SlideShare a Scribd company logo
1 of 36
Download to read offline
PLEXOS 
A P P L I C A T I O N S 
®
Contents 
Market Analysis 
Page 3 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Portfolio Optimization 
Page 7 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Reliability Analysis 
Page 11 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Capacity Expansion Planning 
Page 15 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Hydro Optimization 
Page 19 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Transmission Analysis 
Page 24 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Gas System Planning 
Page 28 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ 
Renewable Generation Integration 
Page 32 
̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣
Market Analysis 
In the past, the US electricity markets were characterized by vertically integrated and monopolistic 
electric utilities. These utility companies owned the generation, transmission and distribution networks 
and electric rates were reviewed and approved by public utility commissions or public boards. 
However, in the past couple of decades, these vertically integrated structures have been replaced by 
regional wholesale markets. 
A number of regions, including the Northeast (NYISO, ISO-New England), Mid-Atlantic (PJM 
Interconnection), much of the Midwest (Midwest ISO and Southwest Power Pool), Texas (ERCOT) and 
California (CAISO) - organize their markets under an independent system operator (ISO) - sometimes 
also referred to as a regional transmission organization (RTO). By adopting this ISO/RTO structure, these 
regions have moved to expand competition in electricity from the vertically integrated to a competitive 
markets for energy, capacity and ancillary products. 
In fact, two-thirds of the electricity consumed in the U.S. are provided an ISO/RTO. Other regions - 
including the Southeast (FRCC, SERC, TVA), Inter-Mountain West and Northwest - chose to retain the 
traditional regulatory model. Under this regime, vertically-integrated utilities retain functional control 
over the transmission system and therefore choose which generator is dispatched to serve load. Some 
argue that such a model has led to preferential treatment by these utilities for their own generation 
rather than more affordable and environmentally responsible generation available from competitive 
suppliers and marketers. 
U.S. natural gas markets are also highly competitive. Natural gas market prices are determined 
competitively on spot and futures markets reflecting current and expected supply and demand 
conditions. The market price is determined through the actions of thousands of well-informed buyers 
and sellers. U.S. natural gas markets comprises of Midwest, Northeast, Gulf, Southeast and Western gas 
regions. 
ISO Market Structure and Products 
The energy markets operated by ISO’s US typically include a two settlement market: day ahead market, 
or financial commitment, and a real time or spot market. The day-ahead allows generators to 
reasonably know whether they will be committed at least 12 hours before the start of the electric day. 
Day ahead commitments are similar to a binding forward financial contract, where generators are 
financially responsible for their dispatch the day prior. If they are unable to meet the dispatch in the real 
time, or spot market, generators would have to purchase the difference between their day-ahead and 
real time positions. The day-ahead market is normally an hourly market while the real time or spot 
market is normally a 5 minute market (prices are settled and posted every 5 minutes). 
Generators bid into both the day-ahead and real time markets using a bid curve to approximate their 
marginal costs (typically their fuel and some notional operating costs). They are also allowed to provide 
start-up costs for their commitment as well as minimum up and down times. All of these factors are 
included in the algorithms established by the ISO to calculate the hourly price of electricity. The price 
is set by the most expensive unit in the generator bid stack or the marginal unit. 
energyexemplar.com Page 3
In addition to the day-ahead and real time energy markets, which indicate the price of energy required 
to serve electric load over time, ISO’s have also devised their markets to provide locational price signals 
as well. In this case, ISO’s operate a nodal electric market where the price of energy is determined by 
the availability of transmission to deliver electricity across the network. In areas where there is 
insufficient transmission to deliver all of a region’s demand, prices tend to increase to reflect the 
increased costs to supply load. This is also known as congestion pricing. In the end, prices for 
electricity are published both across time as well as across the network in which the ISO operates. 
These prices are fully transparent and provide all market sectors the appropriate signals about the 
available supply and demand of electricity. 
Generators in the ISO operated markets submit bids which are typically capped at a certain or 
prescribed level (roughly $1000 to $1200/MWh). As generators bids are capped and therefore they are 
less likely to recoup their fixed costs in the energy market, ISO also provide generators with a capacity 
market. These capacity markets are conducted in a bid auction for the right to supply generation 
capacity. Generators are paid to be able to meet certain reliability criteria. These markets should also 
provide sufficient incentive for new generation to enter the market, particularly when capacity and 
energy prices increase over time. 
Generators also bid into different ancillary services markets. These could include regulation, spinning 
reserve, non-spinning or non-synch reserve and replacement reserves. 
Lastly, the ISO also operate and manage the high voltage transmission network. Financial transmission 
rights (FTR) / Congestion Revenue Rights (CRR) market. 
PLEXOS® Integrated Energy Model 
The markets served by ISO’s have grown increasing complex. With this complexity requires new 
software tools for market participants of the deregulated markets. PLEXOS provides of software solution 
to match the complexities. 
PLEXOS offers multiple horizon simulations, including sub-hourly, to be able to model both the 
day-ahead and real time spot markets. PLEXOS supports multiple spatial analyses, from a full nodal 
network model to a zonal or regional model. As such, it is capable of calculating the system marginal 
price, transmission congestion costs and losses, and other market metrics published by the ISO’s. 
PLEXOS offers the same algorithms that the ISO use to dispatch their markets and is often used by the 
ISO themselves for internal and external market studies. 
Users of PLEXOS can create a multi-band bid and offer curves for both generation and demand. They 
can create unit commitment constraints to match actual market decisions including minimum generation, 
start costs and minimum up and down times. PLEXOS allows generation bid caps as well as the regional 
price of value of loss load (VoLL). All of PLEXOS’s feature rich properties allow users to capture the 
complexities of the US deregulated electricity markets in a single software platform. 
energyexemplar.com Page 4
Additional properties available in PLEXOS to address the deregulated electricity markets as operated 
by the ISO’s are outlined in the table below. 
Planning Objectives PLEXOS Capability 
Renewables Integration and System 
Flexibility Requirement Assessments 
Least Cost Resource Change within 
and Across Regions 
Minimizing production costs and 
consumer costs to electricity and 
natural gas rate payers 
Sizing Natural Gas Network 
Components and Natural Gas 
Storage 
Environmental Policies 
Integrated Reliability Evaluation 
• Sub-Hourly Co-Optimization of Ancillary Services with Energy 
Market and Transmission Power Flows 
• Stochastic Optimization and Stochastic Renewables Models 
• PHEV, EE, DR, SG, Energy Storage Models 
• Co-Optimization of Generation and Transmission Expansion 
• Generation Retirements and Environmental Retrofit Models 
• Reliability Evaluation 
• Co-Optimization of Production cost of Electrical and Natural 
Sectors 
• Electrical Network Contingencies and Natural Gas Network 
Contingencies 
• Co-Optimization of Natural Gas Network Expansion along with 
Electricity Sector Expansion 
• Electrical Network Contingencies and Natural Gas Network 
Contingencies 
• Co-Optimization of Annual and Mid-Term constraints 
• Integrated Reliability Evaluation to Ensure LOLE and other Metrics 
Maintained with Co-Optimization of Electric and Gas Sector 
Expansion or True Monte Carlo 
US PLEXOS® Integrated Datasets for Power and Natural 
Gas Sector Challenges 
In the past few years there has been a convergence in environmental policy and public policy, in 
combination with recent shale gas developments which have combined to increased reliance of the 
power sector on natural gas generation. As a result, gas and electric coordination has emerged as a 
complex topic for regulators and market operators with concerns of potential gas constraints that impact 
electric system operation and reliability. Many studies have been initiated for gas electric coordination 
in the major interconnects (Eastern Interconnect, ERCOT and WECC) of the US. Furthermore, integration 
of renewables have driven Integrated Resource Plan (IRP) managers and ISO’s to consider sub-hourly 
ancillary co-optimization analysis in production cost models for major areas of the US. Thus the study 
process and the complexity of issues is driving the demand for integrated datasets and integrated 
models. In other words, one software package that can handle all the complexities of planning and 
operations and market analysis in the short, medium and long term. 
Energy Exemplar has developed integrated datasets serving North America, combining both a nodal 
electric model as well as the natural gas network. We have three separate electric interconnection 
models, the Eastern Interconnect (EI), Texas (ERCOT) and the Western Interconnect (WECC). 
On top of these three models is a gas model serving North America. The gas network includes the full 
scope of gas production and transportation system, from well head or production field to natural gas 
pipelines, storage and end user demands. 
energyexemplar.com Page 5
The intersection of these two models is the natural gas fired electric generator. With the combination of 
the gas electric dataset into a single model by PLEXOS, users can evaluate the combination of gas 
constraints on the electric system, particularly in the winter when natural gas demand peaks, as well as 
the interaction of price between the electric and gas models. 
Planning Objectives PLEXOS Capability 
Production 
Cost 
Annual Environmental Constraints 
Mid Term 
Optimization 
Capacity 
Expansion 
Planning 
Reliability 
Evaluation 
Generation Characteristics 
Electrical Network Data 
Natural Gas Network Data 
Demand and Energy Shapes 
Fuel Prices 
Hurdle and Wheeling Rates 
Constraints 
Others 
Energy Constraints 
Mid Term Optimizations 
Others 
Integrated Planning 
Database in PLEXOS 
Generator Costs 
Transmission Line Costs 
Pipeline Costs 
Gas Storage Costs 
Energy Efficency Cost Curve 
Demand Shapes 
Others 
Single Database 
Facilitates Multiple 
Types of Studies 
FOR Transmission 
FOR Generation 
FOR Gas Pipeline 
Renewable Variability 
and Uncertainties 
Demand Uncertainty 
Others 
Testimonial 
“I've only been using PLEXOS for a couple of months, but I'm very excited about the flexibility and ease 
with which I can test a wide variety of different scenarios. By only supplying key inputs I get surprisingly 
accurate results, which I can confidently stand behind. So far PLEXOS has had more to offer than I've 
needed, and each time when I run into a dead end I get quick responses with from a diligent technical 
support.” 
Jacobus Swart 
NamPower 
Africa 
energyexemplar.com Page 6
Portfolio Optimization 
Portfolio Optimization includes the following four activities. 
1. Operation. On a daily basis, the operators in the control center (or on the trading floor) solve unit 
commitment and economic dispatch problems to minimum system costs while maximizing the profit 
from trading with neighbouring utilities or markets. 
2. Generating Asset Evaluation. Examples of generating assets include generators, energy contracts, 
demand response programs, energy storage units, etc. Performing the Generating Asset 
Evaluation involves quantifying the value of generating assets. Simulations both with and without 
the generating asset are performed for the technical life time of the generating asset. Then, the 
generating asset value is calculated as the production cost difference between the solutions with 
and without the generating asset. Generating Asset Evaluation can also be used to examine the 
difference between the generating asset operation and the energy and Ancillary Service markets. 
3. Budgeting. Portfolio simulation can be used to predict the production cost, fuel consumption, 
traded energy, emission production, etc. Solutions can then be used to support decisions on rate 
design, fuel procurements, emission allowance allocation, etc. 
4. Long-term Capacity Expansion. Long-term Capacity Expansion planning can be done using 
simulations that determine optimal generation or transmission facility investment (or retirement) to 
meet projected load growth while still complying with reliability criteria, emission limits, 
renewable energy portfolio standard (RPS), etc. 
Portfolio Optimization by PLEXOS® 
PLEXOS solves Portfolio Optimization problem using the Security Constrained Unit Commitment (SCUC) 
and Economic Dispatch (ED) algorithm. This algorithm makes use of Mixed Integer Programming (MIP) 
to minimize a cost function subject to all operational constraints. The cost function may include the 
generating cost, generator startup and shutdown costs, sales contract revenue, purchase contract cost, 
energy or AS market sales revenue and purchase cost, transmission wheeling charges, etc. The 
constraints can include things such as energy balance (i.e., at any moment, the generation plus 
purchase are equal to the load plus sales), AS requirements, generating asset chronology (i.e., min up 
/ down time, ramp rate, energy resources (i.e., energy limits, fuel limits, emission limits, water limits), 
transmission limits, etc. For example, Portfolio Optimization can be formulated as follows: 
Minimize Portfolio Production Cost = generator fuel and VOM cost + generator start cost 
+ contract purchase cost – contract sale saving 
+ transmission wheeling 
+ energy / AS / fuel / capacity market purchase cost 
– energy / AS / fuel / capacity market sale revenue 
Subject to 
• Energy balance constr aints 
• Operation reserve constraints 
• Generator and contr act chronological constraints: ramp, min up /down, min capacit y, et c. 
energyexemplar.com Page 7
• Generator and contract energy limits: hourly / daily / weekly / … 
• Transmission limits 
• Fuel limits: pipeline, daily / weekly/ … 
• Emission limits: daily / weekly / … 
• Others 
The PLEXOS MIP algorithm solves the Portfolio Optimization problem by simultaneously obtaining 
optimal solutions to unit commitment, economic dispatch, contract exercise, and market activates. This 
approach produces what is called “ co-optimization” solutions. 
Combined Cycle Generator Modeling 
Due to the nature of the MIP formulation, the combined cycle generator can be modelled precisely using 
its components, i.e., gas turbine generators and steam turbine generator. For example, the following 
chart illustrates the 2x1 combined cy cle generator representation in PLEX OS. 
Each component, the gas turbine generators and the steam turbine generator, is modelled as a regular 
generator. The red line in the chart represents the waste heat transfer from the gas turbines to the Heat 
Steam Recovery Generator (HSRG), and is modelled as a constraint in the PLEXOS MIP formulation. 
Then, the PLEXOS unit commitment and economic dispatch algorithm can be used to determine the best 
operational mode t o minimize the portf olio production cost of this sy stem. 
PLEXOS® LT-PLAN - Long-term Capacity Expansion 
Long-term (LT ) Capacity Expansion determines optimal investment decisions over long period of time, 
usually up to 30 years. The PLEXOS LT-PLAN module accomplishes this by minimizing the Net Present 
Value of forward-looking investment costs and the portfolio production cost. Therefore, the portfolio 
cost minimization problem is expanded to include the investment cost and the investment-related 
constraints as f ollows: 
Minimize Portfolio Production Cost + In vestment Cost S ubject to 
• Portfolio operation constraints 
• Investment Constraints 
energyexemplar.com Page 8
Here, Investment Cost may include cost of new generator builds, cost of transmission expansion, and/or 
cost of generator retirements. The Investment Constraints may include regional capacity reserve 
margins, resource addition and retirement candidates (i.e. maximum units built / # retired), technical 
and financial life spans, technology / fuel mix rules, Renewable Portfolio standard (RPS), etc. The build 
and retirement candidates might include thermal generators, geothermal generators, hydro or pumped 
storage hydro generators, wind or solar generators, transaction and demand side participation, 
transmission augmentations, or generator retrofits. 
The PLEXOS LT-PLAN solution is illustrated by the following chart. The x-axis corresponds to the 
investment and the y-axis corresponds to the cost. As the investment increases, the production cost, 
P(x), decreases (blue line) and the capital cost, C(x) increases (green line). The total cost (red line) is the 
sum of the capital and production costs, C(x) + P(x). The PLEXOS LT–PLAN simulation returns the optimal 
investment decision (x*) while observing the investment and operational constraints. 
Total Cost C(x) + P(x) 
Optimal Investment x* 
Capital Cost C(x) 
Investment x 
Cost ($) 
Production Cost P(x) 
Stochastic Simulations to Incorporate Risk 
In the portfolio optimization, risk is an important consideration in the corporate decision-making 
environment. To incorporate risk, PLEXOS uses stochastic simulation to produce solutions with a statistic 
distribution for a given set of the stochastic drivers, such as fuel prices, load forecast, renewable 
generation profiles, market prices, etc. These stochastic drivers can be specified in PLEXOS 
exogenously, i.e., the user provides the stochastic time series, or endogenously, i.e., PLEXOS produces 
the stochastic time series for the stochastic drivers based on parameters provided by the user. For 
example, the following chart shows a weekly gas price distribution over one hundred samples. 
energyexemplar.com Page 9
Here, the first four bars represent the maximum value, minimum value, standard deviation, and mean 
value over the one hundred gas price samples. The remaining bars represent the one hundred 
samples. 
For the given stochastic driver time series, PLEXOS performs multiple iterations of simulations and 
produces multiple iterations of solutions. The following histogram shows the distribution of portfolio 
production costs for a week over the stochastic drivers of gas price, load forecast and market price 
forecast. 
The chart shows that the mean production cost in this week is about $180 million with a worst case 
scenario of $260 million and a best case scenario of $161 million. The distribution of the weekly 
production cost provides value insight to the corporate decision makers. 
Testimonial 
“Wärtsilä has used PLEXOS successfully for several years now. Purpose of our modelling work is to 
quantify the value of flexibility for power systems and for individual customer portfolios. The studies 
have clearly identified the need of more flexible generating resources in the future. Also, Energy 
Exemplar’s willingness to develop the software, based on our needs, is highly appreciated”. 
Ville Rimali 
Wärtsilä 
Europe 
energyexemplar.com Page 10
Reliability Analysis 
The PLEXOS simulator is a powerful tool for performing reliability studies on electric power systems. The 
simulator can calculate the standard metrics of LOLP, LOLE, EDNS and EENS from the PASA simulation 
phase using convolution. However, PLEXOS can also use the detailed chronological simulation of ST 
Schedule to produce the same metrics via Monte Carlo. 
Energy Exemplar adopted this approach in the valuation of Loss of Load Expectation (LOLE) for the 
market operated by ISO-New England, which covers the six states of New England in the north-eastern 
US. The following describes this approach we used with PLEXOS. 
How to setup PLEXOS® for Reliability via Monte Carlo 
In a reliability study we are only interested in whether or not the system can meet the electric load, and 
possibly ancillary services requirements, given all generation technical, transmission, fuel availability 
and other user-defined constraints. The dispatch order of generators and the system marginal price is 
not useful and thus we can simplify the simulation by removing all costs apart from the pseudo cost of 
unserved energy (Value of Lost Load or VoLL). To do so, simply mark all cost information with a Scenario 
and exclude that Scenario from your reliability Model run. Example of cost parameters include: 
• Generator [Heat R ate] and [Load P oint] 
• Generator [ VO&M Charge] 
• Fuel [Price] 
• Generator [Offer Price] 
Having done this, the simulation will be less complex, with the objective function containing only costs 
of unserved energy, dump energy and perhaps reserve shortage. 
Loss of Load Expectation (LOLE) 
Normally we compute the Loss of load probability (LOLP) as a reliability metric. This is a measure of the 
probability that demand will exceed the capacity of the system in a given period and is expressed as a 
percentage. As noted above, the periods when demand exceeds supply is a shortage event. An 
alternative metric is the Loss of Load Expectation (LOLE), which is the number of days of outage or the 
number of times in a given period that the load will be greater than the demand. This can be expressed 
as LOLE = LOLP * N/24. A value of 1.0 LOLE over a single year signifies multiple periods or hours over 
the year in which there were shortages. It is unlikely these shortages occurred in a single day but likely 
over multiple hours over several or more days. 
We used the Monte Carlo feature in PLEXOS to calculate the probability of the LOLE for each load 
probability forecast in the New England. The first calculation was to benchmark the ISO-New England 
Installed Capacity Requirement (“ICR”) calculation for the study period, or in this case the 2017 Peak 
Load Forecast. The following demand forecast from ISO-NE’s ICR report (see Table 1 below) was used 
for this analysis. 
energyexemplar.com Page 11
Table 1 
We then performed a LOLE calculation with an average load-weighted risk approach. We prepared a 
range of 16 different installed capacity levels in the ISO-NE control area and for each capacity level 
evaluated the average load weighted LOLE at each of the above 10 load probabilities in Table 1. 
The following figure, shows the demand distribution on the y-axis and the capacity distribution on the 
x-axis. There are a total of 160 capacity and demand pairs in the following chart for which we 
computed the average load weighted LOLE for using PLEXOS. 
Figure 1 
Then we prepared an average load weighted LOLE calculation for the 10 load probabilities for each 
capacity point and derived 16 average load weighted LOLE’s as a function of installed capacity for 
the ISO-NE control area. We derived a value of LOLE at the ISO-NE Net Installed Capacity 
Requirement (NICR) value of 0.1 day per year which is consistent with reliability criteria for NICR. 
With the 16 LOLE calculations we were also able to compute the cost of lost load at each installed 
capacity level using the PLEXOS 8,760 hour time series simulation. PLEXOS estimates Unserved 
Energy (USE) at each hourly interval if demand is greater than generation, or a shortage event. 
energyexemplar.com Page 12
This can happen primarily in summer months with reduced thermal generator capacities in 
combination with load risk and forced generator outages. We then approximated the Value of Lost 
Load (VoLL). For this analysis, we assumed a VoLL $20,000/MWh. Figure 2, below, displays an 
example time series path of one of the load weighted risk replications for the 8760 hour simulation 
performed. We charted the cost of lost load in millions of dollars, which is the result of multiplication 
of the USE at each interval as described above by the value of VoLL selected above. 
Figure 2 
In Figure 2, the show an example of the 8760-hour simulation path for the peak demand and installed 
capacity pair with the cost of unserved energy is displayed on an hour by hour basis in millions of 
dollars. We ran 160 of these paths using Monte Carlo simulation and then took an average load 
weighted cost of lost load across the demand risk for each of the 16 installed capacity values. 
energyexemplar.com Page 13
Figure 3, below displays a curve of the LOLE calculations as a function of percent of Net Installed 
capacity Requirement (“NICR”) for the New England Control Area as well as the cost of lost load as a 
function of percent NICR. 
Figure 3 
Figure 3 shows that the system LOLE reliability metric degrades rapidly for installed capacity values 
below NICR. Also, the cost of lost load increases rapidly below NICR. 
Testimonial 
"I have been using PLEXOS to study the impact of wind and solar variability on power system reliability, 
both for thermal and hydrothermal systems. PLEXOS makes quite easy to run Monte Carlo simulations 
and to define different modelling scenarios. Its flexibility has allowed us to evaluate how operational 
aspects such as solar and wind profiles, transmission constraints, hydro inflows, operational reserve 
levels, and energy storage may impact the adequacy contribution of variable generation." 
Professor Esteban Gil 
Universidad Federico Santa Maria 
South America 
energyexemplar.com Page 14
Capacity Expansion Planning 
Flexible power generation and interconnection capacity 
needs of the Italian power system using PLEXOS® LT plan 
One of the main developments of the last few years on the Italian power market has been the significant 
increase of renewable capacity in the form of wind and solar power plants. Using a PLEXOS dataset 
based on data available from Terna and various utilities, we have modelled the Italian power market 
through the six geographical zones and considered the medium term expected scenarios. The Southern 
zones (namely South, Sicily and Sardinia), already characterised by a significant amount of renewable 
capacity, are expected to experience the largest concentration of renewable development. In addition, 
these regions are characterised by a relative lower level of interconnection with neighboring countries 
compared to the Northern zones. Given the variability introduced on the system by the increasing 
renewable capacity and the relative isolation of the Southern zones, the deployment of flexible power 
plants and the expansion of interconnection capacity are assessed using the PLEXOS Long Term (LT) Plan 
feature. This feature, designed for long term optimal investment analysis, provides useful insights about 
potential bottlenecks, system flexibility and power prices, and is a critical tool for analysts, researchers, 
regulatory and utility decision makers to evaluate network adequacy and expansion, security of supply, 
investment options and energy policy development. 
Introduction and Model Description 
The power market simulation and analysis software PLEXOS® Integrated Energy Model has been used to 
represent the Italian power market in 2012 and its development in the medium term, considered up to 
the year 2017. Energy Exemplar built a dataset including all the relevant plants within each 
geographical market zone in 2012, with the poles of limited production aggregated to the surrounding 
geographical zones as: BRNN, FOGN and ROS to the SUD zone, and PRGP to the SICI zone. 
Figure 1: Geographical zones of the Italian power market. 
Installed capacities of conventional plants and aggregated figures of renewable generators are 
obtained from Terna reports, utilities websites and ENTSO’s Scenario Outlook & Adequacy Forecasts 
reports. Such capacities cover the year 2012 and extend up to 2018. In addition, for each technology 
we have taken a representative set of operational characteristics (heat rates, ramp rates, start costs etc.) 
and applied it to each of the plants of that particular technology. Renewable generation profiles are 
obtained from the in-built PLEXOS® feature to create stochastic samples from a given profile, taken as 
the real 2012 data in this instance. 
energyexemplar.com Page 15
The long term country demand profiles, and zonal profiles for Italy, were built using the 2012 hourly 
values and the PLEXOS in-built load forecasting feature that uses a given base profile, annual peak and 
energy demand forecasts; such a procedure was applied to each of the countries included in the model 
(Italy, France, Switzerland, Austria, Slovenia, Albania, Montenegro and Greece). 
The aim of this study was to assess the need for additional interconnector capacity or the development 
of flexible power plants, and for that reason we employed PLEXOS® Long Term (LT) Plan feature. 
Long Term Capacity Expansion Planning with PLEXOS® 
Assessing the risk and return of new investments both in new power plants and in the reinforcement of 
the transmission grid requires highly specialized tools. PLEXOS® Integrated Energy Model feature of 
Capacity Expansion refers to the problem of finding the optimal combination of generation new builds 
(and retirements) and transmission upgrades (and retirements) that minimizes the net present value 
(NPV) of the total costs of the system over a long-term planning horizon. That is, to simultaneously solve 
a generation and transmission capacity expansion problem and a dispatch problem from a central 
planning, long-term perspective. 
The optimization problem takes into account in the objective function two types of costs; capital costs 
(costs of new generator builds and transmission expansion costs) and production costs (costs of 
operating the system with any given set of existing and new builds and transmission network as well as 
the notional cost of unserved energy). The PLEXOS LT Plan phase by default spans the whole simulation 
planning horizon in a single optimization 'step', while it gives the user the option to control the type of 
chronology used, and choose between preserving the full chronology (Fitted chronology) or using the 
partial chronology (Load duration curves, LDC). 
Results and Discussion 
In this case study we define generator and transmission expansion candidates which PLEXOS will assess 
in order to give the optimal solution. Therefore, in the inputs we define the optional investments to be 
either the expansion of the existing interconnectors (with France, Switzerland, Slovenia and Greece) or 
the building of new ones (with Croatia, Montenegro and Albania), as per Terna development plans. In 
addition, we give PLEXOS the option to select to build new CCGT, GT or ST power plants in all of the 6 
Italian zones. 
The optimal solution as calculated by the PLEXOS LT Plan shows that between 2015 and 2017 all the 
existing interconnectors used to import electricity into the country are congested most of the time (see 
Figure 2); the list includes those with France, Switzerland, Austria and Slovenia and excludes only the 
one with Greece, which is operating mainly for export. 
Figure 2: Congestion of interconnectors with Northern neighbour countries 
energyexemplar.com Page 16
Given the need for more interconnector capacity, the PLEXOS solution is to build an interconnector 
linking the South zone with Albania. This interconnector is indeed in the Terna plans and the PLEXOS 
result is well suited, given that most of the renewable capacity and therefore the greatest need for 
balance of intermittent generation is located in the South. Together with the security of supply 
constraint, which is met by this new build, the other critical parameter largely impacted by the 
availability of interconnection capacity is the price in the country. Given the limited horizon in the 
PLEXOS model compared to the typical economic lifetime of an interconnector project, further builds are 
prevented, as the cash-flow from the lower-cost imported electricity savings does not justify the 
investment. The net result is a higher power price compared to the neighbour countries. 
In addition to the interconnector with Albania, the PLEXOS optimization includes also the building of 
new CCGT plants in Sicily. This result is justified by the limited spare capacity of conventional plants on 
the island and represents a measure to prevent the prices to be too sensitive to the generation from 
renewables, as shown in Figure 3. Nevertheless, the price in Sicily is higher than in the rest of Italy, as 
shown in Figure 4, with significant peaks in the summer. The congestion of the interconnector with the 
mainland for most of the year suggests that an increased capacity might limit the price spread, but the 
cash-flow argument used for the interconnectors with neighbour countries applies also to the one 
between Sicily and the mainland. 
Figure 3: Effect of new-built CCGT plants on Sicilian power prices 
Figure 4: Comparison of power prices among the 6 Italian zones 
Another insight also obtained from the PLEXOS LT Plan results is the level of congestion of all of the 
interconnectors exporting electricity from the South zone, as shown in Figure 5. 
energyexemplar.com Page 17
Figure 5: Congestion of interconnectors connected to the South zone 
Conclusions 
The Terna plans to increase these export capacities and the new interconnector with Albania described 
above, is a way to address the large imbalance between demand and supply, as shown in Figure 6. 
Such expansion would also avoid the significant cycling costs and low capacity factors of the 
conventional power plants in the region, thus mitigating their effect on the energy prices in the area with 
likely positive effects for all the country. 
Figure 6: Demand and supply in the South zone 
Testimonial 
"Since I started working with PLEXOS, I have been surprised of how powerful and useful it is. PLEXOS 
covers such extensive and accurate approach of modelling the market and provides different 
possibilities of modelling the different factors and drivers of the power market. I used PLEXOS to model 
different power markets across the world, every of which had their own particularities, which implies the 
difficulty of different approach when modelling. Thanks to such a powerful tool, the required knowledge 
and the incredibly great support from energy exemplar, every client case I used PLEXOS for the 
modelling part, the client happened to be very satisfied with the results and my company as well. I 
strongly recommend it to those new potential users thinking about joining the PLEXOS practice!” 
Elena De Juan Salgado 
Boston Consulting Group 
Europe 
energyexemplar.com Page 18
Hydro Optimization 
Power systems having both hydro-electric and thermal generation require a systematic and coordinated 
approach in order to determine an optimal policy for dam operations. The goal of a hydro-thermal 
planning tool is to minimize the expected thermal costs along the simulation period. These types of 
problems generally require stochastic analysis to deal with inflow uncertainty. This can increase the 
mathematical size of the problem and can easily become cumbersome to solve. 
PLEXOS Integrated Energy Model offers many features to deal with the hydro-thermal coordination 
problem. In addition, it offers a seamless integration of phases, making it possible to determine an 
optimal planning solution in the medium-term and then use the obtained results in a detailed short-term 
unit commitment and economic dispatch (UCED) problem with increased granularity. For example, 
weekly targets as constraints filter down to produce hourly electricity spot prices. 
The Challenge 
The systematic coordination of a system composed of both hydro-electric and thermal plants requires 
determining an operational strategy that for each stage of the planning horizon produces a scheduling 
plan of generation. This strategy minimizes the expected operational cost along the period, which is 
mainly composed of fuel costs plus penalties for failure in load supply. The problem becomes complex 
to solve because generally in hydro systems: 
• Natural inflows ( by nature) are stochastic processes. 
• Availability of w ater stored in dams is limit ed. 
• There are complex cascading h ydro systems. 
• Water usage policies and en vironmental releases such as irrigation settlement s. 
Water as a fuel supply is cost-free, but its opportunity cost is fundamental to finding the optimal strategy 
for operations. This issue creates the need for a decision in a given time period. Storages can’t be 
drained too low, which might incur generation shortfalls or excessive thermal output. On the other hand, 
we also want to avoid spillage of water and lost generation opportunities. Figure 1 summarizes the 
dilemma a hydro power planner faces to operate a dam. 
Figure 1: Diagram showing the dilemma hydro power planner faces under uncertainty 
energyexemplar.com Page 19
The Solution 
PLEXOS can find a hydro releasing policy that minimizes the expected thermal cost by formulating an 
optimization problem such as the following: 
Min {Variable Costs} 
Subject to: 
Energy Balance Equation 
FlowLimits 
GenerationLimits 
Hydro Balance: 1 
The hydro balance equation shows the link between decisions in both the present and future. 
Since water is free (no fuel cost) it is necessary to specify a final condition so as to minimise thermal costs 
along the simulation period, and to avoid the storage being completely drained. These final conditions 
can be represented as a target or a proxy for opportunity costs such as a deviation from targets, usually 
known as the future cost function or scrap value function. 
To handle uncertainty in the inflows, PLEXOS offers stochastic optimization techniques in both 2-stage 
and multistage. Both techniques minimize the expected cost (or maximum benefits) of the system. 
PLEXOS® Features Explored 
MT and ST schedule 
To determine optimal targets or deviation targets, PLEXOS can analyse a longer horizon using Medium 
Term (MT) analysis and if the mathematical size of the problem is unsolvable a reduction in granularity 
(called demand blocks) can be applied to produce a mathematical problem that is faster to solve. Then 
the targets or deviation targets can be calculated from this optimal solution. This simplification produces 
an end volume at each block, then the MT problem passes the target or future cost function to each short 
term (ST) step so as to obtain a higher resolution release policy. Figure 2 shows an example of MT target 
(red line) and ST end volumes (blue area). 
energyexemplar.com Page 20
Cascading Hydro with Storage and Waterways 
To create models of cascading hydro networks a combination of Storage, Waterway, and Generator 
objects can be used. PLEXOS offers the capability to model a cascading hydroelectric system like the 
one shown in Figure 3. 
Figure 3: Schematic representation of Storages and Waterways 
Storage objects are used to represent storage reservoirs with any storage capability or even simple 
junctions in a river-chain. Each storage can connect to one or more generators or waterways to create 
a model of a river chain. 
Waterway objects connect the storages or spill water from the storage 'to the sea'. Waterway flows can 
delay the water flow, can have bounds placed in their flows and can limit the rate of change in their 
flows. The Constraint class makes it possible to relate water flow rates and generator efficiencies to 
storage elevations. 
Pumped Storages Power Plants 
Pumped storage plants store energy in the form of water. Pumps move water from a lower elevation 
reservoir (the 'tail' storage) to a higher elevation ('head' storage). To optimise the operation of a 
pumped storage power plant, PLEXOS formulates an optimization problem to decide when to release 
and pump water in order to minimize costs (or maximize benefits). In general one should expect that 
low-cost off-peak electric power is used to run the pumps and during periods of high electric demand 
and high price, the stored water is released through turbines to generate power. 
Figure 4: Pumped Storage cycle. Generation left hand side and pumping right hand side 
energyexemplar.com Page 21
Stochastic Optimization 
PLEXOS can find the best outcome given the uncertainty in inflows. The problem is summarized in Figure 
1 and can be solved using a stochastic optimization formulation. PLEXOS offers a two stages and 
multistage optimization approach. The difference is that multistage techniques allows a re-evaluation of 
the policy after some time, the period when this happens is called a “Stage”. In a two-stage approach, 
the optimal policy is never re-evaluated because the information is not revealed at an intermediate 
stage during the simulation. 
These two types of problems are represented in the below scenario trees. 
Root 1st Period 2nd Period 2nd Stage Root 
1st Stage 
1st Period 
2nd Stage 
2nd Period 
Figure 5: Left hand side represent 2 Stages SO, right hand side represents multi stage SO 
Multi Stage Tree Reduction 
When using multistage stochastic optimization, a large number of possible scenarios can be generated. 
For such a high number of scenarios, it is impossible to numerically obtain a solution for the multi-stage 
optimisation problem. 
... 
Root Stage 1 Stage 2 Stage 3 Stage T 
That number of scenarios is equal to: 
Branches_perStage(NStages) 
Example: 21 stages and 3 branches per node 
321 = 1.04604 x 1010 Scenarios! 
This problem is impossible to solve 
Figure 6: Multi Stage dimensionality issue 
To help solve this problem, PLEXOS offers scenario reduction techniques. These techniques use 
strategies to reduce the number of scenarios in the optimization problem using algorithms for 
constructing a multi-stage scenario tree out of a given set of scenarios. 
Since generating a very small number of scenarios by Monte Carlo Simulations is not desired because 
less scenarios give less information, the objective is to lose minimum information by the reduction 
process applied to the whole set of scenarios. 
energyexemplar.com Page 22
Case Study Results and Discussion 
The case study summarized in Figure 7 illustrates the application of stochastic techniques in the hydro 
planning problem. The power system under study consists of 3 Power plants and there are 12 possible 
inflow sequences. The objective is to find an optimal trajectory for the storage along 1 year. 
Max Cap = 40,000 MW 
Hydro Hydro 
Initial Volume = 10600 GWh 
Max Volume = 106200 GWh 
Min Volume = 1000 GWh 
Max Cap = 20,000 MW 
Coal 
Nuclear 
Max Cap = 12,000 MW 
Load 
Figure 7: Left hand side schematic of the Power System under study, Right hand side load profile 
Three simulations are performed: Deterministic, 2 Stage and Multistage. The optimal trajectories 
obtained are summarized in Figure 8. 
Figure 8: Comparison of Trajectories for deterministic, 2 stages and multistage (4 stages). 
2 stages obtains one single trajectory as there is no chance to re-evaluate the decision through time. On 
the other hand, multistage perform a re-evaluation at each stage, therefore producing a set of optimal 
past dependant trajectories. The deterministic approach gives optimal trajectories for each sample but 
it is not capable of answering the question “what decision do I have to make now given the uncertainty 
in the inputs?” 
To evaluate the quality of the policies obtained, we can randomly select one of the policies, run the 12 
inflow possibilities and calculate the expected costs. The results are summarised in Table 1. 
Deterministic (Fixed Targets) 
Expected Costs (Million $) 42,612 
Table 1: Summary of results 
2 Stages 
21,638 
Multistage 
20,329 
The results show that multistage stochastic optimization manages the storage better. Also 2 stages gives 
lower expected generation costs compared to the case with deterministic fixed trajectories. 
Conclusions 
Hydro – thermal power system modelling has lots of challenges and optimization techniques are 
necessary to provide the required answers. PLEXOS features can solve hydro – thermal coordination 
problems to ensure the user minimizes the cost or alternatively maximizes the benefits of a 
hydro-thermal portfolio. PLEXOS offers the flexibility to customise the stochastic resultant problem, 
providing the user with a powerful tool to manage hydro uncertainty that can be integrated with the rest 
of PLEXOS features. 
energyexemplar.com Page 23
Transmission Analysis 
SAPP establishment and development 
The Southern African Power Pool (SAPP) was formed in 1995 to promote trading of electricity between 
nations in the Southern African Development Community (SADC). Initially, national utilities of each 
SADC country were included to co-operatively trade electricity (via bilateral contracts and a Short Term 
Energy market (STEM)). The STEM was replaced in 2009 with a competitive market (the Day Ahead 
Market (DAM)) and inclusion of Independent Power Producers (IPPs) and Independent Transmission 
Companies (ITCs) was later allowed. 
The SAPP membership of 16 (Table 1, as of 2013) is shown in a-Tanzania-Kenya Interconnector., the 
majority of SAPP members are interconnected with the only isolated members being ESCOM (Malawi), 
ENE (Angola) and TANESCO (Tanzania). 
Entity 
Botswana Power Corporation 
Electricidade de Mocambique 
Hidro Electrica Cahora Bassa 
Mozambique Transmission Company 
Electricity Supply Corporation of Malawi 
Empresa Nacional de Electridade 
Eskom 
Lesotho Electricity Corporation 
NamPower 
Societe Nationale d’Electricite 
Swaziland Electricity Company 
Tanzania Electricity Supply Company 
ZESCO Ltd 
Copperbelt Energy Corporation 
Lunsemfwa Hydro Power Company 
Zimbabwe Electricity Supply Authority 
OP = Operating Member 
NP = Non-Operating Member 
OB = Observer 
ITC = Independent Transmission Company 
Status 
OP 
OP 
OB 
OB 
NP 
NP 
OP 
OP 
OP 
OP 
OP 
NP 
OP 
ITC 
IPP 
OP 
Abbreviation 
BPC 
EdM 
HCB 
MOTRACO 
ESCOM 
ENE 
Eskom 
LEC 
NamPower 
SNEL 
SEC 
TANESCO 
ZESCO 
CEC 
LHPC 
ZESA 
Country 
Botswana 
Mozambique 
Mozambique 
Mozambique 
Malawi 
Angola 
South Africa 
Lesotho 
Namibia 
DRC 
Swaziland 
Tanzania 
Zambia 
Zambia 
Zambia 
Zimbabwe 
Table 1: SAPP membership (2013) 
A constrained SAPP 
The interconnected SAPP has been significantly constrained for generation capacity in the last decade. 
SAPP demand (incl. typical 15% reserve margin) for compared to net SAPP capacity (with/without South 
Africa) has been consistently higher since 2006. This trend is magnified when excluding the dominant 
player in the SAPP (Eskom, South Africa). Although, there are a number of rehabilitation and new 
generation projects currently underway to remove these constraints in the medium term (mostly in 
Botswana, Mozambique, South Africa, Zambia and Zimbabwe). 
energyexemplar.com Page 24
In addition to existing generation capacity constraints, transmission capacity constraints have had a 
significant effect on the volume of trading within SAPP (whether via bilateral contracts or DAM). For 
2013/2014, on average, 70% of energy matched in the DAM was not traded and 77% of bilateral 
contracts granted were not traded. 
Again, there are projects in the pipeline that to rectify these transmission constraints including the 
ZIZABONA project and the Central Transmission Corridor project. Other notable priority SAPP 
transmission projects include the interconnection of NP members i.e. Namibia-Angola Interconnector, 
Mozambique-Malawi Interconnector and Zambia-Tanzania-Kenya Interconnector. 
SAPP modelling with PLEXOS® 
A sufficiently detailed regional transmission model of the SAPP in the short term, medium term and long 
term will allow existing national utilities and regulators as well as prospective IPPs and ITCs in the SAPP 
to fully assess the risks and opportunities present. This is where a software tool like the PLEXOS® 
Integrated Energy Model (“PLEXOS®”) can assist. 
Based on only public domain information and generally accepted industry practice, a regional level 
SAPP transmission model has been developed in PLEXOS. This dataset includes a representation of each 
SAPP country (including load profiles and hourly demand and energy forecasts for 2010-2025), existing 
transmission interconnectors, existing major generators and country specific fuels. 
The transmission components of the PLEXOS SAPP dataset are shown geographically in Figure 1 
(extracted directly from PLEXOS mapping interface) with the SAPP interconnectors summarised in Table 
2. 
From 
Botswana 
Botswana 
Botswana 
Botswana 
DRC 
DRC 
Lesotho 
Mozambique (Central) 
Mozambique (South) 
Mozambique (South) 
Mozambique (South) 
Mozambique (South) 
Mozambique (North) 
Mozambique (Central) 
Namibia 
Namibia 
South Africa 
South Africa 
Zambia 
Zambia 
To 
South Africa 
South Africa 
Zimbabwe 
Zimbabwe 
Zambia 
Zambia 
South Africa 
Mozambique (North) 
South Africa 
South Africa 
South Africa 
Swaziland 
Zimbabwe 
Zimbabwe 
South Africa 
South Africa 
Swaziland 
Zombabwe 
Namibia 
Zimbabwe 
Voltage Level (kV) 
400 
132 
400 
220 
330 
500 
132 
110 
533 
110 
400 
400 
330 
110 
400 
220 
400 
132 
350 
330 
Transfer Capacity (MW) 
190 
425 
220 
205 
247 
560 
90 
30 
1920 
67 
1100 
1000 
220 
38 
380 
195 
1100 
15 
180 
428 
Table 2: Existing SAPP interconnectors modelled in PLEXOS dataset 
energyexemplar.com Page 25
Figure 1: Existing SAPP transmission model in PLEXOS (geographical) 
Interconnectors (the central corridor example) 
The developed SAPP dataset was used to assess three case studies: 
• 2012 SAPP as -is (Existing S APP system with e xisting bilateral contracts) 
• 2012: SAPP Free (existing SAPP system ignoring bilat eral contracts) 
• 2012: SAPP Unconstrained (existing SAPP with no tr ansmission constraints) 
The central corridor (Botswana-Zimbabwe-Zambia) is known to be a significant transmission constraint. 
This can be seen in Figure 2 where a typical days’ power-flows taken from the PLEXOS SAPP model are 
shown. As can be seen, when free trade is allowed, the South Africa-Botswana interconnector gets 
pushed to its maximum capacity. Some of this power is used in Botswana but a considerable amount is 
wheeled via the Botswana-Zimbabwe interconnector further north especially when no transmission 
constraints are imposed. 
Figure 2: SAPP central corridor power-flows over a typical day (SA-Botswana) 
energyexemplar.com Page 26
Conclusions 
PLEXOS has been used to develop a regional level transmission model of the SAPP. This model includes 
all major generators, loads and load profiles, transmission interconnectors, storages for pumped 
storage generators, country specific generator fuels and CO2 emissions from generators. 
The developed PLEXOS model was used to assess the impact of existing transmission constraints and 
bilateral contracts in SAPP. These case studies revealed that existing energy imbalances in SAPP 
countries can be significantly reduced if interconnectors are freed up to allow for the most optimal trade 
of electricity between SAPP nations. In addition, in a scenario where all SAPP nations are assumed to 
be interconnected and no transmission constraints exist, energy imbalances are removed completely. 
Testimonial 
“It is truly amazing how Energy Exemplar seem to be breaking new boundaries. Firstly, the introduction 
of chronological optimization for the Long Term Optimization studies seems to be paced right at time 
where renewables are the “flavour of the moment”. Secondly the introduction of the gas module again 
pitched at the time where shale gas is shaping the market. Not only are the new features paced 
appropriately, the algorithms and results are truly stunning and this will definitely help to put policy 
options on a scientific footing. PLEXOS has been fascinating to use to produce the South African 
Integrated Resource Plan (IRP), the stochastic optimization aspect of it was helpful to establish the 
position of least regret. We are more confident that the next IRP will be more informative given that 
PLEXOS has given us new questions which need answers...” 
Sipho Mdhluli 
ESKOM 
Africa 
energyexemplar.com Page 27
Gas System Planning 
These are interesting times for the Eastern Australian gas market with the impending LNG play coming 
online. The previously stable and long-term contract market for domestic gas supply on the east coast 
will be subject to market forces that are in part determined on the global stage. Exactly how the market 
will respond to these changes is not yet clear, however, one important question on the mind of every 
market participant is: “do we have enough gas to meet medium to long term domestic demand?” In 
answering this question and given the opaque nature of the gas market, there exists an asymmetry of 
opinions in the demand – supply market analysis. 
Historically, the Eastern Australian gas market has been relatively insulated from international market 
pressures, operating on a somewhat “self-sufficient” business model. However, the recent large scale 
development of export LNG facilities is about to change all of that as the eastern Australian gas market 
has found itself in the midst of the largest structural revolution since the privatisation of gas infrastructure 
assets in the 1990s. Predictably, participants in the eastern gas market are keen to understand the 
effects this impending LNG play will have not only on their market positions, but also on the whole 
production – demand supply chain on the domestic front. In order to predict any effect the LNG 
development will have on the domestic market, a comprehensive understanding of the domestic supply 
chain is necessary. 
This paper aims to analyse the demand - supply interactions of the eastern Australian gas market, in 
order to establish any potential risk of gas shortage in the medium to long term. Employing a model 
developed through the new gas module from PLEXOS, an analysis of the market is carried out from 2013 
- 2024. An examination of this nature is fundamental to understanding not only the LNG effects on the 
market, but also to identify any potential supply shortfalls looming in the near future. 
Gas Model Description 
Scheduling of gas energy markets require highly specialized tools to conquer the complexity of this 
dynamic, commercial and regulatory landscape. PLEXOS integrated gas and electricity simulation 
software package provides technical and mathematical solutions to meet planning needs. The gas 
module in PLEXOS allows detailed modelling of the physical delivery of gas from producing fields, 
through pipelines and storages (including linepack), to demand points with the capability to model any 
physical constraint along the supply chain. Furthermore, the PLEXOS® Integrated Energy Model has the 
ability to optimize gas and electricity markets by simultaneously solving both markets’ parameters, 
allowing decision makers to trade-off gas investments, constraints and costs against other alternatives. 
The following elements are the main components of the gas network modelled in the present study: 
energyexemplar.com Page 28
Model Inputs 
Icon Class Description 
Gas Field Field from which gas is extracted. 
Gas Storage Storage where gas can be injected and extracted. 
Gas Pipeline Pipeline for transporting gas. 
Gas Node Connection point in gas network. 
Gas Demand Demand for gas covering one or more nodes. 
The model developed for this report is built with information available in the National Gas Market 
Bulletin and the Australia Energy Market Operator (AEMO). The demand profiles for 2013 used for the 
demand zones illustrated in Figure 1 are obtained from the National Gas Market Bulletin. 
Figure 1: Gas network modelled in PLEXOS, the main demand zones included in this study are: 
Mount Isa, Gladstone, Brisbane, Adelaide, Sydney, Melbourne and Hobart 
Using the projections supplied by AEMO in the Gas Statement of Opportunities (GSOO) 2013, a 
demand forecast is built as depicted in Figure 2 showing projections until 2024 for the major demand 
centres. 
To accommodate the impact on gas production from the LNG export demand, we run a sensitivity study 
on the eastern Australian gas market with the production from the Bowen Surat gas fields (largest known 
and proven CSG basin) turned off and completely unavailable for domestic market. This assumption 
implies that all the production from this reserve is for export only therefore left out of this study (domestic 
demand-supply model). In addition, pipeline outage and maintenances are not included, and all 
pipelines are assumed to be online for the next 12 years. We also assume that the NSW CSG 
developments go ahead and are all available from the start of the planning horizon. 
energyexemplar.com Page 29
Results and discussions 
Firstly, we run a “base” model of the eastern Australian gas market for 12 years with all the producing 
fields available for production. As expected, we see no gas shortages in the system with some CSG gas 
fields not even required to come online in this time. 
Figure 2: Demand outlook from 2013 - 2024 as projected by the GSOO 2013 
As a sensitivity to model the LNG effects on the demand – supply dynamics on the eastern domestic 
market, we turn off and completely make production from the Bowen Surat gas fields (the largest proven 
producing CSG reserves in eastern Australia) unavailable for domestic demand. A justification for this 
sensitivity is the assumption that all the gas produced from this basin for the next 12 years are fully 
contracted to LNG export. From the results, we observe that there is enough gas in the eastern reserves 
to accommodate the impending LNG play as there are no shortages in any of the demand zones 
considered in this study. In addition, we observe that CSG fields which were offline in the “base” model 
came online producing at almost full capacity to offset the ‘no production’ scenario from the Bowen 
Surat gas fields. 
energyexemplar.com Page 30
Figure 3: Gas production with Bowen-Surat reserve completely contracted to LNG export from 
2013 - 2024 
This result is consistent with other studies in the literature, reaffirming the notion that eastern Australia 
has enough gas in its reserves to accommodate LNG exports at the current production rates and demand 
outlook for the next decade. 
Final comments 
Given the level of uncertainty surrounding the east coast gas market, there is a need for a sophisticated 
and complex analysis of the different scenarios and sensitivities surrounding the current market. As such, 
some open questions arising from this study, all of which can be addressed with some further modelling 
employing PLEXOS, include: 
• Will increasing LNG e xports create a domestic short age and t o what e xtent will this be seen in the 
short term? 
• How does the gas landscape change with the intr oduction of a new carbon scheme in futur e years? 
• How will the domestic gas mark et react to a netback of gas price t o international LNG prices? 
• Will a shift in the domestic demand outlook over the ne xt decade impact the suppl y - demand 
dynamics of the market? 
Testimonial 
“PLEXOS is our tool of choice for NEM market & gas modelling. It gives us the flexibility to set up the 
model as we choose, and its scenario management is very sophisticated, allowing consistent 
assumptions to be applied to short, medium or long-term outlooks”. 
Ben Howard 
AGL 
Asia-Pacific 
energyexemplar.com Page 31
Renewable Generation Integration 
The uncertainty and variability nature of the renewable generation penetration creates integration 
challenges within the electric industry from the portfolio scale to the regional ISO level. The challenges 
include: 
1. Is the Power Market or the portfolio ready for the renewable generation variability and uncertainty? 
2. What can be done to be prepared for the renewable generation? 
3. What is the cost for this readiness? 
4. Any changes are needed for the power market or portfolio operational procedure? 
5. Can new market products improve the readiness? 
6. Intra-hourly inter-BAA generation and capacity sharing? 
7. All questions are leading toward a better solution – Energy Imbalance Market (EIM). 
This article first reviews the uncertainty and variability of the renewable generation; then briefly 
describes the approach to prepare the system for the renewable generation; third, the EIM is presented 
for the ramp capacity sharing between the Balancing Authority Areas (BAA) to improve the system 
readiness for the greater renewable generation penetration. 
The Uncertainty and Variability of Renewable Generation 
Here the renewable generation usually refers to the wind miller generation and solar generation. The 
following two tables shows the 5-min actual solar and wind generation and Day-ahead (DA) and 
Hour-ahead (HA) forecasts for a 130 MW solar project and a 220 MW wind project. 
energyexemplar.com Page 32
The following histograms shows the solar and wind generation forecast error distributions. 
The DA and HA unit commitment will be performed based on the DA and HA solar and wind generation 
forecasts. Especially, the DA unit commitment may be quite off from the actual solar and wind 
generation. 
energyexemplar.com Page 33
What can be done to prepare for the Renewable Generation? 
To cover the uncertainty and variability of the renewable generation, additional reserves can be 
introduced during the DA and HA unit commitment. The additional reserves are usually called 
“Flexibility Up” and “Flexibility Down” reserves. For the detail description of the reserves for the 
renewable generation, please refer the article. 
The flexibility up and down reserve requirements are determined by the statistics of the renewable 
generation forecast errors. The flexibility up and down reserves are provided by the generator ramp 
capacity. However to quantify the system readiness is best through the sub-hourly simulations with the 
flexibility up and down deployment. 
Energy Exemplar performs a few renewable generation integration studies using the 3-stage DA-HA-RT 
sequential simulation approach. This approach can be illustrated in the following flow-chart. 
Hourly DA SCUC/ED 
Simulation in 24 hours 
24-hour Unit 
Commitment 
Schedules for 
Long-starts 
Hourly DA SCUC/ED 
Simulation with five hours 
look-ahead 
Unit Commitment 
for all generators 
5-min RT SCED Simulation 
with 5-min look ahead 
DA Forecasted 
Load/Wind/Solar 
HA Forecasted 
Load/Wind/Solar 
Sub-hourly “Actual” 
Load/Wind/Solar 
Contingency, Flex and 
Regulation Reserve 
Contingency, Flex and 
Regulation Reserve 
Contingency, Flex and 
Regulation Reserve 
The 3-stage DA-HA-RT sequential simulation approach is described as follows. 
• PLEXOS DA simulation mimics the DA Security Constrained Unit Commitment and Economic 
Dispatch (SCUC/SCED) 
- Day-ahead forecasted load/wind/solar generation time series are used; 
- Hourly simulation interval; 
- The SCUC/ED optimization window is one day plus a few hour look-ahead; 
- The transmission network is modelled at the zonal or nodal level; 
- The contingency, DA flexibility / regulation up and down reserves are modelled. 
• PLEXOS HA simulation mimics the intra-day or Hour-ahead SCUC/SCED 
- 3-hour-ahead forecasted load/wind/solar generation time series are used; 
- Hourly simulation interval; 
- The SCUC/ED optimization window is a few hours plus a few hour look-ahead; 
- The transmission network is modelled at the zonal or nodal level; 
- The contingency, 3-HA flexibility / regulation up and down reserves are modelled; 
- The unit commitment patterns from the DA simulation for the long start up generators are frozen; 
energyexemplar.com Page 34
• PLEXOS RT simulation mimics the 5-min real-time SCED 
- The “actual” 5-min load/wind/solar generation time series are used; 
- 5-min simulation interval; 
- The SCUC/ED optimization window is a few 5 minutes plus a few 5-min look-ahead; 
- The transmission network is modelled at the zonal or nodal level; 
- The contingency and regulation up / down reserves are modelled. However, the flexibility up and 
down reserves are not modelled. The implication is that the capacity held in the 3-HA simulation 
for the flexibility reserves is deployed to cover the load and renewable generation variability and 
uncertainty at the 5-min interval; 
- The unit commitment patterns from the DA simulation for all generators, except the peaking 
generators, are frozen. 
The solutions from the 5-min RT simulation will include the over-generation, un-served energy, 
contingency and regulation reserve shortfall. Usually the non-zero values of these indices indicate the 
system is not completely ready for the renewable generation or the inadequacy of the system ramp 
capacity. In addition, the 3-stage Da-HA-RT sequential simulation approach can be used to quantify 
the effectiveness of the system operation procedure evolution, new products, etc. 
Energy Imbalance Market 
One of the effective operation procedure is the Energy Imbalance Market (EIM). In a EIM, each BAA in 
the EIM performs the DA and HA Security Constrained Unit Commitment and Dispatch to minimize its 
production cost. However, at the sub-hourly level, the members of the EIM will provide the generation 
ramp capacity in a form of sub-hourly bidding quantity and price. The generation ramp capacity will 
cover the sub-hourly load and renewable generation uncertainty and variability in the EIM in an 
economic manner. Therefore, EIM allows the generation and flexibility and regulation reserve provision 
sharing at a sub-hourly interval to cover the renewable generation variability and uncertainty with the 
minimum cost. For the details of the EIM studies and VGS studies, please refer to the project reports. 
To evaluate the benefit of the EIM, the sub-hourly RT simulation in the 3-stage DA-HA-RT sequential 
simulation is performed twice: the Business As Usual (BAU) and EIM. In the sub-hourly RT simulation for 
the BAU case, the hourly interchange between the BAA’s from the HA simulation are frozen to mimic the 
current BAA operation practice. In the sub-hourly RT simulation for the EIM case, the constraints of the 
hourly interchange between the BAA’s is relaxed to allow the sub-hourly interchange among the 
members of the EIM. The produce cost difference of these two simulations is the benefit of the EIM. 
Testimonial 
“For the last four years I used Energy Exemplar’s PLEXOS modelling tool. This has, for the first time, 
allowed for the effects of increasing amounts of renewable non-synchronous generation to be analysed 
in terms of costs, curtailment and system services availability in the future electricity systems of Western 
Europe.” 
Edward Mc Garrigle 
Bord Gais Energy 
Europe 
energyexemplar.com Page 35
L e a d i n g t h e f i e l d i n 
E n e r g y M a r k e t M o d e l l i n g 
Roseville 
Hartford 
London 
Johannesburg 
Clients Adelaide 
Of f ices 
Energy Exemplar Pty Ltd 
Software Development Office 
17 Bagot St 
North Adelaide 
SA 5006, Australia 
+61 8 8361 9312 
info@energyexemplar.com 
Energy Exemplar LLC 
West Coast USA Office 
Suite 120, 3013 Douglas Blvd 
Roseville, CA 95661 
United States of America 
+1 916 722 1484 
westcoastusa@energyexemplar.com 
Energy Exemplar Ltd 
Europe Office 
Building 3, Chiswick Park 
566 Chiswick High Road 
Chiswick, London, W4 5YA 
United Kingdom 
+44 208 899 6500 
europe@energyexemplar.com 
Energy Exemplar LLC 
East Coast USA Office 
20 Church Street, Ste. 790 
Hartford, CT 06103 
United States of America 
+1 860 461 0761 
eastcoastusa@energyexemplar.com 
Energy Exemplar Pty Ltd 
Africa Office 
West Tower Nelson Mandela Square 
Cnr 5th & Maude Street 
Sandton, 2196 
Johannesburg, South Africa 
+27 11 881 5889 
africa@energyexemplar.com 
e n e r g y e x e m p l a r . c o m

More Related Content

What's hot

Introduction to energy storage
Introduction to energy storageIntroduction to energy storage
Introduction to energy storagePhilip Fischer
 
Solar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridSolar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridMD Jannatul Giyem
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingBIJAY NAYAK
 
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...How To Apply Energy Storage Technologies In Commercial And Industrial Applica...
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...Davide Bonomi
 
Renewable energy grid integration
Renewable energy grid integrationRenewable energy grid integration
Renewable energy grid integrationRCREEE
 
Virtual Power Plants: Decentralized and Efficient Power Distribution
Virtual Power Plants: Decentralized and Efficient Power DistributionVirtual Power Plants: Decentralized and Efficient Power Distribution
Virtual Power Plants: Decentralized and Efficient Power DistributionShafkat Chowdhury
 
Electricity Markets Regulation - Lesson 8 - Pricing
Electricity Markets Regulation - Lesson 8 - PricingElectricity Markets Regulation - Lesson 8 - Pricing
Electricity Markets Regulation - Lesson 8 - PricingLeonardo ENERGY
 
Solar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxSolar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxNiuru Ranaweera
 
Peer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchainsPeer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchainsLeonardo ENERGY
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load schedulingMayank Sharma
 
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITS
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITSSMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITS
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITSiQHub
 
Smart grid and micro grid
Smart grid and micro gridSmart grid and micro grid
Smart grid and micro gridPurna chandar
 

What's hot (20)

Introduction to energy storage
Introduction to energy storageIntroduction to energy storage
Introduction to energy storage
 
Solar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridSolar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro grid
 
Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...How To Apply Energy Storage Technologies In Commercial And Industrial Applica...
How To Apply Energy Storage Technologies In Commercial And Industrial Applica...
 
Renewable energy grid integration
Renewable energy grid integrationRenewable energy grid integration
Renewable energy grid integration
 
Virtual Power Plants: Decentralized and Efficient Power Distribution
Virtual Power Plants: Decentralized and Efficient Power DistributionVirtual Power Plants: Decentralized and Efficient Power Distribution
Virtual Power Plants: Decentralized and Efficient Power Distribution
 
Economic load dispatch
Economic load  dispatchEconomic load  dispatch
Economic load dispatch
 
Electricity Markets Regulation - Lesson 8 - Pricing
Electricity Markets Regulation - Lesson 8 - PricingElectricity Markets Regulation - Lesson 8 - Pricing
Electricity Markets Regulation - Lesson 8 - Pricing
 
Solar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxSolar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptx
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
Peer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchainsPeer-to-peer energy trading using blockchains
Peer-to-peer energy trading using blockchains
 
Renewable energy and storage
Renewable energy and storageRenewable energy and storage
Renewable energy and storage
 
Electric markets
Electric marketsElectric markets
Electric markets
 
Optimal load scheduling
Optimal load schedulingOptimal load scheduling
Optimal load scheduling
 
Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System Integration of Renewable Distributed Generators in Distribution System
Integration of Renewable Distributed Generators in Distribution System
 
Microgrid Solar
Microgrid SolarMicrogrid Solar
Microgrid Solar
 
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITS
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITSSMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITS
SMART CHARGING, V1G AND V2G – POSSIBILITIES AND BENEFITS
 
Restructuring
RestructuringRestructuring
Restructuring
 
Smart grid and micro grid
Smart grid and micro gridSmart grid and micro grid
Smart grid and micro grid
 

Similar to PLEXOS applications

Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Power System Operation
 
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Power System Operation
 
What are Balancing Services in power system
What are Balancing Services in power system What are Balancing Services in power system
What are Balancing Services in power system Power System Operation
 
P20021 enel-x-monetizing-energy-assets-e book
P20021 enel-x-monetizing-energy-assets-e bookP20021 enel-x-monetizing-energy-assets-e book
P20021 enel-x-monetizing-energy-assets-e bookWalterLopez553897
 
Reinforcement learning for electrical markets and the energy transition
Reinforcement learning for electrical markets and the energy transitionReinforcement learning for electrical markets and the energy transition
Reinforcement learning for electrical markets and the energy transitionUniversité de Liège (ULg)
 
01012010 demand response
01012010 demand response 01012010 demand response
01012010 demand response miguelazo84
 
Utility ownership of combined heat and power an economic model based approach
Utility ownership of combined heat and power an economic model based approachUtility ownership of combined heat and power an economic model based approach
Utility ownership of combined heat and power an economic model based approacheSAT Journals
 
Electricity Market Day 2015 - Colas Chabanne, ENTSO-E WG Market Design and ...
Electricity Market Day 2015 -  Colas Chabanne, ENTSO-E  WG Market Design and ...Electricity Market Day 2015 -  Colas Chabanne, ENTSO-E  WG Market Design and ...
Electricity Market Day 2015 - Colas Chabanne, ENTSO-E WG Market Design and ...Fingrid Oyj
 
Executive summary Utilities opportunity and betterment
Executive summary Utilities opportunity and bettermentExecutive summary Utilities opportunity and betterment
Executive summary Utilities opportunity and bettermentSagar Zilpe
 
That's our forecast 2007
That's our forecast 2007That's our forecast 2007
That's our forecast 2007TCLABZ.com
 
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET Journal
 
Electric Distribution Grids in a 21st Century Energy System
Electric Distribution Grids in a 21st Century Energy SystemElectric Distribution Grids in a 21st Century Energy System
Electric Distribution Grids in a 21st Century Energy SystemLorenzo Kristov
 
Global Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesGlobal Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesCTRM Center
 
Fuel Cells for Residential, Commercial and Military Power
Fuel Cells for Residential, Commercial and Military PowerFuel Cells for Residential, Commercial and Military Power
Fuel Cells for Residential, Commercial and Military PowerReportsnReports
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaAmitava Nag
 
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Power System Operation
 

Similar to PLEXOS applications (20)

Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
 
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
Incorporating Electric Storage Resources into Wholesale Electricity Markets W...
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
What are Balancing Services in power system
What are Balancing Services in power system What are Balancing Services in power system
What are Balancing Services in power system
 
P20021 enel-x-monetizing-energy-assets-e book
P20021 enel-x-monetizing-energy-assets-e bookP20021 enel-x-monetizing-energy-assets-e book
P20021 enel-x-monetizing-energy-assets-e book
 
COMPETITIVE MARKET
COMPETITIVE MARKET COMPETITIVE MARKET
COMPETITIVE MARKET
 
Reinforcement learning for electrical markets and the energy transition
Reinforcement learning for electrical markets and the energy transitionReinforcement learning for electrical markets and the energy transition
Reinforcement learning for electrical markets and the energy transition
 
01012010 demand response
01012010 demand response 01012010 demand response
01012010 demand response
 
Utility ownership of combined heat and power an economic model based approach
Utility ownership of combined heat and power an economic model based approachUtility ownership of combined heat and power an economic model based approach
Utility ownership of combined heat and power an economic model based approach
 
Electricity Market Day 2015 - Colas Chabanne, ENTSO-E WG Market Design and ...
Electricity Market Day 2015 -  Colas Chabanne, ENTSO-E  WG Market Design and ...Electricity Market Day 2015 -  Colas Chabanne, ENTSO-E  WG Market Design and ...
Electricity Market Day 2015 - Colas Chabanne, ENTSO-E WG Market Design and ...
 
Executive summary Utilities opportunity and betterment
Executive summary Utilities opportunity and bettermentExecutive summary Utilities opportunity and betterment
Executive summary Utilities opportunity and betterment
 
That's our forecast 2007
That's our forecast 2007That's our forecast 2007
That's our forecast 2007
 
Future Design of Electricity Markets
 Future Design of Electricity Markets Future Design of Electricity Markets
Future Design of Electricity Markets
 
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
IRJET- Demand Response Optimization using Genetic Algorithm and Particle Swar...
 
Electric Distribution Grids in a 21st Century Energy System
Electric Distribution Grids in a 21st Century Energy SystemElectric Distribution Grids in a 21st Century Energy System
Electric Distribution Grids in a 21st Century Energy System
 
Global Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM CapabilitiesGlobal Renewables Transition Requires Dedicated ETRM Capabilities
Global Renewables Transition Requires Dedicated ETRM Capabilities
 
MESC comments to MISO
MESC comments to MISOMESC comments to MISO
MESC comments to MISO
 
Fuel Cells for Residential, Commercial and Military Power
Fuel Cells for Residential, Commercial and Military PowerFuel Cells for Residential, Commercial and Military Power
Fuel Cells for Residential, Commercial and Military Power
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in India
 
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
 

Recently uploaded

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 

Recently uploaded (20)

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 

PLEXOS applications

  • 1. PLEXOS A P P L I C A T I O N S ®
  • 2. Contents Market Analysis Page 3 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Portfolio Optimization Page 7 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Reliability Analysis Page 11 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Capacity Expansion Planning Page 15 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Hydro Optimization Page 19 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Transmission Analysis Page 24 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Gas System Planning Page 28 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣ Renewable Generation Integration Page 32 ̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣̣
  • 3. Market Analysis In the past, the US electricity markets were characterized by vertically integrated and monopolistic electric utilities. These utility companies owned the generation, transmission and distribution networks and electric rates were reviewed and approved by public utility commissions or public boards. However, in the past couple of decades, these vertically integrated structures have been replaced by regional wholesale markets. A number of regions, including the Northeast (NYISO, ISO-New England), Mid-Atlantic (PJM Interconnection), much of the Midwest (Midwest ISO and Southwest Power Pool), Texas (ERCOT) and California (CAISO) - organize their markets under an independent system operator (ISO) - sometimes also referred to as a regional transmission organization (RTO). By adopting this ISO/RTO structure, these regions have moved to expand competition in electricity from the vertically integrated to a competitive markets for energy, capacity and ancillary products. In fact, two-thirds of the electricity consumed in the U.S. are provided an ISO/RTO. Other regions - including the Southeast (FRCC, SERC, TVA), Inter-Mountain West and Northwest - chose to retain the traditional regulatory model. Under this regime, vertically-integrated utilities retain functional control over the transmission system and therefore choose which generator is dispatched to serve load. Some argue that such a model has led to preferential treatment by these utilities for their own generation rather than more affordable and environmentally responsible generation available from competitive suppliers and marketers. U.S. natural gas markets are also highly competitive. Natural gas market prices are determined competitively on spot and futures markets reflecting current and expected supply and demand conditions. The market price is determined through the actions of thousands of well-informed buyers and sellers. U.S. natural gas markets comprises of Midwest, Northeast, Gulf, Southeast and Western gas regions. ISO Market Structure and Products The energy markets operated by ISO’s US typically include a two settlement market: day ahead market, or financial commitment, and a real time or spot market. The day-ahead allows generators to reasonably know whether they will be committed at least 12 hours before the start of the electric day. Day ahead commitments are similar to a binding forward financial contract, where generators are financially responsible for their dispatch the day prior. If they are unable to meet the dispatch in the real time, or spot market, generators would have to purchase the difference between their day-ahead and real time positions. The day-ahead market is normally an hourly market while the real time or spot market is normally a 5 minute market (prices are settled and posted every 5 minutes). Generators bid into both the day-ahead and real time markets using a bid curve to approximate their marginal costs (typically their fuel and some notional operating costs). They are also allowed to provide start-up costs for their commitment as well as minimum up and down times. All of these factors are included in the algorithms established by the ISO to calculate the hourly price of electricity. The price is set by the most expensive unit in the generator bid stack or the marginal unit. energyexemplar.com Page 3
  • 4. In addition to the day-ahead and real time energy markets, which indicate the price of energy required to serve electric load over time, ISO’s have also devised their markets to provide locational price signals as well. In this case, ISO’s operate a nodal electric market where the price of energy is determined by the availability of transmission to deliver electricity across the network. In areas where there is insufficient transmission to deliver all of a region’s demand, prices tend to increase to reflect the increased costs to supply load. This is also known as congestion pricing. In the end, prices for electricity are published both across time as well as across the network in which the ISO operates. These prices are fully transparent and provide all market sectors the appropriate signals about the available supply and demand of electricity. Generators in the ISO operated markets submit bids which are typically capped at a certain or prescribed level (roughly $1000 to $1200/MWh). As generators bids are capped and therefore they are less likely to recoup their fixed costs in the energy market, ISO also provide generators with a capacity market. These capacity markets are conducted in a bid auction for the right to supply generation capacity. Generators are paid to be able to meet certain reliability criteria. These markets should also provide sufficient incentive for new generation to enter the market, particularly when capacity and energy prices increase over time. Generators also bid into different ancillary services markets. These could include regulation, spinning reserve, non-spinning or non-synch reserve and replacement reserves. Lastly, the ISO also operate and manage the high voltage transmission network. Financial transmission rights (FTR) / Congestion Revenue Rights (CRR) market. PLEXOS® Integrated Energy Model The markets served by ISO’s have grown increasing complex. With this complexity requires new software tools for market participants of the deregulated markets. PLEXOS provides of software solution to match the complexities. PLEXOS offers multiple horizon simulations, including sub-hourly, to be able to model both the day-ahead and real time spot markets. PLEXOS supports multiple spatial analyses, from a full nodal network model to a zonal or regional model. As such, it is capable of calculating the system marginal price, transmission congestion costs and losses, and other market metrics published by the ISO’s. PLEXOS offers the same algorithms that the ISO use to dispatch their markets and is often used by the ISO themselves for internal and external market studies. Users of PLEXOS can create a multi-band bid and offer curves for both generation and demand. They can create unit commitment constraints to match actual market decisions including minimum generation, start costs and minimum up and down times. PLEXOS allows generation bid caps as well as the regional price of value of loss load (VoLL). All of PLEXOS’s feature rich properties allow users to capture the complexities of the US deregulated electricity markets in a single software platform. energyexemplar.com Page 4
  • 5. Additional properties available in PLEXOS to address the deregulated electricity markets as operated by the ISO’s are outlined in the table below. Planning Objectives PLEXOS Capability Renewables Integration and System Flexibility Requirement Assessments Least Cost Resource Change within and Across Regions Minimizing production costs and consumer costs to electricity and natural gas rate payers Sizing Natural Gas Network Components and Natural Gas Storage Environmental Policies Integrated Reliability Evaluation • Sub-Hourly Co-Optimization of Ancillary Services with Energy Market and Transmission Power Flows • Stochastic Optimization and Stochastic Renewables Models • PHEV, EE, DR, SG, Energy Storage Models • Co-Optimization of Generation and Transmission Expansion • Generation Retirements and Environmental Retrofit Models • Reliability Evaluation • Co-Optimization of Production cost of Electrical and Natural Sectors • Electrical Network Contingencies and Natural Gas Network Contingencies • Co-Optimization of Natural Gas Network Expansion along with Electricity Sector Expansion • Electrical Network Contingencies and Natural Gas Network Contingencies • Co-Optimization of Annual and Mid-Term constraints • Integrated Reliability Evaluation to Ensure LOLE and other Metrics Maintained with Co-Optimization of Electric and Gas Sector Expansion or True Monte Carlo US PLEXOS® Integrated Datasets for Power and Natural Gas Sector Challenges In the past few years there has been a convergence in environmental policy and public policy, in combination with recent shale gas developments which have combined to increased reliance of the power sector on natural gas generation. As a result, gas and electric coordination has emerged as a complex topic for regulators and market operators with concerns of potential gas constraints that impact electric system operation and reliability. Many studies have been initiated for gas electric coordination in the major interconnects (Eastern Interconnect, ERCOT and WECC) of the US. Furthermore, integration of renewables have driven Integrated Resource Plan (IRP) managers and ISO’s to consider sub-hourly ancillary co-optimization analysis in production cost models for major areas of the US. Thus the study process and the complexity of issues is driving the demand for integrated datasets and integrated models. In other words, one software package that can handle all the complexities of planning and operations and market analysis in the short, medium and long term. Energy Exemplar has developed integrated datasets serving North America, combining both a nodal electric model as well as the natural gas network. We have three separate electric interconnection models, the Eastern Interconnect (EI), Texas (ERCOT) and the Western Interconnect (WECC). On top of these three models is a gas model serving North America. The gas network includes the full scope of gas production and transportation system, from well head or production field to natural gas pipelines, storage and end user demands. energyexemplar.com Page 5
  • 6. The intersection of these two models is the natural gas fired electric generator. With the combination of the gas electric dataset into a single model by PLEXOS, users can evaluate the combination of gas constraints on the electric system, particularly in the winter when natural gas demand peaks, as well as the interaction of price between the electric and gas models. Planning Objectives PLEXOS Capability Production Cost Annual Environmental Constraints Mid Term Optimization Capacity Expansion Planning Reliability Evaluation Generation Characteristics Electrical Network Data Natural Gas Network Data Demand and Energy Shapes Fuel Prices Hurdle and Wheeling Rates Constraints Others Energy Constraints Mid Term Optimizations Others Integrated Planning Database in PLEXOS Generator Costs Transmission Line Costs Pipeline Costs Gas Storage Costs Energy Efficency Cost Curve Demand Shapes Others Single Database Facilitates Multiple Types of Studies FOR Transmission FOR Generation FOR Gas Pipeline Renewable Variability and Uncertainties Demand Uncertainty Others Testimonial “I've only been using PLEXOS for a couple of months, but I'm very excited about the flexibility and ease with which I can test a wide variety of different scenarios. By only supplying key inputs I get surprisingly accurate results, which I can confidently stand behind. So far PLEXOS has had more to offer than I've needed, and each time when I run into a dead end I get quick responses with from a diligent technical support.” Jacobus Swart NamPower Africa energyexemplar.com Page 6
  • 7. Portfolio Optimization Portfolio Optimization includes the following four activities. 1. Operation. On a daily basis, the operators in the control center (or on the trading floor) solve unit commitment and economic dispatch problems to minimum system costs while maximizing the profit from trading with neighbouring utilities or markets. 2. Generating Asset Evaluation. Examples of generating assets include generators, energy contracts, demand response programs, energy storage units, etc. Performing the Generating Asset Evaluation involves quantifying the value of generating assets. Simulations both with and without the generating asset are performed for the technical life time of the generating asset. Then, the generating asset value is calculated as the production cost difference between the solutions with and without the generating asset. Generating Asset Evaluation can also be used to examine the difference between the generating asset operation and the energy and Ancillary Service markets. 3. Budgeting. Portfolio simulation can be used to predict the production cost, fuel consumption, traded energy, emission production, etc. Solutions can then be used to support decisions on rate design, fuel procurements, emission allowance allocation, etc. 4. Long-term Capacity Expansion. Long-term Capacity Expansion planning can be done using simulations that determine optimal generation or transmission facility investment (or retirement) to meet projected load growth while still complying with reliability criteria, emission limits, renewable energy portfolio standard (RPS), etc. Portfolio Optimization by PLEXOS® PLEXOS solves Portfolio Optimization problem using the Security Constrained Unit Commitment (SCUC) and Economic Dispatch (ED) algorithm. This algorithm makes use of Mixed Integer Programming (MIP) to minimize a cost function subject to all operational constraints. The cost function may include the generating cost, generator startup and shutdown costs, sales contract revenue, purchase contract cost, energy or AS market sales revenue and purchase cost, transmission wheeling charges, etc. The constraints can include things such as energy balance (i.e., at any moment, the generation plus purchase are equal to the load plus sales), AS requirements, generating asset chronology (i.e., min up / down time, ramp rate, energy resources (i.e., energy limits, fuel limits, emission limits, water limits), transmission limits, etc. For example, Portfolio Optimization can be formulated as follows: Minimize Portfolio Production Cost = generator fuel and VOM cost + generator start cost + contract purchase cost – contract sale saving + transmission wheeling + energy / AS / fuel / capacity market purchase cost – energy / AS / fuel / capacity market sale revenue Subject to • Energy balance constr aints • Operation reserve constraints • Generator and contr act chronological constraints: ramp, min up /down, min capacit y, et c. energyexemplar.com Page 7
  • 8. • Generator and contract energy limits: hourly / daily / weekly / … • Transmission limits • Fuel limits: pipeline, daily / weekly/ … • Emission limits: daily / weekly / … • Others The PLEXOS MIP algorithm solves the Portfolio Optimization problem by simultaneously obtaining optimal solutions to unit commitment, economic dispatch, contract exercise, and market activates. This approach produces what is called “ co-optimization” solutions. Combined Cycle Generator Modeling Due to the nature of the MIP formulation, the combined cycle generator can be modelled precisely using its components, i.e., gas turbine generators and steam turbine generator. For example, the following chart illustrates the 2x1 combined cy cle generator representation in PLEX OS. Each component, the gas turbine generators and the steam turbine generator, is modelled as a regular generator. The red line in the chart represents the waste heat transfer from the gas turbines to the Heat Steam Recovery Generator (HSRG), and is modelled as a constraint in the PLEXOS MIP formulation. Then, the PLEXOS unit commitment and economic dispatch algorithm can be used to determine the best operational mode t o minimize the portf olio production cost of this sy stem. PLEXOS® LT-PLAN - Long-term Capacity Expansion Long-term (LT ) Capacity Expansion determines optimal investment decisions over long period of time, usually up to 30 years. The PLEXOS LT-PLAN module accomplishes this by minimizing the Net Present Value of forward-looking investment costs and the portfolio production cost. Therefore, the portfolio cost minimization problem is expanded to include the investment cost and the investment-related constraints as f ollows: Minimize Portfolio Production Cost + In vestment Cost S ubject to • Portfolio operation constraints • Investment Constraints energyexemplar.com Page 8
  • 9. Here, Investment Cost may include cost of new generator builds, cost of transmission expansion, and/or cost of generator retirements. The Investment Constraints may include regional capacity reserve margins, resource addition and retirement candidates (i.e. maximum units built / # retired), technical and financial life spans, technology / fuel mix rules, Renewable Portfolio standard (RPS), etc. The build and retirement candidates might include thermal generators, geothermal generators, hydro or pumped storage hydro generators, wind or solar generators, transaction and demand side participation, transmission augmentations, or generator retrofits. The PLEXOS LT-PLAN solution is illustrated by the following chart. The x-axis corresponds to the investment and the y-axis corresponds to the cost. As the investment increases, the production cost, P(x), decreases (blue line) and the capital cost, C(x) increases (green line). The total cost (red line) is the sum of the capital and production costs, C(x) + P(x). The PLEXOS LT–PLAN simulation returns the optimal investment decision (x*) while observing the investment and operational constraints. Total Cost C(x) + P(x) Optimal Investment x* Capital Cost C(x) Investment x Cost ($) Production Cost P(x) Stochastic Simulations to Incorporate Risk In the portfolio optimization, risk is an important consideration in the corporate decision-making environment. To incorporate risk, PLEXOS uses stochastic simulation to produce solutions with a statistic distribution for a given set of the stochastic drivers, such as fuel prices, load forecast, renewable generation profiles, market prices, etc. These stochastic drivers can be specified in PLEXOS exogenously, i.e., the user provides the stochastic time series, or endogenously, i.e., PLEXOS produces the stochastic time series for the stochastic drivers based on parameters provided by the user. For example, the following chart shows a weekly gas price distribution over one hundred samples. energyexemplar.com Page 9
  • 10. Here, the first four bars represent the maximum value, minimum value, standard deviation, and mean value over the one hundred gas price samples. The remaining bars represent the one hundred samples. For the given stochastic driver time series, PLEXOS performs multiple iterations of simulations and produces multiple iterations of solutions. The following histogram shows the distribution of portfolio production costs for a week over the stochastic drivers of gas price, load forecast and market price forecast. The chart shows that the mean production cost in this week is about $180 million with a worst case scenario of $260 million and a best case scenario of $161 million. The distribution of the weekly production cost provides value insight to the corporate decision makers. Testimonial “Wärtsilä has used PLEXOS successfully for several years now. Purpose of our modelling work is to quantify the value of flexibility for power systems and for individual customer portfolios. The studies have clearly identified the need of more flexible generating resources in the future. Also, Energy Exemplar’s willingness to develop the software, based on our needs, is highly appreciated”. Ville Rimali Wärtsilä Europe energyexemplar.com Page 10
  • 11. Reliability Analysis The PLEXOS simulator is a powerful tool for performing reliability studies on electric power systems. The simulator can calculate the standard metrics of LOLP, LOLE, EDNS and EENS from the PASA simulation phase using convolution. However, PLEXOS can also use the detailed chronological simulation of ST Schedule to produce the same metrics via Monte Carlo. Energy Exemplar adopted this approach in the valuation of Loss of Load Expectation (LOLE) for the market operated by ISO-New England, which covers the six states of New England in the north-eastern US. The following describes this approach we used with PLEXOS. How to setup PLEXOS® for Reliability via Monte Carlo In a reliability study we are only interested in whether or not the system can meet the electric load, and possibly ancillary services requirements, given all generation technical, transmission, fuel availability and other user-defined constraints. The dispatch order of generators and the system marginal price is not useful and thus we can simplify the simulation by removing all costs apart from the pseudo cost of unserved energy (Value of Lost Load or VoLL). To do so, simply mark all cost information with a Scenario and exclude that Scenario from your reliability Model run. Example of cost parameters include: • Generator [Heat R ate] and [Load P oint] • Generator [ VO&M Charge] • Fuel [Price] • Generator [Offer Price] Having done this, the simulation will be less complex, with the objective function containing only costs of unserved energy, dump energy and perhaps reserve shortage. Loss of Load Expectation (LOLE) Normally we compute the Loss of load probability (LOLP) as a reliability metric. This is a measure of the probability that demand will exceed the capacity of the system in a given period and is expressed as a percentage. As noted above, the periods when demand exceeds supply is a shortage event. An alternative metric is the Loss of Load Expectation (LOLE), which is the number of days of outage or the number of times in a given period that the load will be greater than the demand. This can be expressed as LOLE = LOLP * N/24. A value of 1.0 LOLE over a single year signifies multiple periods or hours over the year in which there were shortages. It is unlikely these shortages occurred in a single day but likely over multiple hours over several or more days. We used the Monte Carlo feature in PLEXOS to calculate the probability of the LOLE for each load probability forecast in the New England. The first calculation was to benchmark the ISO-New England Installed Capacity Requirement (“ICR”) calculation for the study period, or in this case the 2017 Peak Load Forecast. The following demand forecast from ISO-NE’s ICR report (see Table 1 below) was used for this analysis. energyexemplar.com Page 11
  • 12. Table 1 We then performed a LOLE calculation with an average load-weighted risk approach. We prepared a range of 16 different installed capacity levels in the ISO-NE control area and for each capacity level evaluated the average load weighted LOLE at each of the above 10 load probabilities in Table 1. The following figure, shows the demand distribution on the y-axis and the capacity distribution on the x-axis. There are a total of 160 capacity and demand pairs in the following chart for which we computed the average load weighted LOLE for using PLEXOS. Figure 1 Then we prepared an average load weighted LOLE calculation for the 10 load probabilities for each capacity point and derived 16 average load weighted LOLE’s as a function of installed capacity for the ISO-NE control area. We derived a value of LOLE at the ISO-NE Net Installed Capacity Requirement (NICR) value of 0.1 day per year which is consistent with reliability criteria for NICR. With the 16 LOLE calculations we were also able to compute the cost of lost load at each installed capacity level using the PLEXOS 8,760 hour time series simulation. PLEXOS estimates Unserved Energy (USE) at each hourly interval if demand is greater than generation, or a shortage event. energyexemplar.com Page 12
  • 13. This can happen primarily in summer months with reduced thermal generator capacities in combination with load risk and forced generator outages. We then approximated the Value of Lost Load (VoLL). For this analysis, we assumed a VoLL $20,000/MWh. Figure 2, below, displays an example time series path of one of the load weighted risk replications for the 8760 hour simulation performed. We charted the cost of lost load in millions of dollars, which is the result of multiplication of the USE at each interval as described above by the value of VoLL selected above. Figure 2 In Figure 2, the show an example of the 8760-hour simulation path for the peak demand and installed capacity pair with the cost of unserved energy is displayed on an hour by hour basis in millions of dollars. We ran 160 of these paths using Monte Carlo simulation and then took an average load weighted cost of lost load across the demand risk for each of the 16 installed capacity values. energyexemplar.com Page 13
  • 14. Figure 3, below displays a curve of the LOLE calculations as a function of percent of Net Installed capacity Requirement (“NICR”) for the New England Control Area as well as the cost of lost load as a function of percent NICR. Figure 3 Figure 3 shows that the system LOLE reliability metric degrades rapidly for installed capacity values below NICR. Also, the cost of lost load increases rapidly below NICR. Testimonial "I have been using PLEXOS to study the impact of wind and solar variability on power system reliability, both for thermal and hydrothermal systems. PLEXOS makes quite easy to run Monte Carlo simulations and to define different modelling scenarios. Its flexibility has allowed us to evaluate how operational aspects such as solar and wind profiles, transmission constraints, hydro inflows, operational reserve levels, and energy storage may impact the adequacy contribution of variable generation." Professor Esteban Gil Universidad Federico Santa Maria South America energyexemplar.com Page 14
  • 15. Capacity Expansion Planning Flexible power generation and interconnection capacity needs of the Italian power system using PLEXOS® LT plan One of the main developments of the last few years on the Italian power market has been the significant increase of renewable capacity in the form of wind and solar power plants. Using a PLEXOS dataset based on data available from Terna and various utilities, we have modelled the Italian power market through the six geographical zones and considered the medium term expected scenarios. The Southern zones (namely South, Sicily and Sardinia), already characterised by a significant amount of renewable capacity, are expected to experience the largest concentration of renewable development. In addition, these regions are characterised by a relative lower level of interconnection with neighboring countries compared to the Northern zones. Given the variability introduced on the system by the increasing renewable capacity and the relative isolation of the Southern zones, the deployment of flexible power plants and the expansion of interconnection capacity are assessed using the PLEXOS Long Term (LT) Plan feature. This feature, designed for long term optimal investment analysis, provides useful insights about potential bottlenecks, system flexibility and power prices, and is a critical tool for analysts, researchers, regulatory and utility decision makers to evaluate network adequacy and expansion, security of supply, investment options and energy policy development. Introduction and Model Description The power market simulation and analysis software PLEXOS® Integrated Energy Model has been used to represent the Italian power market in 2012 and its development in the medium term, considered up to the year 2017. Energy Exemplar built a dataset including all the relevant plants within each geographical market zone in 2012, with the poles of limited production aggregated to the surrounding geographical zones as: BRNN, FOGN and ROS to the SUD zone, and PRGP to the SICI zone. Figure 1: Geographical zones of the Italian power market. Installed capacities of conventional plants and aggregated figures of renewable generators are obtained from Terna reports, utilities websites and ENTSO’s Scenario Outlook & Adequacy Forecasts reports. Such capacities cover the year 2012 and extend up to 2018. In addition, for each technology we have taken a representative set of operational characteristics (heat rates, ramp rates, start costs etc.) and applied it to each of the plants of that particular technology. Renewable generation profiles are obtained from the in-built PLEXOS® feature to create stochastic samples from a given profile, taken as the real 2012 data in this instance. energyexemplar.com Page 15
  • 16. The long term country demand profiles, and zonal profiles for Italy, were built using the 2012 hourly values and the PLEXOS in-built load forecasting feature that uses a given base profile, annual peak and energy demand forecasts; such a procedure was applied to each of the countries included in the model (Italy, France, Switzerland, Austria, Slovenia, Albania, Montenegro and Greece). The aim of this study was to assess the need for additional interconnector capacity or the development of flexible power plants, and for that reason we employed PLEXOS® Long Term (LT) Plan feature. Long Term Capacity Expansion Planning with PLEXOS® Assessing the risk and return of new investments both in new power plants and in the reinforcement of the transmission grid requires highly specialized tools. PLEXOS® Integrated Energy Model feature of Capacity Expansion refers to the problem of finding the optimal combination of generation new builds (and retirements) and transmission upgrades (and retirements) that minimizes the net present value (NPV) of the total costs of the system over a long-term planning horizon. That is, to simultaneously solve a generation and transmission capacity expansion problem and a dispatch problem from a central planning, long-term perspective. The optimization problem takes into account in the objective function two types of costs; capital costs (costs of new generator builds and transmission expansion costs) and production costs (costs of operating the system with any given set of existing and new builds and transmission network as well as the notional cost of unserved energy). The PLEXOS LT Plan phase by default spans the whole simulation planning horizon in a single optimization 'step', while it gives the user the option to control the type of chronology used, and choose between preserving the full chronology (Fitted chronology) or using the partial chronology (Load duration curves, LDC). Results and Discussion In this case study we define generator and transmission expansion candidates which PLEXOS will assess in order to give the optimal solution. Therefore, in the inputs we define the optional investments to be either the expansion of the existing interconnectors (with France, Switzerland, Slovenia and Greece) or the building of new ones (with Croatia, Montenegro and Albania), as per Terna development plans. In addition, we give PLEXOS the option to select to build new CCGT, GT or ST power plants in all of the 6 Italian zones. The optimal solution as calculated by the PLEXOS LT Plan shows that between 2015 and 2017 all the existing interconnectors used to import electricity into the country are congested most of the time (see Figure 2); the list includes those with France, Switzerland, Austria and Slovenia and excludes only the one with Greece, which is operating mainly for export. Figure 2: Congestion of interconnectors with Northern neighbour countries energyexemplar.com Page 16
  • 17. Given the need for more interconnector capacity, the PLEXOS solution is to build an interconnector linking the South zone with Albania. This interconnector is indeed in the Terna plans and the PLEXOS result is well suited, given that most of the renewable capacity and therefore the greatest need for balance of intermittent generation is located in the South. Together with the security of supply constraint, which is met by this new build, the other critical parameter largely impacted by the availability of interconnection capacity is the price in the country. Given the limited horizon in the PLEXOS model compared to the typical economic lifetime of an interconnector project, further builds are prevented, as the cash-flow from the lower-cost imported electricity savings does not justify the investment. The net result is a higher power price compared to the neighbour countries. In addition to the interconnector with Albania, the PLEXOS optimization includes also the building of new CCGT plants in Sicily. This result is justified by the limited spare capacity of conventional plants on the island and represents a measure to prevent the prices to be too sensitive to the generation from renewables, as shown in Figure 3. Nevertheless, the price in Sicily is higher than in the rest of Italy, as shown in Figure 4, with significant peaks in the summer. The congestion of the interconnector with the mainland for most of the year suggests that an increased capacity might limit the price spread, but the cash-flow argument used for the interconnectors with neighbour countries applies also to the one between Sicily and the mainland. Figure 3: Effect of new-built CCGT plants on Sicilian power prices Figure 4: Comparison of power prices among the 6 Italian zones Another insight also obtained from the PLEXOS LT Plan results is the level of congestion of all of the interconnectors exporting electricity from the South zone, as shown in Figure 5. energyexemplar.com Page 17
  • 18. Figure 5: Congestion of interconnectors connected to the South zone Conclusions The Terna plans to increase these export capacities and the new interconnector with Albania described above, is a way to address the large imbalance between demand and supply, as shown in Figure 6. Such expansion would also avoid the significant cycling costs and low capacity factors of the conventional power plants in the region, thus mitigating their effect on the energy prices in the area with likely positive effects for all the country. Figure 6: Demand and supply in the South zone Testimonial "Since I started working with PLEXOS, I have been surprised of how powerful and useful it is. PLEXOS covers such extensive and accurate approach of modelling the market and provides different possibilities of modelling the different factors and drivers of the power market. I used PLEXOS to model different power markets across the world, every of which had their own particularities, which implies the difficulty of different approach when modelling. Thanks to such a powerful tool, the required knowledge and the incredibly great support from energy exemplar, every client case I used PLEXOS for the modelling part, the client happened to be very satisfied with the results and my company as well. I strongly recommend it to those new potential users thinking about joining the PLEXOS practice!” Elena De Juan Salgado Boston Consulting Group Europe energyexemplar.com Page 18
  • 19. Hydro Optimization Power systems having both hydro-electric and thermal generation require a systematic and coordinated approach in order to determine an optimal policy for dam operations. The goal of a hydro-thermal planning tool is to minimize the expected thermal costs along the simulation period. These types of problems generally require stochastic analysis to deal with inflow uncertainty. This can increase the mathematical size of the problem and can easily become cumbersome to solve. PLEXOS Integrated Energy Model offers many features to deal with the hydro-thermal coordination problem. In addition, it offers a seamless integration of phases, making it possible to determine an optimal planning solution in the medium-term and then use the obtained results in a detailed short-term unit commitment and economic dispatch (UCED) problem with increased granularity. For example, weekly targets as constraints filter down to produce hourly electricity spot prices. The Challenge The systematic coordination of a system composed of both hydro-electric and thermal plants requires determining an operational strategy that for each stage of the planning horizon produces a scheduling plan of generation. This strategy minimizes the expected operational cost along the period, which is mainly composed of fuel costs plus penalties for failure in load supply. The problem becomes complex to solve because generally in hydro systems: • Natural inflows ( by nature) are stochastic processes. • Availability of w ater stored in dams is limit ed. • There are complex cascading h ydro systems. • Water usage policies and en vironmental releases such as irrigation settlement s. Water as a fuel supply is cost-free, but its opportunity cost is fundamental to finding the optimal strategy for operations. This issue creates the need for a decision in a given time period. Storages can’t be drained too low, which might incur generation shortfalls or excessive thermal output. On the other hand, we also want to avoid spillage of water and lost generation opportunities. Figure 1 summarizes the dilemma a hydro power planner faces to operate a dam. Figure 1: Diagram showing the dilemma hydro power planner faces under uncertainty energyexemplar.com Page 19
  • 20. The Solution PLEXOS can find a hydro releasing policy that minimizes the expected thermal cost by formulating an optimization problem such as the following: Min {Variable Costs} Subject to: Energy Balance Equation FlowLimits GenerationLimits Hydro Balance: 1 The hydro balance equation shows the link between decisions in both the present and future. Since water is free (no fuel cost) it is necessary to specify a final condition so as to minimise thermal costs along the simulation period, and to avoid the storage being completely drained. These final conditions can be represented as a target or a proxy for opportunity costs such as a deviation from targets, usually known as the future cost function or scrap value function. To handle uncertainty in the inflows, PLEXOS offers stochastic optimization techniques in both 2-stage and multistage. Both techniques minimize the expected cost (or maximum benefits) of the system. PLEXOS® Features Explored MT and ST schedule To determine optimal targets or deviation targets, PLEXOS can analyse a longer horizon using Medium Term (MT) analysis and if the mathematical size of the problem is unsolvable a reduction in granularity (called demand blocks) can be applied to produce a mathematical problem that is faster to solve. Then the targets or deviation targets can be calculated from this optimal solution. This simplification produces an end volume at each block, then the MT problem passes the target or future cost function to each short term (ST) step so as to obtain a higher resolution release policy. Figure 2 shows an example of MT target (red line) and ST end volumes (blue area). energyexemplar.com Page 20
  • 21. Cascading Hydro with Storage and Waterways To create models of cascading hydro networks a combination of Storage, Waterway, and Generator objects can be used. PLEXOS offers the capability to model a cascading hydroelectric system like the one shown in Figure 3. Figure 3: Schematic representation of Storages and Waterways Storage objects are used to represent storage reservoirs with any storage capability or even simple junctions in a river-chain. Each storage can connect to one or more generators or waterways to create a model of a river chain. Waterway objects connect the storages or spill water from the storage 'to the sea'. Waterway flows can delay the water flow, can have bounds placed in their flows and can limit the rate of change in their flows. The Constraint class makes it possible to relate water flow rates and generator efficiencies to storage elevations. Pumped Storages Power Plants Pumped storage plants store energy in the form of water. Pumps move water from a lower elevation reservoir (the 'tail' storage) to a higher elevation ('head' storage). To optimise the operation of a pumped storage power plant, PLEXOS formulates an optimization problem to decide when to release and pump water in order to minimize costs (or maximize benefits). In general one should expect that low-cost off-peak electric power is used to run the pumps and during periods of high electric demand and high price, the stored water is released through turbines to generate power. Figure 4: Pumped Storage cycle. Generation left hand side and pumping right hand side energyexemplar.com Page 21
  • 22. Stochastic Optimization PLEXOS can find the best outcome given the uncertainty in inflows. The problem is summarized in Figure 1 and can be solved using a stochastic optimization formulation. PLEXOS offers a two stages and multistage optimization approach. The difference is that multistage techniques allows a re-evaluation of the policy after some time, the period when this happens is called a “Stage”. In a two-stage approach, the optimal policy is never re-evaluated because the information is not revealed at an intermediate stage during the simulation. These two types of problems are represented in the below scenario trees. Root 1st Period 2nd Period 2nd Stage Root 1st Stage 1st Period 2nd Stage 2nd Period Figure 5: Left hand side represent 2 Stages SO, right hand side represents multi stage SO Multi Stage Tree Reduction When using multistage stochastic optimization, a large number of possible scenarios can be generated. For such a high number of scenarios, it is impossible to numerically obtain a solution for the multi-stage optimisation problem. ... Root Stage 1 Stage 2 Stage 3 Stage T That number of scenarios is equal to: Branches_perStage(NStages) Example: 21 stages and 3 branches per node 321 = 1.04604 x 1010 Scenarios! This problem is impossible to solve Figure 6: Multi Stage dimensionality issue To help solve this problem, PLEXOS offers scenario reduction techniques. These techniques use strategies to reduce the number of scenarios in the optimization problem using algorithms for constructing a multi-stage scenario tree out of a given set of scenarios. Since generating a very small number of scenarios by Monte Carlo Simulations is not desired because less scenarios give less information, the objective is to lose minimum information by the reduction process applied to the whole set of scenarios. energyexemplar.com Page 22
  • 23. Case Study Results and Discussion The case study summarized in Figure 7 illustrates the application of stochastic techniques in the hydro planning problem. The power system under study consists of 3 Power plants and there are 12 possible inflow sequences. The objective is to find an optimal trajectory for the storage along 1 year. Max Cap = 40,000 MW Hydro Hydro Initial Volume = 10600 GWh Max Volume = 106200 GWh Min Volume = 1000 GWh Max Cap = 20,000 MW Coal Nuclear Max Cap = 12,000 MW Load Figure 7: Left hand side schematic of the Power System under study, Right hand side load profile Three simulations are performed: Deterministic, 2 Stage and Multistage. The optimal trajectories obtained are summarized in Figure 8. Figure 8: Comparison of Trajectories for deterministic, 2 stages and multistage (4 stages). 2 stages obtains one single trajectory as there is no chance to re-evaluate the decision through time. On the other hand, multistage perform a re-evaluation at each stage, therefore producing a set of optimal past dependant trajectories. The deterministic approach gives optimal trajectories for each sample but it is not capable of answering the question “what decision do I have to make now given the uncertainty in the inputs?” To evaluate the quality of the policies obtained, we can randomly select one of the policies, run the 12 inflow possibilities and calculate the expected costs. The results are summarised in Table 1. Deterministic (Fixed Targets) Expected Costs (Million $) 42,612 Table 1: Summary of results 2 Stages 21,638 Multistage 20,329 The results show that multistage stochastic optimization manages the storage better. Also 2 stages gives lower expected generation costs compared to the case with deterministic fixed trajectories. Conclusions Hydro – thermal power system modelling has lots of challenges and optimization techniques are necessary to provide the required answers. PLEXOS features can solve hydro – thermal coordination problems to ensure the user minimizes the cost or alternatively maximizes the benefits of a hydro-thermal portfolio. PLEXOS offers the flexibility to customise the stochastic resultant problem, providing the user with a powerful tool to manage hydro uncertainty that can be integrated with the rest of PLEXOS features. energyexemplar.com Page 23
  • 24. Transmission Analysis SAPP establishment and development The Southern African Power Pool (SAPP) was formed in 1995 to promote trading of electricity between nations in the Southern African Development Community (SADC). Initially, national utilities of each SADC country were included to co-operatively trade electricity (via bilateral contracts and a Short Term Energy market (STEM)). The STEM was replaced in 2009 with a competitive market (the Day Ahead Market (DAM)) and inclusion of Independent Power Producers (IPPs) and Independent Transmission Companies (ITCs) was later allowed. The SAPP membership of 16 (Table 1, as of 2013) is shown in a-Tanzania-Kenya Interconnector., the majority of SAPP members are interconnected with the only isolated members being ESCOM (Malawi), ENE (Angola) and TANESCO (Tanzania). Entity Botswana Power Corporation Electricidade de Mocambique Hidro Electrica Cahora Bassa Mozambique Transmission Company Electricity Supply Corporation of Malawi Empresa Nacional de Electridade Eskom Lesotho Electricity Corporation NamPower Societe Nationale d’Electricite Swaziland Electricity Company Tanzania Electricity Supply Company ZESCO Ltd Copperbelt Energy Corporation Lunsemfwa Hydro Power Company Zimbabwe Electricity Supply Authority OP = Operating Member NP = Non-Operating Member OB = Observer ITC = Independent Transmission Company Status OP OP OB OB NP NP OP OP OP OP OP NP OP ITC IPP OP Abbreviation BPC EdM HCB MOTRACO ESCOM ENE Eskom LEC NamPower SNEL SEC TANESCO ZESCO CEC LHPC ZESA Country Botswana Mozambique Mozambique Mozambique Malawi Angola South Africa Lesotho Namibia DRC Swaziland Tanzania Zambia Zambia Zambia Zimbabwe Table 1: SAPP membership (2013) A constrained SAPP The interconnected SAPP has been significantly constrained for generation capacity in the last decade. SAPP demand (incl. typical 15% reserve margin) for compared to net SAPP capacity (with/without South Africa) has been consistently higher since 2006. This trend is magnified when excluding the dominant player in the SAPP (Eskom, South Africa). Although, there are a number of rehabilitation and new generation projects currently underway to remove these constraints in the medium term (mostly in Botswana, Mozambique, South Africa, Zambia and Zimbabwe). energyexemplar.com Page 24
  • 25. In addition to existing generation capacity constraints, transmission capacity constraints have had a significant effect on the volume of trading within SAPP (whether via bilateral contracts or DAM). For 2013/2014, on average, 70% of energy matched in the DAM was not traded and 77% of bilateral contracts granted were not traded. Again, there are projects in the pipeline that to rectify these transmission constraints including the ZIZABONA project and the Central Transmission Corridor project. Other notable priority SAPP transmission projects include the interconnection of NP members i.e. Namibia-Angola Interconnector, Mozambique-Malawi Interconnector and Zambia-Tanzania-Kenya Interconnector. SAPP modelling with PLEXOS® A sufficiently detailed regional transmission model of the SAPP in the short term, medium term and long term will allow existing national utilities and regulators as well as prospective IPPs and ITCs in the SAPP to fully assess the risks and opportunities present. This is where a software tool like the PLEXOS® Integrated Energy Model (“PLEXOS®”) can assist. Based on only public domain information and generally accepted industry practice, a regional level SAPP transmission model has been developed in PLEXOS. This dataset includes a representation of each SAPP country (including load profiles and hourly demand and energy forecasts for 2010-2025), existing transmission interconnectors, existing major generators and country specific fuels. The transmission components of the PLEXOS SAPP dataset are shown geographically in Figure 1 (extracted directly from PLEXOS mapping interface) with the SAPP interconnectors summarised in Table 2. From Botswana Botswana Botswana Botswana DRC DRC Lesotho Mozambique (Central) Mozambique (South) Mozambique (South) Mozambique (South) Mozambique (South) Mozambique (North) Mozambique (Central) Namibia Namibia South Africa South Africa Zambia Zambia To South Africa South Africa Zimbabwe Zimbabwe Zambia Zambia South Africa Mozambique (North) South Africa South Africa South Africa Swaziland Zimbabwe Zimbabwe South Africa South Africa Swaziland Zombabwe Namibia Zimbabwe Voltage Level (kV) 400 132 400 220 330 500 132 110 533 110 400 400 330 110 400 220 400 132 350 330 Transfer Capacity (MW) 190 425 220 205 247 560 90 30 1920 67 1100 1000 220 38 380 195 1100 15 180 428 Table 2: Existing SAPP interconnectors modelled in PLEXOS dataset energyexemplar.com Page 25
  • 26. Figure 1: Existing SAPP transmission model in PLEXOS (geographical) Interconnectors (the central corridor example) The developed SAPP dataset was used to assess three case studies: • 2012 SAPP as -is (Existing S APP system with e xisting bilateral contracts) • 2012: SAPP Free (existing SAPP system ignoring bilat eral contracts) • 2012: SAPP Unconstrained (existing SAPP with no tr ansmission constraints) The central corridor (Botswana-Zimbabwe-Zambia) is known to be a significant transmission constraint. This can be seen in Figure 2 where a typical days’ power-flows taken from the PLEXOS SAPP model are shown. As can be seen, when free trade is allowed, the South Africa-Botswana interconnector gets pushed to its maximum capacity. Some of this power is used in Botswana but a considerable amount is wheeled via the Botswana-Zimbabwe interconnector further north especially when no transmission constraints are imposed. Figure 2: SAPP central corridor power-flows over a typical day (SA-Botswana) energyexemplar.com Page 26
  • 27. Conclusions PLEXOS has been used to develop a regional level transmission model of the SAPP. This model includes all major generators, loads and load profiles, transmission interconnectors, storages for pumped storage generators, country specific generator fuels and CO2 emissions from generators. The developed PLEXOS model was used to assess the impact of existing transmission constraints and bilateral contracts in SAPP. These case studies revealed that existing energy imbalances in SAPP countries can be significantly reduced if interconnectors are freed up to allow for the most optimal trade of electricity between SAPP nations. In addition, in a scenario where all SAPP nations are assumed to be interconnected and no transmission constraints exist, energy imbalances are removed completely. Testimonial “It is truly amazing how Energy Exemplar seem to be breaking new boundaries. Firstly, the introduction of chronological optimization for the Long Term Optimization studies seems to be paced right at time where renewables are the “flavour of the moment”. Secondly the introduction of the gas module again pitched at the time where shale gas is shaping the market. Not only are the new features paced appropriately, the algorithms and results are truly stunning and this will definitely help to put policy options on a scientific footing. PLEXOS has been fascinating to use to produce the South African Integrated Resource Plan (IRP), the stochastic optimization aspect of it was helpful to establish the position of least regret. We are more confident that the next IRP will be more informative given that PLEXOS has given us new questions which need answers...” Sipho Mdhluli ESKOM Africa energyexemplar.com Page 27
  • 28. Gas System Planning These are interesting times for the Eastern Australian gas market with the impending LNG play coming online. The previously stable and long-term contract market for domestic gas supply on the east coast will be subject to market forces that are in part determined on the global stage. Exactly how the market will respond to these changes is not yet clear, however, one important question on the mind of every market participant is: “do we have enough gas to meet medium to long term domestic demand?” In answering this question and given the opaque nature of the gas market, there exists an asymmetry of opinions in the demand – supply market analysis. Historically, the Eastern Australian gas market has been relatively insulated from international market pressures, operating on a somewhat “self-sufficient” business model. However, the recent large scale development of export LNG facilities is about to change all of that as the eastern Australian gas market has found itself in the midst of the largest structural revolution since the privatisation of gas infrastructure assets in the 1990s. Predictably, participants in the eastern gas market are keen to understand the effects this impending LNG play will have not only on their market positions, but also on the whole production – demand supply chain on the domestic front. In order to predict any effect the LNG development will have on the domestic market, a comprehensive understanding of the domestic supply chain is necessary. This paper aims to analyse the demand - supply interactions of the eastern Australian gas market, in order to establish any potential risk of gas shortage in the medium to long term. Employing a model developed through the new gas module from PLEXOS, an analysis of the market is carried out from 2013 - 2024. An examination of this nature is fundamental to understanding not only the LNG effects on the market, but also to identify any potential supply shortfalls looming in the near future. Gas Model Description Scheduling of gas energy markets require highly specialized tools to conquer the complexity of this dynamic, commercial and regulatory landscape. PLEXOS integrated gas and electricity simulation software package provides technical and mathematical solutions to meet planning needs. The gas module in PLEXOS allows detailed modelling of the physical delivery of gas from producing fields, through pipelines and storages (including linepack), to demand points with the capability to model any physical constraint along the supply chain. Furthermore, the PLEXOS® Integrated Energy Model has the ability to optimize gas and electricity markets by simultaneously solving both markets’ parameters, allowing decision makers to trade-off gas investments, constraints and costs against other alternatives. The following elements are the main components of the gas network modelled in the present study: energyexemplar.com Page 28
  • 29. Model Inputs Icon Class Description Gas Field Field from which gas is extracted. Gas Storage Storage where gas can be injected and extracted. Gas Pipeline Pipeline for transporting gas. Gas Node Connection point in gas network. Gas Demand Demand for gas covering one or more nodes. The model developed for this report is built with information available in the National Gas Market Bulletin and the Australia Energy Market Operator (AEMO). The demand profiles for 2013 used for the demand zones illustrated in Figure 1 are obtained from the National Gas Market Bulletin. Figure 1: Gas network modelled in PLEXOS, the main demand zones included in this study are: Mount Isa, Gladstone, Brisbane, Adelaide, Sydney, Melbourne and Hobart Using the projections supplied by AEMO in the Gas Statement of Opportunities (GSOO) 2013, a demand forecast is built as depicted in Figure 2 showing projections until 2024 for the major demand centres. To accommodate the impact on gas production from the LNG export demand, we run a sensitivity study on the eastern Australian gas market with the production from the Bowen Surat gas fields (largest known and proven CSG basin) turned off and completely unavailable for domestic market. This assumption implies that all the production from this reserve is for export only therefore left out of this study (domestic demand-supply model). In addition, pipeline outage and maintenances are not included, and all pipelines are assumed to be online for the next 12 years. We also assume that the NSW CSG developments go ahead and are all available from the start of the planning horizon. energyexemplar.com Page 29
  • 30. Results and discussions Firstly, we run a “base” model of the eastern Australian gas market for 12 years with all the producing fields available for production. As expected, we see no gas shortages in the system with some CSG gas fields not even required to come online in this time. Figure 2: Demand outlook from 2013 - 2024 as projected by the GSOO 2013 As a sensitivity to model the LNG effects on the demand – supply dynamics on the eastern domestic market, we turn off and completely make production from the Bowen Surat gas fields (the largest proven producing CSG reserves in eastern Australia) unavailable for domestic demand. A justification for this sensitivity is the assumption that all the gas produced from this basin for the next 12 years are fully contracted to LNG export. From the results, we observe that there is enough gas in the eastern reserves to accommodate the impending LNG play as there are no shortages in any of the demand zones considered in this study. In addition, we observe that CSG fields which were offline in the “base” model came online producing at almost full capacity to offset the ‘no production’ scenario from the Bowen Surat gas fields. energyexemplar.com Page 30
  • 31. Figure 3: Gas production with Bowen-Surat reserve completely contracted to LNG export from 2013 - 2024 This result is consistent with other studies in the literature, reaffirming the notion that eastern Australia has enough gas in its reserves to accommodate LNG exports at the current production rates and demand outlook for the next decade. Final comments Given the level of uncertainty surrounding the east coast gas market, there is a need for a sophisticated and complex analysis of the different scenarios and sensitivities surrounding the current market. As such, some open questions arising from this study, all of which can be addressed with some further modelling employing PLEXOS, include: • Will increasing LNG e xports create a domestic short age and t o what e xtent will this be seen in the short term? • How does the gas landscape change with the intr oduction of a new carbon scheme in futur e years? • How will the domestic gas mark et react to a netback of gas price t o international LNG prices? • Will a shift in the domestic demand outlook over the ne xt decade impact the suppl y - demand dynamics of the market? Testimonial “PLEXOS is our tool of choice for NEM market & gas modelling. It gives us the flexibility to set up the model as we choose, and its scenario management is very sophisticated, allowing consistent assumptions to be applied to short, medium or long-term outlooks”. Ben Howard AGL Asia-Pacific energyexemplar.com Page 31
  • 32. Renewable Generation Integration The uncertainty and variability nature of the renewable generation penetration creates integration challenges within the electric industry from the portfolio scale to the regional ISO level. The challenges include: 1. Is the Power Market or the portfolio ready for the renewable generation variability and uncertainty? 2. What can be done to be prepared for the renewable generation? 3. What is the cost for this readiness? 4. Any changes are needed for the power market or portfolio operational procedure? 5. Can new market products improve the readiness? 6. Intra-hourly inter-BAA generation and capacity sharing? 7. All questions are leading toward a better solution – Energy Imbalance Market (EIM). This article first reviews the uncertainty and variability of the renewable generation; then briefly describes the approach to prepare the system for the renewable generation; third, the EIM is presented for the ramp capacity sharing between the Balancing Authority Areas (BAA) to improve the system readiness for the greater renewable generation penetration. The Uncertainty and Variability of Renewable Generation Here the renewable generation usually refers to the wind miller generation and solar generation. The following two tables shows the 5-min actual solar and wind generation and Day-ahead (DA) and Hour-ahead (HA) forecasts for a 130 MW solar project and a 220 MW wind project. energyexemplar.com Page 32
  • 33. The following histograms shows the solar and wind generation forecast error distributions. The DA and HA unit commitment will be performed based on the DA and HA solar and wind generation forecasts. Especially, the DA unit commitment may be quite off from the actual solar and wind generation. energyexemplar.com Page 33
  • 34. What can be done to prepare for the Renewable Generation? To cover the uncertainty and variability of the renewable generation, additional reserves can be introduced during the DA and HA unit commitment. The additional reserves are usually called “Flexibility Up” and “Flexibility Down” reserves. For the detail description of the reserves for the renewable generation, please refer the article. The flexibility up and down reserve requirements are determined by the statistics of the renewable generation forecast errors. The flexibility up and down reserves are provided by the generator ramp capacity. However to quantify the system readiness is best through the sub-hourly simulations with the flexibility up and down deployment. Energy Exemplar performs a few renewable generation integration studies using the 3-stage DA-HA-RT sequential simulation approach. This approach can be illustrated in the following flow-chart. Hourly DA SCUC/ED Simulation in 24 hours 24-hour Unit Commitment Schedules for Long-starts Hourly DA SCUC/ED Simulation with five hours look-ahead Unit Commitment for all generators 5-min RT SCED Simulation with 5-min look ahead DA Forecasted Load/Wind/Solar HA Forecasted Load/Wind/Solar Sub-hourly “Actual” Load/Wind/Solar Contingency, Flex and Regulation Reserve Contingency, Flex and Regulation Reserve Contingency, Flex and Regulation Reserve The 3-stage DA-HA-RT sequential simulation approach is described as follows. • PLEXOS DA simulation mimics the DA Security Constrained Unit Commitment and Economic Dispatch (SCUC/SCED) - Day-ahead forecasted load/wind/solar generation time series are used; - Hourly simulation interval; - The SCUC/ED optimization window is one day plus a few hour look-ahead; - The transmission network is modelled at the zonal or nodal level; - The contingency, DA flexibility / regulation up and down reserves are modelled. • PLEXOS HA simulation mimics the intra-day or Hour-ahead SCUC/SCED - 3-hour-ahead forecasted load/wind/solar generation time series are used; - Hourly simulation interval; - The SCUC/ED optimization window is a few hours plus a few hour look-ahead; - The transmission network is modelled at the zonal or nodal level; - The contingency, 3-HA flexibility / regulation up and down reserves are modelled; - The unit commitment patterns from the DA simulation for the long start up generators are frozen; energyexemplar.com Page 34
  • 35. • PLEXOS RT simulation mimics the 5-min real-time SCED - The “actual” 5-min load/wind/solar generation time series are used; - 5-min simulation interval; - The SCUC/ED optimization window is a few 5 minutes plus a few 5-min look-ahead; - The transmission network is modelled at the zonal or nodal level; - The contingency and regulation up / down reserves are modelled. However, the flexibility up and down reserves are not modelled. The implication is that the capacity held in the 3-HA simulation for the flexibility reserves is deployed to cover the load and renewable generation variability and uncertainty at the 5-min interval; - The unit commitment patterns from the DA simulation for all generators, except the peaking generators, are frozen. The solutions from the 5-min RT simulation will include the over-generation, un-served energy, contingency and regulation reserve shortfall. Usually the non-zero values of these indices indicate the system is not completely ready for the renewable generation or the inadequacy of the system ramp capacity. In addition, the 3-stage Da-HA-RT sequential simulation approach can be used to quantify the effectiveness of the system operation procedure evolution, new products, etc. Energy Imbalance Market One of the effective operation procedure is the Energy Imbalance Market (EIM). In a EIM, each BAA in the EIM performs the DA and HA Security Constrained Unit Commitment and Dispatch to minimize its production cost. However, at the sub-hourly level, the members of the EIM will provide the generation ramp capacity in a form of sub-hourly bidding quantity and price. The generation ramp capacity will cover the sub-hourly load and renewable generation uncertainty and variability in the EIM in an economic manner. Therefore, EIM allows the generation and flexibility and regulation reserve provision sharing at a sub-hourly interval to cover the renewable generation variability and uncertainty with the minimum cost. For the details of the EIM studies and VGS studies, please refer to the project reports. To evaluate the benefit of the EIM, the sub-hourly RT simulation in the 3-stage DA-HA-RT sequential simulation is performed twice: the Business As Usual (BAU) and EIM. In the sub-hourly RT simulation for the BAU case, the hourly interchange between the BAA’s from the HA simulation are frozen to mimic the current BAA operation practice. In the sub-hourly RT simulation for the EIM case, the constraints of the hourly interchange between the BAA’s is relaxed to allow the sub-hourly interchange among the members of the EIM. The produce cost difference of these two simulations is the benefit of the EIM. Testimonial “For the last four years I used Energy Exemplar’s PLEXOS modelling tool. This has, for the first time, allowed for the effects of increasing amounts of renewable non-synchronous generation to be analysed in terms of costs, curtailment and system services availability in the future electricity systems of Western Europe.” Edward Mc Garrigle Bord Gais Energy Europe energyexemplar.com Page 35
  • 36. L e a d i n g t h e f i e l d i n E n e r g y M a r k e t M o d e l l i n g Roseville Hartford London Johannesburg Clients Adelaide Of f ices Energy Exemplar Pty Ltd Software Development Office 17 Bagot St North Adelaide SA 5006, Australia +61 8 8361 9312 info@energyexemplar.com Energy Exemplar LLC West Coast USA Office Suite 120, 3013 Douglas Blvd Roseville, CA 95661 United States of America +1 916 722 1484 westcoastusa@energyexemplar.com Energy Exemplar Ltd Europe Office Building 3, Chiswick Park 566 Chiswick High Road Chiswick, London, W4 5YA United Kingdom +44 208 899 6500 europe@energyexemplar.com Energy Exemplar LLC East Coast USA Office 20 Church Street, Ste. 790 Hartford, CT 06103 United States of America +1 860 461 0761 eastcoastusa@energyexemplar.com Energy Exemplar Pty Ltd Africa Office West Tower Nelson Mandela Square Cnr 5th & Maude Street Sandton, 2196 Johannesburg, South Africa +27 11 881 5889 africa@energyexemplar.com e n e r g y e x e m p l a r . c o m