SPICE MODEL of SSM3J117TU (Professional+BDP Model) in SPICE PARK
Thermally Matched Strain Gauges (Mc Gough)
1. Thermal Calibration Of Strain Gauges For High Quality Strut Load
Measurement
Peter McGough, Kent Wheeler
Leighton Kumagai Joint Venture, Perth, Western Australia
Abstract
Strut loads within braced excavations are commonly measured using resistance or vibrating wire
strain gauges (VWSG’s). There is a common misconception that modern strain gauges are thermally
matched to the steel struts and that thermal and earth pressure loads can be determined
accurately without initial thermal calibration of each strain gauge. Experience from a major
construction project in Perth, Western Australia has shown that very high temperatures and
thermal loads can develop within struts due to exposure to sunlight, and thus thermal calibration of
strain gauges is essential in determining accurate zero load readings for calculation of earth
pressure and thermal loads in struts.
The procedure for thermally calibrating strain gauges prior to loading is explained. This procedure
allows the total strut load to be simply determined, whilst also being independent on the initial
temperature at installation. Several examples of strain gauge calibration and determination of
earth pressure and thermal effects for several sheet piled excavations for the New Metro Rail
Project in Perth, Western Australia are presented. Comparisons of the loads measured with spot
welded vibrating wire strain gauges and spot welded resistance strain gauges are also presented.
Keywords: Calibration, Vibrating Wire Strain Gauges, Resistance Strain Gauges, Strut Loads,
Excavation
1. INTRODUCTION
For flexible strutted (braced) excavations, loads within individual struts are commonly measured
using VWSG’s due to their simplicity and general cost benefits when compared to load cells. During
the initial development phase of VWSG’s it was recognised that the difference between the thermal
behaviour of the gauge and strut needed to be determined. However over the years, and with the
commercialisation of VWSG’s, this need for calibration has been forgotten by some in the belief
that strain gauges are now thermally matched to the steel on which they are typically placed.
Some examples of the misconceptions that have developed are as follows:
“thermally matched electronic gauges have virtually eliminated the need for such corrections”
(Boone and Crawford, 2000).
“Most VWSG systems are self correcting to take into account the difference in coefficient of
thermal expansion between the strut and VWSG. All of the VWSG’s used to measure strut loads
have been thermally matched and calibrated to the steel on which they are placed. This means
that the co-efficient of thermal expansion of the gauge is equal to the co-efficient of thermal
expansion of the steel” (Hashash et.al., 2003)
As no two VWSG’s will ever be the same due to slight variations in manufacturing, along with minor
variations in wire thickness and wire length, welding, and installation method, it is clear that no
gauge shall possess the same co-efficient of thermal expansion as another gauge. Hence as each
gauge possesses a different co-efficient of thermal expansion, there cannot exist the concept of
thermally matched strain gauges.
The co-efficient of thermal expansion for each VWSG under zero external load therefore needs to
be determined, prior to a strut being placed within an excavation and loaded. A simple procedure
for thermally calibrating each VWSG on a strut is explained within this paper, and is subsequently
used to determine earth pressure and thermal loads upon a strut. The procedure also allows for
expected thermal loading within a strut to confirmed prior to its installation and thus checked with
design assumptions. Examples of measured thermal and earth pressure loads using this method in
2. several deep excavations within the New Metro Rail Project in Perth, Western Australia are
presented later in this paper.
2. THERMAL CALIBRATION METHOD:
VWSG’s are normally welded/installed on a strut outside of the excavation at least a week before
installation into the excavation. For the New Metro Rail – City Project, both circular hollow
sections (CHS) and welded column (WC) sections were used as struts, with VSWG’s were installed in
groups of four on each strut as shown in cross section within Figure 1 below.
Figure 1 – Cross Sectional Location of Strain Gauges
The gauges used were Slope Indicator Spot Weldable Strain Gauges, which were welded directly to
the strut at a distance of three strut diameters from the loaded end of the strut to reduce end
effects. A typical installation prior to covering with waterproofing material is shown in Figure 2
below.
Figure 2 – Typical Strain Gauge Installation
Once all VSWG’s are affixed , the strut is laid on wooden timbers and simply supported in the same
position as it would be in the strutted excavation (i.e. final upright position is also upright during
the calibration), but with the ends free to move due to thermal expansion. If the strut was to span
the whole excavation it was simply supported at both ends on blocks of timber, or if the strut was
to have a king post attached as occurred with some of the larger CHS struts it was supported by
additional timbers at the centre of the struts. A typical layout for thermal calibration is illustrated
below.
Figure 3 - Typical Calibration Layout
Once the strut is in the calibration position, a portable datalogger (Slope Indicator VW Minlogger) is
attached to each VWSG and the strut allowed to expand and contract (undisturbed) over a period of
3. 1-5 days. The change in microstrain in each of the VWSG’s over a typical calibration period is
illustrated in Figure 4a. The change in microstrain is due to the thermal expansion of the gauge, as
the strut ends are free to move thus not under any load. The effect of thermal expansion gauge of
the gauge therefore must be determined (calibrated) and the calibration subtracted from the
measured microstrain once the strut is lowered into the excavation and the ends fixed. The
thermal calibration of each VWSG is then a simple procedure of plotting the temperature v
microstrain response of each gauge for the calibration period. The calibration is typically a linear
response as illustrated in Figure 4b.
FS Area 3, Level 2, Strut FS s6036 - Strain Gauge 320 Foreshore, Area 3, Level 2 Strut, FS s6036 - Strain Gauge
Calibration 320 Therm al Calibration
700.0 100 700
90
650.0 650
80
y = 2.2323x + 494.08
70 R2 = 0.9713
600.0 600
Temperature (C)
60
Microstrain
Microstrain
550.0 50 550
40
500.0 500
30
20
450.0 450
10
400.0 0 400
9/11/05 11/11/05 13/11/05 15/11/05 17/11/05 19/11/05 21/11/05 0 10 20 30 40 50
Date Tem perature
Microstrain Calibration Period Temp All Data Linear (All Data)
Figure 4a – Variation of Gauge Microstrain Figure 4b – Thermal Clibration of VWSG
with Temperature under Zero External Load under Zero External Load
The orientation of the strut is critical to the VWSG calibration process as illustrated in Figure 5,
where a rotation of the strut resulted in significantly different thermal response to that observed in
the initial position.
500 70
Strain gauges installed. Strut lowered into
Strut laid on ground Calibration Period Receival Box
outside of box into
480
correct position
60
Strut Rotated outside
460 of box into correct
position
440 50
Strut in correct
Temperature (C)
420 orientation within
40
Microstrain
Receival Box
400
30
380
360 20
340
10
320
300 0
12/02/05 19/02/05 26/02/05 5/03/05 12/03/05 19/03/05
Date
Freq Temp
Figure 5 – Variation of Gauge Microstrain with Strut Orientation under Zero External Load
4. This calibration is then used to account for the self expansion of the gauge, with the calculated
microstrain for the gauge at any temperature (and at zero load) subtracted from the measured
microstrain at the corresponding temperature. Thus the change in microstrain is used to determine
the actual load within the strut. An example of the calculation process in shown below where
strain is calculated from the raw frequency and temperature readings of the VWSG.
εt = B * f2 + C
εi = (T * α g1 ) + (α g2 )
where
εt = Measured Strain
εi = Strain due to Gauge Thermal Expansion
B = Frequency to Microstrain Conversion Factor
C = Factor
α g1 = Coefficient of Thermal Expansion of Gauge
α g2 = Microstrain Intercept for Gauge
and then
dε = εt - εi
As the load and moments due to self weight of the strut is neglected in calculating applied loads
the load (N) in each VWSG is then calculated from change in strain as per the equation
N = Es * As * (dε * 10 -6 )
where
N = Gauge Load (kN)
When the VSWG’s are placed in the positions shown in Figure1, the average load in the strut is
determined by simple averaging of the four VWSG loads. The effect of the gauge calibration
procedure is confirmed by the zero net strut load during the calibration period, and also during the
initial strut installation, as illustrated in Figure 6. In contrast, if thermal effects of the gauges
were not considered (i.e. the difference from the initial microstrain reading used) there would
have been apparent variations in load of up to +/- 250kN during the calibration period as illustrated
in Figure 7, which equates to an error of up to 500kN in this case, given that the ends were free to
move and there were no external loads on the strut. In many cases an error of 500kN would equate
to 10% to 25% of most design strut loads.
STRUT LOADS FOR STRUT ST4 (LEVEL 3 - ESPLANADE LAUNCH BOX)
750.0 110.0
Struts Bolted to walers
100.0
500.0
90.0
250.0
80.0
Average temperature ( C)
O
0.0
Strut Load (kN)
70.0
-250.0 60.0
50.0
-500.0
40.0
-750.0
30.0
-1000.0
20.0
-1250.0 10.0
17/12/04 18/12/04 19/12/04 20/12/04 21/12/04 22/12/04
Date
VWSG 013 VWSG 014 VWSG 015 VWSG 016 Average Strut Load Average Temperature
Figure 6 –Effect of thermal calibration of strain gauge in negating gauge thermal expansion in
unconfined and semi confined state
5. STRUT LOADS FOR STRUT ST4 (LEVEL 3 - ESPLANADE LAUNCH BOX)
750.0 110.0
Struts Bolted to walers
100.0
500.0
90.0
250.0
80.0
Average temperature ( C)
O
0.0
Strut Load (kN)
70.0
-250.0 60.0
50.0
-500.0
40.0
-750.0
30.0
-1000.0
20.0
-1250.0 10.0
17/12/04 18/12/04 19/12/04 20/12/04 21/12/04 22/12/04
Date
VWSG 013 VWSG 014 VWSG 015 VWSG 016 Average Strut Load Average Temperature
Figure 7 –Apparent loads within unconfined strut with no thermal calibration of strain gauge
Once the struts become constrained (i.e. concrete packing is installed between the waler and
sheet-pile walls), the effects of thermal expansion of the strut becomes apparent, with definitive
thermal loads being recorded above that of the normal VWSG thermal expansion as illustrated in
Figure 8.
STRUT LOADS FOR PERTH YARD 2 (LEVEL 1 - CUT & COVER)
750.0 210.0
10/1/05 Calibration of 20/1/05 Preloading of 1/2/05 Commencement of
Strut outside of box Struts to 10-20 ton second level of excavation
from 9.75mRL
14/1/05 Lifting of Strut 190.0
into box and packing of
concrete behind walers
500.0
170.0
150.0
250.0
Average temperature ( OC)
130.0
Strut Load (kN)
0.0 110.0
90.0
-250.0
70.0
50.0
-500.0
30.0
-750.0 10.0
10-Jan-05 17-Jan-05 24-Jan-05 31-Jan-05 7-Feb-05 14-Feb-05
Dates
STR-605 STR-606 STR-607 STR-608 Average Strut Load Average Temperature
Figure 8 –Development of thermal loads within strut once confined position established (Note:
tensile forces induced by bolting to walers)
3. DETERMINATION OF EARTH PRESSURE AND THERMAL STRUT LOADS
The determination of earth pressure and thermal loads introduced by expansion of the strut under
high heat loads (0O-70OC) such as experienced on the New Metro Rail - City Project is usually
undertaken via simple observation of the average strut load graphs, where subtraction of the
average peak load from the average night time load gives a good indication of thermally induced
load, and the night time load gives a good approximation of average earth pressures during each
6. stage of excavation. However, as a significant number of vibrating wire piezometers with
temperature measurements were available on this project a more refined estimate of earth
pressures was developed. It was observed that the water temperature on the project did not vary
during the year or during the project remaining consistent at 21.1oC, this therefore was the
reference temperature for calculation of earth pressure due to excavation and for thermal loading
due to strut expansion.
The data for the strut shown in Figure 8 clearly shows the fluctuation in average strut load during
the calibration phase (unconfined), the installation phase (semi confined) and the excavation phase
(confined). The transition from unconfined to semi confined state is clearly observed in the
individual strain gauge increases, and also in the daily increases in load due to the semi
confinement of the strut (i.e. some deflection of the strut/waler/pile system occurs prior to a
reaction load being taken up in the strut). In the semi confined state, net loads in the evening
returned to just below zero when the temperature lowered to a point below the strut installation
temperature and the strut contracted to a position where gaps occurred between the waler and the
sheet pile, resulting in the minor tensile load on the strut, which was confirmed by the data. In the
confined state the daily fluctuations are still apparent due to thermal expansion of strut, however
overall loads continue to increase as excavation progresses below the strut and active earth
pressures provide a reactive force to the system.
STRUT LOADS FOR PERTH YARD 2 (LEVEL 1 - CUT & COVER)
500.0 210.0
10/1/05 Calibration
of Strut outside of
14/1/05 Lifting of Strut 20/1/05 Preloading 1/2/05 Commencement
190.0
into box and packing of of Struts to 10-20 of second level of
concrete behind walers excavation from 9.75mRL
170.0
250.0
150.0
Average temperature (OC)
130.0
Strut Load (kN)
0.0 110.0
90.0
70.0
-250.0
50.0
30.0
-500.0 10.0
10-Jan-05 17-Jan-05 24-Jan-05 31-Jan-05 7-Feb-05 14-Feb-05
Dates
Average Strut Load Thermal Load at 21C Reaction Load Average Temperature
Figure 9 – Determination of Thermal Strut Loads and Earth Pressure Loads
Using this normalised 21.1OC baseline, and the previous strut example, the thermal loads can be
clearly seen to consistent over the life of the strut as shown in Figure 9. The reaction load in the
unconfined case is opposite an equal to the thermal load as the reaction load is taken up as
expansion of the strut. In the semi confined case the reaction load is again opposite, and
approximately 80% of the thermal load indicating significant movement in the system before the
remaining 20% is shown up as load in the strut. Once excavation commenced the confinement and
reaction load becomes apparent with the active earth pressure slowly increasing with depth and
time whilst thermal loads continued to fluctuate daily from –approximately -25kN to 150kN
Thus by using this method in conjunction with thermally calibrated strain gauges the earth
pressures at any stage can be determined and compared with predictions. In conjunction with this,
predictions of loading due to thermal expansion can be validated at the calibration stage and also
applied to future designs.
7. 4. VALIDATION OF THERMAL CALIBARTION METHOD VIA COMPARISON OF VWSG’S AND
RESISTANCE STRAIN GAUGES
In one diaphragm wall excavation within the New Metro Rail Project several struts were
instrumented with welded VWSG’s at one end of the struts, and welded resistance strain gauges
(RSG’s) at one end, thus allowing direct comparison of the results.
The VWSG’s were thermally calibrated as per the procedure outlined previously with one
improvement. In this instance the struts were installed with the walers and loosely bolted
together, but not attached to the walls. The waler and struts were then supported by cables from
the roof thus allowing system the hang under self weight as it would be once excavation
commenced. This was considered a perfect calibration set up and is shown in Figure 10.
Hangers
Gap
Figure 10 – Calibration of Struts and Waler System in Hanging Position
In contrast the RSG’s were installed by others with no thermal calibration of the gauge. The initial
RSG reading was taken as zero irrespective of the strut or gauge temperature. Measurements of
temperature were also not recorded at the struts, but at the datalogger some distance away.
However given that the excavation was within a covered underground station, temperature
fluctuations were not significant.
Figures 11 an examples of the interpreted loads within one of the double instrumented struts. The
results validate that both types strain gauges measure the same variations in load and similar scale
of load but the uncalibrated RSG’s consistently recorded lower loads (as was the case in all other
double instrumented struts). The lower loads within the RSG’s was generally expected, given that
no allowance for apparent increase in load due to thermal expansion of the resistance gauge wires
was considered. The example shows that the effect of strain gauge expansion is up to 300-400 kN of
the 1750 kN peak loads (17-22%), thus indicating that the uncalibrated RSG’s were underestimating
loads by a significant amount. In Figure 11 this under-estimation of load was also evident when the
strut /wall connection was cut and the strut left in its hanging position until it was removed. There
was an apparent daily variation in tension of 100-250KN in the uncalibrated RSG’s in a strut that
had no load and was unconfined. As the strut was in its original position, the tensile load should
have been closer to zero with no daily variation as was the case with the thermally calibrated
VSWG readings, which consistently showed a minor tensile load of 50kN, thus confirming the
validity of the thermally calibrated readings (and method) prior to, and after loading.
In addition to the above, the potential error in choosing a baseline reading with the uncalibrated
RSG’s was potentially in the order of 100 kN as there was a variation in microstrain readings in the
unloaded state. Given the above the potential total errors in using an uncalibrated strain gauge
could approach 30%, which poses significant risk to people working in strutted excavations.
8. Strut WS 18 Removed
Strut WS 17 Removed
Srut Loads - Strut WS_S17 (William Street Station)
Strut WS 19 Removed
2250.00 100
Base Slab Pour (GL 16-13.5)
Strut WS 20 Removed
2000.00
90
Base Slab Pour (GL 18-16)
1750.00 Excavation for strut
Calibration in hanging Position
installation to north of
Commence Excavation to Formation
struts (confirm dates) 80
1500.00
1250.00 Blinding complete to GL
70
15 by 14/11/05. No
blinding under this strut
1000.00
Average temperature (OC)
60
Strut Load (kN)
750.00
500.00 50
250.00
40
0.00
30
-250.00
-500.00
20
Second Slab Pour
-750.00
10
-1000.00
-1250.00 0
24-Oct-05
31-Oct-05
7-Nov-05
14-Nov-05
21-Nov-05
28-Nov-05
5-Dec-05
12-Dec-05
19-Dec-05
26-Dec-05
2-Jan-06
Date
Average Load (V Wire) Ave Load (Resistance) Ave Temp (V Wire) Ave Temp (Resistance)
5. CONCLUSIONS
In recent times measurement of strut loads within strutted excavations has typically been
undertaken using VWSG’s or RSG’s which are typically more cost effective than load cells.
However, the misconception that strain gauges are thermally matched with steel struts has
developed and evidence has been shown that this is incorrect and that thermal calibration of
individual strain gauges is required and should form best practice for strut monitoring.
A method has been explained for thermally calibrating strain gauges in order to accurately
determine the load within a strut. The thermal calibration can also be used to determine the
thermal expansion force within a strut that is confined, and also to separate this force from active
earth pressure on the strut. Thermal calibration method was validated in by comparison to
excavation activities and comparison of measured loads in unconfined struts before and after
excavation.
It was shown that thermal expansion forces in struts can be significant and should accounted for in
strut designs, and validated by strain gauge measurement prior to strut installation. It was also
confirmed that VWSG’s produce similar results to that measured from RSG’s provided both are
thermally calibrated.
6. REFERENCES
Hashash, Y., Marulanda, C., Kershaw, K., Cordin, E., Druss, D., Bobrow, D., and Das, P., (2003).
Temeprature Correction and Strut Loads in Central Artery Excavations. ASCE, Journal of
Geotechnical and Geoenvironmental Engineering, pp 495-505, June.
Boone, S. J., and Crawford, A. M., (2000). Temperature, Elastic Modulus, and Strut Load
Relationships For Braced Excavations. ASCE, Journal of Geotechnical and Geoenvironmental
Engineering, 126(10), 870–881.