1. ®
Preparing for the CAPM Exam
Project Management Institute
California Central Valley Chapter
(PMI – CCVC)
Time Management June 20, 2011
2. Agenda
• Matching Game – (50 min) – <Matching Handout>
• Break – (10 min)
• Address Questions from Reading – (50 min)
• Slides – what you need to know
• CPM Example – <Group Exercise: Handout>
• Break – (10 min)
• Questions – Drill/Practice – (60 min) – <FASTrac>
• Summary: <how to prepare, handouts>
Time Management June 20, 2011
3. The Primary Topics for Project Time
Management:
• Determining what resources are available and
when
• Determining how much time the project will take
to complete
• Calculating the critical path and the float of a
network diagram
• Know how to compress a project schedule
• Know the different types of network Analysis
Time Management June 20, 2011
4. Project Time Management
6.1 Activity Definition
Project Time Management
6.0
Activity Activity Activity Schedule
Activity Schedule
Definition Resource Duration Control
Sequencing Development
6.1 Estimating Estimating 6.6
6.2 6.5
6.3 6.4
4
Time Management April 4, 2011
5. Key Concepts for
Activity Definition
Def: Activity Definition
Output: Activity List, Activity Attributes
Diff: Deliverables and Activities
Diff: WBS, Work Package, Activity
Def: Constraints
Def: Assumptions
Def: Enterprise Environmental Factors
5
Time Management April 4, 2011
6. Key Concepts for
Activity Definition
Def:Organizational Process Assets
Def: Decomposition
Def: Rolling Wave
Def: Templates
6
Time Management April 4, 2011
7. Project Time Management
6.2 Activity Sequencing
Project Time Management
6.0
Activity Activity Activity
Schedule
Activity Schedule
Definition Resource Duration
Control
Sequencing Development
6.1 Estimating Estimating
6.6
6.2 6.5
6.3 6.4
7
Time Management April 4, 2011
9. Project Time Management
6.3 Activity Resource Estimating
Project Time Management
6.0
Activity Activity Activity
Schedule
Activity Schedule
Definition Resource Duration
Control
Sequencing Development
6.1 Estimating Estimating
6.6
6.2 6.5
6.3 6.4
9
Time Management April 4, 2011
10. Key Concepts for
Activity Resource Estimating
Def: Activity Resource Estimating
Output: Activity Resource Requirements
Def: Published Estimating Data
Def: Alternative Analysis
Def: Bottom-up estimates
Def: Resource Breakdown Structure
Def: Resource Calendar
10
Time Management April 4, 2011
11. Project Time Management
6.4 Activity Duration Estimating
Project Time Management
6.0
Activity Activity Activity Schedule
Activity Schedule
Definition Resource Duration Control
Sequencing Development
6.1 Estimating Estimating 6.6
6.2 6.5
6.3 6.4
11
Time Management April 4, 2011
12. Key Concepts for
Activity Duration Estimating
Def: Activity Duration Estimating
Def: Work Periods
Output: Activity Duration Estimate
Def: Expert Judgement
Def: Analogous Estimating
Def: Parametric Estimates
Def: Three Point Estimates
Diff: Management Reserve & Contingency
Reserve
12
Time Management April 4, 2011
13. Project Time Management
6.5 Schedule Development
Project Time Management
6.0
Activity Activity Activity
Schedule
Activity Schedule
Definition Resource Duration
Control
Sequencing Development
6.1 Estimating Estimating
6.6
6.2 6.5
6.3 6.4
13
Time Management April 4, 2011
14. Key Concepts for
Schedule Development
Def: Schedule Development
Input: Calendars
Output: Project Schedule
Def: Critical Path
Def: Float, Slack
Know the purpose of the CPM Forward Pass
and Backward Pass
14
Time Management April 4, 2011
15. Key Concepts for
Schedule Development
Def: PERT, 3 Point Average, GERT
Def: Critical Chain Method
Def: Normal Distribution
Def: Monte Carlo Simulation (what-if
analysis)
Def: Duration Compression
Def: Schedule Model Data
Def: Crashing
Def: Fast Tracking
15
Time Management April 4, 2011
16. Key Concepts for
Schedule Development
Def: Heuristics
Def: Resource Leveling (smoothing)
Diff: Project Network Diagrams, Bar Charts,
Logic Bar Chart and Milestone Charts
16
Time Management April 4, 2011
17. Project Time Management
6.6 Schedule Control
Project Time Management
6.0
Activity Activity Activity
Schedule
Activity Schedule
Definition Resource Duration
Control
Sequencing Development
6.1 Estimating Estimating
6.6
6.2 6.5
6.3 6.4
17
Time Management April 4, 2011
18. Key Concepts for
Schedule Control
Def: Schedule Baseline
Input: Schedule Baseline
Output: Schedule Model Data, & Baseline
Updates
Def: Performance Measurement
Def: Variance Analysis
Def: Schedule Management Plan
18
Time Management April 4, 2011
19. Group Exercise
“Critical Path Scenario”
19
Time Management June 20, 2011
20. Group Critical Path Exercise
Activity Preceding Activity Estimated Duration
Start 0
2.3.3.1 Start 20
2.3.3.2 2.3.3.1 25
2.3.3.3 2.3.3.2 8
2.3.3.4 2.3.3.3 8
2.3.3.5 2.3.3.3 6
2.3.3.6 2.3.3.5 8
2.3.3.7 2.3.3.4, 2.3.3.6 4, 4 + 16 hour FS lag
End 2.3.3.7 0
20
Time Management June 20, 2011
21. Group Exercise
“FASTrac Selections”
21
Time Management June 20, 2011
22. Group FASTrac Exercise
ID Number ID Number
Group 1 Group 2
401 451
410 668
382 408
400 640
439 399
463 437
1295 411
386 1308
413 507
390 472
513 477
22
Time Management June 20, 2011