City council 8 6-13 ai 21 and 22 smith blvd presentation
- 1. Smith Blvd & Paulann Blvd
Improvements
Robert Schneeman, Interim Director of
Economic Development
- 7. Paulann & Smith Blvd. Extension
Cost Estimates Original Estimate $350,000
Council Meeting July 2012
Option 2
Paulann Blvd. Half Width (32โ)
& Smith Blvd.(26โ)
$443,030.23
Option 1
Paulann Blvd. Full Width (64โ)
& Smith Blvd.(26โ)
$512,867.58