Exam 70-178: Microsoft Project 2010
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Objective:
The exam covers features of Microsoft Project 2010 to manage a project schedule and communicate the
project to the stakeholders. Some of the features include implementing a project plan with schedule,
resource, budget and milestones.
Candidate should have prior experience in scheduling, collaborating delivering a project using Project
2010 standard or professional. Candidate should also know the project life cycle and key project
management concepts.
When you pass Exam 70-178: Microsoft Project 2010, Managing Projects, you receive a certificate from
Microsoft in Microsoft Certified Technology Specialist (MCTS): Managing Projects with Microsoft Project
2010.
Related Microsoft Courses:
 Course 50413A: Mastering Microsoft Project 2010 ( 3 days) – classroom training
 Visit www.nrclc.com/Project2010 to view the list of Microsoft Project 2010 hands-on classroom
training provided at NR Computer Learning Center in Orange California.
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Topics in the Exam:
Initializing Project 2010
 Create a new project.
 creating a template from a completed
project
 creating a project from an existing
template
 Create a project from an existing
project
 Create a project from a Microsoft
SharePoint task list
 Create a project from a Microsoft
Office Excel workbook
 Create and maintain calendars.
 setting working or non-working
hours and days (exceptions and work
weeks) for calendars
 setting base calendar
 setting resource calendar
 setting hours per day
 applying calendars at the project
 task
 and resource levels
 Create custom fields.
 Creating basic formulas
 Create a graphical indicator criteria
 Create a lookup table
 Create a task and resource custom
fields
 Customize option settings.
 default task types
 manual vs. auto-scheduling
 project options
 calendar options (for example,
working hours per day and hours per
week)
 customized ribbon and quick access
toolbar (for example, settings to
share with others)
Creating a Task-Based Schedule
 Set up project information.
 defining project start date
 applying calendars and current date
 entering project properties
 displaying the project summary task
on a new project
 Create and modify a project task structure.
 creating and modifying summary tasks
and subtasks
 rearranging tasks
 creating milestones
 manually scheduled tasks
 outlining
 Build a logical schedule model.
 Specifying date constraints

 Specifying deadlines
 setting or changing the task mode
(manual or auto)
 dependencies (links)
 Create a user-controlled schedule.
 entering duration
 estimated durations
 user-controlled summary tasks
 Manage multiple projects.
 shared resource pool
 links between projects
 inserting sub-projects
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Managing Resources and Assignments
 Enter and edit resource information.
 max units
 resource types
 cost rate table
 cost per use
 availability
 resource group
 generic
 Apply task types and scheduling calculations.
 effort-driven tasks
 formula (work = duration x
units)
 choosing a task type
 Assign resources.
 assigning multiple resources
 assigning resources to tasks
 using units that represent part-
time work
 Edit assignments.
 task usage
 resource usage
 task forms
 editing assignments by setting
the task type in preparation for
assignment editing
 Manage resource allocation.
 viewing availability across
multiple projects
 changing assignment
information
 leveling and replacing resources
 Manage resource allocations by using Team
Planner.
 displaying current resource
allocations and assignments
 managing unassigned tasks
 resolving resource conflicts
 level resource overallocations
 substituting resources (moving
task assignments from one
resource to another)
 Model project costs.
 resource-based costs (work,
material, cost)
 cost per use
 fixed costs
 accrual method
Tracking and Analyzing a Project
 Set and maintain baselines.
 baselining an entire project
 baselining selected tasks
 multiple baselines
 updating a baseline (for
example rolling up to summary
tasks, resetting the baseline)
 Update actual progress.
 percentage completion
 actual or remaining duration
 actual work
 remaining work
 status date
 current date
 rescheduling uncompleted
work
 actual start and actual finish
 actual work and usage views
 cancelling an unneeded task
(for example
 inactivate a task
 set active flag or zero out
remaining work)
 Compare progress against a baseline.
 date variance
 work variance
 cost variance
 showing variance of the current
plan against baseline (tracking
Gantt)
 task slippage
 selecting a view to display
variance
 Resolve potential schedule problems by
using the Task Inspector.
 Task Inspector warnings and
suggestions
 identifying resource
overallocations
 Display Critical Path information.
 single or master projects
 viewing total slack
 displaying progress against
baseline or deadlines
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Communicating Project Information
 Apply views.
 applying views
 grouping
 filtering and highlighting
 auto-filter
 sorting
 tables
 Customize views.
 customizing views
 grouping
 filtering and highlighting
 sorting
 tables
 sharing a view (Organizer)
 Format views.
 gridlines
 bar styles
 Gantt chart styles
 text styles
 timeline
 cell formatting
 Share data with external sources.
 visual reports
 enhanced copy and paste
 copy picture
 sync to SharePoint (for example
 upload schedule
 sync with SharePoint list
 e-mail timeline)
 attaching documents or linking
hyperlinks to supporting
information
 exporting data to Excel
 Print schedules and reports.
 reporting progress status
 saving to PDF or XPS
 printing Gantt information
 schedule
 or timeline
 printing based on date range
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Basic Terminologies
Acceptance criteria
Actual Duration
Actual Effort
Activity
Activity Duration
Activity Duration Estimating
Activity List
Activity Sequence
Actual Cost
Baseline
Budget
Budget at Completion (BAC)
Budgeted Cost of Work Performed (BCWP)
Budgeted Cost of Work Scheduled (BCSSW)
Business Requirements
Change Request
Communications
Consensus
Constraint
Contract
Cost Estimating
Cost Performance Index (CPI)
Cost Variance (CV)
Crashing
Critical Path
Critical Path Method
Customer
Deliverable
Dependency
Duration
Duration Compression
Early Finish Date
Early Start Date
Earned Value (EV)
Estimate at Completion (EAC)
Estimate to Complete (ETC)
Fast Tracking
Finish-to-Finish Dependency
Finish-to-Start Dependency
Float
Free Float
Forecast
Gantt chart
Historical Information
Lag
Late Finish Date
Late Start Date
Milestone
Negative Variance
Network Diagram
Planned Value (PV)
Positive Variance
Precedence Diagramming Method (OPDM)
Predecessor
Program Evaluation and Review Techniques
(PERT)
Project
Project Life Cycle
Project Management
Project Manager
Project Scope
Project team Members
Resource
Resource Leveling
Schedule
Schedule Performance Index (SPI)
Schedule Variance (SV)
Start-to-finish dependency
Start-to-start dependency
Successor
Task
Time Estimate
Variance
Work Breakdown Structure (WBS)
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Cost Calculation Formulas
Terms Formulas
Cost Variance (CV) CV = EV-AC
Earned Value (EV) EV = BCWP
Estimate at Completion (EAC) EAC = AC + ETC
Estimate to Complete (ETC)
Program Evalaution and Review
Techniques (PERT)
PERT = Optimistic (O) + Pessimistic (P) + 4 * Most Likely (ML)
Schedule Variance (SV) SV = EV-PV
SV = Planned Date – Actual Date
Cost Performance Index (CPI) CPI = EV/AC
Schedule Performance Index
(SPI)
SPI = EV - PV
Preparation Materials:
NR Computer Learning Center provide following options for preparing for the exam:
 Classroom Training
To view the list of hands-on instructor led classroom training, visit www.nrclc.com/Project2010
 Online Classes
For more information on our 6 week online training classes starting that every month, visit
www.nrclc.com/Project2010.
 Corporate Training
To request for corporate training, visit http://www.nrclc.com/CorporateTraining
To join our email list to receive information on promotion, webinars, event and monthly newsletter, visit
www.nrclc.com.
For more information on exam, visit http://www.microsoft.com/learning/en/us/exam.aspx?ID=70-178
© NR Computer Learning Center
2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475
Exam 70-178: Microsoft Project 2010
Contact us to Get Free
Online Microsoft Project 2010 Training Videos
NR Computer Learning Center
2100 W. Orangewood, Suite 110
Orange, CA 92868
www.nrclc.com
(714) 505-3475
Twitter: @NRCLC
Facebook: www.facebook.com/NRCLC
Blog: www.nrclc.com/blog

More Related Content

More from NR Computer Learning Center

App Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersApp Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersNR Computer Learning Center
 
Building a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BIBuilding a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BINR Computer Learning Center
 
Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.NR Computer Learning Center
 
Stem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersStem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersNR Computer Learning Center
 
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BIBuilding a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BINR Computer Learning Center
 
Microsoft Office Specialist (MOS) Excel 2013 certification pathway
Microsoft Office Specialist (MOS) Excel 2013 certification pathwayMicrosoft Office Specialist (MOS) Excel 2013 certification pathway
Microsoft Office Specialist (MOS) Excel 2013 certification pathwayNR Computer Learning Center
 
AP Computer Science Test Prep - Part 2 - Object Oriented Programming
AP Computer Science Test Prep - Part 2 - Object Oriented ProgrammingAP Computer Science Test Prep - Part 2 - Object Oriented Programming
AP Computer Science Test Prep - Part 2 - Object Oriented ProgrammingNR Computer Learning Center
 
AP Computer Science Test Prep - Part 3 - Data Structure & Algorithm
AP Computer Science Test Prep - Part 3 - Data Structure & AlgorithmAP Computer Science Test Prep - Part 3 - Data Structure & Algorithm
AP Computer Science Test Prep - Part 3 - Data Structure & AlgorithmNR Computer Learning Center
 

More from NR Computer Learning Center (20)

Office 2019 tips & tricks
Office 2019 tips & tricksOffice 2019 tips & tricks
Office 2019 tips & tricks
 
App Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport CentersApp Development with Apple Swift Certification at Certiport Centers
App Development with Apple Swift Certification at Certiport Centers
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
National College Testing Association (NCTA)
National College Testing Association (NCTA)National College Testing Association (NCTA)
National College Testing Association (NCTA)
 
National College Testing Association (NCTA)
National College Testing Association (NCTA)National College Testing Association (NCTA)
National College Testing Association (NCTA)
 
Building a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BIBuilding a Dashboard in an hour with Power Pivot and Power BI
Building a Dashboard in an hour with Power Pivot and Power BI
 
Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.Introduction to the basic mathematical concept with Python Turtle.
Introduction to the basic mathematical concept with Python Turtle.
 
Stem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented CareersStem presentation - Pathways to Technology Oriented Careers
Stem presentation - Pathways to Technology Oriented Careers
 
MTA 98 364 - database fundamentals
MTA 98 364 - database fundamentalsMTA 98 364 - database fundamentals
MTA 98 364 - database fundamentals
 
MTA 361 software development fundamentals
MTA 361   software development fundamentalsMTA 361   software development fundamentals
MTA 361 software development fundamentals
 
Introduction to java
Introduction to javaIntroduction to java
Introduction to java
 
Introduction to c++
Introduction to c++Introduction to c++
Introduction to c++
 
Executive dashboard for small business
Executive dashboard for small businessExecutive dashboard for small business
Executive dashboard for small business
 
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BIBuilding a Dashboard in an Hour using Microsoft PowerPivot & Power BI
Building a Dashboard in an Hour using Microsoft PowerPivot & Power BI
 
Arduino for teens
Arduino for teensArduino for teens
Arduino for teens
 
Microsoft Office Specialist (MOS) Excel 2013 certification pathway
Microsoft Office Specialist (MOS) Excel 2013 certification pathwayMicrosoft Office Specialist (MOS) Excel 2013 certification pathway
Microsoft Office Specialist (MOS) Excel 2013 certification pathway
 
Computer Summer Camp for Kids and Teens
Computer Summer Camp for Kids and TeensComputer Summer Camp for Kids and Teens
Computer Summer Camp for Kids and Teens
 
MTA Database Certification Prep Training
MTA Database Certification Prep TrainingMTA Database Certification Prep Training
MTA Database Certification Prep Training
 
AP Computer Science Test Prep - Part 2 - Object Oriented Programming
AP Computer Science Test Prep - Part 2 - Object Oriented ProgrammingAP Computer Science Test Prep - Part 2 - Object Oriented Programming
AP Computer Science Test Prep - Part 2 - Object Oriented Programming
 
AP Computer Science Test Prep - Part 3 - Data Structure & Algorithm
AP Computer Science Test Prep - Part 3 - Data Structure & AlgorithmAP Computer Science Test Prep - Part 3 - Data Structure & Algorithm
AP Computer Science Test Prep - Part 3 - Data Structure & Algorithm
 

Recently uploaded

Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024Elizabeth Walsh
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxUmeshTimilsina1
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxJisc
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 

Recently uploaded (20)

Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 

Exam 70 178 - microsoft project 2010

  • 1. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010
  • 2. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Objective: The exam covers features of Microsoft Project 2010 to manage a project schedule and communicate the project to the stakeholders. Some of the features include implementing a project plan with schedule, resource, budget and milestones. Candidate should have prior experience in scheduling, collaborating delivering a project using Project 2010 standard or professional. Candidate should also know the project life cycle and key project management concepts. When you pass Exam 70-178: Microsoft Project 2010, Managing Projects, you receive a certificate from Microsoft in Microsoft Certified Technology Specialist (MCTS): Managing Projects with Microsoft Project 2010. Related Microsoft Courses:  Course 50413A: Mastering Microsoft Project 2010 ( 3 days) – classroom training  Visit www.nrclc.com/Project2010 to view the list of Microsoft Project 2010 hands-on classroom training provided at NR Computer Learning Center in Orange California.
  • 3. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Topics in the Exam: Initializing Project 2010  Create a new project.  creating a template from a completed project  creating a project from an existing template  Create a project from an existing project  Create a project from a Microsoft SharePoint task list  Create a project from a Microsoft Office Excel workbook  Create and maintain calendars.  setting working or non-working hours and days (exceptions and work weeks) for calendars  setting base calendar  setting resource calendar  setting hours per day  applying calendars at the project  task  and resource levels  Create custom fields.  Creating basic formulas  Create a graphical indicator criteria  Create a lookup table  Create a task and resource custom fields  Customize option settings.  default task types  manual vs. auto-scheduling  project options  calendar options (for example, working hours per day and hours per week)  customized ribbon and quick access toolbar (for example, settings to share with others) Creating a Task-Based Schedule  Set up project information.  defining project start date  applying calendars and current date  entering project properties  displaying the project summary task on a new project  Create and modify a project task structure.  creating and modifying summary tasks and subtasks  rearranging tasks  creating milestones  manually scheduled tasks  outlining  Build a logical schedule model.  Specifying date constraints   Specifying deadlines  setting or changing the task mode (manual or auto)  dependencies (links)  Create a user-controlled schedule.  entering duration  estimated durations  user-controlled summary tasks  Manage multiple projects.  shared resource pool  links between projects  inserting sub-projects
  • 4. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Managing Resources and Assignments  Enter and edit resource information.  max units  resource types  cost rate table  cost per use  availability  resource group  generic  Apply task types and scheduling calculations.  effort-driven tasks  formula (work = duration x units)  choosing a task type  Assign resources.  assigning multiple resources  assigning resources to tasks  using units that represent part- time work  Edit assignments.  task usage  resource usage  task forms  editing assignments by setting the task type in preparation for assignment editing  Manage resource allocation.  viewing availability across multiple projects  changing assignment information  leveling and replacing resources  Manage resource allocations by using Team Planner.  displaying current resource allocations and assignments  managing unassigned tasks  resolving resource conflicts  level resource overallocations  substituting resources (moving task assignments from one resource to another)  Model project costs.  resource-based costs (work, material, cost)  cost per use  fixed costs  accrual method Tracking and Analyzing a Project  Set and maintain baselines.  baselining an entire project  baselining selected tasks  multiple baselines  updating a baseline (for example rolling up to summary tasks, resetting the baseline)  Update actual progress.  percentage completion  actual or remaining duration  actual work  remaining work  status date  current date  rescheduling uncompleted work  actual start and actual finish  actual work and usage views  cancelling an unneeded task (for example  inactivate a task  set active flag or zero out remaining work)  Compare progress against a baseline.  date variance  work variance  cost variance  showing variance of the current plan against baseline (tracking Gantt)  task slippage  selecting a view to display variance  Resolve potential schedule problems by using the Task Inspector.  Task Inspector warnings and suggestions  identifying resource overallocations  Display Critical Path information.  single or master projects  viewing total slack  displaying progress against baseline or deadlines
  • 5. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Communicating Project Information  Apply views.  applying views  grouping  filtering and highlighting  auto-filter  sorting  tables  Customize views.  customizing views  grouping  filtering and highlighting  sorting  tables  sharing a view (Organizer)  Format views.  gridlines  bar styles  Gantt chart styles  text styles  timeline  cell formatting  Share data with external sources.  visual reports  enhanced copy and paste  copy picture  sync to SharePoint (for example  upload schedule  sync with SharePoint list  e-mail timeline)  attaching documents or linking hyperlinks to supporting information  exporting data to Excel  Print schedules and reports.  reporting progress status  saving to PDF or XPS  printing Gantt information  schedule  or timeline  printing based on date range
  • 6. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Basic Terminologies Acceptance criteria Actual Duration Actual Effort Activity Activity Duration Activity Duration Estimating Activity List Activity Sequence Actual Cost Baseline Budget Budget at Completion (BAC) Budgeted Cost of Work Performed (BCWP) Budgeted Cost of Work Scheduled (BCSSW) Business Requirements Change Request Communications Consensus Constraint Contract Cost Estimating Cost Performance Index (CPI) Cost Variance (CV) Crashing Critical Path Critical Path Method Customer Deliverable Dependency Duration Duration Compression Early Finish Date Early Start Date Earned Value (EV) Estimate at Completion (EAC) Estimate to Complete (ETC) Fast Tracking Finish-to-Finish Dependency Finish-to-Start Dependency Float Free Float Forecast Gantt chart Historical Information Lag Late Finish Date Late Start Date Milestone Negative Variance Network Diagram Planned Value (PV) Positive Variance Precedence Diagramming Method (OPDM) Predecessor Program Evaluation and Review Techniques (PERT) Project Project Life Cycle Project Management Project Manager Project Scope Project team Members Resource Resource Leveling Schedule Schedule Performance Index (SPI) Schedule Variance (SV) Start-to-finish dependency Start-to-start dependency Successor Task Time Estimate Variance Work Breakdown Structure (WBS)
  • 7. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Cost Calculation Formulas Terms Formulas Cost Variance (CV) CV = EV-AC Earned Value (EV) EV = BCWP Estimate at Completion (EAC) EAC = AC + ETC Estimate to Complete (ETC) Program Evalaution and Review Techniques (PERT) PERT = Optimistic (O) + Pessimistic (P) + 4 * Most Likely (ML) Schedule Variance (SV) SV = EV-PV SV = Planned Date – Actual Date Cost Performance Index (CPI) CPI = EV/AC Schedule Performance Index (SPI) SPI = EV - PV Preparation Materials: NR Computer Learning Center provide following options for preparing for the exam:  Classroom Training To view the list of hands-on instructor led classroom training, visit www.nrclc.com/Project2010  Online Classes For more information on our 6 week online training classes starting that every month, visit www.nrclc.com/Project2010.  Corporate Training To request for corporate training, visit http://www.nrclc.com/CorporateTraining To join our email list to receive information on promotion, webinars, event and monthly newsletter, visit www.nrclc.com. For more information on exam, visit http://www.microsoft.com/learning/en/us/exam.aspx?ID=70-178
  • 8. © NR Computer Learning Center 2100 W. Orangewood . Suite 110 . Orange , CA 92868 , www.nrclc.com . (714) 505-3475 Exam 70-178: Microsoft Project 2010 Contact us to Get Free Online Microsoft Project 2010 Training Videos NR Computer Learning Center 2100 W. Orangewood, Suite 110 Orange, CA 92868 www.nrclc.com (714) 505-3475 Twitter: @NRCLC Facebook: www.facebook.com/NRCLC Blog: www.nrclc.com/blog