54   Chapter 2
exam questions
1. Which of the following is NOT a Project Constraint?
QualityA.	
ScaleB.	
TimeC.	
CostD.	
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he’s run over his budget because the staff turned out to be more expensive than
planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
QualityA.	
ResourceB.	
TimeC.	
D.	 Cost
3. Which of the following is NOT an example of operational work?
Building a purchase order system for accounts payableA.	
Submitting weekly purchase orders through a purchase order systemB.	
Deploying weekly anti-virus software updatesC.	
Yearly staff performance evaluationsD.	
4. You’re managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is
the BEST way to handle this situation?
Refuse to work with him because he’s being difficultA.	
Appeal to the accountant’s manager and ask to have him required to take trainingB.	
Get a special dispensation so that the accountant doesn’t have to go to the trainingC.	
Work with him to understand his concerns and do what you can to help alleviate them withoutD.	
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
Resource ListA.	
Stakeholder RegisterB.	
Enterprise Environmental FactorsC.	
Project PlanD.	
Exam Questions
Download at Boykma.Com
you are here 4   55
organizations, constraints, and projects
6. Your manager asks you where to find a list of projects that should be managed together. What is
the BEST place to find this information?
Project PlanA.	
Project CharterB.	
Portfolio CharterC.	
Program CharterD.	
7. You want to know specifically which business goal a group of projects and programs are going to
accomplish. Which is the best place to look for this information?
Project PlanA.	
Project CharterB.	
Portfolio CharterC.	
Program CharterD.	
8. A project coordinator is having trouble securing programmers for her project. Every time she asks
her boss to give a resource to the project he says that they are too busy to help out with her project.
Which type of organization is she working in?
FunctionalA.	
Weak MatrixB.	
Strong MatrixC.	
ProjectizedD.	
9. A project manager is having trouble securing programmers for her project. Every time she asks
the programming manager for resources for her project, he says they’re all assigned to other work.
So she is constantly having to go over his head to overrule him. Which type of organization is she
working for?
FunctionalA.	
Weak MatrixB.	
Strong MatrixC.	
ProjectizedD.	
Exam Questions
Download at Boykma.Com

More Related Content

What's hot

What's hot (18)

08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Pmp5
Pmp5Pmp5
Pmp5
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Pmp4
Pmp4Pmp4
Pmp4
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Pmp Questions and Answers series #1
Pmp Questions and Answers series #1Pmp Questions and Answers series #1
Pmp Questions and Answers series #1
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 

Viewers also liked

Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Faraj , PMP
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility examJamil Faraj , PMP
 
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروع
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروعالمحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروع
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروعEgypt Scholars Inc.
 
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروع
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروعالمحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروع
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروعEgypt Scholars Inc.
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعEgypt Scholars Inc.
 

Viewers also liked (11)

Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Pmp1
Pmp1Pmp1
Pmp1
 
Pmp3
Pmp3Pmp3
Pmp3
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروع
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروعالمحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروع
المحاضرة السابعة: تنفيذ المشروع وإدارة فريق العمل والاتصالات خلال المشروع
 
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروع
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروعالمحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروع
المحاضرة الثالثة: المتطلبات وتحديد نطاق العمل و هيكل تجزئة المشروع
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروع
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 

Similar to 2

Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSeshne Govender
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development ProcessSattrix Software Solutions
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMProduct School
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxcroysierkathey
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
Performance Management - Herman Augnis
Performance Management - Herman Augnis Performance Management - Herman Augnis
Performance Management - Herman Augnis Preeti Bhaskar
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersAdeolu Adeleye
 
Cara praktis penerapan wbt
Cara praktis penerapan wbtCara praktis penerapan wbt
Cara praktis penerapan wbtzahrinafirda
 
Workbook answers
Workbook answersWorkbook answers
Workbook answersqtntpam
 

Similar to 2 (20)

Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM Certifications
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
Assignment .pdf
Assignment .pdfAssignment .pdf
Assignment .pdf
 
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PMFeature Prioritization Techniques for an Agile PMs by Microsoft PM
Feature Prioritization Techniques for an Agile PMs by Microsoft PM
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Kinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docxKinsley FosterJuly 27, 2019PM 430Software .docx
Kinsley FosterJuly 27, 2019PM 430Software .docx
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Performance Management - Herman Augnis
Performance Management - Herman Augnis Performance Management - Herman Augnis
Performance Management - Herman Augnis
 
PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project Managers
 
PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
Cara praktis penerapan wbt
Cara praktis penerapan wbtCara praktis penerapan wbt
Cara praktis penerapan wbt
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
Workbook answers
Workbook answersWorkbook answers
Workbook answers
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 

2

  • 1. 54   Chapter 2 exam questions 1. Which of the following is NOT a Project Constraint? QualityA. ScaleB. TimeC. CostD. 2. A project manager is running a data center installation project. He finds that his stakeholder is angry because he’s run over his budget because the staff turned out to be more expensive than planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much drive space as he needs. Which of the following constraints was not affected by this problem? QualityA. ResourceB. TimeC. D. Cost 3. Which of the following is NOT an example of operational work? Building a purchase order system for accounts payableA. Submitting weekly purchase orders through a purchase order systemB. Deploying weekly anti-virus software updatesC. Yearly staff performance evaluationsD. 4. You’re managing a project to build a new accounting system. One of the accountants in another department really likes the current system and is refusing to be trained on the new one. What is the BEST way to handle this situation? Refuse to work with him because he’s being difficultA. Appeal to the accountant’s manager and ask to have him required to take trainingB. Get a special dispensation so that the accountant doesn’t have to go to the trainingC. Work with him to understand his concerns and do what you can to help alleviate them withoutD. compromising your project 5. Which of the following is used for identifying people who are impacted by the project? Resource ListA. Stakeholder RegisterB. Enterprise Environmental FactorsC. Project PlanD. Exam Questions Download at Boykma.Com
  • 2. you are here 4   55 organizations, constraints, and projects 6. Your manager asks you where to find a list of projects that should be managed together. What is the BEST place to find this information? Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 7. You want to know specifically which business goal a group of projects and programs are going to accomplish. Which is the best place to look for this information? Project PlanA. Project CharterB. Portfolio CharterC. Program CharterD. 8. A project coordinator is having trouble securing programmers for her project. Every time she asks her boss to give a resource to the project he says that they are too busy to help out with her project. Which type of organization is she working in? FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. 9. A project manager is having trouble securing programmers for her project. Every time she asks the programming manager for resources for her project, he says they’re all assigned to other work. So she is constantly having to go over his head to overrule him. Which type of organization is she working for? FunctionalA. Weak MatrixB. Strong MatrixC. ProjectizedD. Exam Questions Download at Boykma.Com