2. DIFFERENT STEPS FOR
CONSTRUCTION OF TUNNEL
1) Erecting supports for sides & roof if
necessary .
2) Setting up the drilling .
3) Loading holes with explosive & firing
them .
4) Ventilation & removing the dust after
explosion .
3. DIFFERENT STEPS FOR
CONSTRUCTION OF TUNNEL
5) Loading & hauling muck .
6) Removing ground water if necessary .
7) Placing reinforcement .
8) placing concrete lining .
6. CONSTRUCTION OF TUNNEL IN HARD
ROCK / METHODS
1) Full face method
2) Heading & benching method
3) Drift method
4) Pilot tunnel method
5) Perimeter method