1. 54 Chapter 2
exam questions
1. Which of the following is NOT a Project Constraint?
QualityA.
ScaleB.
TimeC.
CostD.
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he’s run over his budget because the staff turned out to be more expensive than
planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
QualityA.
ResourceB.
TimeC.
D. Cost
3. Which of the following is NOT an example of operational work?
Building a purchase order system for accounts payableA.
Submitting weekly purchase orders through a purchase order systemB.
Deploying weekly anti-virus software updatesC.
Yearly staff performance evaluationsD.
4. You’re managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is
the BEST way to handle this situation?
Refuse to work with him because he’s being difficultA.
Appeal to the accountant’s manager and ask to have him required to take trainingB.
Get a special dispensation so that the accountant doesn’t have to go to the trainingC.
Work with him to understand his concerns and do what you can to help alleviate them withoutD.
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
Resource ListA.
Stakeholder RegisterB.
Enterprise Environmental FactorsC.
Project PlanD.
Exam Questions
Download at Boykma.Com
2. you are here 4 55
organizations, constraints, and projects
6. Your manager asks you where to find a list of projects that should be managed together. What is
the BEST place to find this information?
Project PlanA.
Project CharterB.
Portfolio CharterC.
Program CharterD.
7. You want to know specifically which business goal a group of projects and programs are going to
accomplish. Which is the best place to look for this information?
Project PlanA.
Project CharterB.
Portfolio CharterC.
Program CharterD.
8. A project coordinator is having trouble securing programmers for her project. Every time she asks
her boss to give a resource to the project he says that they are too busy to help out with her project.
Which type of organization is she working in?
FunctionalA.
Weak MatrixB.
Strong MatrixC.
ProjectizedD.
9. A project manager is having trouble securing programmers for her project. Every time she asks
the programming manager for resources for her project, he says they’re all assigned to other work.
So she is constantly having to go over his head to overrule him. Which type of organization is she
working for?
FunctionalA.
Weak MatrixB.
Strong MatrixC.
ProjectizedD.
Exam Questions