2008 08-14-gantt
- 1. ID Durat Time distribution (in months)
Task Names Required Employees
ion 1 2 3 4 5 6 7 8 9 10 11 12
Development Phase (data Project manager, consultant doctor, content
1 .5m*
collection, translation) writer
Plan for implementation Project manager, interface designer, hardware
2 1.5m
engineer
Project manager, interface designer, content
3 Design 1.5m
writer
Project manager, interface designer, content
4 Implementation 1.5m
writer, hardware engineer, technician
Project manager, interface designer, hardware
5 Testing and trouble shooting .5m
engineer, technician
6 Report generation Project manager, content writer 2m
ID Durat Time distribution (in months)
Task Names Required Employees
ion 1 2 3 4 5 6 7 8 9 10 11 12
Development Phase (data Project manager, consultant doctor, content .5m
1
collection, translation) writer
Plan for implementation Project manager, interface designer, hardware 1.5m
2
engineer
Project manager, interface designer, content 1.5m
3 Design
writer
Project manager, interface designer, content 1.5m
4 Implementation
writer, hardware engineer, technician
Project manager, interface designer, hardware .5m
5 Testing and trouble shooting
engineer, technician
6 Report generation Project manager, content writer 2m
ID Durat Time distribution (in months)
Task Names Required Employees
ion 1 2 3 4 5 6 7 8 9 10 11 12
Plan for implementation Project manager, interface designer, hardware 1.5m
2
engineer
Project manager, interface designer, content 1.5m
3 Design
writer
Project manager, interface designer, content 1.5m
4 Implementation
writer, hardware engineer, technician
Project manager, interface designer, hardware .5m
5 Testing and trouble shooting
engineer, technician
6 Report generation Project manager, content writer 2m
* m = months