SlideShare a Scribd company logo
1 of 5
Download to read offline
Standalone
Vertical Roller Mills
without
Hot Gas Generator
OPTIMISED GRINDING




I Standalone VRMs without HGG
by Dr Daniel Strohmeyer,                       Water and energy are precious resources and without them life would not
Loesche GmbH, Germany                          be as we know it today. Both commodities will become more expensive
                                               and scarcer in the future. Consequently, saving energy and water is
                                               essential for ecologically- and economically-viable production, particularly
                                               in the cement industry.


F
      or vertical roller mills (VRM), water
      injection on the grinding table is a                         Figure 1: Loesche vertical roller mill for cement grinding
      common way to stabilise the grinding                         – material flow, feed materials and products
bed and gives a smoother mill operation
with lower vibration levels. However,
there are some drawbacks to water use
in a VRM. The feed moisture for OPC is
commonly very low and in case water is
added to the grinding process it has to
be evaporated requiring thermal energy.
If cooler exhaust gases are available in a
cement plant this will not pose a major
problem, but for a standalone grinding
this source of hot gases is not available to
drive-off any additional water. In this case
a hot gas generator is needed to dry the
material and to provide sufficient energy
for the grinding system. This solution not
only wastes fuel, it also creates further
expenses.
   In some parts of the world the cement       what is the centre of the rotating grinding         the grinding table. Lumps, which escape
industry is not permitted to utilise water     table. The product is then driven outwards          the rollers and are too heavy to rise with
or its use is limited. Loesche has been        by centrifugal forces, underneath the               the gas flow drop through the louvre ring
working on a system that can provide           rollers where the grinding takes place.             to a reject system and are then fed back
grinding without the need for any water        Ground material moves over the dam                  via the reject system.
injection. Even if some water is available     ring and goes up with the gas flow to the              Raw mills or coal mills operate using
the main aim is a grinding system that can     classifier. The material has either reached         the same size of rollers. What is particular
be run without the need for permanent          the required fineness and leaves the mill           for Loesche cement mills is the 2+2 or
operation of a hot gas generator.              towards the bag filter or is sent back for          3+3 system, which features a combination
                                               further grinding, via the grid cone onto            of different sizes of rollers. In cement
VRMs
A vertical roller mill can process many        Figure 2: grinding plant flowsheet
materials such as clinker, slag, gypsum,
fly ash or limestone to produce various
cement types of various finesse. The mill
is part of a process that begins at the
quarry. Only after the initial material has
been through the raw material grinding,
preheater, kiln and the cooler it reaches
the finish mill where additives are added
and the final product is obtained. Both
Loesche and its customers are essentially
concerned with this final product and
its properties which are influenced by all
stages of the cement making process.
   Material enters the VRM via a rotary
feeder that poses as an air lock (see Figure
1), then moves down the feed chute to


INTERNATIONAL CEMENT REVIEW JUNE 2011
OPTIMISED GRINDING




Figure 3: assumed grindability for Ambuja Cement´s Dadri and Nalagarh projects
                                                                                                   A system fan provides the draft through
                                                                                                   the machine and different sources of
                                                                                                   hot gases can be utilized if required.
                                                                                                   Furthermore a wide range of feed
                                                                                                   materials are tolerated and conveyed to
                                                                                                   the mill via the feeding system.

                                                                                                   Ambuja Cement’s Dadri and
                                                                                                   Nalagarh grinding stations
                                                                                                   In 2007, Loesche received an enquiry
                                                                                                   for two grinding stations in India. Both
                                                                                                   would have a cement capacity of 1.6Mta
                                                                                                   and each would be supplied with a
                                                                                                   Loesche VRM with 250tph of grinding
                                                                                                   capacity. The Dadri project is situated
                                                                                                   near New Delhi and the Nalagarh mill
mills, Loesche has a ‘S’ support roller and        internal friction within the material layer     is located further to the north, close to
a ‘M’ master roller. The ‘S’ roller is solely      making it difficult to efficiently apply the    the Himalayas. It became apparent that
to prepare and stabilise the grinding bed.         grinding forces. So the ‘S’ roller removes      the grinding stations would need to be
The most difficult thing to achieve when           the air from the grinding bed and               operated without a hot gas generator
producing cement is to keep the grinding           prepares the material for the master roller     and consequently water injection for
bed stable. In comparison to raw material          to carry out the grinding.                      the purpose of grinding bed stabilisation
grinding, with cement milling there are               The flowsheet for a grinding system          was not permitted. Loesche looked at
more fines and some parts of the grinding          with a VRM (see Figure 2) shows that,           the customer’s requirements before
bed tend to become partly fluidised,               after the classifier, product is precipitated   deciding on the best solution. The main
caused by entrapped air. This reduces the          and then recovered from the bag filter.         constituents to be ground were clinker, fly

Ambuja Cement‘s grinding station Nalagarh, India




                                                                                               JUNE 2011 INTERNATIONAL CEMENT REVIEW
OPTIMISED GRINDING                                                                                                        OPTIMISED GRINDING




 Figure 3: assumed grindability for Ambuja Cement´s Dadri and Nalagarh projects
                                                                                                      A system fan provides the draft through
  Table 1: key data for Dadri and Nalagarh                                        Table 2: Dadri performance different sources of
                                                                                                 the machine and data
  grinding stations                                                                                      hot gases can be utilized if required.
                                                                                  Dadri                  Furthermore a wide range of feed
                                                                                                                                     PPC
   PPC capacity (tph)                        250                                  LM 56.3+3              materials are tolerated and conveyed to
                                                                                                                          Guarantee      Achieved
   Gearbox power (kW)                        5400 (Flender)                                              the mill via the feeding system.
   Classifier LSKS 102 CS (kW)               560                                Mill throughput (tph)                             250          253
   Fan motor power (kW)                      3000                               Fineness                 Ambuja Cement’s Dadri and
                                                                                                                                4000         3920
   Mill diameter (m)                         13.5                               Feed moisture (%) Nalagarh grinding stations         –          1.1
   Height (m)                                20                                 Product moisture (%) 2007, Loesche received an enquiry
                                                                                                         In                          –          0.3
   Grinding table diameter (m)              5.6                                Specific power consumption grinding stations in India. Both
                                                                                                         for two (kWh/t) 30.75              25.60
   Grinding table weight (t)                 109                                (mill, fan, classifier, aux) have a cement capacity of 1.6Mta
                                                                                                         would
   Master roller (mm)                        3 x2450                                                    and each would be supplied with a
   Support roller (mm)                       3 x 1600                                                    Loesche VRM with 250tph of grinding
                                                                                                         capacity. The Dadri project is situated
                                                                                                           ash or clinker sources would be sourced.
                                                                                                         near New Delhi and had Nalagarh mill
                                                                                                           Therefore, Loesche the to assume a
mills, and gypsum (up to five per cent) all
  ash Loesche has a ‘S’ support roller and         internal friction within theto carry out a
                                                       Standard procedure is material layer              iscertain ‘grindability the north, close to
                                                                                                            located further to factor‘ and specific
aof which have different‘S’ roller is solely
    ‘M’ master roller. The physical properties making it test to establish a proper sizing
                                                    grinding difficult to efficiently apply the          the Himalayas. It becamethe feed mix (see
                                                                                                           power consumption for apparent that
to prepareleading to different grindabilities
  basically and stabilise the grinding bed.        grinding mill andSo the ‘S’ box. However,
                                                    for the forces. the gear roller removes              the grinding stations would need to be
                                                                                                           Figure 3). The assumptions were based
The most difficultindividualachieve when
  and a particular thing to behaviour              the the from theboth of the projects it
                                                    at air start of grinding bed and                     operated without a hot gas generator
                                                                                                           on Loesche’s experience and knowledge
producing cement is to keep the grinding
  inside the mill.                                  was not known where the different fly
                                                   prepares the material for the master roller           and other fly ash cement injection for
                                                                                                           of consequently water grinding plants
bed stable. In comparison to raw material          to carry out the grinding.                            the purpose of grinding bed concluded
                                                                                                           operating in India. Loesche stabilisation
grinding, with cement milling there are               The flowsheet for a grinding system                was notwould need Loesche looked at
                                                                                                           that it permitted. a 56.3+3 mill with
more fines and some parts of the grinding          with a VRM (see Figure 2) shows that,                 thetable diameter of 5.6m. The selected
                                                                                                           a customer’s requirements before
bed tend to become partly fluidised,               after the classifier, product is precipitated         deciding on the best solution. The main
                                                                                                           Flender gear box would have a power
caused by entrapped air. This reduces the          and then recovered from the bag filter.               constituents toof 5400kW,were clinker, fly
                                                                                                           consumption be ground a Loesche
                                                                                                           dynamic classifier LSKS 102CS and a fan
                                                                                                           motor of 3000kW would form the other
                                                                                                           main parts of the system (see Table 1).
                                                                                                              Loesche’s scope of supply for the
                                                                                                           two Indian projects was not for the
                                                                                                           whole grinding plants, but for the mills,
                                                                                                           classifiers, sampling stations and the air
                                                                                                           slides for the product transport. Loesche’s
                                                                                                           product targets were PPC of 4000Blaine
                                                                                                           at 250tph using a specific power
                                                                                                           consumption of 30.75kWh/t for all the
                                                                                                           Loesche equipment and the fan supply
   Figure 4: erection of gear box                                                                          (see Table 2).
                                                                                                              The PPC product would consist of 60
                                                                                                           per cent clinker, five per cent gypsum and
                                                                                                           35 per cent fly ash (2500 Blaine). If the
                                                                                                           plant receives clinker that is high in C3S
                                                                                                           then the fly ash content can be increased
                                                                                                           to the maximum permissible according to
                                                                                                           Indian standards. If the clinker exhibits a
                                                                                                           low C3S value, the plant can increase the
                                                                                                           clinker content and reduce the amount
                                                                                                           of fly ash to obtain the same required
                                                                                                           cement strength development.
                                                                                                               Construction of the mill foundation
                                                                                                           and the base frame. This is followed by
                                                                                                           the erection of the pedestals, which are
                                                                                                           a critical part of the construction phase
                                                                                                           as correct alignment is essential. The
                                                                                                           mill gear box is mounted by applying an
                                                                                                           orange ‘Chockfast’ (see Figure 4) which
                                                                                                           provides good connection of the gear box
 Figure 5: height of Loesche LM 56.3+3 when installed                                                      base plate and the foundation. The mill


INTERNATIONAL CEMENT REVIEW JUNE 2011                                                           JUNE 2011 INTERNATIONAL CEMENT REVIEW
OPTIMISED GRINDING
                                                                                                              OPTIMISED GRINDING




housing is preassembled on the ground
along with the classifier, before being
lifted into place.
    The fly ash feeding system (see Figure
6) conveys design feeds dry fly ash
directly to the classifier as part of the fly
ash already has product fineness and does
not need to be ground. Due to that, the
capacity of the mill is increased. In the
two Indian grinding stations, the fly ash
is fed to the machine via two air slides.
However, other setups allow for at least
four inlets giving a more even distribution
of the fly ash over the circumference of
the classifier.

Summary
Loesche received the order for the two                                                Figure 6: gypsum and fly ash feed system to the mill
grinding systems in April 2007 and the
FOB delivery was in November 2008.              Figure 7: Nalagarh grinding plant
Erection started in December 2008 and
commissioning commenced in December
2009 with the first feed in February 2010.
By April 2010, 250tph of PPC had been
reached and in September 2010 further
optimisation was done leading to a stable
mill operation without any water injection
for grinding bed stabilisation.
   As a result no hot gas generator
was required. The specific power
consumption achieved was 5kWh lower
than expected. That was in part due
to the easier-to-grind clinker and fly
ash compared to the assumed values,
both of which had an impact on the
grindability of the feed mix and the
related specific energy consumption.
______________________________ I

LOESCHE Mill Type LM 56.3+3, Nalagarh, India




   Loesche GmbH
   Hansaallee 243
   40549 Düsseldorf
   Tel. +49 - 211 - 53 53 - 0
   Fax +49 - 211 - 53 53 - 500
   E-Mail: loesche@loesche.de
   www.loesche.com



                                                                                    JUNE 2011 INTERNATIONAL CEMENT REVIEW

More Related Content

What's hot

Monitoring Coal mill Performance
Monitoring Coal mill PerformanceMonitoring Coal mill Performance
Monitoring Coal mill PerformanceManohar Tatwawadi
 
TPS Coal Mills and Fan Performance
TPS Coal Mills and Fan PerformanceTPS Coal Mills and Fan Performance
TPS Coal Mills and Fan PerformanceManohar Tatwawadi
 
Presentation1
Presentation1Presentation1
Presentation1raju_786
 
LOESCHE: OVERVIEW
LOESCHE: OVERVIEWLOESCHE: OVERVIEW
LOESCHE: OVERVIEWLOESCHE
 
Devnya plant tour
Devnya plant tourDevnya plant tour
Devnya plant tourteopetz
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsSHIVAJI CHOUDHURY
 
Udaipur cement industries limited
Udaipur cement industries limitedUdaipur cement industries limited
Udaipur cement industries limitedHome
 
Cement Production Process
Cement Production ProcessCement Production Process
Cement Production ProcessDeepesh Mishra
 
LOESCHE Grinding Technology for the Power Industry
LOESCHE Grinding Technology for the Power IndustryLOESCHE Grinding Technology for the Power Industry
LOESCHE Grinding Technology for the Power IndustryLOESCHE
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoringManohar Tatwawadi
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionShyam Anandjiwala
 
Road construction equipment
Road construction equipment Road construction equipment
Road construction equipment HarshBhanushali14
 
Field study refuse hauler fleet
Field study refuse hauler fleetField study refuse hauler fleet
Field study refuse hauler fleetJoe Petrey
 
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private Limited
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private LimitedROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private Limited
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private LimitedIndiaMART InterMESH Limited
 

What's hot (20)

Monitoring Coal mill Performance
Monitoring Coal mill PerformanceMonitoring Coal mill Performance
Monitoring Coal mill Performance
 
RWF Report
RWF ReportRWF Report
RWF Report
 
TPS Coal Mills and Fan Performance
TPS Coal Mills and Fan PerformanceTPS Coal Mills and Fan Performance
TPS Coal Mills and Fan Performance
 
Presentation1
Presentation1Presentation1
Presentation1
 
LOESCHE: OVERVIEW
LOESCHE: OVERVIEWLOESCHE: OVERVIEW
LOESCHE: OVERVIEW
 
Devnya plant tour
Devnya plant tourDevnya plant tour
Devnya plant tour
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 
Udaipur cement industries limited
Udaipur cement industries limitedUdaipur cement industries limited
Udaipur cement industries limited
 
Cement Production Process
Cement Production ProcessCement Production Process
Cement Production Process
 
coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser
 
LOESCHE Grinding Technology for the Power Industry
LOESCHE Grinding Technology for the Power IndustryLOESCHE Grinding Technology for the Power Industry
LOESCHE Grinding Technology for the Power Industry
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
 
Cpg training file
Cpg training fileCpg training file
Cpg training file
 
RWFfinal
RWFfinalRWFfinal
RWFfinal
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
Road construction equipment
Road construction equipment Road construction equipment
Road construction equipment
 
Asphalt batch plant by majid
Asphalt batch plant by majidAsphalt batch plant by majid
Asphalt batch plant by majid
 
Field study refuse hauler fleet
Field study refuse hauler fleetField study refuse hauler fleet
Field study refuse hauler fleet
 
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private Limited
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private LimitedROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private Limited
ROAD CONSTRUCTION EQUIPMENT By Kesar Road Equipments (India) Private Limited
 
Wheel Defects
Wheel DefectsWheel Defects
Wheel Defects
 

Viewers also liked

LM-Master for Vertical Roller Mills
LM-Master for Vertical Roller MillsLM-Master for Vertical Roller Mills
LM-Master for Vertical Roller MillsLOESCHE
 
Afcm 2015 successful commissioning of ok mill at pt semen gresik v insite
Afcm 2015 successful commissioning of ok mill at pt semen gresik   v insiteAfcm 2015 successful commissioning of ok mill at pt semen gresik   v insite
Afcm 2015 successful commissioning of ok mill at pt semen gresik v insiteFLSmidth & Co. A/S.
 
Life cycle assessment pabrik semen holcim
Life cycle assessment pabrik semen holcimLife cycle assessment pabrik semen holcim
Life cycle assessment pabrik semen holcimHaelis Muslimah
 
Hydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operationHydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operationlinxiaomo
 
Cement Manufacturing hrs_eng
Cement Manufacturing hrs_engCement Manufacturing hrs_eng
Cement Manufacturing hrs_engBhone Thant
 
Vertical raw mill pradeep kumar
Vertical raw mill pradeep kumarVertical raw mill pradeep kumar
Vertical raw mill pradeep kumarpradeepdeepi
 

Viewers also liked (7)

LM-Master for Vertical Roller Mills
LM-Master for Vertical Roller MillsLM-Master for Vertical Roller Mills
LM-Master for Vertical Roller Mills
 
Afcm 2015 successful commissioning of ok mill at pt semen gresik v insite
Afcm 2015 successful commissioning of ok mill at pt semen gresik   v insiteAfcm 2015 successful commissioning of ok mill at pt semen gresik   v insite
Afcm 2015 successful commissioning of ok mill at pt semen gresik v insite
 
Life cycle assessment pabrik semen holcim
Life cycle assessment pabrik semen holcimLife cycle assessment pabrik semen holcim
Life cycle assessment pabrik semen holcim
 
Hydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operationHydraulic system vertical roller mill operation
Hydraulic system vertical roller mill operation
 
Cement Manufacturing hrs_eng
Cement Manufacturing hrs_engCement Manufacturing hrs_eng
Cement Manufacturing hrs_eng
 
VRM
VRMVRM
VRM
 
Vertical raw mill pradeep kumar
Vertical raw mill pradeep kumarVertical raw mill pradeep kumar
Vertical raw mill pradeep kumar
 

Similar to Standalone Vertical Roller Mills Without HGG

Loesche Mills for Cement and Granulated Blast Furnace Slag
Loesche Mills for Cement and Granulated Blast Furnace SlagLoesche Mills for Cement and Granulated Blast Furnace Slag
Loesche Mills for Cement and Granulated Blast Furnace SlagLOESCHE
 
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...LOESCHE
 
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw Material
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw MaterialLoesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw Material
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw MaterialLOESCHE
 
Tata steel west bokaro washery #3 report
Tata steel west bokaro washery #3 reportTata steel west bokaro washery #3 report
Tata steel west bokaro washery #3 reportSuchit Sharma
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTAshish Kholia
 
Pelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipmentsPelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipmentsGulshan Kumar Singh
 
Isa mill technology_used_in_effecient_grinding_circuits
Isa mill technology_used_in_effecient_grinding_circuitsIsa mill technology_used_in_effecient_grinding_circuits
Isa mill technology_used_in_effecient_grinding_circuitsB P Ravi
 
Finalelectricalreport
FinalelectricalreportFinalelectricalreport
FinalelectricalreportNAVEENGEHLOT5
 
Meeting the Market Demand for Greater Grinding Capacities
Meeting the Market Demand for Greater Grinding CapacitiesMeeting the Market Demand for Greater Grinding Capacities
Meeting the Market Demand for Greater Grinding CapacitiesLOESCHE
 
Wet pan mill
Wet pan millWet pan mill
Wet pan millmillball
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultantgubbiseo
 
Manufacturer of asphalt mixing plant and sale asphalt plants converted
Manufacturer of asphalt mixing plant and sale asphalt plants convertedManufacturer of asphalt mixing plant and sale asphalt plants converted
Manufacturer of asphalt mixing plant and sale asphalt plants convertedAtlas Technologies
 
Manufacturer of asphalt mixing plant and sale asphalt plants
Manufacturer of asphalt mixing plant and sale asphalt plantsManufacturer of asphalt mixing plant and sale asphalt plants
Manufacturer of asphalt mixing plant and sale asphalt plantsAtlas Technologies
 
Get Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyGet Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyLOESCHE
 
Design And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering MachineDesign And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering MachineAlbin Cherian
 
APDM - companion flange manufacturing report
APDM - companion flange manufacturing reportAPDM - companion flange manufacturing report
APDM - companion flange manufacturing reportKerrie Noble
 

Similar to Standalone Vertical Roller Mills Without HGG (20)

Loesche Mills for Cement and Granulated Blast Furnace Slag
Loesche Mills for Cement and Granulated Blast Furnace SlagLoesche Mills for Cement and Granulated Blast Furnace Slag
Loesche Mills for Cement and Granulated Blast Furnace Slag
 
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...
Cements Ground in the Vertical Roller Mill Fulfil the Quality Requirements of...
 
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw Material
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw MaterialLoesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw Material
Loesche Technology - Always a Step Ahead: Loesche Mills for Cement Raw Material
 
Tata steel west bokaro washery #3 report
Tata steel west bokaro washery #3 reportTata steel west bokaro washery #3 report
Tata steel west bokaro washery #3 report
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANT
 
Pelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipmentsPelletization of iron ores and the type of wear liners used in thier eqipments
Pelletization of iron ores and the type of wear liners used in thier eqipments
 
CEMNAT MANUFACTRING
CEMNAT MANUFACTRINGCEMNAT MANUFACTRING
CEMNAT MANUFACTRING
 
Isa mill technology_used_in_effecient_grinding_circuits
Isa mill technology_used_in_effecient_grinding_circuitsIsa mill technology_used_in_effecient_grinding_circuits
Isa mill technology_used_in_effecient_grinding_circuits
 
Finalelectricalreport
FinalelectricalreportFinalelectricalreport
Finalelectricalreport
 
Meeting the Market Demand for Greater Grinding Capacities
Meeting the Market Demand for Greater Grinding CapacitiesMeeting the Market Demand for Greater Grinding Capacities
Meeting the Market Demand for Greater Grinding Capacities
 
Wet pan mill
Wet pan millWet pan mill
Wet pan mill
 
REPORT (1)
REPORT (1)REPORT (1)
REPORT (1)
 
Bsp sail project
Bsp sail projectBsp sail project
Bsp sail project
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultant
 
Manufacturer of asphalt mixing plant and sale asphalt plants converted
Manufacturer of asphalt mixing plant and sale asphalt plants convertedManufacturer of asphalt mixing plant and sale asphalt plants converted
Manufacturer of asphalt mixing plant and sale asphalt plants converted
 
Manufacturer of asphalt mixing plant and sale asphalt plants
Manufacturer of asphalt mixing plant and sale asphalt plantsManufacturer of asphalt mixing plant and sale asphalt plants
Manufacturer of asphalt mixing plant and sale asphalt plants
 
Get Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution TechnologyGet Fit For The Future - Dry Ore Comminution Technology
Get Fit For The Future - Dry Ore Comminution Technology
 
Design And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering MachineDesign And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering Machine
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
APDM - companion flange manufacturing report
APDM - companion flange manufacturing reportAPDM - companion flange manufacturing report
APDM - companion flange manufacturing report
 

More from LOESCHE

Reshape Your CO2 Footprint With C/Clay
Reshape Your CO2 Footprint With C/ClayReshape Your CO2 Footprint With C/Clay
Reshape Your CO2 Footprint With C/ClayLOESCHE
 
Alternative Fuel Market After Covid-19 – Focus on Efficiency and Quality
Alternative Fuel Market After Covid-19 – Focus on Efficiency and QualityAlternative Fuel Market After Covid-19 – Focus on Efficiency and Quality
Alternative Fuel Market After Covid-19 – Focus on Efficiency and QualityLOESCHE
 
Setting a New Benchmark
Setting a New BenchmarkSetting a New Benchmark
Setting a New BenchmarkLOESCHE
 
Truck Unloading Station
Truck Unloading StationTruck Unloading Station
Truck Unloading StationLOESCHE
 
PlanEX Discharge System
PlanEX Discharge SystemPlanEX Discharge System
PlanEX Discharge SystemLOESCHE
 
BinEX Discharge System
BinEX Discharge SystemBinEX Discharge System
BinEX Discharge SystemLOESCHE
 
Bunker Discharge System
Bunker Discharge SystemBunker Discharge System
Bunker Discharge SystemLOESCHE
 
Dry Granulated BF Sand: A Groundbreaking and Sustainable Innovation
Dry Granulated BF Sand: A Groundbreaking and Sustainable InnovationDry Granulated BF Sand: A Groundbreaking and Sustainable Innovation
Dry Granulated BF Sand: A Groundbreaking and Sustainable InnovationLOESCHE
 
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...LOESCHE
 
LOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE
 
LOESCHE's Large Cement Mill 72.4+4 CS
LOESCHE's Large Cement Mill 72.4+4 CSLOESCHE's Large Cement Mill 72.4+4 CS
LOESCHE's Large Cement Mill 72.4+4 CSLOESCHE
 
Turning Waste Into Profit
Turning Waste Into ProfitTurning Waste Into Profit
Turning Waste Into ProfitLOESCHE
 
World Café @ LOESCHE Symposium Hanoi
World Café @ LOESCHE Symposium HanoiWorld Café @ LOESCHE Symposium Hanoi
World Café @ LOESCHE Symposium HanoiLOESCHE
 
An Integrated Approach to Alternative Fuel use in Cement Making
An Integrated Approach to Alternative Fuel use in Cement MakingAn Integrated Approach to Alternative Fuel use in Cement Making
An Integrated Approach to Alternative Fuel use in Cement MakingLOESCHE
 
LOESCHE’s Most Recent Step Into AF: Integration of MHC Technologies
LOESCHE’s Most Recent Step Into AF: Integration of MHC TechnologiesLOESCHE’s Most Recent Step Into AF: Integration of MHC Technologies
LOESCHE’s Most Recent Step Into AF: Integration of MHC TechnologiesLOESCHE
 
From Waste to a Reliable Co-Processing
From Waste to a Reliable Co-ProcessingFrom Waste to a Reliable Co-Processing
From Waste to a Reliable Co-ProcessingLOESCHE
 
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant Pakistan
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant PakistanLOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant Pakistan
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant PakistanLOESCHE
 
Optimal Alternative Fuel Burning Starts with Computer Simulation
Optimal Alternative Fuel Burning Starts with Computer SimulationOptimal Alternative Fuel Burning Starts with Computer Simulation
Optimal Alternative Fuel Burning Starts with Computer SimulationLOESCHE
 
State of the Art Waste Conditioning at LOESCHE
State of the Art Waste Conditioning at LOESCHEState of the Art Waste Conditioning at LOESCHE
State of the Art Waste Conditioning at LOESCHELOESCHE
 
Sep 2019
Sep 2019Sep 2019
Sep 2019LOESCHE
 

More from LOESCHE (20)

Reshape Your CO2 Footprint With C/Clay
Reshape Your CO2 Footprint With C/ClayReshape Your CO2 Footprint With C/Clay
Reshape Your CO2 Footprint With C/Clay
 
Alternative Fuel Market After Covid-19 – Focus on Efficiency and Quality
Alternative Fuel Market After Covid-19 – Focus on Efficiency and QualityAlternative Fuel Market After Covid-19 – Focus on Efficiency and Quality
Alternative Fuel Market After Covid-19 – Focus on Efficiency and Quality
 
Setting a New Benchmark
Setting a New BenchmarkSetting a New Benchmark
Setting a New Benchmark
 
Truck Unloading Station
Truck Unloading StationTruck Unloading Station
Truck Unloading Station
 
PlanEX Discharge System
PlanEX Discharge SystemPlanEX Discharge System
PlanEX Discharge System
 
BinEX Discharge System
BinEX Discharge SystemBinEX Discharge System
BinEX Discharge System
 
Bunker Discharge System
Bunker Discharge SystemBunker Discharge System
Bunker Discharge System
 
Dry Granulated BF Sand: A Groundbreaking and Sustainable Innovation
Dry Granulated BF Sand: A Groundbreaking and Sustainable InnovationDry Granulated BF Sand: A Groundbreaking and Sustainable Innovation
Dry Granulated BF Sand: A Groundbreaking and Sustainable Innovation
 
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...
Loesche-Separation Plant for Production of Ultrafine Granulated Blastfurnace ...
 
LOESCHE Waste Conditioning
LOESCHE Waste ConditioningLOESCHE Waste Conditioning
LOESCHE Waste Conditioning
 
LOESCHE's Large Cement Mill 72.4+4 CS
LOESCHE's Large Cement Mill 72.4+4 CSLOESCHE's Large Cement Mill 72.4+4 CS
LOESCHE's Large Cement Mill 72.4+4 CS
 
Turning Waste Into Profit
Turning Waste Into ProfitTurning Waste Into Profit
Turning Waste Into Profit
 
World Café @ LOESCHE Symposium Hanoi
World Café @ LOESCHE Symposium HanoiWorld Café @ LOESCHE Symposium Hanoi
World Café @ LOESCHE Symposium Hanoi
 
An Integrated Approach to Alternative Fuel use in Cement Making
An Integrated Approach to Alternative Fuel use in Cement MakingAn Integrated Approach to Alternative Fuel use in Cement Making
An Integrated Approach to Alternative Fuel use in Cement Making
 
LOESCHE’s Most Recent Step Into AF: Integration of MHC Technologies
LOESCHE’s Most Recent Step Into AF: Integration of MHC TechnologiesLOESCHE’s Most Recent Step Into AF: Integration of MHC Technologies
LOESCHE’s Most Recent Step Into AF: Integration of MHC Technologies
 
From Waste to a Reliable Co-Processing
From Waste to a Reliable Co-ProcessingFrom Waste to a Reliable Co-Processing
From Waste to a Reliable Co-Processing
 
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant Pakistan
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant PakistanLOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant Pakistan
LOESCHE Cement Mill LM 72.4+4 at Hub Cement Plant Pakistan
 
Optimal Alternative Fuel Burning Starts with Computer Simulation
Optimal Alternative Fuel Burning Starts with Computer SimulationOptimal Alternative Fuel Burning Starts with Computer Simulation
Optimal Alternative Fuel Burning Starts with Computer Simulation
 
State of the Art Waste Conditioning at LOESCHE
State of the Art Waste Conditioning at LOESCHEState of the Art Waste Conditioning at LOESCHE
State of the Art Waste Conditioning at LOESCHE
 
Sep 2019
Sep 2019Sep 2019
Sep 2019
 

Recently uploaded

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DaySri Ambati
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 

Recently uploaded (20)

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 

Standalone Vertical Roller Mills Without HGG

  • 2. OPTIMISED GRINDING I Standalone VRMs without HGG by Dr Daniel Strohmeyer, Water and energy are precious resources and without them life would not Loesche GmbH, Germany be as we know it today. Both commodities will become more expensive and scarcer in the future. Consequently, saving energy and water is essential for ecologically- and economically-viable production, particularly in the cement industry. F or vertical roller mills (VRM), water injection on the grinding table is a Figure 1: Loesche vertical roller mill for cement grinding common way to stabilise the grinding – material flow, feed materials and products bed and gives a smoother mill operation with lower vibration levels. However, there are some drawbacks to water use in a VRM. The feed moisture for OPC is commonly very low and in case water is added to the grinding process it has to be evaporated requiring thermal energy. If cooler exhaust gases are available in a cement plant this will not pose a major problem, but for a standalone grinding this source of hot gases is not available to drive-off any additional water. In this case a hot gas generator is needed to dry the material and to provide sufficient energy for the grinding system. This solution not only wastes fuel, it also creates further expenses. In some parts of the world the cement what is the centre of the rotating grinding the grinding table. Lumps, which escape industry is not permitted to utilise water table. The product is then driven outwards the rollers and are too heavy to rise with or its use is limited. Loesche has been by centrifugal forces, underneath the the gas flow drop through the louvre ring working on a system that can provide rollers where the grinding takes place. to a reject system and are then fed back grinding without the need for any water Ground material moves over the dam via the reject system. injection. Even if some water is available ring and goes up with the gas flow to the Raw mills or coal mills operate using the main aim is a grinding system that can classifier. The material has either reached the same size of rollers. What is particular be run without the need for permanent the required fineness and leaves the mill for Loesche cement mills is the 2+2 or operation of a hot gas generator. towards the bag filter or is sent back for 3+3 system, which features a combination further grinding, via the grid cone onto of different sizes of rollers. In cement VRMs A vertical roller mill can process many Figure 2: grinding plant flowsheet materials such as clinker, slag, gypsum, fly ash or limestone to produce various cement types of various finesse. The mill is part of a process that begins at the quarry. Only after the initial material has been through the raw material grinding, preheater, kiln and the cooler it reaches the finish mill where additives are added and the final product is obtained. Both Loesche and its customers are essentially concerned with this final product and its properties which are influenced by all stages of the cement making process. Material enters the VRM via a rotary feeder that poses as an air lock (see Figure 1), then moves down the feed chute to INTERNATIONAL CEMENT REVIEW JUNE 2011
  • 3. OPTIMISED GRINDING Figure 3: assumed grindability for Ambuja Cement´s Dadri and Nalagarh projects A system fan provides the draft through the machine and different sources of hot gases can be utilized if required. Furthermore a wide range of feed materials are tolerated and conveyed to the mill via the feeding system. Ambuja Cement’s Dadri and Nalagarh grinding stations In 2007, Loesche received an enquiry for two grinding stations in India. Both would have a cement capacity of 1.6Mta and each would be supplied with a Loesche VRM with 250tph of grinding capacity. The Dadri project is situated near New Delhi and the Nalagarh mill mills, Loesche has a ‘S’ support roller and internal friction within the material layer is located further to the north, close to a ‘M’ master roller. The ‘S’ roller is solely making it difficult to efficiently apply the the Himalayas. It became apparent that to prepare and stabilise the grinding bed. grinding forces. So the ‘S’ roller removes the grinding stations would need to be The most difficult thing to achieve when the air from the grinding bed and operated without a hot gas generator producing cement is to keep the grinding prepares the material for the master roller and consequently water injection for bed stable. In comparison to raw material to carry out the grinding. the purpose of grinding bed stabilisation grinding, with cement milling there are The flowsheet for a grinding system was not permitted. Loesche looked at more fines and some parts of the grinding with a VRM (see Figure 2) shows that, the customer’s requirements before bed tend to become partly fluidised, after the classifier, product is precipitated deciding on the best solution. The main caused by entrapped air. This reduces the and then recovered from the bag filter. constituents to be ground were clinker, fly Ambuja Cement‘s grinding station Nalagarh, India JUNE 2011 INTERNATIONAL CEMENT REVIEW
  • 4. OPTIMISED GRINDING OPTIMISED GRINDING Figure 3: assumed grindability for Ambuja Cement´s Dadri and Nalagarh projects A system fan provides the draft through Table 1: key data for Dadri and Nalagarh Table 2: Dadri performance different sources of the machine and data grinding stations hot gases can be utilized if required. Dadri Furthermore a wide range of feed PPC PPC capacity (tph) 250 LM 56.3+3 materials are tolerated and conveyed to Guarantee Achieved Gearbox power (kW) 5400 (Flender) the mill via the feeding system. Classifier LSKS 102 CS (kW) 560 Mill throughput (tph) 250 253 Fan motor power (kW) 3000 Fineness Ambuja Cement’s Dadri and 4000 3920 Mill diameter (m) 13.5 Feed moisture (%) Nalagarh grinding stations – 1.1 Height (m) 20 Product moisture (%) 2007, Loesche received an enquiry In – 0.3 Grinding table diameter (m)  5.6 Specific power consumption grinding stations in India. Both for two (kWh/t) 30.75 25.60 Grinding table weight (t) 109 (mill, fan, classifier, aux) have a cement capacity of 1.6Mta would Master roller (mm) 3 x2450 and each would be supplied with a Support roller (mm) 3 x 1600 Loesche VRM with 250tph of grinding capacity. The Dadri project is situated ash or clinker sources would be sourced. near New Delhi and had Nalagarh mill Therefore, Loesche the to assume a mills, and gypsum (up to five per cent) all ash Loesche has a ‘S’ support roller and internal friction within theto carry out a Standard procedure is material layer iscertain ‘grindability the north, close to located further to factor‘ and specific aof which have different‘S’ roller is solely ‘M’ master roller. The physical properties making it test to establish a proper sizing grinding difficult to efficiently apply the the Himalayas. It becamethe feed mix (see power consumption for apparent that to prepareleading to different grindabilities basically and stabilise the grinding bed. grinding mill andSo the ‘S’ box. However, for the forces. the gear roller removes the grinding stations would need to be Figure 3). The assumptions were based The most difficultindividualachieve when and a particular thing to behaviour the the from theboth of the projects it at air start of grinding bed and operated without a hot gas generator on Loesche’s experience and knowledge producing cement is to keep the grinding inside the mill. was not known where the different fly prepares the material for the master roller and other fly ash cement injection for of consequently water grinding plants bed stable. In comparison to raw material to carry out the grinding. the purpose of grinding bed concluded operating in India. Loesche stabilisation grinding, with cement milling there are The flowsheet for a grinding system was notwould need Loesche looked at that it permitted. a 56.3+3 mill with more fines and some parts of the grinding with a VRM (see Figure 2) shows that, thetable diameter of 5.6m. The selected a customer’s requirements before bed tend to become partly fluidised, after the classifier, product is precipitated deciding on the best solution. The main Flender gear box would have a power caused by entrapped air. This reduces the and then recovered from the bag filter. constituents toof 5400kW,were clinker, fly consumption be ground a Loesche dynamic classifier LSKS 102CS and a fan motor of 3000kW would form the other main parts of the system (see Table 1). Loesche’s scope of supply for the two Indian projects was not for the whole grinding plants, but for the mills, classifiers, sampling stations and the air slides for the product transport. Loesche’s product targets were PPC of 4000Blaine at 250tph using a specific power consumption of 30.75kWh/t for all the Loesche equipment and the fan supply Figure 4: erection of gear box (see Table 2). The PPC product would consist of 60 per cent clinker, five per cent gypsum and 35 per cent fly ash (2500 Blaine). If the plant receives clinker that is high in C3S then the fly ash content can be increased to the maximum permissible according to Indian standards. If the clinker exhibits a low C3S value, the plant can increase the clinker content and reduce the amount of fly ash to obtain the same required cement strength development. Construction of the mill foundation and the base frame. This is followed by the erection of the pedestals, which are a critical part of the construction phase as correct alignment is essential. The mill gear box is mounted by applying an orange ‘Chockfast’ (see Figure 4) which provides good connection of the gear box Figure 5: height of Loesche LM 56.3+3 when installed base plate and the foundation. The mill INTERNATIONAL CEMENT REVIEW JUNE 2011 JUNE 2011 INTERNATIONAL CEMENT REVIEW
  • 5. OPTIMISED GRINDING OPTIMISED GRINDING housing is preassembled on the ground along with the classifier, before being lifted into place. The fly ash feeding system (see Figure 6) conveys design feeds dry fly ash directly to the classifier as part of the fly ash already has product fineness and does not need to be ground. Due to that, the capacity of the mill is increased. In the two Indian grinding stations, the fly ash is fed to the machine via two air slides. However, other setups allow for at least four inlets giving a more even distribution of the fly ash over the circumference of the classifier. Summary Loesche received the order for the two Figure 6: gypsum and fly ash feed system to the mill grinding systems in April 2007 and the FOB delivery was in November 2008. Figure 7: Nalagarh grinding plant Erection started in December 2008 and commissioning commenced in December 2009 with the first feed in February 2010. By April 2010, 250tph of PPC had been reached and in September 2010 further optimisation was done leading to a stable mill operation without any water injection for grinding bed stabilisation. As a result no hot gas generator was required. The specific power consumption achieved was 5kWh lower than expected. That was in part due to the easier-to-grind clinker and fly ash compared to the assumed values, both of which had an impact on the grindability of the feed mix and the related specific energy consumption. ______________________________ I LOESCHE Mill Type LM 56.3+3, Nalagarh, India Loesche GmbH Hansaallee 243 40549 Düsseldorf Tel. +49 - 211 - 53 53 - 0 Fax +49 - 211 - 53 53 - 500 E-Mail: loesche@loesche.de www.loesche.com JUNE 2011 INTERNATIONAL CEMENT REVIEW