicOps
 
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?
WHY IS TORSIONAL VIBRATION A BETTER TECHNOLOGY?
 
Advanced Predictive Diagnostic Tool for Engines and critical rotating equip...
Advanced Predictive Diagnostic Tool for Engines  and critical rotating  equip...Advanced Predictive Diagnostic Tool for Engines  and critical rotating  equip...
Advanced Predictive Diagnostic Tool for Engines and critical rotating equip...
 
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...
Preventing Equipment Failures with Real Time Oil Condition Monitoring - Neptu...
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

White Paper - Data center solutions

  • 1. © copyright : Neptunus Power Plant Services White Paper - Data center solutions Category - EPC Projects ________________________________________________________________________________________ Data center downtime due to the malfunctioning of backup power system… whom do you blame? CONTEXT Demand for data in India is soaring and hence the number of data centers are increasing manifolds. The new hyperscale facilities are much more power hungry and designed with tier IV levels of uptime assurance. Unfortunately, the grid power in the country has not been keeping pace in terms of the capacity, reliability and the quality of power supplied. As a result, more than 95% of data centers in India are practically dependent on frequent use of the DG backup power system. But at times even this backup fails? Whom do you blame? How to have backup power solutions for data center.
  • 2. © copyright : Neptunus Power Plant Services CHALLENGE There could be no room for downtime in the data center design. In the event of a grid power outage, the emergency backup power of Diesel Gensets should start in less than 25 seconds to avoid interruptions in operations. However, at times these gensets may just refuse to respond as expected, causing the worst nightmare for the data center operating team. The standard design practice of n+1 redundancy also can’t avoid this possibility. SOLUTION The delay in start-up or scaling-up is not due to the DG set itself, but is often a result of inadequate ‘fuel management system’. Unfortunately, this aspect may get ignored or underplayed during the project design and execution where the focus remains on high-side and high cost elements like the DG set itself. This paper discusses the fuel management system in detail including its objectives, components, design and value in avoiding costly downtime. It can also be retrofitted in an existing data center facility. Power supply architecture & utilities for data centers Figure 1 below shows a power supply system schematic for a typical data center. The primary source of power at the data center is typically the local power grid. In case of a grid power interruption (which is not so uncommon in India), a provision of backup power source is mandatory. This is fulfilled through a DG power plant set-up within the data center premises. This also includes on-site storage and handling of fuel (diesel) with underground tanks and network of pipelines connected to the DG room.
  • 3. © copyright : Neptunus Power Plant Services In the event of grid outage, an automatic switching mechanism is provided to seamlessly switch the connectivity from grid power to DG power. An intermediate emergency power backup is provided with battery operated UPS system for IT load. But no direct backup is available for the CRAH and chillers units in server room, hence the DG backup power needs to start and ramp-up at the earliest so as to take over the entire load. Need for fuel management system The malfunctioning of DG sets by way of failure to start or to synchronize quickly can be traced to an inadequately designed fuel management system. By nature, diesel deteriorates over time, and the longer it is kept idle either in storage tank or inside the diesel generator, the rate of degradation is faster. If such diesel is fed into the DG set, it will lead to sludge formation, clogging of filters and several other problems. In many markets including India, there is a trend towards the use of ‘clean fuel’ which has lesser sulphur content, is sometimes blended with biodiesel and other additives to ensure clean burning and less harmful emissions. While it’s a good move in general, it is also a cause of potential trouble because, compared to earlier grade, this cleaner grade of diesel is prone to faster decomposition and sedimentation when stored for a longer time in the tank. Other factors that drive the need for the fuel management system are critical controls involved at various stages of fuel handling, right from the intake at the tanker unloading bay to intermediate movement between the storage tanks, supply through a network of pipelines, day tank and final supply into the DG set. Leaving this handling operations to manual judgement can be prone to errors. The automated measurement, and control of fuel quality & transfers help in enhancing efficiency, reliability and cost optimization. Can it be retrofitted into the existing data center? For all new generation data centers with hyperscale capacities and tier IV reliability, use of full fledged Fuel Management System is mandatory. But even for the older data centers, it is a worthy upgrade to consider so as to stay competitive and avoid costly downtime in the future. Some of the reasons why older data center should go for the upgraded fuel management system are listed below; 1. For the data centers which have been in operation for some years now pollutants and impurities would have got collected in the fuel tank and can be a cause of DG set failure in future. 2. Older manually operated systems are prone to errors in terms of valve operations & safety lapses. Also these will not detect the fuel leaks leading to fuel wastage and higher operational costs
  • 4. © copyright : Neptunus Power Plant Services 3. Older systems only provided for one direct connection between fuel tank yard and DG set. This has the single point failure risk, that can be avoided with the upgraded fuel management system 4. Inadequate fuel management system can be a hindrance for the future capacity expansion and getting uptime certification etc. Design considerations of the fuel management system Fuel management at the data center site involves management of: ● Quality: Maintaining the right quality is crucial across the life cycle of diesel from the moment it enters the storage tank till its consumed in the DG set. ● Capacity: This largely depends upon factors like how long the DG backup power is required to run and the overall space available. ● Other Factors: There are also some regulatory guidelines (example CCoE, CPCB etc.) that govern the design. Other key factors include; automation for monitoring the fuel levels, detection of leak and theft, measurement of fuel consumption and providing real time insights of the same Points to ponder upon while designing the Fuel Management System 1. Ensuring availability of clean filtered fuel throughout the system, from storage tank to the day tanks is one of the key objectives of the fuel management system. This is achieved by the fuel polishing unit that helps filter out impurities like solid particles, water ingrace, sludge, sedimentation etc. It not only clean the fuel at the intake/ entry point but also during circulation of fuel across the tanks. The key benefits of using the Fuel Polishing System are as follows; • Reduction in DG maintenance expenses • Less likelihood of failure of fuel injectors • Lesser buildup of sludge (sediment, rust, water, etc...) • Reduced noise and smoke during DG set operations 2. Sometimes, additional fine filtration system between day tank and engine is included in the fuel management system to prevent injectors of DG set from choking 3. By design, the fuel management system provides for redundancy in fuel supply piping network between the storage tank and day tank in the DG room. Two routes of piping ensures that there is no single point of failure. Automation is incorporated to switch the alternate route in case the primary one can’t be used. 4. Diesel is a costly fuel and any pilferage can be quite costly. The fuel management system incorporates multiple check-points and metering to maintain an accurate accounting of fuel consumption. This is also helpful in measuring the efficiency of DG sets
  • 5. © copyright : Neptunus Power Plant Services if required. 5. By design the storage tank holds upto 48 hours of running stock of diesel. However, anticipating situations where this storage may not suffice, the fuel management system has provision for the rapid bunkering of the tanks in case of prolonged shutdowns. 6. From the safety viewpoint, the fuel management system incorporates technologies like fusible link valves that help in quicker evacuation of the day tanks in case of fire in the DG Power House. Fitment of spillage tank arrangement under the pipe trench inside DG room will avoid the fire incidence. 7. Provision of a leak detection system across the fuel pipeline helps detect oil pilferage. It can be connected to the central Building Management System (BMS) to raise alarms. 8. Finally, the fuel management system is also required to provide adequate security and protection of the sensitive fuel storage and handling areas through fencing and secured access control. Key components of the fuel management system FIGURE 2 : Fuel Management System Layout & Key Components 1) Tank Yard a) Underground tanks preferred due to better safety b) Tank capacity (std. 90kL - IS10978 std or usage requirement/ space constraint) c) Tank size 13-14 m length x 3.15-3.45 m height d) Tanks redundancy N+1
  • 6. © copyright : Neptunus Power Plant Services e) Space considerations i) Provide for turning radius of the oil tanker ii) Provision of “dike wall” around each tank f) Fire protection & fighting system g) Proper earthing system to provide to the underground tanks 2) Fuel polishing unit i) 1 running 1 standby : (n+n) ii) Pump + filter assembly 3) Fuel transfer pump i) n+n or n+1 redundancy ii) Canopy with Electrical panel b) Fuel input flow meter c) Instrumentation + earthing needed for each tank in the DG room d) Leak detection system - High resistance leak detection to give alarm 4) Related to the DG Room a) Spillage/settling tank fitted in DG room b) Fuel transfer pump - from storage tank to day tank c) Max limit for the day tank is 990 L / DG set as per the CCoE norms d) Automation - valves, instrumentation - connected to fuel automation system e) Panels + PLC for control purpose 5) Fuel Fire safety system a) Piping design b) Tank isolation / Dike walls between two tanks c) Fire hydrant system for tank yard d) Fire alarm system and sprinkler system e) Fire cortons between bays inside DG room f) Explosion proof electrical equipment inside tank yard - Light. Switches g) Minimise downtime
  • 7. © copyright : Neptunus Power Plant Services CONCLUSION Cost of a downtime is far more expensive in a data center than in any other industry. The DG backup power system is prone to failure if it is not shielded with an adequate and automated fuel management system. Sedimentation, impurities, decomposition as well as water ingrace are the main factors causing degradation of diesel that can cause malfunctioning of diesel generators. This was experienced in the USA. During the Hurricane’s Sandy and Katrina, there were numerous instances of downtime reported by the data centers and other infrastructure due to failure of backup power to kick-off when needed. A robust and well designed Fuel Management System ensures that the DG backup power solution will be able to operate with very high reliability, responsiveness and at a lower operating cost. This not only applies to new projects, but can also be retrofitted into existing data center facilities. Domain experts such as the Uptime Institute and The Society of Automotive Engineers (SAE) place a high degree of importance on fuel cleaning and polishing to ensure reliable operation of the DG set. From fuel capacity planning & automation perspective as well there are norms that guide designing of an efficient, reliable and intelligent Fuel Management System. Data center establishments spend millions of dollars in erecting the sophisticated backup power infrastructure for ensuring power reliability and this investment can be justified by caring for the fuel that goes inside by incorporating fuel management system. © copyright : Neptunus Power Plant Services Neptunus combines 23+ years of experience in engines and generators to design and deliver solutions that work. We serve customers from 25 countries in marine, oil & gas, industrial and data center segments. We offer reliable solutions in “advanced predictive maintenance” and “turnkey project engineering”. We undertake a complete EPC package comprising of the backup power plant, associated fuel storage & management, HVAC, MEP and the Fire Protection System. Website: www.neptunus-power.com, Email: info@neptunus-power.com About the authors Author : Uday Purohit, Founder and Managing Director Tel: +91 98200 75933; Email: uday@neptunus-power.com Co-author : Satish Kane, Sr. Manager - Project Management Tel: +91 98894 77269; Email: satish.kane@neptunus-power.com