SlideShare a Scribd company logo
1 of 41
EMERGENCY POWER
TOPOLOGIES AND EVOLUTION
7X24 Fall Phoenix
Curt Gibson PE ATD
Power Solutions Manager
Generac Industrial Power
(209) 483-3910
Curt.Gibson@Generac.com
Introduction
 Curt Gibson
 Data Center Specialist for Generac
 2 – 3 data centers per week
 Accredited Tier Designer
 Registered Professional Engineer
 20 years in engineering of Emergency
Power Systems for ASCO and Generac
2
Goals Today
 Compare costs and reliability of different topologies
 Reliability
 Cost
 Scalability
 Four case studies
 University of Utah
 Venyu Data Center
 C7 Data Centers
 Green House Data
 Question and Answer
3
Typical Data Center Concerns
 Energy efficiency
 True reliability and availability
 Cost efficiency
 Return on investment
 Scalability
4
Recent Trends
 Shorter lead times, just in time
 Cost competition
 Less custom
 Modularity
 Standard products, off the shelf
 Widely available support
5
Modular Era
 Cost competitive
 Future proof
 Higher efficiencies
 Scalable
 Repetitive designs
 Economies of scale
 Lower cost of ownership
6
Paralleling Benefits
 Paralleling is easier now
 Improves reliability
 Lowers cost
 Makes systems more scalable
 Offers more availability
7
Traditional Approaches
 Custom controls
 Specialty schemes
 Larger generators
8
Paralleling Controls are Evolving
 Smaller digital controllers
 Every major manufacturer
 (Cat, Cummins, MTU, Kohler, Generac)
 Costs are decreasing
 Standardization provides reliability and modularity
9
Comparison of Concepts
 N = 5MW
 N+1 during all three construction phases
 Co-location data center
 Outdoor installation
 24 hour tanks
 80dB enclosures
 Four load buses
 480V loads
10
Economical Design Guidelines
 Transformer size (<4MVA)
 Generator size (<2500kW)
 Interrupt ratings (<100kAIC)
 Bus capacity (<6000A)
 Transfer Switch (<4000A)
 Breaker Size (<5000A)
 Distance ($200/ft/MW)
11
Uptime Institute Tier Requirements
TIER REQUIREMENTS Tier I Tier II Tier III Tier IV
Number of Delivery Paths 1 1
1Active
1Passive
2Active
Redundancy N N+1 N+1
N after any
failure
Compartmentalization No No No Yes
Concurrent Maintainability No No Yes Yes
Fault Tolerance No No No Yes
12
 Often confused with
“Common Attributes”
 Tier IV does not require
2N capacity
 Compartmentalization
includes dead lugs
when servicing
 Automatic fault
response is typical in
Tier III
Reliability Calculations
13
 Not “Availability”
 Simple equations
 Only to the UPS
 Probability the load is
fed
 Assumed 98% for
generators
 Assumed 99.9% for
buses
 Stattrek.com calculator
 IEEE 3006.7
Cost vs Reliability
14
Medium Voltage 2N, T4, PR
$2250 $750 $750 $3750 99.994%
Phase 1 Phase 2 Phase 3 Total
Reliability15
 2N systems
 Tier 4 Compliant
 Parallel Redundant
 Main-Tie-Main
 MV Paralleling
Switchgear
 Unit Substations
 Utility on the bus
 Breaker pair transfer
 Reliability
 (N4, n2, P0.98) = 0.99996
 1- ((1-0.999) X 1-(0.999)) = 0.99999
 N4, n2, P0.999 = 0.99999
 (0.99996)(0.99999)(0.99999)= 0.99994
A
Medium Voltage, N+1, T2, DR
$2000 $650 $650 $3300 99.645%16
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+1 systems
 Tier 2 Compliant
 Distributed Redundant
 Single Utility
 MV Paralleling
Switchgear
 Unit Substations
 Utility on the bus
 Breaker pair transfer
 Reliability
 (N4, n3, P0.98) = 0.99766
 0.999
 (N4, n3, P0.999) = 0.99999
 (0.99766)(0.999)(0.99999)= 0.99645
B
Parallel Redundant, 2N, T4, PR,
LV $1700 $600 $600 $2900 99.994%17
Phase 1 Phase 2 Phase 3 Total
Reliability
 2N System
 Tie Breaker
 Tier 4 Compliant
 Parallel Redundant
 Single Utility
 LV Paralleling
Switchgear
 Utility on the bus;
150KAIC
 Breaker pair transfer
 Reliability
 (N4, n2, P0.98) = 0.99996
 1- ((1-0.999) X 1-(0.999)) = 0.99999
 N4, n2, P0.999 = 0.99999
 (0.99996)(0.99999)(0.99999)= 0.99994
C
Cost vs Reliability
18
Distributed Redundant, N+1,T4,
DR $1200 $600 $600 $2400 99.742%19
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+1 System
 Tier 4 Compliant
 Distributed Redundant
 No Paralleling
 Main –Tie –Main
 65KAIC Switchgear
 Breaker pair transfer
 Day One = 2X1875
 Reliability
 (N4, n3, P(0.98)( 0.999) = 0.99742
D
Block Redundant N+1,T4, BR
$1100 $550 $550 $2200 99.742%20
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+1 System
 Tier 4 Compliant
 Block Redundant
 No Paralleling
 Catcher Bus
 65KAIC LV Switchgear
 Breaker pair transfer
 Day One = 2X1750
 Reliability
 (0.98)( 0.999) = 0.97902
 (N4, n3, P0.97902) = 0.99742
E
Cost vs Reliability
21
Single Bus, N+2, T2, DR
$850 $600 $600 $2050 99.745%22
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+2 System
 Tier 2 Compliant
 Distributed Redundant
 Paralleling on Gen
 65KAIC Switchgear
 Breaker pair transfer
 Day One = 2X1000
 Reliability
 (N12, n10, P0.98) = 0.99846
 0.999
 (N4, n3, P0.999) =0.99999
 (099846)(0.99999) (0.999)
 = 0.99745
F
Redundant Bus, N+2, T3, DR
$1000 $600 $600 $2200 99.845%23
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+2 System
 Tier 3 Compliant
 Distributed Redundant
 Paralleling on Gen
 65KAIC Switchgear
 Breaker pair transfer
 Day One = 2X1000
 Reliability
 (N12, n10, P0.98) = 0.99846
 1-(1-0.999)(1-0.999)= 0.99999
 (N4, n3, 0.999)= 0.99999
 =0.99845
G
Redundant Bus, N+4, T4, PR
$1040 $540 $790 $2370 99.998%24
Phase 1 Phase 2 Phase 3 Total
Reliability
 N+4 System
 Tier 4 Compliant
 Parallel Redundant
 Paralleling on Gen
 150KAIC Switchgear
 Breaker pair transfer
 Day One = 2X1000
 Reliability
 (N14, n10, P0.98) = 0.99969
 1 – (1-0.999)(1-0.999)= 0.99999
 0.99999 x 0.99999= 0.99998
H
Topology Phase
1
Phase 2 Phase 3 Total
(Thousand)
Reliability
98%, 99.9%
Reliability
94%, 99%
A Medium Voltage, 2N, PR, T4 $2250 $750 $750 $3750 99.994% 99.91%
B Medium Voltage, N+1, DR, T2 $2000 $650 $650 $3300 99.645% 97.02%
C Parallel Redundant, LV, 2N, PR, T3 $1700 $600 $600 $2900 99.994% 99.91%
D Distributed Redundant, LV, N+1,DR, T3 $1200 $600 $600 $2400 99.742% 97.94%
E Block Redundant, LV, N+1, BR, T3 $1100 $550 $550 $2200 99.742% 96.76%
F Single Bus, LV, N+1, DR, T2 $850 $600 $600 $2050 99.745% 95.87%
G Redundant Bus, LV, N+2, DR, T3 $1000 $600 $600 $2200 99.845% 96.83%
H Redundant Bus. LV, N+4, PR, T4 $1040 $540 $790 $2370 99.998% 99.89%
Comparison of Options
25
Conclusions
26
 Systems that used integrated paralleling were
more reliable at lower costs
 Availability was improved by redundant buses,
but reliability was only slightly affected
 Medium Voltage increased the price but not
reliability
 Scalability offers modular reliability
improvements
University of Utah
 11 MW design, but only 5MW installed
 20,000 Gallon fuel
27
One-Line
28
Outcomes and Conclusions
 Power usage is not as high as forecasted
 Provisions for future growth are available
 Bi-fuel may have improved fuel storage risk
 Smooth project execution
 Video
29
Venyu
 Baton Rouge
 40,000SF Co-Location
30
One-line
31
Factors and Decisions
 Redundant buses allow concurrent
maintenance
 Automatic transfer is fault tolerant
 All generators on line in 8 seconds
 Second floor services and high efficiency
transformers are other innovative aspects
 Video
32
C7 Data Center
 Salt Lake City
 50,000SF Co-Lo
33
One-Line
34
Outcomes and Conclusions
 Innovation is a key to success at C7
 Power usage in the facility is lower than
expected
 Energy efficient servers and cooling may
cause the expansion at this facility to never be
built
 Other buildings are receiving the same units
 Future large expansion is planned with this
topology
35
Green House Data
 Cheyenne Wyoming
36
Green House Data
37
 Cheyenne Wyoming
 5MW total final
 N + 1
 2MW first phase
 Single bus
 Distributed Redundant
Outcomes and Conclusions
38
Topology Phase
1
Phase 2 Phase 3 Total
(Thousand)
Reliability
98%, 99.9%
Reliability
94%, 99%
A Medium Voltage, 2N, PR, T4 $2250 $750 $750 $3750 99.994% 99.91%
B Medium Voltage, N+1, DR, T2 $2000 $650 $650 $3300 99.645% 97.02%
C Parallel Redundant, LV, 2N, PR, T3 $1700 $600 $600 $2900 99.994% 99.91%
D Distributed Redundant, LV, N+1,DR, T3 $1200 $600 $600 $2400 99.742% 97.94%
E Block Redundant, LV, N+1, BR, T3 $1100 $550 $550 $2200 99.742% 96.76%
F Single Bus, LV, N+1, DR, T2 $850 $600 $600 $2050 99.745% 95.87%
G Redundant Bus, LV, N+2, DR, T3 $1000 $600 $600 $2200 99.845% 96.83%
H Redundant Bus. LV, N+4, PR, T4 $1040 $540 $790 $2370 99.998% 99.89%
Comparison of Options
39
Observations and Conclusions
 Short lead-times, lower cost, and risk reduction
are driving decisions.
 New technology is available and being
adopted
 Standard components are favored over
custom
 Scalability is more important than before
 Many solutions exist to accomplish goals
40
Questions
 Thank You
41

More Related Content

Viewers also liked

Redundancy Datacenter Design
Redundancy Datacenter DesignRedundancy Datacenter Design
Redundancy Datacenter DesignJeffrey Lam
 
Artikel Informatie Transactiekosten Bas Daniels
Artikel Informatie Transactiekosten Bas DanielsArtikel Informatie Transactiekosten Bas Daniels
Artikel Informatie Transactiekosten Bas DanielsSebastien Daniels
 
Cordys in 5 steps
Cordys in 5 stepsCordys in 5 steps
Cordys in 5 stepsdkkro
 
Myths and realities about designing high availability data centers
Myths and realities about designing high availability data centersMyths and realities about designing high availability data centers
Myths and realities about designing high availability data centersMorrison Hershfield
 
Embodied Futures and Service Design - Introduction
Embodied Futures and Service Design - IntroductionEmbodied Futures and Service Design - Introduction
Embodied Futures and Service Design - IntroductionRichard Claassens CIPPE
 
(SPOT301) AWS Innovation at Scale
(SPOT301) AWS Innovation at Scale(SPOT301) AWS Innovation at Scale
(SPOT301) AWS Innovation at ScaleAmazon Web Services
 
Benoeming van een functionaris voor gegevensbescherming (FG)
Benoeming van een functionaris voor gegevensbescherming (FG)Benoeming van een functionaris voor gegevensbescherming (FG)
Benoeming van een functionaris voor gegevensbescherming (FG)Richard Claassens CIPPE
 

Viewers also liked (10)

Redundancy Datacenter Design
Redundancy Datacenter DesignRedundancy Datacenter Design
Redundancy Datacenter Design
 
Artikel Informatie Transactiekosten Bas Daniels
Artikel Informatie Transactiekosten Bas DanielsArtikel Informatie Transactiekosten Bas Daniels
Artikel Informatie Transactiekosten Bas Daniels
 
SSME Introduction
SSME IntroductionSSME Introduction
SSME Introduction
 
Authenticatie
AuthenticatieAuthenticatie
Authenticatie
 
Cordys Business Operations Platform
Cordys Business Operations PlatformCordys Business Operations Platform
Cordys Business Operations Platform
 
Cordys in 5 steps
Cordys in 5 stepsCordys in 5 steps
Cordys in 5 steps
 
Myths and realities about designing high availability data centers
Myths and realities about designing high availability data centersMyths and realities about designing high availability data centers
Myths and realities about designing high availability data centers
 
Embodied Futures and Service Design - Introduction
Embodied Futures and Service Design - IntroductionEmbodied Futures and Service Design - Introduction
Embodied Futures and Service Design - Introduction
 
(SPOT301) AWS Innovation at Scale
(SPOT301) AWS Innovation at Scale(SPOT301) AWS Innovation at Scale
(SPOT301) AWS Innovation at Scale
 
Benoeming van een functionaris voor gegevensbescherming (FG)
Benoeming van een functionaris voor gegevensbescherming (FG)Benoeming van een functionaris voor gegevensbescherming (FG)
Benoeming van een functionaris voor gegevensbescherming (FG)
 

Similar to 7X24Fall2014R5

Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentGilberto Mejía
 
Chapter 09
Chapter 09Chapter 09
Chapter 09Tha Mike
 
3Ph_UPS_and_ Lithium_Technology.pdf
3Ph_UPS_and_ Lithium_Technology.pdf3Ph_UPS_and_ Lithium_Technology.pdf
3Ph_UPS_and_ Lithium_Technology.pdfxuyentran26
 
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...Godwin Lobo
 
Multi-Objective design optimization of a Superconducting Fault Current Limiter
Multi-Objective design optimization of a Superconducting Fault Current LimiterMulti-Objective design optimization of a Superconducting Fault Current Limiter
Multi-Objective design optimization of a Superconducting Fault Current LimiterFranco Moriconi
 
“Head of real time and back office systems in operation”
“Head of real time and back office systems in operation”“Head of real time and back office systems in operation”
“Head of real time and back office systems in operation”IMDEA Energia
 
NCTu DIC 2012 term report
NCTu DIC 2012 term reportNCTu DIC 2012 term report
NCTu DIC 2012 term reportMichael Lee
 
lecture11.pdf
lecture11.pdflecture11.pdf
lecture11.pdfgetaneh30
 
Chapter 01
Chapter 01Chapter 01
Chapter 01Tha Mike
 
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Ghazal Falahi
 
Renewable energy course#02
Renewable energy course#02Renewable energy course#02
Renewable energy course#02Syed_Sajjad_Raza
 
Renewable energy course#02 gen
Renewable energy course#02 genRenewable energy course#02 gen
Renewable energy course#02 genSyed_Sajjad_Raza
 
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computationDSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computationDeltares
 
Chapter two Part two.pptx
Chapter two Part two.pptxChapter two Part two.pptx
Chapter two Part two.pptxAbdalleAidrous
 

Similar to 7X24Fall2014R5 (20)

shagufta-final review
shagufta-final reviewshagufta-final review
shagufta-final review
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
 
Chapter 09
Chapter 09Chapter 09
Chapter 09
 
3Ph_UPS_and_ Lithium_Technology.pdf
3Ph_UPS_and_ Lithium_Technology.pdf3Ph_UPS_and_ Lithium_Technology.pdf
3Ph_UPS_and_ Lithium_Technology.pdf
 
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...
Analysis of Low Frequency Oscillations in Autonomous Microgrid in Staic and D...
 
Multi-Objective design optimization of a Superconducting Fault Current Limiter
Multi-Objective design optimization of a Superconducting Fault Current LimiterMulti-Objective design optimization of a Superconducting Fault Current Limiter
Multi-Objective design optimization of a Superconducting Fault Current Limiter
 
“Head of real time and back office systems in operation”
“Head of real time and back office systems in operation”“Head of real time and back office systems in operation”
“Head of real time and back office systems in operation”
 
NCTu DIC 2012 term report
NCTu DIC 2012 term reportNCTu DIC 2012 term report
NCTu DIC 2012 term report
 
19212757
1921275719212757
19212757
 
try
trytry
try
 
lecture11.pdf
lecture11.pdflecture11.pdf
lecture11.pdf
 
Chapter 01
Chapter 01Chapter 01
Chapter 01
 
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
 
Renewable energy course#02
Renewable energy course#02Renewable energy course#02
Renewable energy course#02
 
Renewable energy course#02 gen
Renewable energy course#02 genRenewable energy course#02 gen
Renewable energy course#02 gen
 
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computationDSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
 
219118530 day-1-part-2-c ts-and-vts
219118530 day-1-part-2-c ts-and-vts219118530 day-1-part-2-c ts-and-vts
219118530 day-1-part-2-c ts-and-vts
 
Chapter two Part two.pptx
Chapter two Part two.pptxChapter two Part two.pptx
Chapter two Part two.pptx
 
5378086.ppt
5378086.ppt5378086.ppt
5378086.ppt
 
bucu2_5
bucu2_5bucu2_5
bucu2_5
 

7X24Fall2014R5

  • 1. EMERGENCY POWER TOPOLOGIES AND EVOLUTION 7X24 Fall Phoenix Curt Gibson PE ATD Power Solutions Manager Generac Industrial Power (209) 483-3910 Curt.Gibson@Generac.com
  • 2. Introduction  Curt Gibson  Data Center Specialist for Generac  2 – 3 data centers per week  Accredited Tier Designer  Registered Professional Engineer  20 years in engineering of Emergency Power Systems for ASCO and Generac 2
  • 3. Goals Today  Compare costs and reliability of different topologies  Reliability  Cost  Scalability  Four case studies  University of Utah  Venyu Data Center  C7 Data Centers  Green House Data  Question and Answer 3
  • 4. Typical Data Center Concerns  Energy efficiency  True reliability and availability  Cost efficiency  Return on investment  Scalability 4
  • 5. Recent Trends  Shorter lead times, just in time  Cost competition  Less custom  Modularity  Standard products, off the shelf  Widely available support 5
  • 6. Modular Era  Cost competitive  Future proof  Higher efficiencies  Scalable  Repetitive designs  Economies of scale  Lower cost of ownership 6
  • 7. Paralleling Benefits  Paralleling is easier now  Improves reliability  Lowers cost  Makes systems more scalable  Offers more availability 7
  • 8. Traditional Approaches  Custom controls  Specialty schemes  Larger generators 8
  • 9. Paralleling Controls are Evolving  Smaller digital controllers  Every major manufacturer  (Cat, Cummins, MTU, Kohler, Generac)  Costs are decreasing  Standardization provides reliability and modularity 9
  • 10. Comparison of Concepts  N = 5MW  N+1 during all three construction phases  Co-location data center  Outdoor installation  24 hour tanks  80dB enclosures  Four load buses  480V loads 10
  • 11. Economical Design Guidelines  Transformer size (<4MVA)  Generator size (<2500kW)  Interrupt ratings (<100kAIC)  Bus capacity (<6000A)  Transfer Switch (<4000A)  Breaker Size (<5000A)  Distance ($200/ft/MW) 11
  • 12. Uptime Institute Tier Requirements TIER REQUIREMENTS Tier I Tier II Tier III Tier IV Number of Delivery Paths 1 1 1Active 1Passive 2Active Redundancy N N+1 N+1 N after any failure Compartmentalization No No No Yes Concurrent Maintainability No No Yes Yes Fault Tolerance No No No Yes 12  Often confused with “Common Attributes”  Tier IV does not require 2N capacity  Compartmentalization includes dead lugs when servicing  Automatic fault response is typical in Tier III
  • 13. Reliability Calculations 13  Not “Availability”  Simple equations  Only to the UPS  Probability the load is fed  Assumed 98% for generators  Assumed 99.9% for buses  Stattrek.com calculator  IEEE 3006.7
  • 15. Medium Voltage 2N, T4, PR $2250 $750 $750 $3750 99.994% Phase 1 Phase 2 Phase 3 Total Reliability15  2N systems  Tier 4 Compliant  Parallel Redundant  Main-Tie-Main  MV Paralleling Switchgear  Unit Substations  Utility on the bus  Breaker pair transfer  Reliability  (N4, n2, P0.98) = 0.99996  1- ((1-0.999) X 1-(0.999)) = 0.99999  N4, n2, P0.999 = 0.99999  (0.99996)(0.99999)(0.99999)= 0.99994 A
  • 16. Medium Voltage, N+1, T2, DR $2000 $650 $650 $3300 99.645%16 Phase 1 Phase 2 Phase 3 Total Reliability  N+1 systems  Tier 2 Compliant  Distributed Redundant  Single Utility  MV Paralleling Switchgear  Unit Substations  Utility on the bus  Breaker pair transfer  Reliability  (N4, n3, P0.98) = 0.99766  0.999  (N4, n3, P0.999) = 0.99999  (0.99766)(0.999)(0.99999)= 0.99645 B
  • 17. Parallel Redundant, 2N, T4, PR, LV $1700 $600 $600 $2900 99.994%17 Phase 1 Phase 2 Phase 3 Total Reliability  2N System  Tie Breaker  Tier 4 Compliant  Parallel Redundant  Single Utility  LV Paralleling Switchgear  Utility on the bus; 150KAIC  Breaker pair transfer  Reliability  (N4, n2, P0.98) = 0.99996  1- ((1-0.999) X 1-(0.999)) = 0.99999  N4, n2, P0.999 = 0.99999  (0.99996)(0.99999)(0.99999)= 0.99994 C
  • 19. Distributed Redundant, N+1,T4, DR $1200 $600 $600 $2400 99.742%19 Phase 1 Phase 2 Phase 3 Total Reliability  N+1 System  Tier 4 Compliant  Distributed Redundant  No Paralleling  Main –Tie –Main  65KAIC Switchgear  Breaker pair transfer  Day One = 2X1875  Reliability  (N4, n3, P(0.98)( 0.999) = 0.99742 D
  • 20. Block Redundant N+1,T4, BR $1100 $550 $550 $2200 99.742%20 Phase 1 Phase 2 Phase 3 Total Reliability  N+1 System  Tier 4 Compliant  Block Redundant  No Paralleling  Catcher Bus  65KAIC LV Switchgear  Breaker pair transfer  Day One = 2X1750  Reliability  (0.98)( 0.999) = 0.97902  (N4, n3, P0.97902) = 0.99742 E
  • 22. Single Bus, N+2, T2, DR $850 $600 $600 $2050 99.745%22 Phase 1 Phase 2 Phase 3 Total Reliability  N+2 System  Tier 2 Compliant  Distributed Redundant  Paralleling on Gen  65KAIC Switchgear  Breaker pair transfer  Day One = 2X1000  Reliability  (N12, n10, P0.98) = 0.99846  0.999  (N4, n3, P0.999) =0.99999  (099846)(0.99999) (0.999)  = 0.99745 F
  • 23. Redundant Bus, N+2, T3, DR $1000 $600 $600 $2200 99.845%23 Phase 1 Phase 2 Phase 3 Total Reliability  N+2 System  Tier 3 Compliant  Distributed Redundant  Paralleling on Gen  65KAIC Switchgear  Breaker pair transfer  Day One = 2X1000  Reliability  (N12, n10, P0.98) = 0.99846  1-(1-0.999)(1-0.999)= 0.99999  (N4, n3, 0.999)= 0.99999  =0.99845 G
  • 24. Redundant Bus, N+4, T4, PR $1040 $540 $790 $2370 99.998%24 Phase 1 Phase 2 Phase 3 Total Reliability  N+4 System  Tier 4 Compliant  Parallel Redundant  Paralleling on Gen  150KAIC Switchgear  Breaker pair transfer  Day One = 2X1000  Reliability  (N14, n10, P0.98) = 0.99969  1 – (1-0.999)(1-0.999)= 0.99999  0.99999 x 0.99999= 0.99998 H
  • 25. Topology Phase 1 Phase 2 Phase 3 Total (Thousand) Reliability 98%, 99.9% Reliability 94%, 99% A Medium Voltage, 2N, PR, T4 $2250 $750 $750 $3750 99.994% 99.91% B Medium Voltage, N+1, DR, T2 $2000 $650 $650 $3300 99.645% 97.02% C Parallel Redundant, LV, 2N, PR, T3 $1700 $600 $600 $2900 99.994% 99.91% D Distributed Redundant, LV, N+1,DR, T3 $1200 $600 $600 $2400 99.742% 97.94% E Block Redundant, LV, N+1, BR, T3 $1100 $550 $550 $2200 99.742% 96.76% F Single Bus, LV, N+1, DR, T2 $850 $600 $600 $2050 99.745% 95.87% G Redundant Bus, LV, N+2, DR, T3 $1000 $600 $600 $2200 99.845% 96.83% H Redundant Bus. LV, N+4, PR, T4 $1040 $540 $790 $2370 99.998% 99.89% Comparison of Options 25
  • 26. Conclusions 26  Systems that used integrated paralleling were more reliable at lower costs  Availability was improved by redundant buses, but reliability was only slightly affected  Medium Voltage increased the price but not reliability  Scalability offers modular reliability improvements
  • 27. University of Utah  11 MW design, but only 5MW installed  20,000 Gallon fuel 27
  • 29. Outcomes and Conclusions  Power usage is not as high as forecasted  Provisions for future growth are available  Bi-fuel may have improved fuel storage risk  Smooth project execution  Video 29
  • 30. Venyu  Baton Rouge  40,000SF Co-Location 30
  • 32. Factors and Decisions  Redundant buses allow concurrent maintenance  Automatic transfer is fault tolerant  All generators on line in 8 seconds  Second floor services and high efficiency transformers are other innovative aspects  Video 32
  • 33. C7 Data Center  Salt Lake City  50,000SF Co-Lo 33
  • 35. Outcomes and Conclusions  Innovation is a key to success at C7  Power usage in the facility is lower than expected  Energy efficient servers and cooling may cause the expansion at this facility to never be built  Other buildings are receiving the same units  Future large expansion is planned with this topology 35
  • 36. Green House Data  Cheyenne Wyoming 36
  • 38.  Cheyenne Wyoming  5MW total final  N + 1  2MW first phase  Single bus  Distributed Redundant Outcomes and Conclusions 38
  • 39. Topology Phase 1 Phase 2 Phase 3 Total (Thousand) Reliability 98%, 99.9% Reliability 94%, 99% A Medium Voltage, 2N, PR, T4 $2250 $750 $750 $3750 99.994% 99.91% B Medium Voltage, N+1, DR, T2 $2000 $650 $650 $3300 99.645% 97.02% C Parallel Redundant, LV, 2N, PR, T3 $1700 $600 $600 $2900 99.994% 99.91% D Distributed Redundant, LV, N+1,DR, T3 $1200 $600 $600 $2400 99.742% 97.94% E Block Redundant, LV, N+1, BR, T3 $1100 $550 $550 $2200 99.742% 96.76% F Single Bus, LV, N+1, DR, T2 $850 $600 $600 $2050 99.745% 95.87% G Redundant Bus, LV, N+2, DR, T3 $1000 $600 $600 $2200 99.845% 96.83% H Redundant Bus. LV, N+4, PR, T4 $1040 $540 $790 $2370 99.998% 99.89% Comparison of Options 39
  • 40. Observations and Conclusions  Short lead-times, lower cost, and risk reduction are driving decisions.  New technology is available and being adopted  Standard components are favored over custom  Scalability is more important than before  Many solutions exist to accomplish goals 40

Editor's Notes

  1. Welcome This break out session will cover some advances in emergency power technology, and the options available for the data center designer or builder. I believe the findings being presented will be interesting in real world comparisons, and trends
  2. My name is Curt Gibson, and I am a data center specialist with Generac I see many data center projects each month from all over the USA My data center experience is a byproduct of engineering roles with manufacturers of products for this industry. I also spent a few years as a Facilities Manager for Sun Microsystems in Milpitas grateful for this opportunity to present,
  3. How to design a system This presentation will provide a comparison of costs versus reliability for a eight topologies We will then review four case studies showing how the systems were actually built The results show some interesting preferences and biases when the data center is actually built
  4. Concerns in the design of a data center can be grouped into areas These are pretty consistent in general Emerson Network Power provided this study last year, Focusing on Power, I have listed some key concerns related to this presentation
  5. Over the last 15 years I have seen trends that point in a certain direction Custom products were needed in the early days. I expect this to continue and see only increasing pressure to become more efficient Efficiency by removing labor and risk while increasing return on capital
  6. The modular era is here, due to this trend in efficiency. I stole the graphic on the right from Compass Data Centers We see modularity in UPS’s, HVAC, switchgear, and now also in generators There are many benefits to modularity.
  7. Modularity in generators is provided by the ability to parallel the generators Paralleling includes controls and switching. Of the technologies mentioned, I would like to focus on integrated paralleling It brings many benefits, and seems that many people don’t know that it is available, and very reliable. There are some ways to use the capability to your advantage which may not be obvious.
  8. When we talk about paralleling generators, often this is what engineers think of large generators and paralleleing switchgear Paralleling has traditionally been used when the generator was not large enough for the load Implementing a paralleling system was done by using PLC’s, synchronizers, load sharing modules, relays, and lots of custom engineering There are many risks and costs involved in this way to provide paralleling There are some great benefits by allowing all your sources to feed all your loads. It is more reliable.
  9. Technology is advancing and making life easier. Every major manufacturer On the left is a Generac motherboard, with includes synchronizing and load sharing controls. The next is a Woodward EGCP2, which was intended as a similar single board paralleling system The Horner ACM500 has all the processing to sync and share And the Beaglebone black is
  10. Today we are going to all go through the process of designing a project We will compare the different topologies This is the list of the requirements for our hypothetical project. These requirements are very common for a data center
  11. There are many factors to consider, but for this comparison we would like to keep the components in a the real world. Here is a list of guidelines that show the commonly available sizes of components. This is a very important One of the slide
  12. For the exercise we need to make sure we comply with basic tier compliance guideline. Despite no plans to apply for certification, engineers typically use the Uptime Institute Tiers as a guideline. These are just a few of the requirements.
  13. Reliability calculations are based on these simple equations, and we are only evaluating the emergency power system Reliability is the probability that the load will be fed in the event of an outage. The component probabilities used are estimates 98 % reliability for a generator to start and carry load is higher than average, but data centers tend to be more maintained than average Binomial distribution calculations are provided by Stattrek.com’s online calculator. b(x; n, P) = { n! / [ x! (n - x)! ] } * Px * (1 - P)n - x Availability is the brother to Reliability, but considers the time the unit is available for use. My farrarri is very reliable, it always starts, but it is in the shop most of the time, so it is not available. Steve Fairfax has presented data that show generators to be remarkably un-reliable, but of course he is not talking about your data center, or is he? I’d like to mention that I did receive help on the calculations from Bob Scheugar with HP-EYP in Los Angeles. He has done remarkable work on IEEE 3006.7 which deals with emergency power reliability.
  14. This is the first of eight topologies to be considered We will discuss only the blue items Substation transformers are also not included to keep everything fair
  15. No problems with AIC or bus size First day 2X2500kW Will save some money, but give up a little reliability Not concurrently maintainable, so not T3
  16. Low Voltage 200kAIC, 4000A main bus First day; 2X2500kW
  17. Trust the bus
  18. 65kAIC, 3000A