The 12 Milestones of the
Product Management Process
Jeroen van Rijn
1
March 4th, 2013
Introduction
• I have worked as a product manager and with other
product managers for over 7 years in start-ups and large
corporations.
• During this time I found the following product
management process to be a good generic description for
waterfall style development processes, especially for
consumer electronics.
2
There Are 12 Milestones In
The Product Lifecycle
• P0 - start of planning
• P1 - roadmap complete
• P2 - product drivers approved
• P3 - product concept approved
• P4 - product development kick-off complete
• P5 - design & requirement freeze
• P6 - Go-to-market strategy approved
• P7 - Launch preparation complete
• P8 - Launch
• P9 - Ramp-up complete
• P10 - Mid-cycle update
• P11 - Ramp-down complete
3
P0 - Start of Planning
• This milestone marks the beginning of the product
lifecycle rather than the completion of a deliverable.
• This milestone is usually initiated by the Head of Product
Management.
• This often happens in a cyclical fashion, like once a year,
with a scope of 2 to 3 years out.
4
P1 - Roadmap Complete
• The roadmap maps out a draft product
portfolio with price points, timing and
estimated product volumes.
• Helps forecast future revenues.
• Key inputs:
• Financial growth targets from C-level
executives.
• Market share targets from C-level executives
• Engineering capacity.
• Market data (esp. price elasticity).
5
2014 2015
$x
3M
$x
3.1M
$y
5M
$y
5.5M
Example roadmap
P2 - Product Drivers Approved
• This milestone happens for each individual product on
the roadmap.
• Goal is to understand what drives the development of
each product.
• Basis for the drivers are:
• The financial goals of the product (price & volume).
• Which consumer segments might deliver on the financial goals.
• What the product needs to represent to address the attractive
consumer segments (high-level features and design drivers).
• Competition in the price point and target consumer segment.
• Update the business case with your best estimate.
Highlight if there are unrealistic expectations.
6
P3 - Product Concept Approved
• Between P2 and P3 you work with industrial designers,
user experience designers and other creatives to generate
multiple product concepts.
• If needed, test the concepts in focus groups. Various
agencies can help and will keep your brand name
anonymous.
• Analyze the concepts for cost and warranty implications.
Plug this into your business case to make sure the
concepts can meet the financial goals for the product.
• Recommend a concept to be developed.
7
P4 - Product Development Kick-off Complete
• This is more an R&D milestone than a product
management milestone.
• For this milestone, the R&D program office has assigned
a program manager to the product.
• The program manager pulls together an R&D leadership
team for the program and delivers a resource allocation
plan to meet the schedule of the product.
• The product manager assists the program manager in
communicating to the R&D team what the product is
about.
• Be enthusiastic! Nobody wants to work on a product that the
leadership does not believe in.
8
P5 -Design and Requirements Freeze
• At this point, the design and all requirements are
documented, analyzed and no longer subject to change.
• Requirements will require a negotiation with R&D. It
may be that some requirements cannot be delivered in
the schedule with current staffing levels.
• This is needed so R&D can commit to a schedule.
• Change is possible, but needs to go through a formal
change process, where impacts on schedule, quality and
cost are analyzed before the change is committed.
9
P6 - Go-To-Market Strategy Approved
• Product Development is now underway. Time to plan
how you are going to sell the product.
• Work with sales and marketing to identify and prioritize
channels to market.
• Prioritization of channels may be necessary to deal with resource
constraints or manufacturing constraints.
• This does affect R&D, so make sure they are informed.
• Also create a project plans with marketing, sales, and
support for the completion of materials, trainings, and
marketing campaigns.
10
P7 - Launch Preparation Complete
• The main goal here is that products leaving the factory have a place to go and are
supported by a marketing campaign.
• Marketing materials and ad campaigns need to be prepared and ready to go.
• Sales channels need to be prepared:
• Retails staff (if applicable) needs to be trained on the benefits of the product.
• Space needs to be allocated on store shelves.
• The logistics chain needs to have been set up.
• Support centers need to be prepared to deal with questions about the new
product.
• Warranty centers need to be ready to receive faulty products and repair or
replace them.
11
P8 - Launch
• Best feeling in the world for a product manager.
• All hands on deck and solve issues that pop-up during
launch.
• Potential to be involved in press events.
• Make sure you have your media training done!
• Continued to work through your channel prioritization
plan.
12
P9 - Ramp-Up Complete
• You are getting close to being able to breathe and sleep :-)
• All sales channels are now shipping the product.
• All marketing campaigns are firing on all cylinders.
• Products are leaving the factory and getting into
consumers’ hands.
• This is also a good time to measure performance in the
market:
• Actual sales vs forecast.
• Net Promoter Score.
13
P10 - Mid-Cycle Update
• It is common for products that are available in the market
to get a mid-cycle update. These may be:
• Updated colors, materials.
• Software update.
• Different bundling of accessories.
• Major reasons for an update:
• Keep the product fresh in the consumers’ mind.
• Fix bugs.
• Reduce warranty and support costs.
• Mid-cycle updates need to be planned in a similar way as
the all the steps described until here, but are obviously
much smaller in scope.
14
P11 - Ramp-Down Complete
• At the end of the product life-cycle, it is time to ramp it
down.
• Focus on stopping manufacturing early, so all channels
can sell out their inventory.
• Maintain some parts and replacement product inventory
for warranty for the last customers to buy your product.
• Ramp down marketing campaigns and recall marketing
materials.
• Very important process:
• Left-over inventory can kill your business case!
• Document learnings from consumers.
15
The End
16
Jeroen van Rijn can be contacted through:
•LinkedIn: https://www.linkedin.com/in/jeroenvanrijn

More Related Content

What's hot

Agile pilot project selection
Agile pilot project selectionAgile pilot project selection
Agile pilot project selection
hemantg1
 
What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...
Invensis Learning
 
Business case-template
Business case-templateBusiness case-template
Business case-template
Jo Padilha
 

What's hot (20)

Global R&D – An Update on the Latest Scenario and the Challenges Facing It
Global R&D – An Update on the Latest Scenario and the Challenges Facing ItGlobal R&D – An Update on the Latest Scenario and the Challenges Facing It
Global R&D – An Update on the Latest Scenario and the Challenges Facing It
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinar
 
Blue Ocean Strategy Corporate Training Program
Blue Ocean Strategy Corporate Training ProgramBlue Ocean Strategy Corporate Training Program
Blue Ocean Strategy Corporate Training Program
 
Agile
AgileAgile
Agile
 
P3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management FrameworkP3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management Framework
 
Value Innovation
Value Innovation Value Innovation
Value Innovation
 
Projektportfolio Management
Projektportfolio ManagementProjektportfolio Management
Projektportfolio Management
 
Webinar How PMs Use AI to 10X Their Productivity by Product School EiR.pdf
Webinar How PMs Use AI to 10X Their Productivity by Product School EiR.pdfWebinar How PMs Use AI to 10X Their Productivity by Product School EiR.pdf
Webinar How PMs Use AI to 10X Their Productivity by Product School EiR.pdf
 
Ansoff
AnsoffAnsoff
Ansoff
 
Agile pilot project selection
Agile pilot project selectionAgile pilot project selection
Agile pilot project selection
 
The Modern PMO
The Modern PMOThe Modern PMO
The Modern PMO
 
Scrum In Ten Slides
Scrum In Ten SlidesScrum In Ten Slides
Scrum In Ten Slides
 
Scrum roles
Scrum rolesScrum roles
Scrum roles
 
Agile - Scrum
Agile - ScrumAgile - Scrum
Agile - Scrum
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)
 
Stage gate process in IT product development
Stage gate process in IT product developmentStage gate process in IT product development
Stage gate process in IT product development
 
What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...What is Agile Project Management? | Agile Project Management | Invensis Learn...
What is Agile Project Management? | Agile Project Management | Invensis Learn...
 
Business case-template
Business case-templateBusiness case-template
Business case-template
 
Scrum methodology in practice
Scrum methodology in practiceScrum methodology in practice
Scrum methodology in practice
 

Viewers also liked

Project milestones-and-budgeting
Project milestones-and-budgetingProject milestones-and-budgeting
Project milestones-and-budgeting
Peter Florijn
 
International marketing intelligence
International marketing intelligenceInternational marketing intelligence
International marketing intelligence
Dr. Amit Joshi
 
Design and Implementation of In-Service Teacher Training
Design and Implementation of In-Service Teacher TrainingDesign and Implementation of In-Service Teacher Training
Design and Implementation of In-Service Teacher Training
Peter Beech
 
Process control fundamentals
Process control fundamentalsProcess control fundamentals
Process control fundamentals
haiyong wang
 
Employee retention
Employee retentionEmployee retention
Employee retention
bhawnajha091
 

Viewers also liked (20)

Project milestones-and-budgeting
Project milestones-and-budgetingProject milestones-and-budgeting
Project milestones-and-budgeting
 
Project milestone
Project milestoneProject milestone
Project milestone
 
Building a Milestone Plan
Building a Milestone PlanBuilding a Milestone Plan
Building a Milestone Plan
 
The Critical Role of Sales Throughout the New Product Development Process
The Critical Role of Sales Throughout the New Product Development ProcessThe Critical Role of Sales Throughout the New Product Development Process
The Critical Role of Sales Throughout the New Product Development Process
 
Product Development Process Diagram
Product Development Process Diagram Product Development Process Diagram
Product Development Process Diagram
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
How to Make the Inc 500 List
How to Make the Inc 500 ListHow to Make the Inc 500 List
How to Make the Inc 500 List
 
Introduction to depreciation
Introduction to depreciationIntroduction to depreciation
Introduction to depreciation
 
International marketing intelligence
International marketing intelligenceInternational marketing intelligence
International marketing intelligence
 
Design and Implementation of In-Service Teacher Training
Design and Implementation of In-Service Teacher TrainingDesign and Implementation of In-Service Teacher Training
Design and Implementation of In-Service Teacher Training
 
Understanding IT Governance and Risk Management
Understanding IT Governance and Risk ManagementUnderstanding IT Governance and Risk Management
Understanding IT Governance and Risk Management
 
3. ITIL Categorization for Remedyforce- An Evolution into Service Desk Self S...
3.	ITIL Categorization for Remedyforce- An Evolution into Service Desk Self S...3.	ITIL Categorization for Remedyforce- An Evolution into Service Desk Self S...
3. ITIL Categorization for Remedyforce- An Evolution into Service Desk Self S...
 
Process control fundamentals
Process control fundamentalsProcess control fundamentals
Process control fundamentals
 
steps of implementation of HRIS
steps of implementation of HRISsteps of implementation of HRIS
steps of implementation of HRIS
 
PRINTED MATERIALS
PRINTED MATERIALSPRINTED MATERIALS
PRINTED MATERIALS
 
Immunohistochemistry METHODS
Immunohistochemistry  METHODSImmunohistochemistry  METHODS
Immunohistochemistry METHODS
 
Employee retention
Employee retentionEmployee retention
Employee retention
 
Customer Success Management ( CSM ) Org Structures by Gainsight
Customer Success Management ( CSM ) Org Structures by GainsightCustomer Success Management ( CSM ) Org Structures by Gainsight
Customer Success Management ( CSM ) Org Structures by Gainsight
 
Employee retention (HR topic)
Employee retention (HR topic)Employee retention (HR topic)
Employee retention (HR topic)
 
Employee retention
Employee retentionEmployee retention
Employee retention
 

Similar to The 12 Milestones of Product Management

EIS-PM-Devt-Services-Boot Camp_Combined (1)
EIS-PM-Devt-Services-Boot Camp_Combined (1)EIS-PM-Devt-Services-Boot Camp_Combined (1)
EIS-PM-Devt-Services-Boot Camp_Combined (1)
Thomas Squeo
 
Mktg. New Product Development Strategy .pptx
Mktg. New Product Development Strategy .pptxMktg. New Product Development Strategy .pptx
Mktg. New Product Development Strategy .pptx
AparnaKanchan1
 
Go to market brochure
Go to market brochureGo to market brochure
Go to market brochure
Jovana Savic
 
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Tim Kasse
 
Product Management in New Companies
Product Management in New CompaniesProduct Management in New Companies
Product Management in New Companies
T.J. Kuhny
 

Similar to The 12 Milestones of Product Management (20)

Product planning
Product planningProduct planning
Product planning
 
PM 1 (1).pptx
PM 1 (1).pptxPM 1 (1).pptx
PM 1 (1).pptx
 
EIS-PM-Devt-Services-Boot Camp_Combined (1)
EIS-PM-Devt-Services-Boot Camp_Combined (1)EIS-PM-Devt-Services-Boot Camp_Combined (1)
EIS-PM-Devt-Services-Boot Camp_Combined (1)
 
The seven stages of the Product Marketing launch process.
The seven stages of the Product Marketing launch process.The seven stages of the Product Marketing launch process.
The seven stages of the Product Marketing launch process.
 
Mktg. New Product Development Strategy .pptx
Mktg. New Product Development Strategy .pptxMktg. New Product Development Strategy .pptx
Mktg. New Product Development Strategy .pptx
 
Product roadmap 101
Product roadmap 101Product roadmap 101
Product roadmap 101
 
Building an Amazing Relationship Between Product Management and Marketing
Building an Amazing Relationship Between Product Management and MarketingBuilding an Amazing Relationship Between Product Management and Marketing
Building an Amazing Relationship Between Product Management and Marketing
 
Basics of Product and Process Design Management
Basics of Product and Process Design ManagementBasics of Product and Process Design Management
Basics of Product and Process Design Management
 
Go to market brochure
Go to market brochureGo to market brochure
Go to market brochure
 
Module - Project Development & Coaching
Module - Project Development & CoachingModule - Project Development & Coaching
Module - Project Development & Coaching
 
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
Integrating Stage Gate with Product Development Models and the CMMI WB v2.2
 
New Product Development and Stage Gates
New Product Development and Stage GatesNew Product Development and Stage Gates
New Product Development and Stage Gates
 
Using of Target Costing in Different Industry : Auto, IT and Banking
Using of Target Costing in Different Industry : Auto, IT and BankingUsing of Target Costing in Different Industry : Auto, IT and Banking
Using of Target Costing in Different Industry : Auto, IT and Banking
 
Business case writing presentation
Business case writing presentationBusiness case writing presentation
Business case writing presentation
 
New Product Development
New Product DevelopmentNew Product Development
New Product Development
 
The new product process
The new product processThe new product process
The new product process
 
Grp 6 developing global products & brands
Grp   6 developing global products & brandsGrp   6 developing global products & brands
Grp 6 developing global products & brands
 
Product Management in New Companies
Product Management in New CompaniesProduct Management in New Companies
Product Management in New Companies
 
Technology
TechnologyTechnology
Technology
 
NEW GFMS CC PRESENTATION
NEW GFMS CC PRESENTATIONNEW GFMS CC PRESENTATION
NEW GFMS CC PRESENTATION
 

Recently uploaded

一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
eqaqen
 
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
gajnagarg
 
Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........
deejay178
 
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Menggugurkan Kandungan 087776558899
 
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
yynod
 
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
gajnagarg
 
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
yynod
 
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
nirzagarg
 
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
nirzagarg
 
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
ZurliaSoop
 
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
gynedubai
 

Recently uploaded (20)

一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
一比一定(购)堪培拉大学毕业证(UC毕业证)成绩单学位证
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
 
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
Specialize in a MSc within Biomanufacturing, and work part-time as Process En...
 
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Hubli [ 7014168258 ] Call Me For Genuine Models We ...
 
Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........Gabriel_Carter_EXPOLRATIONpp.pptx........
Gabriel_Carter_EXPOLRATIONpp.pptx........
 
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
 
Vip Malegaon Escorts Service Girl ^ 9332606886, WhatsApp Anytime Malegaon
Vip Malegaon Escorts Service Girl ^ 9332606886, WhatsApp Anytime MalegaonVip Malegaon Escorts Service Girl ^ 9332606886, WhatsApp Anytime Malegaon
Vip Malegaon Escorts Service Girl ^ 9332606886, WhatsApp Anytime Malegaon
 
Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negron
 
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
怎样办理宾夕法尼亚大学毕业证(UPenn毕业证书)成绩单学校原版复制
 
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
 
B.tech civil major project by Deepak Kumar
B.tech civil major project by Deepak KumarB.tech civil major project by Deepak Kumar
B.tech civil major project by Deepak Kumar
 
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
Novo Nordisk Kalundborg. We are expanding our manufacturing hub in Kalundborg...
 
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
怎样办理伊利诺伊大学厄巴纳-香槟分校毕业证(UIUC毕业证书)成绩单学校原版复制
 
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In Sagar [ 7014168258 ] Call Me For Genuine Models We ...
 
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Etawah [ 7014168258 ] Call Me For Genuine Models We...
 
UXPA Boston 2024 Maximize the Client Consultant Relationship.pdf
UXPA Boston 2024 Maximize the Client Consultant Relationship.pdfUXPA Boston 2024 Maximize the Client Consultant Relationship.pdf
UXPA Boston 2024 Maximize the Client Consultant Relationship.pdf
 
drug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstingsdrug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstings
 
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
Jual obat aborsi Jakarta ( 085657271886 )Cytote pil telat bulan penggugur kan...
 
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Shimla [ 7014168258 ] Call Me For Genuine Models We...
 
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
 

The 12 Milestones of Product Management

  • 1. The 12 Milestones of the Product Management Process Jeroen van Rijn 1 March 4th, 2013
  • 2. Introduction • I have worked as a product manager and with other product managers for over 7 years in start-ups and large corporations. • During this time I found the following product management process to be a good generic description for waterfall style development processes, especially for consumer electronics. 2
  • 3. There Are 12 Milestones In The Product Lifecycle • P0 - start of planning • P1 - roadmap complete • P2 - product drivers approved • P3 - product concept approved • P4 - product development kick-off complete • P5 - design & requirement freeze • P6 - Go-to-market strategy approved • P7 - Launch preparation complete • P8 - Launch • P9 - Ramp-up complete • P10 - Mid-cycle update • P11 - Ramp-down complete 3
  • 4. P0 - Start of Planning • This milestone marks the beginning of the product lifecycle rather than the completion of a deliverable. • This milestone is usually initiated by the Head of Product Management. • This often happens in a cyclical fashion, like once a year, with a scope of 2 to 3 years out. 4
  • 5. P1 - Roadmap Complete • The roadmap maps out a draft product portfolio with price points, timing and estimated product volumes. • Helps forecast future revenues. • Key inputs: • Financial growth targets from C-level executives. • Market share targets from C-level executives • Engineering capacity. • Market data (esp. price elasticity). 5 2014 2015 $x 3M $x 3.1M $y 5M $y 5.5M Example roadmap
  • 6. P2 - Product Drivers Approved • This milestone happens for each individual product on the roadmap. • Goal is to understand what drives the development of each product. • Basis for the drivers are: • The financial goals of the product (price & volume). • Which consumer segments might deliver on the financial goals. • What the product needs to represent to address the attractive consumer segments (high-level features and design drivers). • Competition in the price point and target consumer segment. • Update the business case with your best estimate. Highlight if there are unrealistic expectations. 6
  • 7. P3 - Product Concept Approved • Between P2 and P3 you work with industrial designers, user experience designers and other creatives to generate multiple product concepts. • If needed, test the concepts in focus groups. Various agencies can help and will keep your brand name anonymous. • Analyze the concepts for cost and warranty implications. Plug this into your business case to make sure the concepts can meet the financial goals for the product. • Recommend a concept to be developed. 7
  • 8. P4 - Product Development Kick-off Complete • This is more an R&D milestone than a product management milestone. • For this milestone, the R&D program office has assigned a program manager to the product. • The program manager pulls together an R&D leadership team for the program and delivers a resource allocation plan to meet the schedule of the product. • The product manager assists the program manager in communicating to the R&D team what the product is about. • Be enthusiastic! Nobody wants to work on a product that the leadership does not believe in. 8
  • 9. P5 -Design and Requirements Freeze • At this point, the design and all requirements are documented, analyzed and no longer subject to change. • Requirements will require a negotiation with R&D. It may be that some requirements cannot be delivered in the schedule with current staffing levels. • This is needed so R&D can commit to a schedule. • Change is possible, but needs to go through a formal change process, where impacts on schedule, quality and cost are analyzed before the change is committed. 9
  • 10. P6 - Go-To-Market Strategy Approved • Product Development is now underway. Time to plan how you are going to sell the product. • Work with sales and marketing to identify and prioritize channels to market. • Prioritization of channels may be necessary to deal with resource constraints or manufacturing constraints. • This does affect R&D, so make sure they are informed. • Also create a project plans with marketing, sales, and support for the completion of materials, trainings, and marketing campaigns. 10
  • 11. P7 - Launch Preparation Complete • The main goal here is that products leaving the factory have a place to go and are supported by a marketing campaign. • Marketing materials and ad campaigns need to be prepared and ready to go. • Sales channels need to be prepared: • Retails staff (if applicable) needs to be trained on the benefits of the product. • Space needs to be allocated on store shelves. • The logistics chain needs to have been set up. • Support centers need to be prepared to deal with questions about the new product. • Warranty centers need to be ready to receive faulty products and repair or replace them. 11
  • 12. P8 - Launch • Best feeling in the world for a product manager. • All hands on deck and solve issues that pop-up during launch. • Potential to be involved in press events. • Make sure you have your media training done! • Continued to work through your channel prioritization plan. 12
  • 13. P9 - Ramp-Up Complete • You are getting close to being able to breathe and sleep :-) • All sales channels are now shipping the product. • All marketing campaigns are firing on all cylinders. • Products are leaving the factory and getting into consumers’ hands. • This is also a good time to measure performance in the market: • Actual sales vs forecast. • Net Promoter Score. 13
  • 14. P10 - Mid-Cycle Update • It is common for products that are available in the market to get a mid-cycle update. These may be: • Updated colors, materials. • Software update. • Different bundling of accessories. • Major reasons for an update: • Keep the product fresh in the consumers’ mind. • Fix bugs. • Reduce warranty and support costs. • Mid-cycle updates need to be planned in a similar way as the all the steps described until here, but are obviously much smaller in scope. 14
  • 15. P11 - Ramp-Down Complete • At the end of the product life-cycle, it is time to ramp it down. • Focus on stopping manufacturing early, so all channels can sell out their inventory. • Maintain some parts and replacement product inventory for warranty for the last customers to buy your product. • Ramp down marketing campaigns and recall marketing materials. • Very important process: • Left-over inventory can kill your business case! • Document learnings from consumers. 15
  • 16. The End 16 Jeroen van Rijn can be contacted through: •LinkedIn: https://www.linkedin.com/in/jeroenvanrijn