SlideShare a Scribd company logo
1 of 56
3RD MUTUAL DRY ROT PROBLEM
A SYSTEMS APPROACH
PART TWO
A SYSTEMS APPROACH PART TWO
• 2.1 The Dry Rot Paradigm
• 2.2 Data Analysis
• 2.3 A Pilot Program
• 2.4 Trade-Off Studies
2.1 THE DRY ROT PARADIGM
• The Dry Rot Dichotomy
• The Legacy Dry Rot Program
• Major Repairs Remaining
• What Can Be Done?
• Prevention/Remediation
• A New Dry Rot Paradigm
• Why No Model Metrics
• A New Metric
THE DRY ROT DICHOTOMY
• Paint Issues
– Facia, Outlookers, Eaves, Trellises, Minor Beams
• Mostly Cosmetic
• Minor to Moderate Costs
• Common to All Model Types
• Detected By PTP (Prior To Paint)
• Examples
– CDS (Cul De Sac) 212, 2011 Mid-Cycle, 2012 Mid-Cycle
THE DRY ROT DICHOTOMY (cont)
• Major Repair Caused By:
– Cracked Stucco, Parapet Leaks, Joints, Overlaps
• Structural
• Catastrophic/High
• Design/Construction Flaws Model Specific
• Detected By Other Than PTP
• Examples
– Villa Paraiso, Garden Villa Types, LH21 Types
THE LEGASY DRY ROT PROGRAM
• Grew Out Of Paint Program
• Program Is Building Centric
• PTP Began As Paint Preparation
• 10 % Of Buildings Inspected/Painted Per Year
• Simple And Logical
BUT
• 90% Not Inspected Per Year
• Up To 9 Years Between Problems Detected
And Corrections Made
• Waits For PTP to Report Dry Rot Damage
• PTP Does Not Look For Internal Problems
• Major Problems Managed Ad Hoc
• Does Not Use Model Metrics
• Poor Spore Control Practices
WHAT HAPPENED
• Major Problems Found Late
• Models With Known Major Problems
– Garden Villa Types-Leaks At Flashing Overlaps,
Water Collection At Support Joints
– LH21 Types-Cracked Stucco/Parapet Leaks
– Villa Paraiso-Cracked Stucco/Parapet Leaks
• Unknown Other Model Problems
• Dry Rot Damage Severe
MAJOR REPAIRS REMAINING
• You Can Ignore the Problem But You Cannot
Ignore the Consequences
• Significant Damage Already Done
• What We Currently Know-Cost Remain Total
– Garden Villa Type 53 $1,000,000. 52 $52,000,000.
• Garden Villa 19
• Casa Dorado 2
• El Mirador 15
• Villa Capri 10
• Villa Puerta 7
MAJOR REPAIRS REMAINING (CONT)
– LH21 Type 28 $100,000. 21 $2,100,000.
• Villa Nueva 15
• Sierra 7
• Aragon 6
– Villa Paraiso 109 $ 50,000. 108 $5,400,000.
• How Can We Protect Our Remaining
Buildings?
EFFORT TO DATE
• Repair Work Started
• Engineering Design Fixes Identified
• RFP to Contractors For Current Year Buildings
• Waiting For PTP To Report Candidate
Buildings
WHAT CAN BE DONE?
• Can A Preventative Program Stop Fungus
Spread And Any Further Damage?
• Can A Temporary Fix Stop Further Damage?
• Will a Temporary Fix Reduce Costs?
• Can We Stop Fungus from Infecting Building
With No Dry Rot?
• Can We Identify Other Models With Systemic
Problems?
PREVENTION/REMEDIATION
• Early Detection of a Problem
• Analyze Problem
– What Models Need Help
– Which Buildings are Candidates for Prevention
– Which Buildings Offer Greatest Savings
• Stop Fungus
– Dry Out Infected Areas
• Prevent Further Leaks
– Seal Roofs and Parapets, Add Flashing
• Prevent Leaks to Undamaged Buildings
• Start Pilot Program to Investigate Cost Savings
A NEW DRY ROT PARADIGM
• Create A Program With Feedback That Reduces
Dry Rot Damage
• Feedback Information Gathered On Models To
Fix Problems More Timely
• Design fixes That Reduce Future Damage
• Continue PTP And New Paint Program
• Include An Early Detection Process
• Set Priorities For Maximum Cost Savings
• Start Pilot Programs to Confirm Cost Savings
WHY NOT USE MANOR METRICS?
• A List Of Building Numbers With Costs Not
Informative
• Easiest Way To Normalize Building Size And
Cost
• Track Systemic Model Problems And Costs
• Easy To Relate To- How Residents Are Charged
• Create A Manor Centric Data Base
• Add Model Type to Dry Rot Reports
– Model Type, Manors/Building, Detected By, and
THE NEW METRIC
• Cost Per Building/Number Of Manors Per
Building/Cycle( Time Between
Paintings)/Month
• If Costs Go Up – Metric Goes Up
• If Number Of Manors Go Up – Metric Goes
Down
• If Cycle Time Goes Up – Metric Goes Down
• If Cycle Time goes Down – Metric Goes Up
THE NEW METRIC (CONT.)
• Normalizes Building Size
• Closely Follows Square Feet Paint
• A Better Tool For Cost Estimating
• Compares Building Size and Model Types
2.2 DATA ANALYSIS
• CDS 212 Pilot Program
• 2011 Mid-Cycle Repair Bid
– 64 Building/18 Model Metrics
– CDS 212 23Building/9 Model Metrics
– 6 Building/2 Model No Dry Rot Found
– Metric By CDS and Map of Distribution
• 2012 Mid-Cycle Repair Bid
– 81 Building/22 Model Metrics
– 51 Building/6 Model No Dry Rot Found
CDS 212
• Pilot Program To Estimate Mid-Cycle Costs
• CDS 212 24 Buildings, 160 Manors
• Cost/ Program Confusion
– 14 Buildings At $98,185.00 Or
– 23 Buildings At $40610.00
• CDS 212 Mostly Large Buildings
• Used to Estimate Costs of Mostly Small
Buildings
2011 MID-CYCLE PROGRAM
• 100 Buildings Painted in 2006 (Old Paint)
• 23 Buildings Repaired in CDS 212
– Actual Costs Available
• 64 Buildings Outsourced For Dry Rot Repairs
– Cost Bid Received, Contract Let, Only Estimated
Costs Available, Repairs in 2015
• 6 Buildings Found No Dry Rot
• 9 Year Cycle (Time Between 2015-2006)
2011 MID-CYCLE ANALYSIS
SUMMARY
• 64 Buildings 18 Models 231 Manors
– Average For Metric $4.60/m/c/m
– 4 Models with high Metrics – Casa Rosa (3), Casa
Rosa (2), Cabrillo (3), Villa Fuente (3)
– 10 Building Have Problems
– High Metric- B-5483 $28.92/m/c/m Cabrillo (3)
• CDS 212 23 Buildings 9 Models 154 Manors
– Average For Metric $2.44
2011 MID-CYCLE (CONT)
• Paint Cycle 100 Buildings 25 Models 577 Manors
Average for Metric $2.49/m/c/m
Distribution of Metrics by CDS Shown But Not
Complete
What do we Do With The L- Buildings?
2011 Mid-Cycle Analysis Painted 2006
Repaired 2015
Models Units Buildings Manors High Low Avg. Problem Buildings
Cordoba 4 1 4 $ 1.66
Valencia 4 2 8 $ 4.02 $ 3.19 $ 3.61
Monterey 8 1 8 $ 2.18
Casa Linda 6 3 18 $ 1.22 $ 0.82 $ 1.06
La Princessa 2 2 4 $ 6.75 $ 5.56 $ 6.16
La Reina 3 1 3 $ 6.08
La reina 4 1 4 $ 1.35
El Doble 3 1 3 $ 3.13
Casa Rosa 3 13 39 $ 18.01 $ 0.91 $ 5.52 B-5509 B-5501
Casa Rosa 2 6 12 $ 24.69 $ 1.16 $ 7.81 B-5514 B-5469
Villa Nueva 21 1 21 $ 6.14
Cabrillo 3 9 27 $ 28.92 $ 0.70 $ 7.33 B-5492 B-5479 B-5483 B-5465
Cabrillo 2 4 8 $ 8.98 $ 1.55 $ 4.17
Cabrillo 1 2 2 $ 4.55 $ 2.40 $ 3.39
Villa Fuente 2 3 6 $ 20.33 $ 2.14 $ 12.17 B-5477 B-5492
Villa Fuente 1 4 4 $ 6.00
Casa Milano 6 8 48 $ 9.21 $ 2.11 $ 2.29
La Quinta 6 2 12 $ 4.39 $ 4.05 $ 4.22
$ 114,858.00 64 231 $ 4.60
CDS 212
Cordoba 4 1 4 $ 10.24 B-2222
Valencia 4 2 8 $ 5.89 $ 2.27 $ 4.08
Monterey 8 4 32 $ 3.81 $ 0.92 $ 2.11
Casa Linda 6 1 6 $ 0.21
San Sebastion 3 4 12 $ 9.33 $ 4.95 $ 7.56
Seville 4 1 4 $ 10.64 B-2225
Monterey 12 2 24 $ 0.62 $ 0.29 $ 0.91
Casa Contenta 8 5 40 $ 2.84 $ 0.41 $ 1.76
Castilla 8 3 24 $ 1.34 $ 0.61 $ 0.80
$ 40,610.70 23 154 $ 2.44
El Mirador 22 5 110 No Dry Rot Found
Casa Linda 6 1 6
93 501
La Princessa 3 2 6
La Reina 2 1 2 Mising from Paint Cycle
Casa Rosa 2 1 2
El Mirador 22 3 66
7 76
$ 155,469.00 100 577 $ 2.49
CDS-226 $ 2.03
CDS-329 $ 4.57
CDS-354 $ 4.57
CDS-374 $ 8.78
CDS-373 $ 1.28
CDS-375 $ 5.53
CDS-361 $ 7.52
CDS-362 $ 3.36
CDS-369 $ 7.20
CDS-368 $ 3.37
CDS-366 $ 7.46
CDS-365 $ 2.64
CDS-364 $ 10.90
2012 MID-CYCLE PROGRAM
• 140 Buildings Painted in 2007 (Old Paint)
• 81 Buildings Outsourced For Dry Rot Repairs
– Cost Bid Received, Contract Let, Only Estimated
Costs Available, Repairs in 2015
• 51 Buildings Found No Dry Rot
• 8 Year Cycle (Time Between 2015-2007)
2012 MID-CYCLE ANALYSIS
SUMMARY
• 81 Buildings 22 Models 279 Manors
– Average for Metric $2.41/m/c/m
– 3 Models With Slightly Higher Metrics – Casa Rosa
(2), Cabrillo (2), San Sebastion (3)
– All Small Buildings
• Paint Cycle 140 Buildings 22 Models 533
Manors
– Average Metric $0.98/m/c/m
2012 Mid-Cycle Analysis Painted 2007
Repaired 2015
Models Units Buildings Manors High Low Avg. Problem Buildings
Cordoba 4 3 12 $ 6.75 $ 1.30 $ 4.07
Valencia 4 5 20 6.58 0.62 $ 2.59
Monterey 8 4 32 3.21 0.38 $ 1.97
Casa Linda 6 2 12 $ 0.29
La Reina 3 2 6 8.19 6.41 $ 7.30 B-3233
Casa Rosa 3 10 30 5.98 0.67 $ 3.11
Casa Rosa 2 3 6 16.72 0.62 $ 8.15 B-3527
Cabrillo 2 4 8 $ 10.61 B-3524 B3532
Monterey 12 2 24 $ 0.38 $ 0.16 $ 0.27
Casa Contenta 8 1 8 $ 0.21
El Doble 4 1 4 $ 2.05
El Prado 2 2 4 $ 1.18 $ 0.86 $ 1.02
Villa Francesca 3 8 24 $ 9.29 $ 0.48 $ 2.80
Villa Lugano 6 4 24 $ 3.55 $ 0.22 $ 1.10
El Prado 3 1 3 $ 0.79
Villa Francesca 2 3 6 $ 1.20 $ 0.52 $ 0.97
Casa Marino 2 1 2 $ 1.00
Casa Siena 2 4 8 $ 1.43 $ 0.90 $ 1.17
Casa Lorenzo 2 10 20 $ 5.36 $ 0.77 $ 1.50
Casa Palma 2 4 8 $ 1.18 $ 0.75 $ 1.08
Casa Monaco 2 3 6 $ 1.59 $ 1.18 $ 1.32
San Sebastion 3 4 12 $ 9.78 $ 4.15 $ 7.52 B-2167 B-2201
$
50,337.00 81 279 $ 2.41
Casa Linda 6 4 24 0
Monterey 12 1 12 0
Casa Contenta 6 6 36 0
Corboba 4 1 4 0
Cabrillo 3 1 3 0
Cabrillo 2 1 2 0
Villa Lugano 6 2 12 0
El Prado 3 2 6 0
Casa Monaco 2 6 12 0
Casa Siena 2 4 8 0 No Dry Rot Found
Casa Palma 2 15 30 0
Casa Lorenzo 2 8 16 0
51 165 0
132 444 $ 1.18
Casa Linda 6 1 6
El Doble 3 1 3
Villa Puerta 24 3 72 Missing from paint cycle
Casa Rosa 3 1 3
El Prado 3 1 3
Casa Sienna 2 1 2
8 89
140 533 $ 0.98
2
2.3 DRY ROT PILOT PROGRAM
• Dry Rot Pilot Program
• LH21 Type
• Garden Villa Type
• Villa Paraiso
• Quantifying Dry Rot Damage
• Early Detection Program
• What Do WE Need?
• PTP/Paint Procedures
• Contractor Role in Dry Rot Program
DRY ROT PILOT PROGRAM
• Proposed Pilot Program
– Paint New Paint in Test
– Repair Procedures Started With 2011 Mid-Cycle
– LH 21
– Garden Villas
– Villa Paraiso
• We Need Good Ideas
• Look for Novel Approaches
• We Need to Train People
• We Need a Champion to Manage Program
QUANTIFY DRY ROT DAMAGE
• Calibrate Damage By Using Test Strips Or Dry
Rot Sensors
• Test Undamaged And Damaged Buildings
• Rank Damage Of Buildings Of Like Models
• Look For Structural/Safety Issues
• Identify Candidate Buildings
WHAT DO WE NEED?
• New Tools to Speed Up Repairs
• Better Procedures for Spore Control
• Better Processes Speed Repairs
– Training
– Teams
• New Detection and Localization Methods
– Test Strips, Special Sensors
– Ultra-Sonic Detectors (Not Ready at this Time)
• More Pilot Programs
CONTRACTOR ROLE IN DRY ROT
PROGRAM
• Contractors Have Various Capabilities, Labor Rates and Skill
Levels
– Low Skill (Wayne,
– Moderate Skill (Foster,
– High Skill (
• Cultivate Contractors to Provide Competitive Bids for All
Skill Levels
• Low Skill is Appropriate for Most 2011 and 2012 Mid-Cycle
Repairs
• Can We Split Bids Into Skill Levels Involved?
• All Contractors Busy-We May Compete With United
• Coordinate 3rd
, GRF, and United Dry Rot Efforts
2.4 TRADE-OFF STUDIES COMPLETED
• Painting Cycle vs Repairs
• How Are Buildings Selected
• Best Practice
• Best Practice vs Epoxy Fill
• Fungicide vs Pre-Painted Wood
HOW ARE BUILDINGS SELECTED?
• 3RD
Mutual Has 1405 Buildings With 6102 Manors
• Buildings Selected Each Year Are a Mix Of Large
And Small
• 10% Based On Square Feet Of Painting Surface
• Approximates 6102/10 Manors Per Year
• Efficient For Painting Program
• Selected Buildings 81 To 317 Per Year
• Buildings Revisited Every 10 Years
PAINTING CYCLE VS REPAIR COSTS
• Painting Costs
– 6102 Manors 610 Manors/Yr
– 10 Year Cycle
• PTP $1,031,008.
• Paint $1,698,484.
• Total $2,729,492. = $37.29 /Manor/Month
• Repair Costs
• Estimate $183,000. = $2.50/Manor/Month
• Major Repairs Not Included
PAINTING COSTS/REPAIR COSTS
• Paint this Year
– 2015 10 Year Cycle
– 2011 9 Year Cycle Repairs to Complete 2015
– 2012 8 Year Cycle Repairs to Complete 2015
• Paint This Year
– 2015 10 Year Cycle
– Defer 2011 Mid-Cycle to 2016 for 10 Year Cycle
– Defer 2012 Mid-Cycle to 2017 for 10 Year Cycle
– What To Do With Repaired But Unpainted Building
PAINTING COSTS/REPAIR COSTS
• Save Costs of Mid-Cycle or Split Cycle Painting
• Save Costs of 2011 / 2012 Mid-Cycle Repairs
• Invest Savings in Prevention
• After 2015, 2011 Mid-Cycle / 2012 Mid-Cycle
Completed Only 5 Years of Old Paint, 2018,
2019, 2020, 2021 and 2022
After 2022 Extend Paint Cycle to 11 Years
DRY ROT REPAIR “BEST PRACTICE”
• Four Steps to Dry Rot Repair
– 1. Cut Away Infected Wood
– 2. Spray Area Around Cut With Fungicide
– 3. Replace with New Wood
– 4. Dispose Infected Wood
• Fungicide
• A dilute Solution of Boric Acid and Water (like soapy
Water)
• When solution dries, leaves Borate Crystals which
interferes with some paints
TRADE-OFF FUNGICIDE VS PRE-
PAINTED WOOD
Fungicide
Positive
Effective
Low Cost
Negative
Interferes With Paint
Contractors Require
Clause Denying
Responsiblity
Pre-Painted Wood
Positive
May be Effective When
Combined With
Improved Procedures
Less Paint Problems
Negative
Higher Cost
TRADE-OFF “BEST PRACTICE” vs EPOXY
FILL
• Best Practice
– Skill Level-Unskilled
– Tools Required- Hammer
– Time Required-Fast
– Overhead- Low
– Spore Control-Good
• Epoxy Fill
– Skill Level- Must be
Trained
– Tools Required- Wire
Brush, Sander, Epoxy
– Time Required-Slower,
need 15-20 Min. to dry
– Overhead-Higher
– Spore Control-Poor
BEST PRACTICE/EPOXY FILL
• All Contractors Interviewed Use Best Practice.
They Consider It Faster (Time is Money)
Therefore Lower Cost.
• There May Be Cases Where Cost (In Time or
Inconvenience) Of Epoxy Fill is Effective.
• Ornate/Carved Wood Such As Banister Posts
are Candidates For Epoxy Fill.
PCM ORGANIZATION FOR DRY ROT
Not a Good Organization For Dry Rot Program
Two Bureaucracys Fighting For Budget
No One In Charge Or Responsible
mgmt
A SYSTEMS APPROACH
PART THREE
What Choices Should We Make
How Should We Be Organized?
What Recommendations Should We Make to
PCM?
What Long Term Decisions Must Be Made?
How Should Budgets Be Allocated?

More Related Content

Similar to Dry Rot - A systems approach 2 by Dave Finley

First School: Town Hall Presentation to Parish (June 2017)
First School: Town Hall Presentation to Parish (June 2017)First School: Town Hall Presentation to Parish (June 2017)
First School: Town Hall Presentation to Parish (June 2017)pennpadre
 
Approved Methodologies and CDM Project Design Document
Approved Methodologies and CDM Project Design DocumentApproved Methodologies and CDM Project Design Document
Approved Methodologies and CDM Project Design DocumentACX
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofitsmelanie_bissonnette
 
DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19Heritage Wind
 
Environment María
Environment MaríaEnvironment María
Environment MaríaMariaRG11
 
Forge - DevCon 2016: Forecast for Design, Make, & Use is Cloudy
Forge - DevCon 2016: Forecast for Design, Make, & Use is CloudyForge - DevCon 2016: Forecast for Design, Make, & Use is Cloudy
Forge - DevCon 2016: Forecast for Design, Make, & Use is CloudyAutodesk
 
CARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCarpet America Recovery Effort
 
3 Real Estate Rehab Management Models
3 Real Estate Rehab Management Models3 Real Estate Rehab Management Models
3 Real Estate Rehab Management ModelsBuild Realty
 
Downtown & Infill Tax Increment Districts
Downtown & Infill Tax Increment DistrictsDowntown & Infill Tax Increment Districts
Downtown & Infill Tax Increment DistrictsVierbicher
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordinationmichaeljmack
 
Retro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldRetro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldMurray Guy
 
Tct 2014 5 yr report presentation 141110-cam
Tct 2014 5 yr report presentation 141110-camTct 2014 5 yr report presentation 141110-cam
Tct 2014 5 yr report presentation 141110-camThe Climate Trust
 
Five Year Report Presentation to Oregon Energy Facility Siting Council
Five Year Report Presentation to Oregon Energy Facility Siting CouncilFive Year Report Presentation to Oregon Energy Facility Siting Council
Five Year Report Presentation to Oregon Energy Facility Siting CouncilThe Climate Trust
 
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...Fundación Natura Colombia
 
Fin. midterm presentation
Fin. midterm presentationFin. midterm presentation
Fin. midterm presentationElena Miyasato
 
Brief presentation for supervisors.
Brief presentation for supervisors.Brief presentation for supervisors.
Brief presentation for supervisors.Peter McNamara
 
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti..."Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...Sustainable Business Partnership
 
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...nrcampbell79
 

Similar to Dry Rot - A systems approach 2 by Dave Finley (20)

First School: Town Hall Presentation to Parish (June 2017)
First School: Town Hall Presentation to Parish (June 2017)First School: Town Hall Presentation to Parish (June 2017)
First School: Town Hall Presentation to Parish (June 2017)
 
Approved Methodologies and CDM Project Design Document
Approved Methodologies and CDM Project Design DocumentApproved Methodologies and CDM Project Design Document
Approved Methodologies and CDM Project Design Document
 
150312 updating history_deep_retrofits
150312 updating history_deep_retrofits150312 updating history_deep_retrofits
150312 updating history_deep_retrofits
 
DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19DOW Public Meeting Slides 12.19.19
DOW Public Meeting Slides 12.19.19
 
Environment María
Environment MaríaEnvironment María
Environment María
 
Forge - DevCon 2016: Forecast for Design, Make, & Use is Cloudy
Forge - DevCon 2016: Forecast for Design, Make, & Use is CloudyForge - DevCon 2016: Forecast for Design, Make, & Use is Cloudy
Forge - DevCon 2016: Forecast for Design, Make, & Use is Cloudy
 
CARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the PandemicCARE Carpet Recycling & COVID: Navigating the Pandemic
CARE Carpet Recycling & COVID: Navigating the Pandemic
 
3 Real Estate Rehab Management Models
3 Real Estate Rehab Management Models3 Real Estate Rehab Management Models
3 Real Estate Rehab Management Models
 
Downtown & Infill Tax Increment Districts
Downtown & Infill Tax Increment DistrictsDowntown & Infill Tax Increment Districts
Downtown & Infill Tax Increment Districts
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
 
Buildings and-carbon nov2008
Buildings and-carbon nov2008Buildings and-carbon nov2008
Buildings and-carbon nov2008
 
Retro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for GoldRetro-Commissioning is like Mining for Gold
Retro-Commissioning is like Mining for Gold
 
Tct 2014 5 yr report presentation 141110-cam
Tct 2014 5 yr report presentation 141110-camTct 2014 5 yr report presentation 141110-cam
Tct 2014 5 yr report presentation 141110-cam
 
Five Year Report Presentation to Oregon Energy Facility Siting Council
Five Year Report Presentation to Oregon Energy Facility Siting CouncilFive Year Report Presentation to Oregon Energy Facility Siting Council
Five Year Report Presentation to Oregon Energy Facility Siting Council
 
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...
Primer Taller Gold Standard en Colombia: Nuevos desarrollos sobre protocolos ...
 
Fin. midterm presentation
Fin. midterm presentationFin. midterm presentation
Fin. midterm presentation
 
Brief presentation for supervisors.
Brief presentation for supervisors.Brief presentation for supervisors.
Brief presentation for supervisors.
 
Project @ Depaul
Project @ DepaulProject @ Depaul
Project @ Depaul
 
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti..."Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...
"Building the Business Case for Sustainability" - Carolyn Whistlecraft, Senti...
 
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...
Capturing Hidden Value in Local Assets - Gordon Gill, Partner at Adrian Smith...
 

More from acclwv

2015 Meeting Agenda
2015 Meeting Agenda2015 Meeting Agenda
2015 Meeting Agendaacclwv
 
Supplier Management and Contract Issues
Supplier Management and Contract Issues Supplier Management and Contract Issues
Supplier Management and Contract Issues acclwv
 
Moving the Community Forward presented by Kathryn Freshley
Moving the Community Forward  presented by Kathryn FreshleyMoving the Community Forward  presented by Kathryn Freshley
Moving the Community Forward presented by Kathryn Freshleyacclwv
 
May 31st Town Hall Meeting
May 31st Town Hall MeetingMay 31st Town Hall Meeting
May 31st Town Hall Meetingacclwv
 
May 19 2014 meeting
May 19 2014 meetingMay 19 2014 meeting
May 19 2014 meetingacclwv
 
ACC May 19, 2014 Meeting Presentation
ACC May 19, 2014 Meeting Presentation ACC May 19, 2014 Meeting Presentation
ACC May 19, 2014 Meeting Presentation acclwv
 
Nov 4 2013 meeting
Nov 4 2013 meetingNov 4 2013 meeting
Nov 4 2013 meetingacclwv
 
Third Mutual Quality of Life Study
Third Mutual Quality of Life StudyThird Mutual Quality of Life Study
Third Mutual Quality of Life Studyacclwv
 
12-03-13 ACC Meeting Agenda Notes
12-03-13 ACC Meeting Agenda Notes12-03-13 ACC Meeting Agenda Notes
12-03-13 ACC Meeting Agenda Notesacclwv
 
GRF Trust Agreement Presentation
GRF Trust Agreement PresentationGRF Trust Agreement Presentation
GRF Trust Agreement Presentationacclwv
 
Dispelling the Myths - ACC Presentation
Dispelling the Myths - ACC PresentationDispelling the Myths - ACC Presentation
Dispelling the Myths - ACC Presentationacclwv
 
Recreation Master Plan $10 Million Real Estate Loan
Recreation Master Plan $10 Million Real Estate LoanRecreation Master Plan $10 Million Real Estate Loan
Recreation Master Plan $10 Million Real Estate Loanacclwv
 

More from acclwv (12)

2015 Meeting Agenda
2015 Meeting Agenda2015 Meeting Agenda
2015 Meeting Agenda
 
Supplier Management and Contract Issues
Supplier Management and Contract Issues Supplier Management and Contract Issues
Supplier Management and Contract Issues
 
Moving the Community Forward presented by Kathryn Freshley
Moving the Community Forward  presented by Kathryn FreshleyMoving the Community Forward  presented by Kathryn Freshley
Moving the Community Forward presented by Kathryn Freshley
 
May 31st Town Hall Meeting
May 31st Town Hall MeetingMay 31st Town Hall Meeting
May 31st Town Hall Meeting
 
May 19 2014 meeting
May 19 2014 meetingMay 19 2014 meeting
May 19 2014 meeting
 
ACC May 19, 2014 Meeting Presentation
ACC May 19, 2014 Meeting Presentation ACC May 19, 2014 Meeting Presentation
ACC May 19, 2014 Meeting Presentation
 
Nov 4 2013 meeting
Nov 4 2013 meetingNov 4 2013 meeting
Nov 4 2013 meeting
 
Third Mutual Quality of Life Study
Third Mutual Quality of Life StudyThird Mutual Quality of Life Study
Third Mutual Quality of Life Study
 
12-03-13 ACC Meeting Agenda Notes
12-03-13 ACC Meeting Agenda Notes12-03-13 ACC Meeting Agenda Notes
12-03-13 ACC Meeting Agenda Notes
 
GRF Trust Agreement Presentation
GRF Trust Agreement PresentationGRF Trust Agreement Presentation
GRF Trust Agreement Presentation
 
Dispelling the Myths - ACC Presentation
Dispelling the Myths - ACC PresentationDispelling the Myths - ACC Presentation
Dispelling the Myths - ACC Presentation
 
Recreation Master Plan $10 Million Real Estate Loan
Recreation Master Plan $10 Million Real Estate LoanRecreation Master Plan $10 Million Real Estate Loan
Recreation Master Plan $10 Million Real Estate Loan
 

Recently uploaded

Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoKayode Fayemi
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lodhisaajjda
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar TrainingKylaCullinane
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatmentnswingard
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...ZurliaSoop
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfMahamudul Hasan
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityHung Le
 
Introduction to Artificial intelligence.
Introduction to Artificial intelligence.Introduction to Artificial intelligence.
Introduction to Artificial intelligence.thamaeteboho94
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalFabian de Rijk
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIINhPhngng3
 
Zone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptxZone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptxlionnarsimharajumjf
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...amilabibi1
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfSkillCertProExams
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Baileyhlharris
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...David Celestin
 

Recently uploaded (17)

Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar Training
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatment
 
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
Jual obat aborsi Jakarta 085657271886 Cytote pil telat bulan penggugur kandun...
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
 
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven CuriosityUnlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
Unlocking Exploration: Self-Motivated Agents Thrive on Memory-Driven Curiosity
 
Introduction to Artificial intelligence.
Introduction to Artificial intelligence.Introduction to Artificial intelligence.
Introduction to Artificial intelligence.
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of Drupal
 
ICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdfICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdf
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio III
 
Zone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptxZone Chairperson Role and Responsibilities New updated.pptx
Zone Chairperson Role and Responsibilities New updated.pptx
 
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait Cityin kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
in kuwait௹+918133066128....) @abortion pills for sale in Kuwait City
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
 
My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Bailey
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
 

Dry Rot - A systems approach 2 by Dave Finley

  • 1. 3RD MUTUAL DRY ROT PROBLEM A SYSTEMS APPROACH PART TWO
  • 2. A SYSTEMS APPROACH PART TWO • 2.1 The Dry Rot Paradigm • 2.2 Data Analysis • 2.3 A Pilot Program • 2.4 Trade-Off Studies
  • 3. 2.1 THE DRY ROT PARADIGM • The Dry Rot Dichotomy • The Legacy Dry Rot Program • Major Repairs Remaining • What Can Be Done? • Prevention/Remediation • A New Dry Rot Paradigm • Why No Model Metrics • A New Metric
  • 4. THE DRY ROT DICHOTOMY • Paint Issues – Facia, Outlookers, Eaves, Trellises, Minor Beams • Mostly Cosmetic • Minor to Moderate Costs • Common to All Model Types • Detected By PTP (Prior To Paint) • Examples – CDS (Cul De Sac) 212, 2011 Mid-Cycle, 2012 Mid-Cycle
  • 5. THE DRY ROT DICHOTOMY (cont) • Major Repair Caused By: – Cracked Stucco, Parapet Leaks, Joints, Overlaps • Structural • Catastrophic/High • Design/Construction Flaws Model Specific • Detected By Other Than PTP • Examples – Villa Paraiso, Garden Villa Types, LH21 Types
  • 6. THE LEGASY DRY ROT PROGRAM • Grew Out Of Paint Program • Program Is Building Centric • PTP Began As Paint Preparation • 10 % Of Buildings Inspected/Painted Per Year • Simple And Logical
  • 7. BUT • 90% Not Inspected Per Year • Up To 9 Years Between Problems Detected And Corrections Made • Waits For PTP to Report Dry Rot Damage • PTP Does Not Look For Internal Problems • Major Problems Managed Ad Hoc • Does Not Use Model Metrics • Poor Spore Control Practices
  • 8. WHAT HAPPENED • Major Problems Found Late • Models With Known Major Problems – Garden Villa Types-Leaks At Flashing Overlaps, Water Collection At Support Joints – LH21 Types-Cracked Stucco/Parapet Leaks – Villa Paraiso-Cracked Stucco/Parapet Leaks • Unknown Other Model Problems • Dry Rot Damage Severe
  • 9. MAJOR REPAIRS REMAINING • You Can Ignore the Problem But You Cannot Ignore the Consequences • Significant Damage Already Done • What We Currently Know-Cost Remain Total – Garden Villa Type 53 $1,000,000. 52 $52,000,000. • Garden Villa 19 • Casa Dorado 2 • El Mirador 15 • Villa Capri 10 • Villa Puerta 7
  • 10. MAJOR REPAIRS REMAINING (CONT) – LH21 Type 28 $100,000. 21 $2,100,000. • Villa Nueva 15 • Sierra 7 • Aragon 6 – Villa Paraiso 109 $ 50,000. 108 $5,400,000. • How Can We Protect Our Remaining Buildings?
  • 11. EFFORT TO DATE • Repair Work Started • Engineering Design Fixes Identified • RFP to Contractors For Current Year Buildings • Waiting For PTP To Report Candidate Buildings
  • 12. WHAT CAN BE DONE? • Can A Preventative Program Stop Fungus Spread And Any Further Damage? • Can A Temporary Fix Stop Further Damage? • Will a Temporary Fix Reduce Costs? • Can We Stop Fungus from Infecting Building With No Dry Rot? • Can We Identify Other Models With Systemic Problems?
  • 13. PREVENTION/REMEDIATION • Early Detection of a Problem • Analyze Problem – What Models Need Help – Which Buildings are Candidates for Prevention – Which Buildings Offer Greatest Savings • Stop Fungus – Dry Out Infected Areas • Prevent Further Leaks – Seal Roofs and Parapets, Add Flashing • Prevent Leaks to Undamaged Buildings • Start Pilot Program to Investigate Cost Savings
  • 14. A NEW DRY ROT PARADIGM • Create A Program With Feedback That Reduces Dry Rot Damage • Feedback Information Gathered On Models To Fix Problems More Timely • Design fixes That Reduce Future Damage • Continue PTP And New Paint Program • Include An Early Detection Process • Set Priorities For Maximum Cost Savings • Start Pilot Programs to Confirm Cost Savings
  • 15.
  • 16. WHY NOT USE MANOR METRICS? • A List Of Building Numbers With Costs Not Informative • Easiest Way To Normalize Building Size And Cost • Track Systemic Model Problems And Costs • Easy To Relate To- How Residents Are Charged • Create A Manor Centric Data Base • Add Model Type to Dry Rot Reports – Model Type, Manors/Building, Detected By, and
  • 17.
  • 18. THE NEW METRIC • Cost Per Building/Number Of Manors Per Building/Cycle( Time Between Paintings)/Month • If Costs Go Up – Metric Goes Up • If Number Of Manors Go Up – Metric Goes Down • If Cycle Time Goes Up – Metric Goes Down • If Cycle Time goes Down – Metric Goes Up
  • 19. THE NEW METRIC (CONT.) • Normalizes Building Size • Closely Follows Square Feet Paint • A Better Tool For Cost Estimating • Compares Building Size and Model Types
  • 20. 2.2 DATA ANALYSIS • CDS 212 Pilot Program • 2011 Mid-Cycle Repair Bid – 64 Building/18 Model Metrics – CDS 212 23Building/9 Model Metrics – 6 Building/2 Model No Dry Rot Found – Metric By CDS and Map of Distribution • 2012 Mid-Cycle Repair Bid – 81 Building/22 Model Metrics – 51 Building/6 Model No Dry Rot Found
  • 21. CDS 212 • Pilot Program To Estimate Mid-Cycle Costs • CDS 212 24 Buildings, 160 Manors • Cost/ Program Confusion – 14 Buildings At $98,185.00 Or – 23 Buildings At $40610.00 • CDS 212 Mostly Large Buildings • Used to Estimate Costs of Mostly Small Buildings
  • 22.
  • 23.
  • 24. 2011 MID-CYCLE PROGRAM • 100 Buildings Painted in 2006 (Old Paint) • 23 Buildings Repaired in CDS 212 – Actual Costs Available • 64 Buildings Outsourced For Dry Rot Repairs – Cost Bid Received, Contract Let, Only Estimated Costs Available, Repairs in 2015 • 6 Buildings Found No Dry Rot • 9 Year Cycle (Time Between 2015-2006)
  • 25. 2011 MID-CYCLE ANALYSIS SUMMARY • 64 Buildings 18 Models 231 Manors – Average For Metric $4.60/m/c/m – 4 Models with high Metrics – Casa Rosa (3), Casa Rosa (2), Cabrillo (3), Villa Fuente (3) – 10 Building Have Problems – High Metric- B-5483 $28.92/m/c/m Cabrillo (3) • CDS 212 23 Buildings 9 Models 154 Manors – Average For Metric $2.44
  • 26. 2011 MID-CYCLE (CONT) • Paint Cycle 100 Buildings 25 Models 577 Manors Average for Metric $2.49/m/c/m Distribution of Metrics by CDS Shown But Not Complete What do we Do With The L- Buildings?
  • 27. 2011 Mid-Cycle Analysis Painted 2006 Repaired 2015 Models Units Buildings Manors High Low Avg. Problem Buildings Cordoba 4 1 4 $ 1.66 Valencia 4 2 8 $ 4.02 $ 3.19 $ 3.61 Monterey 8 1 8 $ 2.18 Casa Linda 6 3 18 $ 1.22 $ 0.82 $ 1.06 La Princessa 2 2 4 $ 6.75 $ 5.56 $ 6.16 La Reina 3 1 3 $ 6.08 La reina 4 1 4 $ 1.35 El Doble 3 1 3 $ 3.13 Casa Rosa 3 13 39 $ 18.01 $ 0.91 $ 5.52 B-5509 B-5501 Casa Rosa 2 6 12 $ 24.69 $ 1.16 $ 7.81 B-5514 B-5469 Villa Nueva 21 1 21 $ 6.14 Cabrillo 3 9 27 $ 28.92 $ 0.70 $ 7.33 B-5492 B-5479 B-5483 B-5465 Cabrillo 2 4 8 $ 8.98 $ 1.55 $ 4.17 Cabrillo 1 2 2 $ 4.55 $ 2.40 $ 3.39 Villa Fuente 2 3 6 $ 20.33 $ 2.14 $ 12.17 B-5477 B-5492 Villa Fuente 1 4 4 $ 6.00 Casa Milano 6 8 48 $ 9.21 $ 2.11 $ 2.29 La Quinta 6 2 12 $ 4.39 $ 4.05 $ 4.22 $ 114,858.00 64 231 $ 4.60
  • 28. CDS 212 Cordoba 4 1 4 $ 10.24 B-2222 Valencia 4 2 8 $ 5.89 $ 2.27 $ 4.08 Monterey 8 4 32 $ 3.81 $ 0.92 $ 2.11 Casa Linda 6 1 6 $ 0.21 San Sebastion 3 4 12 $ 9.33 $ 4.95 $ 7.56 Seville 4 1 4 $ 10.64 B-2225 Monterey 12 2 24 $ 0.62 $ 0.29 $ 0.91 Casa Contenta 8 5 40 $ 2.84 $ 0.41 $ 1.76 Castilla 8 3 24 $ 1.34 $ 0.61 $ 0.80 $ 40,610.70 23 154 $ 2.44 El Mirador 22 5 110 No Dry Rot Found Casa Linda 6 1 6 93 501 La Princessa 3 2 6 La Reina 2 1 2 Mising from Paint Cycle Casa Rosa 2 1 2 El Mirador 22 3 66 7 76 $ 155,469.00 100 577 $ 2.49
  • 29. CDS-226 $ 2.03 CDS-329 $ 4.57 CDS-354 $ 4.57 CDS-374 $ 8.78 CDS-373 $ 1.28 CDS-375 $ 5.53 CDS-361 $ 7.52 CDS-362 $ 3.36 CDS-369 $ 7.20 CDS-368 $ 3.37 CDS-366 $ 7.46 CDS-365 $ 2.64 CDS-364 $ 10.90
  • 30.
  • 31. 2012 MID-CYCLE PROGRAM • 140 Buildings Painted in 2007 (Old Paint) • 81 Buildings Outsourced For Dry Rot Repairs – Cost Bid Received, Contract Let, Only Estimated Costs Available, Repairs in 2015 • 51 Buildings Found No Dry Rot • 8 Year Cycle (Time Between 2015-2007)
  • 32. 2012 MID-CYCLE ANALYSIS SUMMARY • 81 Buildings 22 Models 279 Manors – Average for Metric $2.41/m/c/m – 3 Models With Slightly Higher Metrics – Casa Rosa (2), Cabrillo (2), San Sebastion (3) – All Small Buildings • Paint Cycle 140 Buildings 22 Models 533 Manors – Average Metric $0.98/m/c/m
  • 33. 2012 Mid-Cycle Analysis Painted 2007 Repaired 2015 Models Units Buildings Manors High Low Avg. Problem Buildings Cordoba 4 3 12 $ 6.75 $ 1.30 $ 4.07 Valencia 4 5 20 6.58 0.62 $ 2.59 Monterey 8 4 32 3.21 0.38 $ 1.97 Casa Linda 6 2 12 $ 0.29 La Reina 3 2 6 8.19 6.41 $ 7.30 B-3233 Casa Rosa 3 10 30 5.98 0.67 $ 3.11 Casa Rosa 2 3 6 16.72 0.62 $ 8.15 B-3527 Cabrillo 2 4 8 $ 10.61 B-3524 B3532 Monterey 12 2 24 $ 0.38 $ 0.16 $ 0.27 Casa Contenta 8 1 8 $ 0.21 El Doble 4 1 4 $ 2.05 El Prado 2 2 4 $ 1.18 $ 0.86 $ 1.02 Villa Francesca 3 8 24 $ 9.29 $ 0.48 $ 2.80 Villa Lugano 6 4 24 $ 3.55 $ 0.22 $ 1.10 El Prado 3 1 3 $ 0.79 Villa Francesca 2 3 6 $ 1.20 $ 0.52 $ 0.97 Casa Marino 2 1 2 $ 1.00 Casa Siena 2 4 8 $ 1.43 $ 0.90 $ 1.17 Casa Lorenzo 2 10 20 $ 5.36 $ 0.77 $ 1.50 Casa Palma 2 4 8 $ 1.18 $ 0.75 $ 1.08 Casa Monaco 2 3 6 $ 1.59 $ 1.18 $ 1.32 San Sebastion 3 4 12 $ 9.78 $ 4.15 $ 7.52 B-2167 B-2201 $ 50,337.00 81 279 $ 2.41
  • 34. Casa Linda 6 4 24 0 Monterey 12 1 12 0 Casa Contenta 6 6 36 0 Corboba 4 1 4 0 Cabrillo 3 1 3 0 Cabrillo 2 1 2 0 Villa Lugano 6 2 12 0 El Prado 3 2 6 0 Casa Monaco 2 6 12 0 Casa Siena 2 4 8 0 No Dry Rot Found Casa Palma 2 15 30 0 Casa Lorenzo 2 8 16 0 51 165 0 132 444 $ 1.18 Casa Linda 6 1 6 El Doble 3 1 3 Villa Puerta 24 3 72 Missing from paint cycle Casa Rosa 3 1 3 El Prado 3 1 3 Casa Sienna 2 1 2 8 89 140 533 $ 0.98 2
  • 35. 2.3 DRY ROT PILOT PROGRAM • Dry Rot Pilot Program • LH21 Type • Garden Villa Type • Villa Paraiso • Quantifying Dry Rot Damage • Early Detection Program • What Do WE Need? • PTP/Paint Procedures • Contractor Role in Dry Rot Program
  • 36. DRY ROT PILOT PROGRAM • Proposed Pilot Program – Paint New Paint in Test – Repair Procedures Started With 2011 Mid-Cycle – LH 21 – Garden Villas – Villa Paraiso • We Need Good Ideas • Look for Novel Approaches • We Need to Train People • We Need a Champion to Manage Program
  • 37.
  • 38.
  • 39.
  • 40. QUANTIFY DRY ROT DAMAGE • Calibrate Damage By Using Test Strips Or Dry Rot Sensors • Test Undamaged And Damaged Buildings • Rank Damage Of Buildings Of Like Models • Look For Structural/Safety Issues • Identify Candidate Buildings
  • 41.
  • 42. WHAT DO WE NEED? • New Tools to Speed Up Repairs • Better Procedures for Spore Control • Better Processes Speed Repairs – Training – Teams • New Detection and Localization Methods – Test Strips, Special Sensors – Ultra-Sonic Detectors (Not Ready at this Time) • More Pilot Programs
  • 43.
  • 44. CONTRACTOR ROLE IN DRY ROT PROGRAM • Contractors Have Various Capabilities, Labor Rates and Skill Levels – Low Skill (Wayne, – Moderate Skill (Foster, – High Skill ( • Cultivate Contractors to Provide Competitive Bids for All Skill Levels • Low Skill is Appropriate for Most 2011 and 2012 Mid-Cycle Repairs • Can We Split Bids Into Skill Levels Involved? • All Contractors Busy-We May Compete With United • Coordinate 3rd , GRF, and United Dry Rot Efforts
  • 45. 2.4 TRADE-OFF STUDIES COMPLETED • Painting Cycle vs Repairs • How Are Buildings Selected • Best Practice • Best Practice vs Epoxy Fill • Fungicide vs Pre-Painted Wood
  • 46. HOW ARE BUILDINGS SELECTED? • 3RD Mutual Has 1405 Buildings With 6102 Manors • Buildings Selected Each Year Are a Mix Of Large And Small • 10% Based On Square Feet Of Painting Surface • Approximates 6102/10 Manors Per Year • Efficient For Painting Program • Selected Buildings 81 To 317 Per Year • Buildings Revisited Every 10 Years
  • 47. PAINTING CYCLE VS REPAIR COSTS • Painting Costs – 6102 Manors 610 Manors/Yr – 10 Year Cycle • PTP $1,031,008. • Paint $1,698,484. • Total $2,729,492. = $37.29 /Manor/Month • Repair Costs • Estimate $183,000. = $2.50/Manor/Month • Major Repairs Not Included
  • 48. PAINTING COSTS/REPAIR COSTS • Paint this Year – 2015 10 Year Cycle – 2011 9 Year Cycle Repairs to Complete 2015 – 2012 8 Year Cycle Repairs to Complete 2015 • Paint This Year – 2015 10 Year Cycle – Defer 2011 Mid-Cycle to 2016 for 10 Year Cycle – Defer 2012 Mid-Cycle to 2017 for 10 Year Cycle – What To Do With Repaired But Unpainted Building
  • 49. PAINTING COSTS/REPAIR COSTS • Save Costs of Mid-Cycle or Split Cycle Painting • Save Costs of 2011 / 2012 Mid-Cycle Repairs • Invest Savings in Prevention • After 2015, 2011 Mid-Cycle / 2012 Mid-Cycle Completed Only 5 Years of Old Paint, 2018, 2019, 2020, 2021 and 2022 After 2022 Extend Paint Cycle to 11 Years
  • 50. DRY ROT REPAIR “BEST PRACTICE” • Four Steps to Dry Rot Repair – 1. Cut Away Infected Wood – 2. Spray Area Around Cut With Fungicide – 3. Replace with New Wood – 4. Dispose Infected Wood • Fungicide • A dilute Solution of Boric Acid and Water (like soapy Water) • When solution dries, leaves Borate Crystals which interferes with some paints
  • 51. TRADE-OFF FUNGICIDE VS PRE- PAINTED WOOD Fungicide Positive Effective Low Cost Negative Interferes With Paint Contractors Require Clause Denying Responsiblity Pre-Painted Wood Positive May be Effective When Combined With Improved Procedures Less Paint Problems Negative Higher Cost
  • 52. TRADE-OFF “BEST PRACTICE” vs EPOXY FILL • Best Practice – Skill Level-Unskilled – Tools Required- Hammer – Time Required-Fast – Overhead- Low – Spore Control-Good • Epoxy Fill – Skill Level- Must be Trained – Tools Required- Wire Brush, Sander, Epoxy – Time Required-Slower, need 15-20 Min. to dry – Overhead-Higher – Spore Control-Poor
  • 53. BEST PRACTICE/EPOXY FILL • All Contractors Interviewed Use Best Practice. They Consider It Faster (Time is Money) Therefore Lower Cost. • There May Be Cases Where Cost (In Time or Inconvenience) Of Epoxy Fill is Effective. • Ornate/Carved Wood Such As Banister Posts are Candidates For Epoxy Fill.
  • 54. PCM ORGANIZATION FOR DRY ROT Not a Good Organization For Dry Rot Program Two Bureaucracys Fighting For Budget No One In Charge Or Responsible mgmt
  • 55.
  • 56. A SYSTEMS APPROACH PART THREE What Choices Should We Make How Should We Be Organized? What Recommendations Should We Make to PCM? What Long Term Decisions Must Be Made? How Should Budgets Be Allocated?