A report released on the Wildcreek Golf Course showed it would be a suitable location for the Washoe County School District to build a high school.
The report from Wood Rodgers, a surveying and engineering firm, showed seven different configurations of how a 75-acre high school campus could fit onto the Wildcreek property.
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
Sample Designs of Wildcreek High School
1. Tennis Courts
Fields
Potential School
Site
Wild Creek Feasibility Study - 1
November 9th, 2017
Fields
Fields
Below is a list of opportunities and issues associated with Scenario 1
Opportunities:
• E-W 104 Overhead power lines remain
• Option for partial Regulation Golf Course to remain
• Minimal grading for potential school site and fields
Issues:
• Orr Ditch modification in SW corner of site
• Potential school site adjacent to McCarran Blvd. - noise/traffic concern
• Potential school site near residential neighborhoods - noise/traffic concern
• Traffic modification needed at Wedekind Rd.
• Existing Clubhouse and Executive Golf Course removed
• SE fields located in wetlands (require addn. approval)
0 400’ 800’
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
2. Fields
Fields
Fields
Potential School
Site
Tennis Courts
0 400’ 800’
Wild Creek Feasibility Study - 2
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 2
Opportunities:
• Option for Executive Golf Course to remain
• Option for partial Regulation Golf Course to remain
• E-W 104 Overhead power lines remain
• Minimal grading for potential school site and fields
Issues:
• Orr Ditch modification along West side of site
• Potential school site placed in Emergency Water Release Drainage Area
• Existing Clubhouse removed
• Proposed school site near residential neighborhood - noise/traffic concern
• SE fields located in wetlands (require addn. approval)
Executive Golf Course
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
3. Fields
Fields
Fields
Fields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 3
November 9th, 2017
Below is a list of issues and opportunities associated with Scenario 3
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Proposed school site away from residential neighborhoods
• Option for no Orr Ditch modification
Issues:
• Fields located in Emergency Water Release Drainage Area
• E-W 104 Power Line modification
• Some fields away from potential school site
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
4. Fields
Fields
Fields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
0 400’ 800’
Wild Creek Feasibility Study - 4A
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 4A
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Option for no E-W 104 Power line modification
• Proximity of fields to potential school site
• Potential school site away from residential neighborhoods
Issues:
• Fields located in Emergency Water Release Drainage Area
• Orr Ditch modification along East side of site
5. 0 400’ 800’
Fields
FieldsFields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
Wild Creek Feasibility Study - 4B
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 4B
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Option for no E-W 104 Power line modification
• Proximity of fields to potential school site
• Potential school site away from residential neighborhoods
Issues:
• Fields located in Emergency Water Release Drainage Area
• Orr Ditch modification along East side of site
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
6. Fields
Fields
Potential School
Site
Fields
Fields
Tennis
Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 5
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 5
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Potential school site away from McCarran Blvd
• Minimal grading for potential school site
Issues:
• Potential school site/fields located in Emergency Water Release Drainage Area
• E-W 104 Power Line modification (fields)
• Orr Ditch modification along East side of site
• Potential school site near residential neighborhood
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
7. Fields
Fields
Potential School
Site
Fields
Tennis Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 6
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 6
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Potential school site away from McCarran Blvd
• Potential school site out of Emergency Water Release Drainage Area
• Potential school site away from residential neighborhoods
• Option for no Orr Ditch modification
• Option for no E-W 104 Power Line modification
Issues:
• Fields located in Emergency Water Release Drainage Area
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area