LTE KPI’s and Acceptance
Introduction
Why learn about ACCEPTANCE & KPI…s
› Acceptance is part of Business
Critical Terms & Conditions
› Control of KPI commitments is
control of cash flow and
profitability
› Ericsson had 80BSEK locked in
Acceptances in 2008
› If all projects finished one day
earlier = 500 MSEK/day for
Ericsson
Scope and objectives
› Explain how Acceptance & KPI’s are
impacting business
› Describe Ericsson view on LTE
Acceptance principles and KPI’s
› List LTE KPI approach and point to
further information
Objectives
Scope
› Customer and Ericsson view on
Acceptance and KPI’s -> business Impact
› KPI Based Acceptance
› Understanding the KPI’s
› LTE KPI’s
Overview
LTE ACCeptance principles
› HW should be accepted on delivery. The LTE product HW is tested at the factory
according to Ericsson quality procedure. Normal claims and warranty naturally
apply.
› HW Activation Codes should be accepted when the codes are made available to
the customer in ELIS, the license management system.
› SW should typically be accepted after successful demonstration in the customer
lab, following the Demo Object List (DOL). This should include the mechanisms for
both HW Activation Codes, and for SW Feature Activation Licenses.
› Installation services should be accepted when the node has been installed and
stand-alone tests have been successfully completed.
› Integration services should be accepted when the node has been configured and
integrated into the network, and stand-alone tests have been successfully
completed.
› Tuning services should be accepted when tuning service has been completed
and documented, ideally on a cluster per cluster basis.
Separate payments for HW, SW and Services !
LTE Acceptance tips
Not recommended:
› Contractual formulations including delay of fraction of payment of
HW/SW coupled to fulfillment of service
› Contractual formulations including liquidated damages (referring to
payment of HW/SW) coupled to fulfillment of service
Wrong acceptance approach has:
› Effect of tied capital –increases our Employed capital/Net sales ratio
› Effect of lowered margins – increased costs
If we tie up KPI…s with the HW and SW sales we might end up like this...
CASH FLOW Scenario
Upfront 15%
HW
75%
Delivery
SW
75%
Delivery
Services
75%
Monthly
Progress
Final Acceptance
10%
Recommended Terms
10%
75%
15%
Penalties
Discounts
!
High risk
Bad Cash flow
Cost blow out
KPI Based Acceptance Terms
Upfront 15%
HW
x%
Delivery
SW
y%
Delivery
Services
z%
Progress
Final Acceptance
10%
KPI
Targets
25% plus
50% or less
KPI linked
payment risk
Execution Acceptance Invoice/Collection
CAPITAL
EMPLOYED
TIME
Unbilled
Sales
Billed
Receivables
Inventory
ITO days: 83 days Account Receivables, DSO: 115 days
Overdue
Revenue
recognition
First invoice sent
Total: >80BSEK
Contract terms & conditions, project closure, and billing, key areas to address
“CASH
OUT!”
“CASH
IN!”
Operators are using complex acceptance
procedure with unrealistic KPIs ...
KPI BASED ACCEPTANCE
Why ARE CUSTOMERS DEMANDING KPIS ?
It…s not just about performance ‪ IT…S CONTROL AND COST!
TO CONTROL...
RISKS COSTS
› Internal pressure
› Don’t understand the
technology -> LTE !
› Force Ericsson to fix their
performance issues
› Avoid risk, shift risk to
Ericsson
› Own cash flow
issues
› Extra services at no
cost
› Penalties, discounts
or things for free
› Avoid paying
Ericsson
Ericsson Driving Forces
› Profitability, ability to fulfill contract
› Cash flow, timely invoicing
› Separate payment terms for HW, SW, and Services
› Close contract with clear responsibility, scope and acceptance
criteria
› Control of contract fulfillment
› Additional sales
Contractual Acceptance directive
1. Acceptance should have a defined scope, procedure and
timetable agreed in advance,
2. To be based upon objective and measurable criteria
3. KPI based acceptance should be limited to network and
technology consulting part of rollout contracts and limited to KPIs
defined in the KPI library at the Acceptance Gateway.
4. If products or parts are put into operation, automatic final
acceptance of such parts
Reference: Business Critical Terms&Conditions documents
ContracTual considerations and mu…s
› Contractual Considerations: The MU shall always strive to follow the
Acceptance Principles (Acceptance Approach and the Business Critical Terms
and Conditions).
› Restriction: If the MU deviates from the Acceptance Principles, it should
clearly state the deviations and estimate the risks and associated impact on
the business case for the contract.
‪ Deviations from the Acceptance Principles must be presented to the LTE Deal
Strategy meeting, pre-SDP2.
‪ The MU is responsible to secure required input, Price Governance, material (PPT,
Xls )
‪ Set up of this meeting is done by contacting Christer Gustafsson or Linda Lindberg
(manager EAB/FRP).
Acceptance activities
(typical)
Qualify
Sales
Opportunities
Create
Proposal
Close Deal
Contract
Management
Contract
Handshake
Risk
Full Track
SDP 4SDP 1 Risk SDP 2 Risk SDP 3
Critical Phase
Work out
your strategy
Prepare
offer/
contract/
Strong
wanted
position
Negotiate
Refine
Agree
Work out
the details –
Keep it simple –
Keep costs
down
Execute –
Look for ways
to save and
close out +
add on sales!
Ability to influence
Correction Cost
ACR
Strategy
Payments
Satisfaction
KAM
CSR
System
Solution
Service
Solution
CFR
Cash Flow
Delivery
Execution
Ensure link between
Terms of Payment
and Acceptance
Procedure.
(Particularly Cashflow)
Align Services (SoW)
and Solution with
Acceptance
Commitment incl. KPIs
Ensuring KPI Based
Acceptance is
integrated in total
Acceptance Procedure
Core 3 ‪ Responsibility
KPI Based Acceptance
• Overall Decision
• Ensure Acceptance risks are
understood by team and push
for flow between solution and
Acceptance
• Promote use of KPI Champion
KPI Based Acceptance Champion
Understanding the KPI…s
Basic facts ‪ KPI…s
› Operator thinking: More KPI’s, Operator
is getting more control
› Ericsson thinking: More KPI’s, higher
costs, longer procedure, risk for delays in
payment and penalties
› LTE is new, we can expect a lot of KPI’s
since operators want to protect
themselves
› We can be active and suggest KPI’s,
rather than wait for them - We know what
we are doing
› Right support is provided from the LTE
start – look at the Acceptance gateway
‪ What KPI’s and what values to discuss
‪ Acceptance method
WHAT IS IMPACTING KPI VALUES ?
TARGETS
PRE-CONDITIONS
HOW TO
MEASURE
CONDITIONS
EXCLUSIONS
PROCESSES
Common mistake
Reverse engineering
Often only KPI targets are stated in the contract
TARGETS
PRE-CONDITIONS
HOW TO
MEASURE
CONDITIONS
EXCLUSIONS
PROCESSES
Kpi…S AND PROJECT TYPES
› In Large Rollout Projects where we have a lot of
risks, unknowns and dependancies and where
services are small part - Minimise KPI risks and
costs
› In Standalone projects where we have mostly
services, and we have control - Use KPIs as
business driver
KPIs can result in good business !
LTE KPI…s
LTE kpi Acceptance
Types of Acceptance
› The scope of a contract will determine the type of acceptance used
› Four different types of acceptance are proposed in this document
‪ Product (Supply) Acceptance
‪ Proof of Concept Acceptance
‪ Network (or Cluster) Acceptance
‪ Stability Acceptance
› A network contract may stipulate more than one of these types of
acceptance
› It is desirable to minimise the acceptance testing – it can be
consuming and costly
KPI’s handling will depend on the type of Acceptance
There are 4 KPI recommended for use in LTE acceptance
Session Setup Success Rate
Session Abnormal Release Rate
‪ ONLY used for drive tests with short calls
or
Minutes per Abnormal Release
‪ Used for stats based KPI & drive tests with long calls
DL User Throughput
UL User Throughput
Recommended KPI
For use in LTE Acceptance
1
2
3
4
Recommended KPI
Recommended Location for KPI Measurement
No Recommended KPI
Controlled
Environment Golden Cluster
Network
(Cluster)
Drive Test
Counters /
Statistics
1 Session Setup Success Rate X X X X
2a Session Abnormal Release Rate X X X
2b Minutes per Abnormal Release X X
3 DL User Throughput X X X
4 UL User Throughput X X X
Product (Supply) /
Proof of Concept
Acceptance
Network
Rollout
Acceptance
Network
Stability
Acceptance
Recommended KPI ‪ example
Session Setup Success Rate
98.00%
99.0%
99.3%
99.50%
97.50%
98.00%
98.25%
98.50%
96.00%
96.50%
97.00%
97.50%
98.00%
98.50%
99.00%
99.50%
100.00%
L10A L10B L11 L12 =>
Lab / Controlled
Field / Drive test
Comments and Recommendations for Acceptance:
› SSSR should be tested using terminals which have undergone IODT with Ericsson
› Short calls are recommended for field test acceptance
› Lab and Controlled environment testing is to be undertaken in good radio conditions
(RSRP > -85dBm, SINR > 6dB)
› Exclusions should be included for drive testing where the setup failure is caused by
a factor beyond Ericsson’s control (eg. No coverage due to radio network design
constraints)
Throughput KPI
High Level Summary: Acceptance Process
DL Throughput (EPA 5Hz) vs SNR 10MHz
0
10000
20000
30000
40000
50000
60000
70000
80000
-5 0 5 10 15 20 25 30 35 40
SNR (dB)
Throughput(kbps)
Simulation value
Maximum Acceptance Value
Note: Graph is only an example, real values should be
calculated using Coverage and Dimensioning
Guideline
› Special methodology for the
KPI User throughputs
› Applications, measurement
methods, exclusions
explained
› Theoretical max value
calculations (based on NW
configuration) vs. Practical
value
› Throughput KPI’s are well
documented
› Safe way for Ericsson to
take lead in the KPI
negotiations
Optional KPI
For use in LTE Acceptance
There are 6 optional KPI for possible use in LTE acceptance:
Simultaneous Connected Users per RBS
Intra LTE HO Success rate
Round Trip Time (RTT)
Terminating Session Success Rate (Paging)
Control Plane Latency (Idle to Active)
Cell Availability
9
8
7
6
5
10
quiz
LTE Acceptance Strategy
Quiz
(continue to the next slide to start the Quiz)
ERTIES
ssing, 'Finish' button: Goes to Next Slide
ling, 'Finish' button: Goes to Next Slide
user to leave quiz: At any time
may view slides after quiz: At any time
may attempt quiz: Unlimited times
Summary
Summary ‪ LTE Acceptance & KPI…s
› KPI’s are often financial driver, rather than technical
› Keep it simple, minimize number of KPI’s
› Consult "LTE Acceptance Toolbox" for overall
procedure
› For KPI’s listing (Recommended and Optional), and
their definitions consult "Acceptance KPIs - methods
and values"
› KPI Target values are last in chain - consequence of
pre-conditions
› Special care is given to the throughput related KPI’s
– systematic and structured approach
› Negotiate with customer
› For more information about KPI Based Acceptance
please contact Graham Allen or Marius Sirbu
references
REFERENCES
› LTE Acceptance toolbox
› Business Critical Terms & Conditions
› LTE Acceptance approach – HW, SW, Services Acceptance
› KPI Based Acceptance.
› LTE KPI recommendations and values for rollout projects Acceptance KPIs - methods
and values
› Network Rollout Projects - KPI Tendering&Contracting
› Price Governance material (PPT, Xls )
219905365 lte-kp is-and-acceptance

More Related Content

What's hot

2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
Jean de la Sagesse
 
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.pptdokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
LibaBali
 
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
tharinduwije
 
DT analysis how to analyze crossed feeder issue by dt
DT analysis  how to analyze crossed feeder issue by dtDT analysis  how to analyze crossed feeder issue by dt
DT analysis how to analyze crossed feeder issue by dt
Sandy Sandyy
 
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
ibrahim jerbi
 

What's hot (20)

Volte troubleshooting
Volte troubleshootingVolte troubleshooting
Volte troubleshooting
 
E nodeb
E nodebE nodeb
E nodeb
 
422738668-LTE-Downlink-Throughput-Optimization-Based-on-Performance-Data [Rep...
422738668-LTE-Downlink-Throughput-Optimization-Based-on-Performance-Data [Rep...422738668-LTE-Downlink-Throughput-Optimization-Based-on-Performance-Data [Rep...
422738668-LTE-Downlink-Throughput-Optimization-Based-on-Performance-Data [Rep...
 
Drive test final
Drive test  finalDrive test  final
Drive test final
 
What LTE Parameters need to be Dimensioned and Optimized
What LTE Parameters need to be Dimensioned and OptimizedWhat LTE Parameters need to be Dimensioned and Optimized
What LTE Parameters need to be Dimensioned and Optimized
 
2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
2 g and 3g kpi improvement by parameter optimization (nsn, ericsson, huawei) ...
 
LTE KPI and PI Formula_NOKIA.pdf
LTE KPI and PI Formula_NOKIA.pdfLTE KPI and PI Formula_NOKIA.pdf
LTE KPI and PI Formula_NOKIA.pdf
 
LTE optimization
LTE optimizationLTE optimization
LTE optimization
 
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.pptdokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
dokumen.tips_ericsson-lte-throughput-troubleshooting-techniquesppt.ppt
 
NSN NOKIA 3G KPI for Network planning and optimization
NSN NOKIA 3G KPI for Network planning and optimizationNSN NOKIA 3G KPI for Network planning and optimization
NSN NOKIA 3G KPI for Network planning and optimization
 
wcdma-drive-test-analysis-ppt-libre
wcdma-drive-test-analysis-ppt-librewcdma-drive-test-analysis-ppt-libre
wcdma-drive-test-analysis-ppt-libre
 
huawei-lte-kpi-ref
huawei-lte-kpi-refhuawei-lte-kpi-ref
huawei-lte-kpi-ref
 
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
10 gsm bss network kpi (uplink downlink balance) optimization manual[1].doc
 
DT analysis how to analyze crossed feeder issue by dt
DT analysis  how to analyze crossed feeder issue by dtDT analysis  how to analyze crossed feeder issue by dt
DT analysis how to analyze crossed feeder issue by dt
 
395317358-LTE-Resource-Usage-Optimization.pptx
395317358-LTE-Resource-Usage-Optimization.pptx395317358-LTE-Resource-Usage-Optimization.pptx
395317358-LTE-Resource-Usage-Optimization.pptx
 
Lte capacity monitoring
Lte capacity monitoringLte capacity monitoring
Lte capacity monitoring
 
Lte ho parameters trial_01262011
Lte ho parameters trial_01262011Lte ho parameters trial_01262011
Lte ho parameters trial_01262011
 
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
2-How to Extend DTAC LTE Coverage with Limited RRU Capacity.pdf
 
Nokia kpi and_core_optimization
Nokia kpi and_core_optimizationNokia kpi and_core_optimization
Nokia kpi and_core_optimization
 
Lte basic parameters
Lte basic parametersLte basic parameters
Lte basic parameters
 

Viewers also liked (16)

Lte optimization
Lte optimizationLte optimization
Lte optimization
 
Lte kpi dt guide & measure method.
Lte kpi dt guide & measure method.Lte kpi dt guide & measure method.
Lte kpi dt guide & measure method.
 
Lte kpi accessability
Lte kpi accessabilityLte kpi accessability
Lte kpi accessability
 
Huawei - Lte handover troubleshooting
Huawei - Lte handover troubleshootingHuawei - Lte handover troubleshooting
Huawei - Lte handover troubleshooting
 
Umts Kpi
Umts KpiUmts Kpi
Umts Kpi
 
Syed imran Hussain (Resume)
Syed imran Hussain  (Resume)Syed imran Hussain  (Resume)
Syed imran Hussain (Resume)
 
SCFT report
SCFT reportSCFT report
SCFT report
 
Devendra kumar tiwari
Devendra kumar tiwari Devendra kumar tiwari
Devendra kumar tiwari
 
Ssv template
Ssv templateSsv template
Ssv template
 
Day 1 LTE Technology Overview
Day 1 LTE Technology OverviewDay 1 LTE Technology Overview
Day 1 LTE Technology Overview
 
ABOUT SCFT & CLUSTER AT
ABOUT SCFT & CLUSTER AT ABOUT SCFT & CLUSTER AT
ABOUT SCFT & CLUSTER AT
 
OneZone: Toronto metro-WiFi network overview
OneZone: Toronto metro-WiFi network overviewOneZone: Toronto metro-WiFi network overview
OneZone: Toronto metro-WiFi network overview
 
Lte kpi
Lte kpiLte kpi
Lte kpi
 
4g interview-question
4g interview-question4g interview-question
4g interview-question
 
Oss vs drive test pdcp throughput
Oss vs drive test pdcp throughputOss vs drive test pdcp throughput
Oss vs drive test pdcp throughput
 
SCFT-Training_v8.2-1
SCFT-Training_v8.2-1SCFT-Training_v8.2-1
SCFT-Training_v8.2-1
 

Similar to 219905365 lte-kp is-and-acceptance

AS Lead to Cash Highlevel Process FlowWIP
AS Lead to Cash Highlevel Process FlowWIPAS Lead to Cash Highlevel Process FlowWIP
AS Lead to Cash Highlevel Process FlowWIP
Juliann Hendon
 
Shifting Vendor Management Focus to Risk and Business Outcomes
Shifting Vendor Management Focus to Risk and Business OutcomesShifting Vendor Management Focus to Risk and Business Outcomes
Shifting Vendor Management Focus to Risk and Business Outcomes
CAST
 

Similar to 219905365 lte-kp is-and-acceptance (20)

Binary Stream - ASC 606 - Presentation
Binary Stream - ASC 606 - PresentationBinary Stream - ASC 606 - Presentation
Binary Stream - ASC 606 - Presentation
 
IT Service Catalogues
IT Service CataloguesIT Service Catalogues
IT Service Catalogues
 
Managing Service Providers for Today’s Digital Business
Managing Service Providers for Today’s Digital BusinessManaging Service Providers for Today’s Digital Business
Managing Service Providers for Today’s Digital Business
 
Preparing for ASC 606
Preparing for ASC 606Preparing for ASC 606
Preparing for ASC 606
 
Improve Performance with Enhanced Insight into Profitability and Costs using ...
Improve Performance with Enhanced Insight into Profitability and Costs using ...Improve Performance with Enhanced Insight into Profitability and Costs using ...
Improve Performance with Enhanced Insight into Profitability and Costs using ...
 
AS Lead to Cash Highlevel Process FlowWIP
AS Lead to Cash Highlevel Process FlowWIPAS Lead to Cash Highlevel Process FlowWIP
AS Lead to Cash Highlevel Process FlowWIP
 
Service Contract Analytics - Leverage analytics to improve revenue and profit...
Service Contract Analytics - Leverage analytics to improve revenue and profit...Service Contract Analytics - Leverage analytics to improve revenue and profit...
Service Contract Analytics - Leverage analytics to improve revenue and profit...
 
Technology Challenges of the new Regulatory Environment
Technology Challenges of the new Regulatory EnvironmentTechnology Challenges of the new Regulatory Environment
Technology Challenges of the new Regulatory Environment
 
Return Pool External
Return Pool ExternalReturn Pool External
Return Pool External
 
BiznetGio Presentation Business Continuity
BiznetGio Presentation Business ContinuityBiznetGio Presentation Business Continuity
BiznetGio Presentation Business Continuity
 
Procurement of Services using Oracle EBS
Procurement of Services using Oracle EBSProcurement of Services using Oracle EBS
Procurement of Services using Oracle EBS
 
Outsource.ppt
Outsource.pptOutsource.ppt
Outsource.ppt
 
IFRS 15 Solution Brief (Aptitude Software)
IFRS 15 Solution Brief (Aptitude Software)IFRS 15 Solution Brief (Aptitude Software)
IFRS 15 Solution Brief (Aptitude Software)
 
Warranty Master Breakout Session at IT Nation Connect 2019
Warranty Master Breakout Session at IT Nation Connect 2019Warranty Master Breakout Session at IT Nation Connect 2019
Warranty Master Breakout Session at IT Nation Connect 2019
 
Shifting Vendor Management Focus to Risk and Business Outcomes
Shifting Vendor Management Focus to Risk and Business OutcomesShifting Vendor Management Focus to Risk and Business Outcomes
Shifting Vendor Management Focus to Risk and Business Outcomes
 
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
 
Oracle EPM Day Boston - Improving Performance with Enhanced Insight into Pro...
Oracle EPM Day Boston -  Improving Performance with Enhanced Insight into Pro...Oracle EPM Day Boston -  Improving Performance with Enhanced Insight into Pro...
Oracle EPM Day Boston - Improving Performance with Enhanced Insight into Pro...
 
Good IT Project Management
Good IT Project Management Good IT Project Management
Good IT Project Management
 
Simplifying the Complexity of Salesforce CPQ: Tips & Best Practices
Simplifying the Complexity of Salesforce CPQ: Tips & Best PracticesSimplifying the Complexity of Salesforce CPQ: Tips & Best Practices
Simplifying the Complexity of Salesforce CPQ: Tips & Best Practices
 
Countdown to Compliance: Are you ready for ASC 606 / IFRS 15
Countdown to Compliance: Are you ready for ASC 606 / IFRS 15Countdown to Compliance: Are you ready for ASC 606 / IFRS 15
Countdown to Compliance: Are you ready for ASC 606 / IFRS 15
 

Recently uploaded

Recently uploaded (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 

219905365 lte-kp is-and-acceptance

  • 1. LTE KPI’s and Acceptance
  • 3. Why learn about ACCEPTANCE & KPI…s › Acceptance is part of Business Critical Terms & Conditions › Control of KPI commitments is control of cash flow and profitability › Ericsson had 80BSEK locked in Acceptances in 2008 › If all projects finished one day earlier = 500 MSEK/day for Ericsson
  • 4. Scope and objectives › Explain how Acceptance & KPI’s are impacting business › Describe Ericsson view on LTE Acceptance principles and KPI’s › List LTE KPI approach and point to further information Objectives Scope › Customer and Ericsson view on Acceptance and KPI’s -> business Impact › KPI Based Acceptance › Understanding the KPI’s › LTE KPI’s
  • 6. LTE ACCeptance principles › HW should be accepted on delivery. The LTE product HW is tested at the factory according to Ericsson quality procedure. Normal claims and warranty naturally apply. › HW Activation Codes should be accepted when the codes are made available to the customer in ELIS, the license management system. › SW should typically be accepted after successful demonstration in the customer lab, following the Demo Object List (DOL). This should include the mechanisms for both HW Activation Codes, and for SW Feature Activation Licenses. › Installation services should be accepted when the node has been installed and stand-alone tests have been successfully completed. › Integration services should be accepted when the node has been configured and integrated into the network, and stand-alone tests have been successfully completed. › Tuning services should be accepted when tuning service has been completed and documented, ideally on a cluster per cluster basis. Separate payments for HW, SW and Services !
  • 7. LTE Acceptance tips Not recommended: › Contractual formulations including delay of fraction of payment of HW/SW coupled to fulfillment of service › Contractual formulations including liquidated damages (referring to payment of HW/SW) coupled to fulfillment of service Wrong acceptance approach has: › Effect of tied capital –increases our Employed capital/Net sales ratio › Effect of lowered margins – increased costs If we tie up KPI…s with the HW and SW sales we might end up like this...
  • 8. CASH FLOW Scenario Upfront 15% HW 75% Delivery SW 75% Delivery Services 75% Monthly Progress Final Acceptance 10% Recommended Terms 10% 75% 15% Penalties Discounts ! High risk Bad Cash flow Cost blow out KPI Based Acceptance Terms Upfront 15% HW x% Delivery SW y% Delivery Services z% Progress Final Acceptance 10% KPI Targets 25% plus 50% or less KPI linked payment risk
  • 9. Execution Acceptance Invoice/Collection CAPITAL EMPLOYED TIME Unbilled Sales Billed Receivables Inventory ITO days: 83 days Account Receivables, DSO: 115 days Overdue Revenue recognition First invoice sent Total: >80BSEK Contract terms & conditions, project closure, and billing, key areas to address “CASH OUT!” “CASH IN!” Operators are using complex acceptance procedure with unrealistic KPIs ...
  • 11. Why ARE CUSTOMERS DEMANDING KPIS ? It…s not just about performance ‪ IT…S CONTROL AND COST! TO CONTROL... RISKS COSTS › Internal pressure › Don’t understand the technology -> LTE ! › Force Ericsson to fix their performance issues › Avoid risk, shift risk to Ericsson › Own cash flow issues › Extra services at no cost › Penalties, discounts or things for free › Avoid paying Ericsson
  • 12. Ericsson Driving Forces › Profitability, ability to fulfill contract › Cash flow, timely invoicing › Separate payment terms for HW, SW, and Services › Close contract with clear responsibility, scope and acceptance criteria › Control of contract fulfillment › Additional sales
  • 13. Contractual Acceptance directive 1. Acceptance should have a defined scope, procedure and timetable agreed in advance, 2. To be based upon objective and measurable criteria 3. KPI based acceptance should be limited to network and technology consulting part of rollout contracts and limited to KPIs defined in the KPI library at the Acceptance Gateway. 4. If products or parts are put into operation, automatic final acceptance of such parts Reference: Business Critical Terms&Conditions documents
  • 14. ContracTual considerations and mu…s › Contractual Considerations: The MU shall always strive to follow the Acceptance Principles (Acceptance Approach and the Business Critical Terms and Conditions). › Restriction: If the MU deviates from the Acceptance Principles, it should clearly state the deviations and estimate the risks and associated impact on the business case for the contract. ‪ Deviations from the Acceptance Principles must be presented to the LTE Deal Strategy meeting, pre-SDP2. ‪ The MU is responsible to secure required input, Price Governance, material (PPT, Xls ) ‪ Set up of this meeting is done by contacting Christer Gustafsson or Linda Lindberg (manager EAB/FRP).
  • 15. Acceptance activities (typical) Qualify Sales Opportunities Create Proposal Close Deal Contract Management Contract Handshake Risk Full Track SDP 4SDP 1 Risk SDP 2 Risk SDP 3 Critical Phase Work out your strategy Prepare offer/ contract/ Strong wanted position Negotiate Refine Agree Work out the details – Keep it simple – Keep costs down Execute – Look for ways to save and close out + add on sales! Ability to influence Correction Cost
  • 16. ACR Strategy Payments Satisfaction KAM CSR System Solution Service Solution CFR Cash Flow Delivery Execution Ensure link between Terms of Payment and Acceptance Procedure. (Particularly Cashflow) Align Services (SoW) and Solution with Acceptance Commitment incl. KPIs Ensuring KPI Based Acceptance is integrated in total Acceptance Procedure Core 3 ‪ Responsibility KPI Based Acceptance • Overall Decision • Ensure Acceptance risks are understood by team and push for flow between solution and Acceptance • Promote use of KPI Champion KPI Based Acceptance Champion
  • 18. Basic facts ‪ KPI…s › Operator thinking: More KPI’s, Operator is getting more control › Ericsson thinking: More KPI’s, higher costs, longer procedure, risk for delays in payment and penalties › LTE is new, we can expect a lot of KPI’s since operators want to protect themselves › We can be active and suggest KPI’s, rather than wait for them - We know what we are doing › Right support is provided from the LTE start – look at the Acceptance gateway ‪ What KPI’s and what values to discuss ‪ Acceptance method
  • 19. WHAT IS IMPACTING KPI VALUES ? TARGETS PRE-CONDITIONS HOW TO MEASURE CONDITIONS EXCLUSIONS PROCESSES
  • 20. Common mistake Reverse engineering Often only KPI targets are stated in the contract TARGETS PRE-CONDITIONS HOW TO MEASURE CONDITIONS EXCLUSIONS PROCESSES
  • 21. Kpi…S AND PROJECT TYPES › In Large Rollout Projects where we have a lot of risks, unknowns and dependancies and where services are small part - Minimise KPI risks and costs › In Standalone projects where we have mostly services, and we have control - Use KPIs as business driver KPIs can result in good business !
  • 23. LTE kpi Acceptance Types of Acceptance › The scope of a contract will determine the type of acceptance used › Four different types of acceptance are proposed in this document ‪ Product (Supply) Acceptance ‪ Proof of Concept Acceptance ‪ Network (or Cluster) Acceptance ‪ Stability Acceptance › A network contract may stipulate more than one of these types of acceptance › It is desirable to minimise the acceptance testing – it can be consuming and costly KPI’s handling will depend on the type of Acceptance
  • 24. There are 4 KPI recommended for use in LTE acceptance Session Setup Success Rate Session Abnormal Release Rate ‪ ONLY used for drive tests with short calls or Minutes per Abnormal Release ‪ Used for stats based KPI & drive tests with long calls DL User Throughput UL User Throughput Recommended KPI For use in LTE Acceptance 1 2 3 4
  • 25. Recommended KPI Recommended Location for KPI Measurement No Recommended KPI Controlled Environment Golden Cluster Network (Cluster) Drive Test Counters / Statistics 1 Session Setup Success Rate X X X X 2a Session Abnormal Release Rate X X X 2b Minutes per Abnormal Release X X 3 DL User Throughput X X X 4 UL User Throughput X X X Product (Supply) / Proof of Concept Acceptance Network Rollout Acceptance Network Stability Acceptance
  • 26. Recommended KPI ‪ example Session Setup Success Rate 98.00% 99.0% 99.3% 99.50% 97.50% 98.00% 98.25% 98.50% 96.00% 96.50% 97.00% 97.50% 98.00% 98.50% 99.00% 99.50% 100.00% L10A L10B L11 L12 => Lab / Controlled Field / Drive test Comments and Recommendations for Acceptance: › SSSR should be tested using terminals which have undergone IODT with Ericsson › Short calls are recommended for field test acceptance › Lab and Controlled environment testing is to be undertaken in good radio conditions (RSRP > -85dBm, SINR > 6dB) › Exclusions should be included for drive testing where the setup failure is caused by a factor beyond Ericsson’s control (eg. No coverage due to radio network design constraints)
  • 27. Throughput KPI High Level Summary: Acceptance Process DL Throughput (EPA 5Hz) vs SNR 10MHz 0 10000 20000 30000 40000 50000 60000 70000 80000 -5 0 5 10 15 20 25 30 35 40 SNR (dB) Throughput(kbps) Simulation value Maximum Acceptance Value Note: Graph is only an example, real values should be calculated using Coverage and Dimensioning Guideline › Special methodology for the KPI User throughputs › Applications, measurement methods, exclusions explained › Theoretical max value calculations (based on NW configuration) vs. Practical value › Throughput KPI’s are well documented › Safe way for Ericsson to take lead in the KPI negotiations
  • 28. Optional KPI For use in LTE Acceptance There are 6 optional KPI for possible use in LTE acceptance: Simultaneous Connected Users per RBS Intra LTE HO Success rate Round Trip Time (RTT) Terminating Session Success Rate (Paging) Control Plane Latency (Idle to Active) Cell Availability 9 8 7 6 5 10
  • 29. quiz LTE Acceptance Strategy Quiz (continue to the next slide to start the Quiz)
  • 30. ERTIES ssing, 'Finish' button: Goes to Next Slide ling, 'Finish' button: Goes to Next Slide user to leave quiz: At any time may view slides after quiz: At any time may attempt quiz: Unlimited times
  • 32. Summary ‪ LTE Acceptance & KPI…s › KPI’s are often financial driver, rather than technical › Keep it simple, minimize number of KPI’s › Consult "LTE Acceptance Toolbox" for overall procedure › For KPI’s listing (Recommended and Optional), and their definitions consult "Acceptance KPIs - methods and values" › KPI Target values are last in chain - consequence of pre-conditions › Special care is given to the throughput related KPI’s – systematic and structured approach › Negotiate with customer › For more information about KPI Based Acceptance please contact Graham Allen or Marius Sirbu
  • 34. REFERENCES › LTE Acceptance toolbox › Business Critical Terms & Conditions › LTE Acceptance approach – HW, SW, Services Acceptance › KPI Based Acceptance. › LTE KPI recommendations and values for rollout projects Acceptance KPIs - methods and values › Network Rollout Projects - KPI Tendering&Contracting › Price Governance material (PPT, Xls )