SlideShare a Scribd company logo
1 of 9
Download to read offline
32/54/2011-12/PVSE
                      Ministry of New and Renewable Energy


Performance of Grid Solar PV Power Plants under Demonstration Programme


Under the demonstration programme on megawatt size grid solar power plants,
announced in January, 2008, a total of six grid connected solar PV power projects
have been commissioned in the country. The first plant was commissioned in August
2009 in West Bengal and the latest plant was commissioned in March, 2011 in
Andhra Pradesh.

A brief summary of the status of these projects is given below In Table-I

                                        Table-I

                        Project site   Nominal        PV    Period of  Actual
Sr. Project
                                       Capacity Technology Operation Generation
No. Developer                                        used
                                        (MW)                 in Days   in kWh
                       Jamuria,                 Crystalline
                       Asansol,                 Silicon
  1   WBGEDCL*                            1                    614    1879900
                       West
                       Bengal
                       Awan,                       Crystalline
  2   Azure Power      Amritsar,           1       Silicon           577        3312090
                       Punjab
                       Chandrapur,                 a-Si Thin
  3   Mahagenco                            1                         448        1654280
                       Maharashtra                 Films
                       Nagaur,                     Crystalline
      Reliance
  4                    Rajasthan           5       Silicon, Thin     352        7473378
      Industries
                                                   Films, CPV
      Saphhire        Sivaganga,                   a-Si Thin
      Industrial      Tamil Nadu                   Films
  5                                        5                         190        4271319
      Infrastructures
      Pvt Limited
                      Chittoor,                    Crystalline
                      Andhra                       Silicon
  6   Sri Power                            2                          92         901900
                      Pradesh                      CdTe Thin
                                                   Films


* West Bengal Green Energy Development Corporation Limited.

The number of days of operation of solar plants is different and given in Table-I. It
can be seen that four of these plants have completed one year of their operation and
for these plants the net capacity utilization factor (CUF) of the plant has been
calculated. This data however, does not take into account any impact of non-
availability of the grid or downtime / maintenance of the inverter etc. In all the solar
plants installed under the demonstration programme of the Ministry, the PV capacity
is reported as the net sum of PV module capacity installed. This capacity is not at the
AC side.

The CUF of these four plants is in the range of 12.29% to 18.8%. The plant wise
capacity, actual generation over the given period of plant operation and the plant
CUF are given in Table-II.

                                         Table-II

                                                                    Actual
                                                     Nominal      Generation
 Sr.                                         Days                                Actual
              Project Developer                      Capacity      in units
 No.                                                                             CUF %
                                                      (MW)        during the
                                                                    period
  1    WBGEDCL (Sept 09        Aug 10)         365       1           1130700      12.29
  2    WBGEDCL 2(Sept 10         April 11)     242       1            730500
  3    Azure (Dec 09       Nov 10)             365       1           1571610      16.92
  4    Azure 2 (Dec 10      Jun 11)            212       2*          1740480
  5    Mahagenco (May 10- April 11)            365       1           1347840      15.39
  6    Mahagenco (May 11       June11)          61       1            273640
  7    Reliance (July 10    June 11)           352       5           7473378      18.80
  8    Saphhire (Dec 10      June 11)          190       5           4271319
  9    Sri Power (March 11     May 11)          92       2            901900


* The 2nd MW capacity was added in the month of November, 2010.

From the above Table it is seen that so far the overall performance of the plant in
Rajasthan is best at present. Except for the plant in West Bengal, which was the first
plant and a part of the initial learning curve, the average CUF of all other plants is in
the range of 15% to 19%.

The highest CUF achieved, in any month of a year, for each solar plant is as given
below in Table-III. It can be seen from the Table that all the solar plants have
reported highest CUF during March-May period. Except for WBGEDCL project
where the highest CUF was 14.93%, all other plants have achieved highest CUF in
the range of 20.21% to 23.63%.
Table-III


                                                     Actual        Highest
        Sr.                           Month of
              Project Developer                    Generation      CUF %
        No.                           Highest       in units        so far
                                       CUF

         1    WBGEDCL I              March 2010       116600        14.93
         2    WBGEDCL II             March 2011       113600        14.54
         3    Azure I                 April 2010      149265        20.73
         4    Azure II                April 2011      300900        20.90
         5    Mahagenco I             April 2011      145520        20.21
         6    Mahagenco II            May 2011        156560        21.04
         7    Reliance Ind.          March 2011       879104        23.63
         8    Saphhire                May 2011        733286        20.37
         9    Sri Power              March 2011       334440        22.48


The lowest CUF in any month for each solar plant, where 12 months of operation
have been completed is as given below in Table-IV.

                                      Table-IV


                                                      Actual       Lowest
        Sr.                           Month of     Generation      CUF %
              Project Developer
        No.                           Lowest        in kWh in     reported
                                       CUF         the month        so far

         1    WBGEDCL                 Dec 2009        82200         10.52
         2    Azure Power             Jan 2010        60795          8.17
         3    Mahagenco               May 2010        73620          9.9
         4    Reliance Ind.         August 2010       363300        10.17


In all cases, except WBGEDCL project, the lowest performance reported so far was
within the first two months of the synchronization of the solar plant with the grid.

The specific month-wise performance details of each of the six solar plants, including
the choice of technology and the grid connectivity voltage are given in Table V to
Table X.
Table -V

Project Developer : West Bengal Green Energy Development Corporation Limited
Location :Seebpore Power Station of DPSC Ltd., Block Jamuria, Asansol, West Bengal
Plant Capacity :1 MW, Crystalline Silicon Modules
Grid Connectivity :11 kV


Month-wise Generation Details
Table-VI

Project Developer : Azure Power Pvt. Ltd., New Delhi
Location :Village : Ahwan, Tehsil :Ajnal, Dist. : Amritsar, Punjab
Plant Capacity : 2 MW ( 1 MW in first year), Crystalline Silicon Modules
Grid Connectivity :11 kV

Month wise Generation details
Table-VII

Project Developer : Maharashtra State Power Generation Corporation Limited
Location :Chandrapur STPS, Chandrapur, Maharashtra
Plant Capacity :1 MW, Amorphous Silicon Thin Film Modules
Grid Connectivity :33 kV

Month wise Generation details
Table-VIII


Project Developer :Reliance Industries Limited, Navi Mumbai
Location :Khasra No. 1133, Village Khimsar, Tehsil : Khimsar, Dist. : Nagaur, Rajasthan
Plant Capacity :5 MW,
(4.8 MW crystalline Silicon Modules, 200 kWp Thin Films and CPV,
5 MW capacity was connected in three stages)
Grid Connectivity :33kV

Month wise Generation details
Table-IX

Project Developer : Sapphire Industrial Infrastructures Private Limited, New Delhi
Location :Village Rettai Pillai, Iynarkulam, Taluk New Kalltthur Sivagangai,
Dist. ;Sivanganga, Tamil Nadu
Plant Capacity :5 MW, Amorphous Silicon Thin Film Modules
Grid Connectivity :110 kV


Month wise Generation details
Table - X

 Project Developer : Sri City Power Generation (TN) Pvt. Ltd.
 Location : Varadayapalem Mandal, Dist. : Chittoor, Andhra Pradesh
 Plant Capacity :2 MW,
 (1.3 MW Crystalline Silicon Modules, 0.7 MW CdTe Thin Film Modules)
 Grid Connectivity : 33 kV


Month wise Generation details




32/54/2011-12/PVSE dated 31.7.2011

More Related Content

What's hot

AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporate
finance19
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]
satishmnair
 
A ppt on electicity gen..
A   ppt on electicity gen..A   ppt on electicity gen..
A ppt on electicity gen..
Jitendra Mhaske
 
Dpr dalmia solar_19-08-09power plant
Dpr dalmia solar_19-08-09power plantDpr dalmia solar_19-08-09power plant
Dpr dalmia solar_19-08-09power plant
VIKRAMGUPTAJI
 
CEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power SectorCEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power Sector
Spark Network
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
IPPAI
 

What's hot (17)

AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporate
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]
 
Installed capacity
Installed capacityInstalled capacity
Installed capacity
 
A ppt on electicity gen..
A   ppt on electicity gen..A   ppt on electicity gen..
A ppt on electicity gen..
 
Gseg project
Gseg projectGseg project
Gseg project
 
Dpr dalmia solar_19-08-09power plant
Dpr dalmia solar_19-08-09power plantDpr dalmia solar_19-08-09power plant
Dpr dalmia solar_19-08-09power plant
 
CEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power SectorCEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power Sector
 
Adani power
Adani powerAdani power
Adani power
 
Adani power
Adani powerAdani power
Adani power
 
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
 
Lanthanide Resources and Alternatives
Lanthanide Resources and AlternativesLanthanide Resources and Alternatives
Lanthanide Resources and Alternatives
 
Bob Graham-Queensland Government Owned Generators Comparative Study
Bob Graham-Queensland Government Owned Generators Comparative StudyBob Graham-Queensland Government Owned Generators Comparative Study
Bob Graham-Queensland Government Owned Generators Comparative Study
 
Libya
LibyaLibya
Libya
 
Axy presentation web - may 2011
Axy presentation   web - may 2011Axy presentation   web - may 2011
Axy presentation web - may 2011
 
unchachar
unchacharunchachar
unchachar
 
MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018
 

Similar to Grid solar demo_performance

Grid solar demo_performance
Grid solar demo_performanceGrid solar demo_performance
Grid solar demo_performance
Sanman Rajput
 
Solar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain NaikSolar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain Naik
hussainmaloth
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
ADITYA ARYAN
 

Similar to Grid solar demo_performance (20)

Grid solar demo_performance
Grid solar demo_performanceGrid solar demo_performance
Grid solar demo_performance
 
PGVCL TRAINING REPORT
PGVCL TRAINING REPORTPGVCL TRAINING REPORT
PGVCL TRAINING REPORT
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
JNNSM Solar Power in India
JNNSM Solar Power in IndiaJNNSM Solar Power in India
JNNSM Solar Power in India
 
Reports ntpc
Reports ntpcReports ntpc
Reports ntpc
 
IRJET- Energy Statistics in India
IRJET- Energy Statistics in IndiaIRJET- Energy Statistics in India
IRJET- Energy Statistics in India
 
50 MW solar-thermal-dpr
50 MW solar-thermal-dpr50 MW solar-thermal-dpr
50 MW solar-thermal-dpr
 
Solar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain NaikSolar power generation JICA Trainer Hussain Naik
Solar power generation JICA Trainer Hussain Naik
 
Design of solar Parabolic Trough Plant for a Village in Rajasthan
Design of solar Parabolic Trough Plant for a Village in RajasthanDesign of solar Parabolic Trough Plant for a Village in Rajasthan
Design of solar Parabolic Trough Plant for a Village in Rajasthan
 
A n srivastava
A n srivastavaA n srivastava
A n srivastava
 
Performance report of solar projects under NSM
Performance report of solar projects under NSMPerformance report of solar projects under NSM
Performance report of solar projects under NSM
 
SOLAR POTENTIAL IN INDIA - AN OVERVIEW
SOLAR POTENTIAL IN INDIA - AN OVERVIEWSOLAR POTENTIAL IN INDIA - AN OVERVIEW
SOLAR POTENTIAL IN INDIA - AN OVERVIEW
 
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
RETOOLING NIGERIAS ELECTRICITY GENERATION SUB – SYSTEM FOR SUSTAINABLE GRID O...
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
Energy generation 10_11
Energy generation 10_11Energy generation 10_11
Energy generation 10_11
 
12 B .Storage CEA.pptx
12 B .Storage CEA.pptx12 B .Storage CEA.pptx
12 B .Storage CEA.pptx
 
China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...
Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...Performance Analysis  of  5 MWP Grid-Connected  Solar PV Power Plant Using IE...
Performance Analysis of 5 MWP Grid-Connected Solar PV Power Plant Using IE...
 
Aa jnnsm-2012-13
Aa jnnsm-2012-13Aa jnnsm-2012-13
Aa jnnsm-2012-13
 

Grid solar demo_performance

  • 1. 32/54/2011-12/PVSE Ministry of New and Renewable Energy Performance of Grid Solar PV Power Plants under Demonstration Programme Under the demonstration programme on megawatt size grid solar power plants, announced in January, 2008, a total of six grid connected solar PV power projects have been commissioned in the country. The first plant was commissioned in August 2009 in West Bengal and the latest plant was commissioned in March, 2011 in Andhra Pradesh. A brief summary of the status of these projects is given below In Table-I Table-I Project site Nominal PV Period of Actual Sr. Project Capacity Technology Operation Generation No. Developer used (MW) in Days in kWh Jamuria, Crystalline Asansol, Silicon 1 WBGEDCL* 1 614 1879900 West Bengal Awan, Crystalline 2 Azure Power Amritsar, 1 Silicon 577 3312090 Punjab Chandrapur, a-Si Thin 3 Mahagenco 1 448 1654280 Maharashtra Films Nagaur, Crystalline Reliance 4 Rajasthan 5 Silicon, Thin 352 7473378 Industries Films, CPV Saphhire Sivaganga, a-Si Thin Industrial Tamil Nadu Films 5 5 190 4271319 Infrastructures Pvt Limited Chittoor, Crystalline Andhra Silicon 6 Sri Power 2 92 901900 Pradesh CdTe Thin Films * West Bengal Green Energy Development Corporation Limited. The number of days of operation of solar plants is different and given in Table-I. It can be seen that four of these plants have completed one year of their operation and for these plants the net capacity utilization factor (CUF) of the plant has been calculated. This data however, does not take into account any impact of non- availability of the grid or downtime / maintenance of the inverter etc. In all the solar
  • 2. plants installed under the demonstration programme of the Ministry, the PV capacity is reported as the net sum of PV module capacity installed. This capacity is not at the AC side. The CUF of these four plants is in the range of 12.29% to 18.8%. The plant wise capacity, actual generation over the given period of plant operation and the plant CUF are given in Table-II. Table-II Actual Nominal Generation Sr. Days Actual Project Developer Capacity in units No. CUF % (MW) during the period 1 WBGEDCL (Sept 09 Aug 10) 365 1 1130700 12.29 2 WBGEDCL 2(Sept 10 April 11) 242 1 730500 3 Azure (Dec 09 Nov 10) 365 1 1571610 16.92 4 Azure 2 (Dec 10 Jun 11) 212 2* 1740480 5 Mahagenco (May 10- April 11) 365 1 1347840 15.39 6 Mahagenco (May 11 June11) 61 1 273640 7 Reliance (July 10 June 11) 352 5 7473378 18.80 8 Saphhire (Dec 10 June 11) 190 5 4271319 9 Sri Power (March 11 May 11) 92 2 901900 * The 2nd MW capacity was added in the month of November, 2010. From the above Table it is seen that so far the overall performance of the plant in Rajasthan is best at present. Except for the plant in West Bengal, which was the first plant and a part of the initial learning curve, the average CUF of all other plants is in the range of 15% to 19%. The highest CUF achieved, in any month of a year, for each solar plant is as given below in Table-III. It can be seen from the Table that all the solar plants have reported highest CUF during March-May period. Except for WBGEDCL project where the highest CUF was 14.93%, all other plants have achieved highest CUF in the range of 20.21% to 23.63%.
  • 3. Table-III Actual Highest Sr. Month of Project Developer Generation CUF % No. Highest in units so far CUF 1 WBGEDCL I March 2010 116600 14.93 2 WBGEDCL II March 2011 113600 14.54 3 Azure I April 2010 149265 20.73 4 Azure II April 2011 300900 20.90 5 Mahagenco I April 2011 145520 20.21 6 Mahagenco II May 2011 156560 21.04 7 Reliance Ind. March 2011 879104 23.63 8 Saphhire May 2011 733286 20.37 9 Sri Power March 2011 334440 22.48 The lowest CUF in any month for each solar plant, where 12 months of operation have been completed is as given below in Table-IV. Table-IV Actual Lowest Sr. Month of Generation CUF % Project Developer No. Lowest in kWh in reported CUF the month so far 1 WBGEDCL Dec 2009 82200 10.52 2 Azure Power Jan 2010 60795 8.17 3 Mahagenco May 2010 73620 9.9 4 Reliance Ind. August 2010 363300 10.17 In all cases, except WBGEDCL project, the lowest performance reported so far was within the first two months of the synchronization of the solar plant with the grid. The specific month-wise performance details of each of the six solar plants, including the choice of technology and the grid connectivity voltage are given in Table V to Table X.
  • 4. Table -V Project Developer : West Bengal Green Energy Development Corporation Limited Location :Seebpore Power Station of DPSC Ltd., Block Jamuria, Asansol, West Bengal Plant Capacity :1 MW, Crystalline Silicon Modules Grid Connectivity :11 kV Month-wise Generation Details
  • 5. Table-VI Project Developer : Azure Power Pvt. Ltd., New Delhi Location :Village : Ahwan, Tehsil :Ajnal, Dist. : Amritsar, Punjab Plant Capacity : 2 MW ( 1 MW in first year), Crystalline Silicon Modules Grid Connectivity :11 kV Month wise Generation details
  • 6. Table-VII Project Developer : Maharashtra State Power Generation Corporation Limited Location :Chandrapur STPS, Chandrapur, Maharashtra Plant Capacity :1 MW, Amorphous Silicon Thin Film Modules Grid Connectivity :33 kV Month wise Generation details
  • 7. Table-VIII Project Developer :Reliance Industries Limited, Navi Mumbai Location :Khasra No. 1133, Village Khimsar, Tehsil : Khimsar, Dist. : Nagaur, Rajasthan Plant Capacity :5 MW, (4.8 MW crystalline Silicon Modules, 200 kWp Thin Films and CPV, 5 MW capacity was connected in three stages) Grid Connectivity :33kV Month wise Generation details
  • 8. Table-IX Project Developer : Sapphire Industrial Infrastructures Private Limited, New Delhi Location :Village Rettai Pillai, Iynarkulam, Taluk New Kalltthur Sivagangai, Dist. ;Sivanganga, Tamil Nadu Plant Capacity :5 MW, Amorphous Silicon Thin Film Modules Grid Connectivity :110 kV Month wise Generation details
  • 9. Table - X Project Developer : Sri City Power Generation (TN) Pvt. Ltd. Location : Varadayapalem Mandal, Dist. : Chittoor, Andhra Pradesh Plant Capacity :2 MW, (1.3 MW Crystalline Silicon Modules, 0.7 MW CdTe Thin Film Modules) Grid Connectivity : 33 kV Month wise Generation details 32/54/2011-12/PVSE dated 31.7.2011