ID Subject Outline
Level
WBS        Duration Start Finish PredecesResource Names
0 New Jersey 0 New Jersey ‐ Assessment Item Development ‐ ELA and Mathe 524 days? Tue 4/23/13 Fri 4/24/15
1 Initiate 1 1 New Jersey Item Dev Project Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director
2 Initiate 2 1.1 Review Inputs to Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director
3 Initiate 3 1.1.1 Review Contract 1 day Tue 4/23/13 Tue 4/23/13 Project Manager
4 Initiate 3 1.1.2 Review Project Statement of Work 1 day Thu 4/25/13 Thu 4/25/13 Project Manager
5 Initiate 3 1.1.3 Review ASDS and WestEd Environmental Factors 1 day Thu 4/25/13 Thu 4/25/13 Project Manager
6 Initiate 3 1.1.4 Review Organizational Process Assets 1 day Thu 4/25/13 Thu 4/25/13 Project Manager
7 Initiate 2 1.2 Produce Outputs from Initiation 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager
8 Initiate 3 1.2.1 Develop Project Charter (3.2.1.1) 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager
9 Initiate 3 1.2.2 Develop Preliminary Project Scope Statement (3.2.1.2) 2 days Tue 4/23/13 Wed 4/24/13 2SS Project Manager
10 Initiate 2 1.3 Initiation Phase COMPLETE 0 days Tue 4/23/13 Tue 4/23/13 7SS Project Director
11 Plan 1 3 Planning Processes (3.2.2.1) 22 days? Wed 4/24/13 Thu 5/23/13 Content,Language C
12 Plan 2 3.1 Scope Management Processes 10 days? Wed 4/24/13 Tue 5/7/13 10SS Project Manager
13 Plan 3 3.1.1 Perform Scope Planning (3.2.2.2) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager
14 Plan 3 3.1.2 Complete Scope Definition (3.2.2.3) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager
15 Plan 3 3.1.3 Create WBS to level of Work Packages and Task Orders 
(3.2.2.4)
5 days? Wed 5/1/13 Tue 5/7/13 10SS Project Manager
16 Plan 2 3.2 Activity Planning 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Project Manager
17 Plan 3 3.2.1 Define Activities (3.2.2.5) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord
18 Plan 3 3.2.2 Determine Activity Sequence (3.2.2.6) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord
19 Plan 3 3.2.3 Define Activity Resource Estimates (3.2.2.7) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord
20 Plan 3 3.2.4 Define Activity Duration Estimates (3.2.2.8) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord
21 Plan 2 3.3 Cost Planning 5 days? Wed 4/24/13 Tue 4/30/13 16SS Project Director
22 Plan 3 3.3.1 Develop cost estimates (3.2.2.10) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Test Development Dir
23 Plan 3 3.3.2 Develop cost budget (3.2.2.11) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Operations Director
24 Plan 2 3.4 Complete Quality Plan (3.2.2.12) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Manager
25 Plan 2 3.5 Complete Human Resource Plan (3.2.2.13) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Director
26 Plan 2 3.6 Complete Communication Plan (3.2.2.14) 3 days Wed 4/24/13 Fri 4/26/13 12SS Project Manager
27 Plan 2 3.7 Risk Management Processes 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
28 Plan 3 3.7.1 Establish Risk Management Plan (3.2.2.15) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
29 Plan 3 3.7.2 Perform Initial Risk Identification (3.2.2.16) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
30 Plan 3 3.7.3 Establish Qualitative Risk Analysis Process (3.2.2.17) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15
Page 1
ID Subject Outline
Level
WBS        Duration Start Finish PredecesResource Names
31 Plan 3 3.7.4 Establish Quantitative Risk Analysis Process (3.2.2.18) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
32 Plan 3 3.7.5 Create Risk Response Planning Process (3.2.2.19) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager
33 Plan 2 3.8 Procurement Management Processes 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Director
34 Plan 3 3.8.1 Plan purchases and acquisitions (3.2.2.20) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager
35 Plan 3 3.8.2 Plan project contracting (3.2.2.21) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager
36 Plan 2 3.9 Complete Schedule Development (3.2.2.9) 17 days Wed 5/1/13 Thu 5/23/13 33 Project Manager
37 Plan 2 3.10 Planning Phase COMPLETE 0 days Wed 5/1/13 Wed 5/1/13 36SS Project Manager
38 Transition 1 5 Transition Planning, Execution  & Hand‐offs 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager
39 Transition 2 5.1 Transition Planning ‐ WestEd Protocols 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager
40 Transition 2 5.2 Transition Planning ‐ Subcontract Partners Protocols 4 days Wed 4/24/13 Mon 4/29/13 2SS Project Manager
41 Transition 2 5.3 Transition Planning by Assessment Content Areas 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager
42 2 5.5 Trasition Phase COMPLETE 0 days Wed 4/24/13 Wed 4/24/13 Project Manager
43 Execute 1 7 Execution and Monitoring & Controlling Processes 523 days? Wed 4/24/13 Fri 4/24/15 42SS Product manager
44 Execute 2 7.1  Direct and Manage Project Execution (3.2.3.1) 50 days Thu 5/30/13 Wed 8/7/13 Project Manager,Proj
45 Execute 3 7.1.1 Scheduled Project Status Meetings 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator
46 Execute 3 7.1.2 Ad‐hoc Project Status Meetings 30 days Thu 5/30/13 Wed 7/10/13 Project Coordinator
47 Execute 2 7.2  Monitoring and Controlling Processes (3.2.4) 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator,P
48 Execute 3 7.2.1 Scheduled Project Status Reporting (Monthly and Weekly) 50 days Thu 5/30/13 Wed 8/7/13 2SS Project Coordinator
49 Execute 3 7.2.2 Ad‐hoc Project Status Reporting 30 days Thu 5/30/13 Wed 7/10/13 2SS Project Coordinator
50 Execute 2 7.3 NJ Scope of Work for 2013‐14 (YEAR ONE) 236 days? Wed 4/24/13 Wed 3/19/14 ASDS
51 Execute 3 7.3.1 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Wed 4/24/13 Thu 4/25/13 2SS Project Manager
52 Execute 3 7.3.2 3.1  ESSENTIAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director
53 Execute 3 7.3.3 3.2  GENERAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director
54 Execute 4 7.3.3.1 3.2.1  WORK PLANS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager
55 Execute 4 7.3.3.2 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator
56 Execute 4 7.3.3.3 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager
57 Execute 4 7.3.3.4 3.2.4  YEARLY SCHEDULE 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager
58 Execute 4 7.3.3.5 3.2.5  TECHNICAL QUALITY 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Director
59 Execute 4 7.3.3.6 3.2.6  WEBSITE HOSTING 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator
60 Execute 4 7.3.3.7 3.2.7  DELIVERY OF MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator
61 Execute 4 7.3.3.8 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator
62 Execute 4 7.3.3.9 3.2.9  ALTERNATIVE PROCEDURES 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager
New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15
Page 2
ID Subject Outline
Level
WBS        Duration Start Finish PredecesResource Names
63 Execute 3 7.3.13 3.3  ASSESSMENT ITEM DEVELOPMENT 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content
64 Execute 4 7.3.13.1 3.3.1MATHEMATICS 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content
65 Execute 5 7.3.13.1.3 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content
66 Execute 5 7.3.13.1.4 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content
67 Execute 6 7.3.13.1.4.5 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content
68 Execute 6 7.3.13.1.4.6 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content
69 Execute 7 7.3.13.1.4.6 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content
70 Execute 4 7.3.13.2 3.3.2ENGLISH LANGUAGE ARTS (ELA) 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content
71 Execute 5 7.3.13.2.3 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Wed 4/24/13 Wed 4/24/13 Content
72 Execute 5 7.3.13.2.4 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content
73 Execute 6 7.3.13.2.4.5 3.3.2.2.1READING PASSAGES 1 day? Wed 4/24/13 Wed 4/24/13 Content
74 Execute 6 7.3.13.2.4.6 3.3.2.2.2WRITING PROMPTS 1 day? Wed 4/24/13 Wed 4/24/13 Content
75 Execute 7 7.3.13.2.4.6 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 Content
76 Execute 7 7.3.13.2.4.6 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content
77 Execute 7 7.3.13.2.4.6 3.3.2.2.4OPEN‐ENDED 1 day? Wed 4/24/13 Wed 4/24/13 Content
78 8 7.3.13.2.4.6 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Wed 4/24/13 Wed 4/24/13 Content
79 Execute 3 7.3.29 3.4  ASSESSMENT ITEM CODING 236 days Wed 4/24/13 Wed 3/19/1464SS,70SSContent
80 Execute 3 7.3.30 3.5  ASSESSMENT ITEM TRANSLATION 25 days Wed 4/24/13 Tue 5/28/13 63SS Language Center
81 Execute 3 7.3.31 3.6  PLANNING MEETINGS 234 days Wed 4/24/13 Mon 3/17/14 2SS Project Coordinator
82 Execute 3 7.3.32 3.7  CONTRACTOR STAFF 234 days Wed 4/24/13 Mon 3/17/14 2SS Content
83 Execute 2 7.4 NJ Scope of Work for 2014‐15 (YEAR TWO) 246 days? Thu 4/24/14 Thu 4/2/15 50 ASDS
84 Execute 3 7.4.33 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Thu 4/24/14 Fri 4/25/14 82 Project Manager
85 Execute 3 7.4.34 3.1  ESSENTIAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director
86 Execute 3 7.4.35 3.2  GENERAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director
87 Execute 4 7.4.35.10 3.2.1  WORK PLANS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager
88 Execute 4 7.4.35.11 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator
89 Execute 4 7.4.35.12 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager
90 Execute 4 7.4.35.13 3.2.4  YEARLY SCHEDULE 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager
91 Execute 4 7.4.35.14 3.2.5  TECHNICAL QUALITY 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Director
92 Execute 4 7.4.35.15 3.2.6  WEBSITE HOSTING 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator
93 Execute 4 7.4.35.16 3.2.7  DELIVERY OF MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator
94 Execute 4 7.4.35.17 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator
New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15
Page 3
ID Subject Outline
Level
WBS        Duration Start Finish PredecesResource Names
95 Execute 4 7.4.35.18 3.2.9  ALTERNATIVE PROCEDURES 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager
96 Execute 3 7.4.36 3.3  ASSESSMENT ITEM DEVELOPMENT 1 day? Thu 4/24/14 Thu 4/24/14 63 Content
97 Execute 4 7.4.36.3 3.3.1MATHEMATICS 1 day? Thu 4/24/14 Thu 4/24/14 Content
98 Execute 5 7.4.36.3.5 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content
99 Execute 5 7.4.36.3.6 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 1 day? Thu 4/24/14 Thu 4/24/14 Content
100 Execute 6 7.4.36.3.6.7 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content
101 Execute 6 7.4.36.3.6.8 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Thu 4/24/14 Thu 4/24/14 Content
102 Execute 7 7.4.36.3.6.8 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content
103 Execute 4 7.4.36.4 3.3.2ENGLISH LANGUAGE ARTS (ELA) 1 day? Thu 4/24/14 Thu 4/24/14 Content
104 Execute 5 7.4.36.4.5 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content
105 Execute 5 7.4.36.4.6 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content
106 Execute 6 7.4.36.4.6.7 3.3.2.2.1READING PASSAGES 1 day? Thu 4/24/14 Thu 4/24/14 Content
107 Execute 6 7.4.36.4.6.8 3.3.2.2.2WRITING PROMPTS 1 day? Thu 4/24/14 Thu 4/24/14 Content
108 Execute 7 7.4.36.4.6.8 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content
109 Execute 7 7.4.36.4.6.8 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content
110 Execute 7 7.4.36.4.6.8 3.3.2.2.4OPEN‐ENDED 1 day? Thu 4/24/14 Thu 4/24/14 Content
111 8 7.4.36.4.6.8 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Thu 4/24/14 Thu 4/24/14 Content
112 Execute 3 7.4.37 3.4  ASSESSMENT ITEM CODING 236 days Thu 4/24/14 Thu 3/19/15 96SS Content
113 Execute 3 7.4.38 3.5  ASSESSMENT ITEM TRANSLATION 236 days Fri 4/25/14 Fri 3/20/15 96 Language Center
114 Execute 3 7.4.39 3.6  PLANNING MEETINGS 236 days Fri 4/25/14 Fri 3/20/15 82 Project Coordinator
115 Execute 3 7.4.40 3.7  CONTRACTOR STAFF 245 days Fri 4/25/14 Thu 4/2/15 82 Content
116 Execute 2 7.5 Execution, Monitoring & Controlling COMPLETE 263 days Wed 4/23/14 Fri 4/24/15 Project Manager
117 3 7.5.3 Year One ‐ Project Effort Complete 0 days Wed 4/23/14 Wed 4/23/14 50SS Project Manager
118 3 7.5.4 Year Two ‐ Project Effort Complete 0 days Fri 4/24/15 Fri 4/24/15 Project Manager
119 Close 1 8  Close Project (3.2.5.1) 11 days Fri 4/10/15 Fri 4/24/15 Project Manager
120 Close 2 8.5 Year One ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator
121 Close 2 8.6 Year Two ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator
122 Close 2 8.2 Complete Contract Closure (3.2.5.2) 10 days Mon 4/13/15 Fri 4/24/15 Project Manager
123 Close 2 8.7 Closing Processes COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 122 Project Director
124 Close 1 10 Project COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 123 Project Director
New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15
Page 4

More Related Content

Similar to NJ_RFP_Project-Schedule_v2_cfc_03-02-13

Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxmaoanderton
 
In the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docxIn the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docxjaggernaoma
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortKevin C. McCormack, PMP
 
carta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfcarta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfnazeqhaikal666
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart finalDan Palmer
 
Time unit 2012 nov 12 part 1
Time unit 2012 nov 12   part 1 Time unit 2012 nov 12   part 1
Time unit 2012 nov 12 part 1 Skript
 
UMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group PresentationUMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group PresentationThe Integral Worm
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxwilcockiris
 
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxDirections for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxduketjoy27252
 
Shneha single page
Shneha single pageShneha single page
Shneha single pageshneha patel
 
CUP (BI - T5).docx
CUP (BI - T5).docxCUP (BI - T5).docx
CUP (BI - T5).docxVina97
 
How to plan any project
How to plan any projectHow to plan any project
How to plan any projectBFieggen
 
Project ms pendataan perkebunan kota pekanbaru
Project ms pendataan perkebunan kota pekanbaruProject ms pendataan perkebunan kota pekanbaru
Project ms pendataan perkebunan kota pekanbaruNennyTriwahyunie
 
rm-052-coordinators-and-presenters-mtng.pptx
rm-052-coordinators-and-presenters-mtng.pptxrm-052-coordinators-and-presenters-mtng.pptx
rm-052-coordinators-and-presenters-mtng.pptxLucilleDominguez
 
Hotel opening checklist
Hotel opening checklistHotel opening checklist
Hotel opening checklisttuan nguyen
 

Similar to NJ_RFP_Project-Schedule_v2_cfc_03-02-13 (20)

Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docxSheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
Sheet1Work Breakdown StructureProject NameDistrict 4 Warehouse Mo.docx
 
In the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docxIn the journal article by McCormick and White (Fall 2000) about th.docx
In the journal article by McCormick and White (Fall 2000) about th.docx
 
Sample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure EffortSample_Project Template - 6 0 - Infrastructure Effort
Sample_Project Template - 6 0 - Infrastructure Effort
 
Standard Competition 12 Months
Standard Competition 12 MonthsStandard Competition 12 Months
Standard Competition 12 Months
 
Projec
ProjecProjec
Projec
 
carta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfcarta gantt projek nazeq.pdf
carta gantt projek nazeq.pdf
 
WBS
WBSWBS
WBS
 
Gantt chart final
Gantt chart finalGantt chart final
Gantt chart final
 
Time unit 2012 nov 12 part 1
Time unit 2012 nov 12   part 1 Time unit 2012 nov 12   part 1
Time unit 2012 nov 12 part 1
 
UMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group PresentationUMBC IFSM438 Project Management Group Presentation
UMBC IFSM438 Project Management Group Presentation
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
 
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docxDirections for Downloading and Installing OpenProjMGT 402_Pro.docx
Directions for Downloading and Installing OpenProjMGT 402_Pro.docx
 
Dwdm teaching r13(1)
Dwdm teaching r13(1)Dwdm teaching r13(1)
Dwdm teaching r13(1)
 
Shneha single page
Shneha single pageShneha single page
Shneha single page
 
CUP (BI - T5).docx
CUP (BI - T5).docxCUP (BI - T5).docx
CUP (BI - T5).docx
 
How to plan any project
How to plan any projectHow to plan any project
How to plan any project
 
Project ms pendataan perkebunan kota pekanbaru
Project ms pendataan perkebunan kota pekanbaruProject ms pendataan perkebunan kota pekanbaru
Project ms pendataan perkebunan kota pekanbaru
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
rm-052-coordinators-and-presenters-mtng.pptx
rm-052-coordinators-and-presenters-mtng.pptxrm-052-coordinators-and-presenters-mtng.pptx
rm-052-coordinators-and-presenters-mtng.pptx
 
Hotel opening checklist
Hotel opening checklistHotel opening checklist
Hotel opening checklist
 

More from Carlos F. Camargo, Ph.D. - Realtor, CalBRE #01988431

More from Carlos F. Camargo, Ph.D. - Realtor, CalBRE #01988431 (20)

BackwardsDesignPedagogy_OUSD_Camargo
BackwardsDesignPedagogy_OUSD_CamargoBackwardsDesignPedagogy_OUSD_Camargo
BackwardsDesignPedagogy_OUSD_Camargo
 
Camargo_Strawman_Aspire Public Schools - Work Plan
Camargo_Strawman_Aspire Public Schools - Work PlanCamargo_Strawman_Aspire Public Schools - Work Plan
Camargo_Strawman_Aspire Public Schools - Work Plan
 
AltoWeb_SPEED_Overview-2001
AltoWeb_SPEED_Overview-2001AltoWeb_SPEED_Overview-2001
AltoWeb_SPEED_Overview-2001
 
Women Leaders for the World-GWLN_2008-sm
Women Leaders for the World-GWLN_2008-smWomen Leaders for the World-GWLN_2008-sm
Women Leaders for the World-GWLN_2008-sm
 
GWLN-Proposal-Workbook
GWLN-Proposal-WorkbookGWLN-Proposal-Workbook
GWLN-Proposal-Workbook
 
GWLN-FoundationList
GWLN-FoundationListGWLN-FoundationList
GWLN-FoundationList
 
CP-GWLN-FEMALE ECONOMIC EMANCIPATION
CP-GWLN-FEMALE ECONOMIC EMANCIPATIONCP-GWLN-FEMALE ECONOMIC EMANCIPATION
CP-GWLN-FEMALE ECONOMIC EMANCIPATION
 
8May2009-PovertyEdCrisis-SVEF
8May2009-PovertyEdCrisis-SVEF8May2009-PovertyEdCrisis-SVEF
8May2009-PovertyEdCrisis-SVEF
 
ICT-Vision-Brief-Camargo
ICT-Vision-Brief-CamargoICT-Vision-Brief-Camargo
ICT-Vision-Brief-Camargo
 
Environmental Literacy Grant_View from Space_VfS 2009
Environmental Literacy Grant_View from Space_VfS 2009Environmental Literacy Grant_View from Space_VfS 2009
Environmental Literacy Grant_View from Space_VfS 2009
 
EDS_NGEE-Tropics_Project_Insights-CFC_Redacted
EDS_NGEE-Tropics_Project_Insights-CFC_RedactedEDS_NGEE-Tropics_Project_Insights-CFC_Redacted
EDS_NGEE-Tropics_Project_Insights-CFC_Redacted
 
Ops Research_Narcam_1993-FAA-DOT
Ops Research_Narcam_1993-FAA-DOTOps Research_Narcam_1993-FAA-DOT
Ops Research_Narcam_1993-FAA-DOT
 
ICT-IdentityStrategy_2007.pdf
ICT-IdentityStrategy_2007.pdfICT-IdentityStrategy_2007.pdf
ICT-IdentityStrategy_2007.pdf
 
FHS-OverviewVESLContent
FHS-OverviewVESLContentFHS-OverviewVESLContent
FHS-OverviewVESLContent
 
Building Teams by Defining Roles and Responsibility in Meetings
Building Teams by Defining Roles and Responsibility in MeetingsBuilding Teams by Defining Roles and Responsibility in Meetings
Building Teams by Defining Roles and Responsibility in Meetings
 
Empowering New American Communities in the Bay Area
Empowering New American Communities in the Bay AreaEmpowering New American Communities in the Bay Area
Empowering New American Communities in the Bay Area
 
La Planificación Integrada de Negocios
La Planificación Integrada de NegociosLa Planificación Integrada de Negocios
La Planificación Integrada de Negocios
 
LoanPackageDevelopment
LoanPackageDevelopmentLoanPackageDevelopment
LoanPackageDevelopment
 
ACC - The ABCs of Starting A Business
ACC - The ABCs of Starting A BusinessACC - The ABCs of Starting A Business
ACC - The ABCs of Starting A Business
 
Best Practices Accelerator
Best Practices AcceleratorBest Practices Accelerator
Best Practices Accelerator
 

NJ_RFP_Project-Schedule_v2_cfc_03-02-13

  • 1. ID Subject Outline Level WBS        Duration Start Finish PredecesResource Names 0 New Jersey 0 New Jersey ‐ Assessment Item Development ‐ ELA and Mathe 524 days? Tue 4/23/13 Fri 4/24/15 1 Initiate 1 1 New Jersey Item Dev Project Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director 2 Initiate 2 1.1 Review Inputs to Initiation 4 days Tue 4/23/13 Fri 4/26/13 Project Director 3 Initiate 3 1.1.1 Review Contract 1 day Tue 4/23/13 Tue 4/23/13 Project Manager 4 Initiate 3 1.1.2 Review Project Statement of Work 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 5 Initiate 3 1.1.3 Review ASDS and WestEd Environmental Factors 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 6 Initiate 3 1.1.4 Review Organizational Process Assets 1 day Thu 4/25/13 Thu 4/25/13 Project Manager 7 Initiate 2 1.2 Produce Outputs from Initiation 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager 8 Initiate 3 1.2.1 Develop Project Charter (3.2.1.1) 3 days Tue 4/23/13 Thu 4/25/13 2SS Project Manager 9 Initiate 3 1.2.2 Develop Preliminary Project Scope Statement (3.2.1.2) 2 days Tue 4/23/13 Wed 4/24/13 2SS Project Manager 10 Initiate 2 1.3 Initiation Phase COMPLETE 0 days Tue 4/23/13 Tue 4/23/13 7SS Project Director 11 Plan 1 3 Planning Processes (3.2.2.1) 22 days? Wed 4/24/13 Thu 5/23/13 Content,Language C 12 Plan 2 3.1 Scope Management Processes 10 days? Wed 4/24/13 Tue 5/7/13 10SS Project Manager 13 Plan 3 3.1.1 Perform Scope Planning (3.2.2.2) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager 14 Plan 3 3.1.2 Complete Scope Definition (3.2.2.3) 5 days? Wed 4/24/13 Tue 4/30/13 10SS Project Manager 15 Plan 3 3.1.3 Create WBS to level of Work Packages and Task Orders  (3.2.2.4) 5 days? Wed 5/1/13 Tue 5/7/13 10SS Project Manager 16 Plan 2 3.2 Activity Planning 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Project Manager 17 Plan 3 3.2.1 Define Activities (3.2.2.5) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 18 Plan 3 3.2.2 Determine Activity Sequence (3.2.2.6) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 19 Plan 3 3.2.3 Define Activity Resource Estimates (3.2.2.7) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 20 Plan 3 3.2.4 Define Activity Duration Estimates (3.2.2.8) 6.67 days? Wed 4/24/13 Thu 5/2/13 10SS Content,Project Coord 21 Plan 2 3.3 Cost Planning 5 days? Wed 4/24/13 Tue 4/30/13 16SS Project Director 22 Plan 3 3.3.1 Develop cost estimates (3.2.2.10) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Test Development Dir 23 Plan 3 3.3.2 Develop cost budget (3.2.2.11) 5 days? Wed 4/24/13 Tue 4/30/13 16SS Operations Director 24 Plan 2 3.4 Complete Quality Plan (3.2.2.12) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Manager 25 Plan 2 3.5 Complete Human Resource Plan (3.2.2.13) 3 days Wed 4/24/13 Fri 4/26/13 16SS Project Director 26 Plan 2 3.6 Complete Communication Plan (3.2.2.14) 3 days Wed 4/24/13 Fri 4/26/13 12SS Project Manager 27 Plan 2 3.7 Risk Management Processes 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 28 Plan 3 3.7.1 Establish Risk Management Plan (3.2.2.15) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 29 Plan 3 3.7.2 Perform Initial Risk Identification (3.2.2.16) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 30 Plan 3 3.7.3 Establish Qualitative Risk Analysis Process (3.2.2.17) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15 Page 1
  • 2. ID Subject Outline Level WBS        Duration Start Finish PredecesResource Names 31 Plan 3 3.7.4 Establish Quantitative Risk Analysis Process (3.2.2.18) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 32 Plan 3 3.7.5 Create Risk Response Planning Process (3.2.2.19) 2 days Wed 4/24/13 Thu 4/25/13 12SS Project Manager 33 Plan 2 3.8 Procurement Management Processes 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Director 34 Plan 3 3.8.1 Plan purchases and acquisitions (3.2.2.20) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager 35 Plan 3 3.8.2 Plan project contracting (3.2.2.21) 5 days Wed 4/24/13 Tue 4/30/1316SS,21SSProject Manager 36 Plan 2 3.9 Complete Schedule Development (3.2.2.9) 17 days Wed 5/1/13 Thu 5/23/13 33 Project Manager 37 Plan 2 3.10 Planning Phase COMPLETE 0 days Wed 5/1/13 Wed 5/1/13 36SS Project Manager 38 Transition 1 5 Transition Planning, Execution  & Hand‐offs 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager 39 Transition 2 5.1 Transition Planning ‐ WestEd Protocols 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager 40 Transition 2 5.2 Transition Planning ‐ Subcontract Partners Protocols 4 days Wed 4/24/13 Mon 4/29/13 2SS Project Manager 41 Transition 2 5.3 Transition Planning by Assessment Content Areas 5 days Tue 4/23/13 Mon 4/29/13 2SS Project Manager 42 2 5.5 Trasition Phase COMPLETE 0 days Wed 4/24/13 Wed 4/24/13 Project Manager 43 Execute 1 7 Execution and Monitoring & Controlling Processes 523 days? Wed 4/24/13 Fri 4/24/15 42SS Product manager 44 Execute 2 7.1  Direct and Manage Project Execution (3.2.3.1) 50 days Thu 5/30/13 Wed 8/7/13 Project Manager,Proj 45 Execute 3 7.1.1 Scheduled Project Status Meetings 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator 46 Execute 3 7.1.2 Ad‐hoc Project Status Meetings 30 days Thu 5/30/13 Wed 7/10/13 Project Coordinator 47 Execute 2 7.2  Monitoring and Controlling Processes (3.2.4) 50 days Thu 5/30/13 Wed 8/7/13 Project Coordinator,P 48 Execute 3 7.2.1 Scheduled Project Status Reporting (Monthly and Weekly) 50 days Thu 5/30/13 Wed 8/7/13 2SS Project Coordinator 49 Execute 3 7.2.2 Ad‐hoc Project Status Reporting 30 days Thu 5/30/13 Wed 7/10/13 2SS Project Coordinator 50 Execute 2 7.3 NJ Scope of Work for 2013‐14 (YEAR ONE) 236 days? Wed 4/24/13 Wed 3/19/14 ASDS 51 Execute 3 7.3.1 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Wed 4/24/13 Thu 4/25/13 2SS Project Manager 52 Execute 3 7.3.2 3.1  ESSENTIAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director 53 Execute 3 7.3.3 3.2  GENERAL REQUIREMENTS 30 days Wed 4/24/13 Tue 6/4/13 2SS Project Director 54 Execute 4 7.3.3.1 3.2.1  WORK PLANS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager 55 Execute 4 7.3.3.2 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator 56 Execute 4 7.3.3.3 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager 57 Execute 4 7.3.3.4 3.2.4  YEARLY SCHEDULE 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager 58 Execute 4 7.3.3.5 3.2.5  TECHNICAL QUALITY 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Director 59 Execute 4 7.3.3.6 3.2.6  WEBSITE HOSTING 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator 60 Execute 4 7.3.3.7 3.2.7  DELIVERY OF MATERIALS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator 61 Execute 4 7.3.3.8 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Coordinator 62 Execute 4 7.3.3.9 3.2.9  ALTERNATIVE PROCEDURES 1 day? Wed 4/24/13 Wed 4/24/13 2SS Project Manager New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15 Page 2
  • 3. ID Subject Outline Level WBS        Duration Start Finish PredecesResource Names 63 Execute 3 7.3.13 3.3  ASSESSMENT ITEM DEVELOPMENT 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content 64 Execute 4 7.3.13.1 3.3.1MATHEMATICS 26.33 days? Wed 4/24/13 Thu 5/30/13 2SS Content 65 Execute 5 7.3.13.1.3 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content 66 Execute 5 7.3.13.1.4 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content 67 Execute 6 7.3.13.1.4.5 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content 68 Execute 6 7.3.13.1.4.6 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content 69 Execute 7 7.3.13.1.4.6 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 2SS Content 70 Execute 4 7.3.13.2 3.3.2ENGLISH LANGUAGE ARTS (ELA) 26.33 days Wed 4/24/13 Thu 5/30/13 2SS Content 71 Execute 5 7.3.13.2.3 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Wed 4/24/13 Wed 4/24/13 Content 72 Execute 5 7.3.13.2.4 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content 73 Execute 6 7.3.13.2.4.5 3.3.2.2.1READING PASSAGES 1 day? Wed 4/24/13 Wed 4/24/13 Content 74 Execute 6 7.3.13.2.4.6 3.3.2.2.2WRITING PROMPTS 1 day? Wed 4/24/13 Wed 4/24/13 Content 75 Execute 7 7.3.13.2.4.6 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Wed 4/24/13 Wed 4/24/13 Content 76 Execute 7 7.3.13.2.4.6 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Wed 4/24/13 Wed 4/24/13 Content 77 Execute 7 7.3.13.2.4.6 3.3.2.2.4OPEN‐ENDED 1 day? Wed 4/24/13 Wed 4/24/13 Content 78 8 7.3.13.2.4.6 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Wed 4/24/13 Wed 4/24/13 Content 79 Execute 3 7.3.29 3.4  ASSESSMENT ITEM CODING 236 days Wed 4/24/13 Wed 3/19/1464SS,70SSContent 80 Execute 3 7.3.30 3.5  ASSESSMENT ITEM TRANSLATION 25 days Wed 4/24/13 Tue 5/28/13 63SS Language Center 81 Execute 3 7.3.31 3.6  PLANNING MEETINGS 234 days Wed 4/24/13 Mon 3/17/14 2SS Project Coordinator 82 Execute 3 7.3.32 3.7  CONTRACTOR STAFF 234 days Wed 4/24/13 Mon 3/17/14 2SS Content 83 Execute 2 7.4 NJ Scope of Work for 2014‐15 (YEAR TWO) 246 days? Thu 4/24/14 Thu 4/2/15 50 ASDS 84 Execute 3 7.4.33 3.0  Kick‐off ‐ NJ  ASSESSMENT ITEM DEVELOPMENT 2 days Thu 4/24/14 Fri 4/25/14 82 Project Manager 85 Execute 3 7.4.34 3.1  ESSENTIAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director 86 Execute 3 7.4.35 3.2  GENERAL REQUIREMENTS 236 days Thu 4/24/14 Thu 3/19/15 82 Project Director 87 Execute 4 7.4.35.10 3.2.1  WORK PLANS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager 88 Execute 4 7.4.35.11 3.2.2  DOCUMENTS AND PRINTED MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator 89 Execute 4 7.4.35.12 3.2.3  MONTHLY PROGRESS REPORTS AND MEETING MIN 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager 90 Execute 4 7.4.35.13 3.2.4  YEARLY SCHEDULE 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager 91 Execute 4 7.4.35.14 3.2.5  TECHNICAL QUALITY 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Director 92 Execute 4 7.4.35.15 3.2.6  WEBSITE HOSTING 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator 93 Execute 4 7.4.35.16 3.2.7  DELIVERY OF MATERIALS 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator 94 Execute 4 7.4.35.17 3.2.8  PROGRAM DOCUMENTS ELECTRONIC FOLDER 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Coordinator New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15 Page 3
  • 4. ID Subject Outline Level WBS        Duration Start Finish PredecesResource Names 95 Execute 4 7.4.35.18 3.2.9  ALTERNATIVE PROCEDURES 1 day? Thu 4/24/14 Thu 4/24/14 2SS Project Manager 96 Execute 3 7.4.36 3.3  ASSESSMENT ITEM DEVELOPMENT 1 day? Thu 4/24/14 Thu 4/24/14 63 Content 97 Execute 4 7.4.36.3 3.3.1MATHEMATICS 1 day? Thu 4/24/14 Thu 4/24/14 Content 98 Execute 5 7.4.36.3.5 3.3.1.1GRADES K‐2 MATHEMATICS TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content 99 Execute 5 7.4.36.3.6 3.3.1.2GRADES 3‐12 MATHEMATICS ASSESSMENT ITEM 1 day? Thu 4/24/14 Thu 4/24/14 Content 100 Execute 6 7.4.36.3.6.7 3.3.1.2.1MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content 101 Execute 6 7.4.36.3.6.8 3.3.1.2.2OPEN‐ENDED/PERFORMANCE BASED TASK 1 day? Thu 4/24/14 Thu 4/24/14 Content 102 Execute 7 7.4.36.3.6.8 3.3.1.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content 103 Execute 4 7.4.36.4 3.3.2ENGLISH LANGUAGE ARTS (ELA) 1 day? Thu 4/24/14 Thu 4/24/14 Content 104 Execute 5 7.4.36.4.5 3.3.2.1GRADE K‐2 ELA TASKS 1 day? Thu 4/24/14 Thu 4/24/14 Content 105 Execute 5 7.4.36.4.6 3.3.2.2ELA GRADE 3‐12 ELA ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content 106 Execute 6 7.4.36.4.6.7 3.3.2.2.1READING PASSAGES 1 day? Thu 4/24/14 Thu 4/24/14 Content 107 Execute 6 7.4.36.4.6.8 3.3.2.2.2WRITING PROMPTS 1 day? Thu 4/24/14 Thu 4/24/14 Content 108 Execute 7 7.4.36.4.6.8 3.3.2.2.2.1 ITEM‐SPECIFIC RUBRIC DEVELOPMEN 1 day? Thu 4/24/14 Thu 4/24/14 Content 109 Execute 7 7.4.36.4.6.8 3.3.2.2.3MULTIPLE CHOICE ASSESSMENT ITEMS 1 day? Thu 4/24/14 Thu 4/24/14 Content 110 Execute 7 7.4.36.4.6.8 3.3.2.2.4OPEN‐ENDED 1 day? Thu 4/24/14 Thu 4/24/14 Content 111 8 7.4.36.4.6.8 3.3.2.2.4.1 ITEM‐SPECIFIC RUBRIC DEVELOPM 1 day? Thu 4/24/14 Thu 4/24/14 Content 112 Execute 3 7.4.37 3.4  ASSESSMENT ITEM CODING 236 days Thu 4/24/14 Thu 3/19/15 96SS Content 113 Execute 3 7.4.38 3.5  ASSESSMENT ITEM TRANSLATION 236 days Fri 4/25/14 Fri 3/20/15 96 Language Center 114 Execute 3 7.4.39 3.6  PLANNING MEETINGS 236 days Fri 4/25/14 Fri 3/20/15 82 Project Coordinator 115 Execute 3 7.4.40 3.7  CONTRACTOR STAFF 245 days Fri 4/25/14 Thu 4/2/15 82 Content 116 Execute 2 7.5 Execution, Monitoring & Controlling COMPLETE 263 days Wed 4/23/14 Fri 4/24/15 Project Manager 117 3 7.5.3 Year One ‐ Project Effort Complete 0 days Wed 4/23/14 Wed 4/23/14 50SS Project Manager 118 3 7.5.4 Year Two ‐ Project Effort Complete 0 days Fri 4/24/15 Fri 4/24/15 Project Manager 119 Close 1 8  Close Project (3.2.5.1) 11 days Fri 4/10/15 Fri 4/24/15 Project Manager 120 Close 2 8.5 Year One ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator 121 Close 2 8.6 Year Two ‐ Project Close 10 days Fri 4/10/15 Thu 4/23/15 Project Coordinator 122 Close 2 8.2 Complete Contract Closure (3.2.5.2) 10 days Mon 4/13/15 Fri 4/24/15 Project Manager 123 Close 2 8.7 Closing Processes COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 122 Project Director 124 Close 1 10 Project COMPLETE 0 days Fri 4/24/15 Fri 4/24/15 123 Project Director New Jersey ‐ Assessment Item Development ‐ ELA and Mathematics 2013‐15 Page 4