SlideShare a Scribd company logo
1 of 75
PILE FOUNDATION
By –
C.M.GUPTA
Sr.Prof/Br.2
IRICEN
1
TYPE OF FOUNDATIONS
• SHALLOW
– SINGLE FOOTING
– COMBINED FOOTING
– RAFT
– STRIP
• DEEP
– PILE
– WELL
2
DEEP FOUNDATIONS
• ADEQUATE GRIP- BELOW DEEPEST
ANTICIPATED SCOUR
• DEPTH OF FOUNDATION BELOW WATER LEVEL
FOR Qf –
• NOT LESS THAN 1.33 X MAX DEPTH OF SCOUR
• SHALL NOT REST ON SLOPING ROCK STRATA
• DYNAMIC AUGMENT NEED NOT BE
CONSIDERED
3
CLASSIFICATION OF PILES
• BROAD CALSSIFICATION
– DRIVEN (DISPLACEMENT PILES)
– BORED (REPLACEMENT PILE)
• ON THE BASIS OF MATERIAL
– TIMBER
– STEEL
– PCC
– RCC
– PSC
– COMPOSITE
4
CLASSIFICATION OF PILES
• Method of construction
– Driven precast piles
– Driven cast in situ piles
– Bored precast piles
– Bored cast in situ piles
• Mode of load transmission
– End bearing piles
– Friction piles
– Friction cum end bearing piles
5
CLASSIFICATION OF PILES
• Sectional area
– Circular
– Square
– Tubular
– Octagonal
– H-section
• Size
– Micro (mini) piles (<150 mm)
– Small diameter pile (>150 mm < 600 mm)
– Large diameter pile (>600 mm)
6
CLASSIFICATION OF PILES
• INCLINATION
– VERTICAL PILES
– RAKER (BATTER PILES)
7
8
9
END BEARING PILE
10
FRICTION PILES
11
DRIVEN PILING
12
BORED PILING
13
CONSTRUCTION OF PILE FOUNDATION
• Driven precast piles
• Driven cast in situ piles
• Bored cast in situ piles
14
Driven precast piles
15
Drop hammer
Single/ double acting hammer
Diesel hammer
Vibratory hammer
Driven cast in situ Piles
– Steel casing pipe
with shoe at
bottom driven to
reqd depth
– Casting after
placing
reinforcement cage
16
Bored cast in situ piles
– Guide casing of 3-4 m at top of bore hole
– Bailer – chiesel
– Bentonite slurry for stabilisation
– Flushing
– Concreting after placing rein. cage
– Tremie method of concreting
– Concrete grade m 20 or higher
– High slump concrete
17
INSTALLATION OF BORED CAST IN
SITU PILES
• BAILER AND CHISEL METHOD
• AUGUR BORING
• BORING USING OSCILLATORS
• VIBRATORY DRILLING RIGS
18
BAILER AND CHISEL METHOD
19
AUGAR
BORING
20
UNDER REAMING RIG
21
BORED CAST IN SITU PILES
• Stabilization of bore
–Drilling Mud Circulation
(Bentonite Slurry)
Bentonite is impure clay
consisting of Montmorillonite.
Na cation responsible for
support
22
MUD CIRCULATION
23
TREMIE CONCRETING
• concrete to be rich in cement (min 370 kg/ m3),
slump – 150 -180 mm
• casing- temp/permanent
• sliding plug/steel plate flushed ahead of first
charge – to prevent mixing of water
• hopper and tremie should be closed system
• dia of tremie pipe – 200mm for 20mm aggregare
• concreting to be uninterrupted
• top of concrete in pile – above cutoff level
• min embedment in pile cap – 50 mm
24
TREMIE CONCRETING
25
TREMIE CONCRETING
26
Method statements for casting of piles
27
Method statements for casting of piles
28
Method statements for casting of piles
29
Method statements for pile cap casting
30
Method statements for pile cap casting
31
Method statements for pile cap casting
32
SELECTION OF TYPE OF PILES
• Availability of space and head room
• Proximity to structures
• Reliability – driven precast better
• Limitation of length- driven piles – 25 - 30 m
33
SOCKETTING IN ROCK
• For the end bearing piles
– Sound relatively homogenous rock including
granite and gneiss -- 1 to 2D
– Moderately weathered closely formed
including schist & slate ---- 2 to 3D
– Soft rock --- 3 to 4D
34
SEQUENCING OF PILING
• Normally from centre to periphery or from one
side to other
• Possibility of harm to adjacent piles be
considered. More damage in compact soils
• Order of installation should avoid creating a
compacted block of ground
• In stiff clay or compacted sand layers – from
center to outward or from one edge to across the
group
• In very soft soils – from outside to inside
35
SPACING OF PILES
• Determined based on the
–Type of soil
–Empirical approach
• Practical aspects of installing a pile
• Nature of load transfer
• Possible reduction in bearing capacity of a
group of piles
36
SPACING OF PILES
• For end bearing piles
– Governed by competency of bearing strata
– Not less than 2.5 D
• For friction piles
– Sufficiently apart to avoid overlapping zones
– Not less than 3 D
• Closure spacing possible in loose sand or fillings
for driven piles only
• Max spacing 4 D
37
LOAD CARRYING CAPACITY OF PILE
• In context of foundation engineering
• Load that a pile can carry without undergoing
continuous settlement for insignificant load
increments – by virtue of its boundary
conditions
• Failure of surrounding soil occurs before
failure of pile material
38
FACTORS INFLUENCING PILE CAPACITY
• Surrounding soil
• Installation technique
• Spacing of piles
• Symmetry of the group
• Location of pile cap
• Shape of pile cap
• Location of pile in a group
• Drainage conditions in soil
39
LOAD CARRYING CAPACITY OF SINGLE
PILE
• Dynamic pile formula – by using the data
obtained during piling ( conservation of energy)
– Hiley’s Formula
• More reliable for non-cohesive soils
• Not reliable for cohesive soils
• Static formula – using soil test results
• Load test – after 4 weeks of casting of pile
• Resistance due to skin friction available only
below scour line
• Drag down force
40
Engineering news formula
41
Hileys formula
42
LOAD CARRYING CAPACITY
• Annex B-1 of IS:2911 Part 1, Sec.2:2010 - For Granular soil
•Similar formula for clayey soil is also given in Annex B-2
43
44
Bearing capacity factor Nγ
45
46
Bearing capacity factor Nq
47
48
49
50
FACTOR OF SAFETY
• THE MINIMUM FOS – 2.5 FOR STATIC
FORMULA
• MINIMUM FOS – 2 FOR LOAD TEST
51
BEARING CAPACITY OF A PILE GROUP
• MAY BE
– EQUAL TO THE BC OF SINGLE PILE X NO. OF PILES
– LESS THAN THE ABOVE
• FRICTION PILES, CAST OR DRIVEN INTO
PROGRESSIVELY STIFFER MATERIALS & END
BEARING PILES – EQUAL
• FRICTION PILES INSTALLED IN SOFT AND CLAYEY
SOILS – LESS
• DRIVEN PILES IN LOOSE SANDY SOILS – MORE
DUE TO EFFECT OF COMPACTION
52
BEARING CAPACITY OF A PILE GROUP
STRATA TYPE OF PILE BC PF PILE GROUP
1. DENSE SAND NOT
UNDERLAIN BY WEAK
DEPOSITS
DRIVEN NO. OF PILES X SPC
2. LOOSE SANDY SOILS ½ (NO. OF PILES X SPC)
3. SAND NOT
UNDERLAIN BY WEAK
DEPOSITS
BORED ⅔ (NO. OF PILES X SPC)
SPC – SINGLE PILE CAPACITY
FOR PILES DRIVEN INTO SOFT OR MEDIUM CLAYS WITH 3
TO 4 D SPACING – ULTIMATE GROUP CAPACITY = ⅔ OF
THE SUM OF SINGLE PILE CAPACITY
53
PERMISIBLE TOLERANCE FOR PILES
• ALIGNMENT CONTROL
– VERTICAL PILES – DEVIATION OF 1.5%
– RAKER PILES – DEVIATION OF 4%
• SHIFT
– FOR PILES LESS THAN OR EQUAL TO 600 MM DIA
• NOT MORE THAN 75 MM OR D/4 WHICHEVER IS LESS
– FOR MORE THAN 600 MM. DIA. PILES
• 75 MM OR D/10 WHICHEVER IS MORE
• EXCESS DEVIATION BEYOND DESIGN LIMITS –PILE TO
BE REPLACED OR SUPPLEMENTED BY ADDITIONAL
PILES
54
OVERLOADING OF PILES
• 10% OF THE PILE CAPACITY MAY BE ALLOWED
ON EACH PILE
• MAX OVERLOADING ON A GROUP SHALL BE
RESTRICTED TO 40% OF THE ALLOWABLE
LOAD ON A SINGLE PILE
• SHALL NOT BE ALLOWED AT INITIAL DESIGN
STAGE
55
LOAD TEST
• STRESS TEST
– MAINTAINED LOAD TEST
– CONSTANT RATE OF PENETRATION TEST
– LATERAL LOAD TEST
– DYNAMIC LOAD TEST
– CYCLIC LOAD TEST
• STRAIN TEST
– LOW STRAIN INTEGRITY TEST
– HIGH STRAIN INTEGRITY TEST
56
PILE LOAD TESTING
(IS-2911 PART-IV)
• Initial Test
• Purpose
1. Determination of ultimate load capacity and
arrival at safe load by application of factor of
safety,
2. To provide guidelines for setting up the limits of
acceptance for routine tests,
3. To get an idea of suitability of piling system, and
4. To have a check on calculated load by dynamic
or static approaches.
57
PILE LOAD TESTING
(IS-2911 PART-IV)
• The number of initial tests may be selected as given below
depending upon the nature of sub-strata, number of piles and past
experience at the site.
• For small size projects (for piles less than 1 000 numbers), a
minimum of two tests.
• For large size projects (for piles more than 1 000 numbers), a
minimum of two tests for first 1 000 piles and additional one test
for every additional 1 000 piles and part thereof.
• The frequency of testing stipulated above is applicable for each
diameter of pile and rated capacity of pile in each type (mode) of
loading.
• The number of tests may be increased/decreased depending upon
whether the strata is erratic/uniform, subjected to a minimum of
two tests.
58
PILE LOAD TESTING
(IS-2911 PART-IV)
• Routine Test
– On ½ percent of piles, can be increased to
2% depending on strata
• Purpose
1. Checking the safe load as determined from static
analysis
2. Detection of any unusual performance contrary
to the findings of the initial test, if already done;
and
3. Workmanship.
59
PILE LOAD TESTING
(IS-2911 PART-IV)
• Routine Test
•The piles to be tested for routine tests may preferably be selected on
the basis of the following:
a. Abnormal variation in concrete consumption.
b. Sudden drop in concrete level during construction of piles.
c. Problems encountered during boring and tremie operation.
d. Significant variation in depth of pile with respect to other
adjoining piles and boring record.
e. Anomalies observed during the driving operation in case of driven
piles.
f. Piles under sensitive locations of structures.
g. Any doubt arising from non destructive test results.
60
PILE LOAD TESTING
(IS-2911 PART-IV)
• VERTICAL LOAD TEST
–Maintained load method
–Cyclic load test (To separate skin friction and end bearing)
–CRP test (Uniform penetration)
• LATERAL LOAD TEST
• PULL OUT TEST
61
LOAD TEST-INITIAL TEST
• The safe load on a single pile will be least of the
following
For piles dia upto 600 mm
– Two third of the final load at which total displacement
attains a value of 12 mm
– 50 % of the final load at which the total displacement
equals 10 % of the dia. of pile and 7.5% of bulb dia in
case of under reamed piles
For piles dia more than 600 mm
– Two third of the final load at which total displacement
attains a value of 18 mm or 2% of dia whoever is less
– 50 % of the final load at which the total displacement
equals 10 % of the dia. of pile and 7.5% of bulb dia in
case of under reamed piles
62
LOAD TEST - INITIAL
• THE SAFE LOAD FOR GROUP OF PILES
– FINAL LOAD AT WHICH TOTAL
DISPLACEMENT IS 25 MM
– TWO THIRD OF FINAL LOAD AT WHICH
DISPLACEMENT IS 40 MM
63
LOAD SETTLEMENT CURVE
SAFE LOAD
Least of 2/3
P1 or ½ P2
FOR GROUP
Least of Load
corrp. to 25 mm
sett or 2/3
corrp. to 40 mm
sett.
LOAD IN
INCREMENTS
OF 20%
Final load
maintained for
24h
64
LOAD TEST – ROUTINE TEST
• Test load will be atleast 1.5 times the
working load
• Max. settlement should not > 12 mm
for piles dia upto 600 mm
• 18 mm or 2 percent of pile diameter whichever
is less for piles of diameter more than 600 mm.
• for group of piles max. Settlement
should not > 25 mm
65
STATIC LOAD TEST
66
PILE LOAD TEST
(KENTELEDGE ARRANGEMENT)
67
PILE LOAD TEST
(WITH ANCHOR PILES)
68
DYNAMIC PILE TESTING
• SUPPLEMENTS STATIC TESTING
• HIGH STRAIN TESTING
– PROVIDES DATA ON FORCE & ACCELERATION OF PILE
– EVALUATION OF BEARING CAPACITY
– FACILITATE IMMEDIATE DECISION ABOUT ACCEPTANCE
OR REJECTION OF PILE
• LOW STRAIN TESTING
– FOR TESTING CONTINUITY OF PILE
– INFORMATION ABOUT DIMENSIONS AND
CONSISTANCY OF MATERIAL
ASTM D 4945
69
DYNAMIC PILE TESTING as per ASTM D 4945
70
DYNAMIC PILE TESTING
71
DEFECTS IN CAST IN SITU PILES
• HONEY COMBING DUE TO INADEQUATE
VIBRATIONS
• SEGREGATION DUE TO IMPROPER CONCRETE
PLACEMENT METHODS
• WASHOUT OF CEMENT DUE TO GROUNDWATER
FLOW
• CRACKS IN PILE SHAFT DUE TO SHRINKAGE
• INCLUSION OF FOREIGN MATERIAL
• NECKING DUE TO COLLAPSE OF SIDE WALLS
DURING WITHDRAWAL OF TEMPORARY CASING
72
NECKING IN PILE
73
NECKING IN PILE
74
75

More Related Content

Similar to Pile Foundation Design and Construction

CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...Dan Brown and Associates, PC
 
BM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.pptBM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.pptDinesh566323
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology GAURAV. H .TANDON
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionShyam Anandjiwala
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHApoorv Dhawan
 
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSCPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSSuyash Awasthi
 
Pile &amp; pier_foundation_analysis_&amp;_design
Pile &amp; pier_foundation_analysis_&amp;_designPile &amp; pier_foundation_analysis_&amp;_design
Pile &amp; pier_foundation_analysis_&amp;_designMohamad Binesh
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdfPradeepPokhrel5
 
Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored pilesSahl Buhary
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxcharantinku6799
 
Building Materials & Construction Module-2
Building Materials & Construction Module-2Building Materials & Construction Module-2
Building Materials & Construction Module-2Abhilash B L
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)S M Rahat Rahman
 
Test on fresh concrete and harden concrete
Test on fresh concrete and harden concreteTest on fresh concrete and harden concrete
Test on fresh concrete and harden concreteMOHAMMED JIRUWALA
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresProSIM R & D Pvt. Ltd.
 

Similar to Pile Foundation Design and Construction (20)

CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...CFA and DD Piles in Earthquake Country  - DM Holloway - SEAOSC Seminar - Long...
CFA and DD Piles in Earthquake Country - DM Holloway - SEAOSC Seminar - Long...
 
SIP- final - LinkedIn
SIP- final - LinkedInSIP- final - LinkedIn
SIP- final - LinkedIn
 
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
TCD2011 - Kunne bedre kompetanse avverget Macondo-ulykken i Mexico-gulfen? v/...
 
BM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.pptBM-Maintenance-Damia Cement.ppt
BM-Maintenance-Damia Cement.ppt
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSCPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
 
Pile &amp; pier_foundation_analysis_&amp;_design
Pile &amp; pier_foundation_analysis_&amp;_designPile &amp; pier_foundation_analysis_&amp;_design
Pile &amp; pier_foundation_analysis_&amp;_design
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 
Study of design and construction methods of bored piles
Study of design and construction methods of bored pilesStudy of design and construction methods of bored piles
Study of design and construction methods of bored piles
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptx
 
LSM
LSMLSM
LSM
 
Building Materials & Construction Module-2
Building Materials & Construction Module-2Building Materials & Construction Module-2
Building Materials & Construction Module-2
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)
 
Test on fresh concrete and harden concrete
Test on fresh concrete and harden concreteTest on fresh concrete and harden concrete
Test on fresh concrete and harden concrete
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
GeoVancouver Presentation
GeoVancouver PresentationGeoVancouver Presentation
GeoVancouver Presentation
 
Design flexible and rigid pavements
Design flexible and rigid pavementsDesign flexible and rigid pavements
Design flexible and rigid pavements
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
 

More from Naresh Prasad Keshari

More from Naresh Prasad Keshari (8)

21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx21204 - Track Management System (TMS).pptx
21204 - Track Management System (TMS).pptx
 
6. CMG_Durability _ concrete.pptx
6. CMG_Durability _ concrete.pptx6. CMG_Durability _ concrete.pptx
6. CMG_Durability _ concrete.pptx
 
5. Certification of speed on bridges April 20.pptx
5. Certification of speed on bridges April 20.pptx5. Certification of speed on bridges April 20.pptx
5. Certification of speed on bridges April 20.pptx
 
Masonry Arch Bridges_May_2021.pptx
Masonry Arch Bridges_May_2021.pptxMasonry Arch Bridges_May_2021.pptx
Masonry Arch Bridges_May_2021.pptx
 
webinar on speed raising to 130or 160 kmph.pptx
webinar on speed raising to 130or 160 kmph.pptxwebinar on speed raising to 130or 160 kmph.pptx
webinar on speed raising to 130or 160 kmph.pptx
 
PSC Design and construction.ppt
PSC Design and construction.pptPSC Design and construction.ppt
PSC Design and construction.ppt
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
 
Uhm cee-03-03
Uhm cee-03-03Uhm cee-03-03
Uhm cee-03-03
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 

Pile Foundation Design and Construction

  • 2. TYPE OF FOUNDATIONS • SHALLOW – SINGLE FOOTING – COMBINED FOOTING – RAFT – STRIP • DEEP – PILE – WELL 2
  • 3. DEEP FOUNDATIONS • ADEQUATE GRIP- BELOW DEEPEST ANTICIPATED SCOUR • DEPTH OF FOUNDATION BELOW WATER LEVEL FOR Qf – • NOT LESS THAN 1.33 X MAX DEPTH OF SCOUR • SHALL NOT REST ON SLOPING ROCK STRATA • DYNAMIC AUGMENT NEED NOT BE CONSIDERED 3
  • 4. CLASSIFICATION OF PILES • BROAD CALSSIFICATION – DRIVEN (DISPLACEMENT PILES) – BORED (REPLACEMENT PILE) • ON THE BASIS OF MATERIAL – TIMBER – STEEL – PCC – RCC – PSC – COMPOSITE 4
  • 5. CLASSIFICATION OF PILES • Method of construction – Driven precast piles – Driven cast in situ piles – Bored precast piles – Bored cast in situ piles • Mode of load transmission – End bearing piles – Friction piles – Friction cum end bearing piles 5
  • 6. CLASSIFICATION OF PILES • Sectional area – Circular – Square – Tubular – Octagonal – H-section • Size – Micro (mini) piles (<150 mm) – Small diameter pile (>150 mm < 600 mm) – Large diameter pile (>600 mm) 6
  • 7. CLASSIFICATION OF PILES • INCLINATION – VERTICAL PILES – RAKER (BATTER PILES) 7
  • 8. 8
  • 9. 9
  • 14. CONSTRUCTION OF PILE FOUNDATION • Driven precast piles • Driven cast in situ piles • Bored cast in situ piles 14
  • 15. Driven precast piles 15 Drop hammer Single/ double acting hammer Diesel hammer Vibratory hammer
  • 16. Driven cast in situ Piles – Steel casing pipe with shoe at bottom driven to reqd depth – Casting after placing reinforcement cage 16
  • 17. Bored cast in situ piles – Guide casing of 3-4 m at top of bore hole – Bailer – chiesel – Bentonite slurry for stabilisation – Flushing – Concreting after placing rein. cage – Tremie method of concreting – Concrete grade m 20 or higher – High slump concrete 17
  • 18. INSTALLATION OF BORED CAST IN SITU PILES • BAILER AND CHISEL METHOD • AUGUR BORING • BORING USING OSCILLATORS • VIBRATORY DRILLING RIGS 18
  • 19. BAILER AND CHISEL METHOD 19
  • 22. BORED CAST IN SITU PILES • Stabilization of bore –Drilling Mud Circulation (Bentonite Slurry) Bentonite is impure clay consisting of Montmorillonite. Na cation responsible for support 22
  • 24. TREMIE CONCRETING • concrete to be rich in cement (min 370 kg/ m3), slump – 150 -180 mm • casing- temp/permanent • sliding plug/steel plate flushed ahead of first charge – to prevent mixing of water • hopper and tremie should be closed system • dia of tremie pipe – 200mm for 20mm aggregare • concreting to be uninterrupted • top of concrete in pile – above cutoff level • min embedment in pile cap – 50 mm 24
  • 27. Method statements for casting of piles 27
  • 28. Method statements for casting of piles 28
  • 29. Method statements for casting of piles 29
  • 30. Method statements for pile cap casting 30
  • 31. Method statements for pile cap casting 31
  • 32. Method statements for pile cap casting 32
  • 33. SELECTION OF TYPE OF PILES • Availability of space and head room • Proximity to structures • Reliability – driven precast better • Limitation of length- driven piles – 25 - 30 m 33
  • 34. SOCKETTING IN ROCK • For the end bearing piles – Sound relatively homogenous rock including granite and gneiss -- 1 to 2D – Moderately weathered closely formed including schist & slate ---- 2 to 3D – Soft rock --- 3 to 4D 34
  • 35. SEQUENCING OF PILING • Normally from centre to periphery or from one side to other • Possibility of harm to adjacent piles be considered. More damage in compact soils • Order of installation should avoid creating a compacted block of ground • In stiff clay or compacted sand layers – from center to outward or from one edge to across the group • In very soft soils – from outside to inside 35
  • 36. SPACING OF PILES • Determined based on the –Type of soil –Empirical approach • Practical aspects of installing a pile • Nature of load transfer • Possible reduction in bearing capacity of a group of piles 36
  • 37. SPACING OF PILES • For end bearing piles – Governed by competency of bearing strata – Not less than 2.5 D • For friction piles – Sufficiently apart to avoid overlapping zones – Not less than 3 D • Closure spacing possible in loose sand or fillings for driven piles only • Max spacing 4 D 37
  • 38. LOAD CARRYING CAPACITY OF PILE • In context of foundation engineering • Load that a pile can carry without undergoing continuous settlement for insignificant load increments – by virtue of its boundary conditions • Failure of surrounding soil occurs before failure of pile material 38
  • 39. FACTORS INFLUENCING PILE CAPACITY • Surrounding soil • Installation technique • Spacing of piles • Symmetry of the group • Location of pile cap • Shape of pile cap • Location of pile in a group • Drainage conditions in soil 39
  • 40. LOAD CARRYING CAPACITY OF SINGLE PILE • Dynamic pile formula – by using the data obtained during piling ( conservation of energy) – Hiley’s Formula • More reliable for non-cohesive soils • Not reliable for cohesive soils • Static formula – using soil test results • Load test – after 4 weeks of casting of pile • Resistance due to skin friction available only below scour line • Drag down force 40
  • 43. LOAD CARRYING CAPACITY • Annex B-1 of IS:2911 Part 1, Sec.2:2010 - For Granular soil •Similar formula for clayey soil is also given in Annex B-2 43
  • 44. 44
  • 47. 47
  • 48. 48
  • 49. 49
  • 50. 50
  • 51. FACTOR OF SAFETY • THE MINIMUM FOS – 2.5 FOR STATIC FORMULA • MINIMUM FOS – 2 FOR LOAD TEST 51
  • 52. BEARING CAPACITY OF A PILE GROUP • MAY BE – EQUAL TO THE BC OF SINGLE PILE X NO. OF PILES – LESS THAN THE ABOVE • FRICTION PILES, CAST OR DRIVEN INTO PROGRESSIVELY STIFFER MATERIALS & END BEARING PILES – EQUAL • FRICTION PILES INSTALLED IN SOFT AND CLAYEY SOILS – LESS • DRIVEN PILES IN LOOSE SANDY SOILS – MORE DUE TO EFFECT OF COMPACTION 52
  • 53. BEARING CAPACITY OF A PILE GROUP STRATA TYPE OF PILE BC PF PILE GROUP 1. DENSE SAND NOT UNDERLAIN BY WEAK DEPOSITS DRIVEN NO. OF PILES X SPC 2. LOOSE SANDY SOILS ½ (NO. OF PILES X SPC) 3. SAND NOT UNDERLAIN BY WEAK DEPOSITS BORED ⅔ (NO. OF PILES X SPC) SPC – SINGLE PILE CAPACITY FOR PILES DRIVEN INTO SOFT OR MEDIUM CLAYS WITH 3 TO 4 D SPACING – ULTIMATE GROUP CAPACITY = ⅔ OF THE SUM OF SINGLE PILE CAPACITY 53
  • 54. PERMISIBLE TOLERANCE FOR PILES • ALIGNMENT CONTROL – VERTICAL PILES – DEVIATION OF 1.5% – RAKER PILES – DEVIATION OF 4% • SHIFT – FOR PILES LESS THAN OR EQUAL TO 600 MM DIA • NOT MORE THAN 75 MM OR D/4 WHICHEVER IS LESS – FOR MORE THAN 600 MM. DIA. PILES • 75 MM OR D/10 WHICHEVER IS MORE • EXCESS DEVIATION BEYOND DESIGN LIMITS –PILE TO BE REPLACED OR SUPPLEMENTED BY ADDITIONAL PILES 54
  • 55. OVERLOADING OF PILES • 10% OF THE PILE CAPACITY MAY BE ALLOWED ON EACH PILE • MAX OVERLOADING ON A GROUP SHALL BE RESTRICTED TO 40% OF THE ALLOWABLE LOAD ON A SINGLE PILE • SHALL NOT BE ALLOWED AT INITIAL DESIGN STAGE 55
  • 56. LOAD TEST • STRESS TEST – MAINTAINED LOAD TEST – CONSTANT RATE OF PENETRATION TEST – LATERAL LOAD TEST – DYNAMIC LOAD TEST – CYCLIC LOAD TEST • STRAIN TEST – LOW STRAIN INTEGRITY TEST – HIGH STRAIN INTEGRITY TEST 56
  • 57. PILE LOAD TESTING (IS-2911 PART-IV) • Initial Test • Purpose 1. Determination of ultimate load capacity and arrival at safe load by application of factor of safety, 2. To provide guidelines for setting up the limits of acceptance for routine tests, 3. To get an idea of suitability of piling system, and 4. To have a check on calculated load by dynamic or static approaches. 57
  • 58. PILE LOAD TESTING (IS-2911 PART-IV) • The number of initial tests may be selected as given below depending upon the nature of sub-strata, number of piles and past experience at the site. • For small size projects (for piles less than 1 000 numbers), a minimum of two tests. • For large size projects (for piles more than 1 000 numbers), a minimum of two tests for first 1 000 piles and additional one test for every additional 1 000 piles and part thereof. • The frequency of testing stipulated above is applicable for each diameter of pile and rated capacity of pile in each type (mode) of loading. • The number of tests may be increased/decreased depending upon whether the strata is erratic/uniform, subjected to a minimum of two tests. 58
  • 59. PILE LOAD TESTING (IS-2911 PART-IV) • Routine Test – On ½ percent of piles, can be increased to 2% depending on strata • Purpose 1. Checking the safe load as determined from static analysis 2. Detection of any unusual performance contrary to the findings of the initial test, if already done; and 3. Workmanship. 59
  • 60. PILE LOAD TESTING (IS-2911 PART-IV) • Routine Test •The piles to be tested for routine tests may preferably be selected on the basis of the following: a. Abnormal variation in concrete consumption. b. Sudden drop in concrete level during construction of piles. c. Problems encountered during boring and tremie operation. d. Significant variation in depth of pile with respect to other adjoining piles and boring record. e. Anomalies observed during the driving operation in case of driven piles. f. Piles under sensitive locations of structures. g. Any doubt arising from non destructive test results. 60
  • 61. PILE LOAD TESTING (IS-2911 PART-IV) • VERTICAL LOAD TEST –Maintained load method –Cyclic load test (To separate skin friction and end bearing) –CRP test (Uniform penetration) • LATERAL LOAD TEST • PULL OUT TEST 61
  • 62. LOAD TEST-INITIAL TEST • The safe load on a single pile will be least of the following For piles dia upto 600 mm – Two third of the final load at which total displacement attains a value of 12 mm – 50 % of the final load at which the total displacement equals 10 % of the dia. of pile and 7.5% of bulb dia in case of under reamed piles For piles dia more than 600 mm – Two third of the final load at which total displacement attains a value of 18 mm or 2% of dia whoever is less – 50 % of the final load at which the total displacement equals 10 % of the dia. of pile and 7.5% of bulb dia in case of under reamed piles 62
  • 63. LOAD TEST - INITIAL • THE SAFE LOAD FOR GROUP OF PILES – FINAL LOAD AT WHICH TOTAL DISPLACEMENT IS 25 MM – TWO THIRD OF FINAL LOAD AT WHICH DISPLACEMENT IS 40 MM 63
  • 64. LOAD SETTLEMENT CURVE SAFE LOAD Least of 2/3 P1 or ½ P2 FOR GROUP Least of Load corrp. to 25 mm sett or 2/3 corrp. to 40 mm sett. LOAD IN INCREMENTS OF 20% Final load maintained for 24h 64
  • 65. LOAD TEST – ROUTINE TEST • Test load will be atleast 1.5 times the working load • Max. settlement should not > 12 mm for piles dia upto 600 mm • 18 mm or 2 percent of pile diameter whichever is less for piles of diameter more than 600 mm. • for group of piles max. Settlement should not > 25 mm 65
  • 67. PILE LOAD TEST (KENTELEDGE ARRANGEMENT) 67
  • 68. PILE LOAD TEST (WITH ANCHOR PILES) 68
  • 69. DYNAMIC PILE TESTING • SUPPLEMENTS STATIC TESTING • HIGH STRAIN TESTING – PROVIDES DATA ON FORCE & ACCELERATION OF PILE – EVALUATION OF BEARING CAPACITY – FACILITATE IMMEDIATE DECISION ABOUT ACCEPTANCE OR REJECTION OF PILE • LOW STRAIN TESTING – FOR TESTING CONTINUITY OF PILE – INFORMATION ABOUT DIMENSIONS AND CONSISTANCY OF MATERIAL ASTM D 4945 69
  • 70. DYNAMIC PILE TESTING as per ASTM D 4945 70
  • 72. DEFECTS IN CAST IN SITU PILES • HONEY COMBING DUE TO INADEQUATE VIBRATIONS • SEGREGATION DUE TO IMPROPER CONCRETE PLACEMENT METHODS • WASHOUT OF CEMENT DUE TO GROUNDWATER FLOW • CRACKS IN PILE SHAFT DUE TO SHRINKAGE • INCLUSION OF FOREIGN MATERIAL • NECKING DUE TO COLLAPSE OF SIDE WALLS DURING WITHDRAWAL OF TEMPORARY CASING 72
  • 75. 75