Flow chart of the process of application for
building plan approval
Consultant prepare and
submit the building plan
MPSJ
Plan is checked for
compliance of basic
requirements for
submission of plan.
If incomplete,
prepare letter of
non-compliance
and return to
consultant
If complied, open
file, calculate plan
processing fee and
send payment
notice to
Circulate plan to relevant
departments, i.e. Jabatan
Bomba, Health Department
and other departments, where
Jabatan Bomba, Health
Department and other
departments give comments
regarding the plan
Plan will be checked and if
there are complications or case
is not " straight forward " one,
the plan will be referred to the
Building Plans Committee
If does not
comply with
requirements,
letter
requesting
revision will be
prepared and
If complies with
requirements,
approval letter will be
prepared.
The consultant will be
contacted to collect the
building plan which has been
endorsed with approval
The approved
plan is filed.

More Related Content

What's hot

Intelligent building
Intelligent buildingIntelligent building
Intelligent buildingMohd. Ikhwan
 
Solids and voids an analysis of need for open space
Solids and voids   an analysis of need for open spaceSolids and voids   an analysis of need for open space
Solids and voids an analysis of need for open spaceGeeva Chandana
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSDigital Space Consultancy Ltd
 
Menara Dayabumi Analysis Report
Menara Dayabumi Analysis ReportMenara Dayabumi Analysis Report
Menara Dayabumi Analysis ReportjolynnTJL
 
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTA
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTAPERANAN PERANCANG BANDAR DALAM FIRMA SWASTA
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTAPenat Tapi Puas
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Reportashleyyeap
 
Cnh2 petaling jaya civic centre
Cnh2   petaling jaya civic centreCnh2   petaling jaya civic centre
Cnh2 petaling jaya civic centre杉 江紫
 
Local authority of lumut, perak
Local authority of lumut, perakLocal authority of lumut, perak
Local authority of lumut, perakEraz
 
Transfer of development right
Transfer of development rightTransfer of development right
Transfer of development rightDurgesh Tipayale
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAFakhrul Afifi
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Building Services Report
Building Services ReportBuilding Services Report
Building Services ReportJoanne Yunn Tze
 

What's hot (20)

BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnostic
 
Telekom Tower
Telekom TowerTelekom Tower
Telekom Tower
 
Intelligent building
Intelligent buildingIntelligent building
Intelligent building
 
Pm final
Pm finalPm final
Pm final
 
Utilitas 2 lift dan elevator
Utilitas 2 lift dan elevatorUtilitas 2 lift dan elevator
Utilitas 2 lift dan elevator
 
Solids and voids an analysis of need for open space
Solids and voids   an analysis of need for open spaceSolids and voids   an analysis of need for open space
Solids and voids an analysis of need for open space
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Building technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBSBuilding technology 1 "Industrialized Building System" IBS
Building technology 1 "Industrialized Building System" IBS
 
Menara Dayabumi Analysis Report
Menara Dayabumi Analysis ReportMenara Dayabumi Analysis Report
Menara Dayabumi Analysis Report
 
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTA
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTAPERANAN PERANCANG BANDAR DALAM FIRMA SWASTA
PERANAN PERANCANG BANDAR DALAM FIRMA SWASTA
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
 
High righ presentation
High righ presentationHigh righ presentation
High righ presentation
 
Cnh2 petaling jaya civic centre
Cnh2   petaling jaya civic centreCnh2   petaling jaya civic centre
Cnh2 petaling jaya civic centre
 
Local authority of lumut, perak
Local authority of lumut, perakLocal authority of lumut, perak
Local authority of lumut, perak
 
Transfer of development right
Transfer of development rightTransfer of development right
Transfer of development right
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Building Services Report
Building Services ReportBuilding Services Report
Building Services Report
 

More from chiasueyi

Cnc documentary
Cnc documentaryCnc documentary
Cnc documentarychiasueyi
 
Design journal 5
Design journal 5Design journal 5
Design journal 5chiasueyi
 
Design journal 4
Design journal 4Design journal 4
Design journal 4chiasueyi
 
Psy final project
Psy final projectPsy final project
Psy final projectchiasueyi
 
psy Report (1)
psy Report (1)psy Report (1)
psy Report (1)chiasueyi
 
Psy journal 2
Psy journal 2Psy journal 2
Psy journal 2chiasueyi
 
Psy journal 1
Psy journal 1Psy journal 1
Psy journal 1chiasueyi
 
Animated movies
Animated moviesAnimated movies
Animated movieschiasueyi
 
Animated movies (1) new
Animated movies (1) newAnimated movies (1) new
Animated movies (1) newchiasueyi
 
Object essay final
Object essay finalObject essay final
Object essay finalchiasueyi
 
Design journal 2
Design journal 2Design journal 2
Design journal 2chiasueyi
 
Design journal 2
Design journal 2Design journal 2
Design journal 2chiasueyi
 
Ici company profile
Ici company profileIci company profile
Ici company profilechiasueyi
 

More from chiasueyi (20)

Csi outdoor
Csi outdoorCsi outdoor
Csi outdoor
 
20 sketch
20 sketch20 sketch
20 sketch
 
20 sketch
20 sketch20 sketch
20 sketch
 
Week3
Week3Week3
Week3
 
Week2
Week2Week2
Week2
 
Cnc documentary
Cnc documentaryCnc documentary
Cnc documentary
 
Design journal 5
Design journal 5Design journal 5
Design journal 5
 
Design journal 4
Design journal 4Design journal 4
Design journal 4
 
Psy final project
Psy final projectPsy final project
Psy final project
 
psy Report (1)
psy Report (1)psy Report (1)
psy Report (1)
 
Psy journal 2
Psy journal 2Psy journal 2
Psy journal 2
 
Psy journal 1
Psy journal 1Psy journal 1
Psy journal 1
 
Animated movies
Animated moviesAnimated movies
Animated movies
 
Animated movies (1) new
Animated movies (1) newAnimated movies (1) new
Animated movies (1) new
 
Object essay final
Object essay finalObject essay final
Object essay final
 
Design journal 2
Design journal 2Design journal 2
Design journal 2
 
Design journal 2
Design journal 2Design journal 2
Design journal 2
 
Project
Project Project
Project
 
Ici company profile
Ici company profileIci company profile
Ici company profile
 
Ici
IciIci
Ici
 

Flow chart of the process of application for build

  • 1. Flow chart of the process of application for building plan approval Consultant prepare and submit the building plan MPSJ Plan is checked for compliance of basic requirements for submission of plan. If incomplete, prepare letter of non-compliance and return to consultant If complied, open file, calculate plan processing fee and send payment notice to Circulate plan to relevant departments, i.e. Jabatan Bomba, Health Department and other departments, where Jabatan Bomba, Health Department and other departments give comments regarding the plan Plan will be checked and if there are complications or case is not " straight forward " one, the plan will be referred to the Building Plans Committee If does not comply with requirements, letter requesting revision will be prepared and If complies with requirements, approval letter will be prepared. The consultant will be contacted to collect the building plan which has been endorsed with approval The approved plan is filed.