SlideShare a Scribd company logo
1 of 7
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 1
1.0 PURPOSE
The purpose of this Method Statement is to establish a uniform procedure for: -
a) Welding joint of stainless-steel pipe and fittings (Sch. 10)
b) Threaded joint of stainless-steel pipe and fittings (Sch. 40)
It aims to ensure that the work force involved to perform the operations have a complete
understanding of the operating standards and safety practices associated with the use
of machinery/equipment /tools.
2.0 SCOPE
The scope of works shall not be limited to piping works only. It shall include supply,
deliver, installation, testing, commissioning and defect liability maintenance for the entire
Cold Water plumbing system.
3.0 HANDLING AND STORAGE OF MATERIALS
Upon delivery at site, all pipes will be hoisted carefully and stored in a dry suitably
designated area. Materials shall preferably be place on timber at both ends, stacked
neatly. Fittings will be stored in a dry store.
4.0 INSPECTION OF MATERIALS
Inspection is then carried out to ensure that materials delivered is new and without
any damage. The materials will not be used for installations unless it has been
inspected and verified for conformance to specifications. Only pipe that conforming to
SPAN standard shall be approved and accepted. Inspection and verification will be
carried out upon Supplier Delivery Order and documented in Material Inspection
Checklist form
This inspection will be carried out by Site Supervisors. The acceptance of material
delivered shall be at the discretion of the consultant representatives with verification by
his immediate superior, resident engineer.
5.0 SITE PLANNING AND PREPARATION
a. All relevant documents shall be approved for execution.
b. All the personnel involved in the job should attend the safety training.
c. Ensure all workers are equipped with PPE (i.e., hard hat with chin strap, goggles,
safety shoes, gloves, safety harness, etc.) relevant to the nature of work to be
carried out.
d. Determine manpower and delegation of task.
e. Fully barricade the work area and restrict entry to authorized personnel only.
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 2
f. Deliver to the site the required materials to be installed.
g. All required machineries, tools and equipment shall be placed into the designated
area.
h. Prior to installation of the steel frames and bracket plates, the location should be
cleaned and must be free from any obstructions.
i. Prior to transferring of the Evaporator from yard to outside of building, the road must
be checked and free from obstructions for the truck and mobile crane to have easy
access.
j. Prior to shifting of the evaporator from outside to inside of the building, ensure that
the steel bed frame and railing are properly fixed, aligned and levelled.
k. All qualified and authorized personnel shall be notified when commencing works.
l. For night work, ensure that lightings are adequate.
m. A proper line of communication throughout the job must be detailed.
n. Anticipated problems shall be discussed and resolved immediately.
o. Material catalogue and / or sample to be submitted early for approval prior to actual
construction to avoid delay to physical construction.
p. Daily checklist and measurement sheet for recording purpose and shall be
established to provide information for claim and producing as-built drawing level.
6.0 ACTUAL WORK METHODOLOGY
6.1 WORK METHOD FOR WELDING JOINT – SCHEDULE 10, ASTM A312 TYPE 304
6.1.1 Materials
 Stainless Steel Pipe and Fittings (Schedule 10) - 65mm till 150mm sizes
6.1.2 Tools & Machinery
i) Magnetic drill machine, Drill machine, wrench, hammer, pliers, etc.
ii) Level bar or Level hose
iii) Mobile Crane or Boom Truck
iv) Chain blocks, Slings, shackles, belts, chains, etc.
v) Welding Machine, Electrodes and welding units
vi) Measuring tape, pipe fitter’s wrap-around, marker pen, cleaning rags
vii) Cutting/Grinding machine with carborundum cutting & sanding/grinding
disc
viii)Pie tape, Curve-o-mark, Angle Grinder, Emery disc
ix) Electrical extension wires
x) Level bar or Level hose
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 3
6.1.3 Installation Procedure
a) All the welding shall be as per the drawing or standard.
b) Welding must be carried out by qualified and certified welder as per
the below welding preparation and procedures: -
i) Cutting and bevelling
 Mark off the dimension of each pipe and fittings as per the
approved drawing.
 Proceed with cutting of Stainless-steel pipes and fittings,
which shall be done by using cutting disc.
 Once the pipes and fittings are cut, commence with the edge
preparation.
 the edge cleaning and bevelling shall be done using abrasive
grinding disc/bevelling machines.
 Line number, Spool Numbers and Joint Numbers are to be
clearly identified and marked on the spool with the welder
identification for each joint.
ii) Purging arrangement
 Before fit-up, arrange sponge/foam along with argon, gas,
hoses from both sides of the joint.
 Before start of welding open the purging gas in the joint, so
we can get back purging gas during the welding.
iii) Fit-Up and Tack Welding
 Once the surface is bevelled and cleaned proceed for tack
welding
 Welders should put on proper safety equipment prior for
welding.
 Fit-up assembly shall be carried out by using locally prepared
couplers. All the required pipe holdings work benches,
assembling brackets’’ bolts etc. Would be made in house to
suit the pipe size.
 For Butt welds uniform root gap of 1.5-3mm shall be
maintained.
 Before commences the welding ensure that spool is aligned
properly.
 Once required levelness and alignment achieved proceed for
welding.
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 4
 The pipe shall be tack welded in three equidistant positions,
Tack welding shall as per approved drawing and standard by
a qualified welder.
iv) Welding
 Ensure that edges are free from dust, rust, oil, grease, paint
etc.
 Welding shall be done as per approved drawing and by
complying with the particular piping standard. Preheating and
welding consumable shall be checked before starting of
welding.
 Each welding layer shall be cleaned before starting to weld
next layer. The cleaned area shall be free from slags. Any
visual defects like cracks, pores, spatters weld shall be
removed by grinding before the next layer is applied. The
ends of weld layer shall be removed by grinding in tack points
of each weld. Any possible welds excess layer will be
removed by grinding.
 For the fabrication & welding of stainless-steel pipes and
fittings only stainless-steel tools and consumables (Wire brush
chipping, Hammer, and Abrasive disc) shall be used.
 Appearance of finished weld shall be as even as possible and
free from spatter, under cutting, cracks, excess reinforcement
etc.
6.2 WORK METHOD FOR THREADED JOINT – SCHEDULE 40, ASTM A312 TYPE
304
6.2.1 Material
Stainless Steel Pipe and Fittings (Schedule 10) - 20mm till 50mm sizes
6.2.2 Tools & Machinery
i) Measuring tape, marker pen, cleaning rags and twine.
ii) Scaffold
iii) Threading machine
iv) Fibre cutter
v) Drill Machine
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 5
6.2.3 Installation Procedure
a) Check construction drawings and establish area or works that pipe to be
installed.
b) Determine the pipe route and measure pipe length to be cut.
c) Employing the fibre cutting machine, cut required lengths of stainless-
steel pipe necessary at the work shop.
d) Set the threading machine die to the correct size of pipe to be threaded.
e) Insert pipe into threading machine and thread with at least two passed.
The first to obtain the basic pitch thread (BS 21) and the polish off the
threads. These are termed the rough cut and the fine cut. Two passes
are also necessary so as not to damage the high tensile die.
f) Before removing the complete pipe, the completed threads need to be
checked by screwing in a Stainless-Steel pipe socket of the same
diameter into the threads. If the threaded pipe cannot penetrate at least
four (4) revolutions into the socket it means that the threads are not good
and needs to be redo.
g) Upon completing the threading of all the pipes, apply sealing (Teflon)
tape on to all the threaded joints. This should be done in a clock wise
rotation with the roll of tape moving away from you.
h) Sockets are next fixed onto one end of each completed pipe. This is
achieved either by locking the pipe on a vice and wrenching tight the
socket or by employing two wrenches in opposing directions.
i) Deliver all the above completed pipes with sockets to the site where they
are to be installed.
j) Mark the start and end points of the pipe to be installed on the soft fit of
the slab for horizontal installation or wall for vertical installation.
k) Drill both points marked using the hand drill, insert drop-in anchor and set
them.
l) Screw in two length of stud bolts into the drop-in anchor and pull a twine
from the first stud to the second stud.
m) From the twine, mark the intermediate hangers that are required between
the start and end points.
n) Repeat procedures (10) and (11) to complete the intermediate pipe
supports.
o) The pipes are now hanged onto the supports, jointed and tightened
together using pipe wrenches.
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 6
p) When a significant section of pipes is completed or before it is to be
installed in a plumbing shaft, the pipes have to be tested by means of
hydrostatic pressure tests.
6.3 Work Flow Chart Installation of Stainless Steel
PREPARE SHOP
DRAWINGS FOR AREAS
OF WORK
SUBMIT TO
CLIENT/CONSULTANT
FOR APPROVAL
ORDER MATERIALS TO
BE INSTALLED
MATERIALS
INSPECTION BY
RE/COW
INSTALLED PIPING PRESSURE TEST PIPING
TEST INSPECTION BY
RE/COW
TEST FAIL
TEST PASS REPEAT TEST
CLOSE INSPECTION BY
RE/COW
METHOD STATEMENT – COLD WATER PIPING WORK
pg. 7
7.0 QUALITY CONTROL PROCEDURES
7.1 Verification Document
 Request For Inspection Form (RFI)
 Installation Checklist
 Test Form
8.0 SAFETY
Prior to work commencing all plant and equipment to be used will be inspected and
confirmed for used by contractor's safety representative.
Tool Box meeting shall be undertaken on a minimum weekly basis.

More Related Content

What's hot

ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil worksMuhammad Shahid
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Minh Bui Si
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouringBharatha Rathnayke
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03vppradeepkumar
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
Scaffolding awareness presentation
Scaffolding awareness presentationScaffolding awareness presentation
Scaffolding awareness presentationbobrobbo
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and ControlsAbbas Tahir
 
Method Statement of precast pilie and its risk assessment
Method Statement of precast pilie and its risk assessmentMethod Statement of precast pilie and its risk assessment
Method Statement of precast pilie and its risk assessmentjihanshagor
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
Post tensioning company method statement | shivforce.in
Post tensioning company   method statement | shivforce.in Post tensioning company   method statement | shivforce.in
Post tensioning company method statement | shivforce.in Sathish Kumar
 
Various Load Cases In Pipe Stress Analysis
Various Load Cases In Pipe Stress AnalysisVarious Load Cases In Pipe Stress Analysis
Various Load Cases In Pipe Stress Analysisjudithmorrison01
 
Pipeline stress analysis with ceaser ii
Pipeline stress analysis with ceaser iiPipeline stress analysis with ceaser ii
Pipeline stress analysis with ceaser iiAbhishek Srivastav
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideChukwuma Anyanwu, PMP, CCP
 

What's hot (20)

ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Scaffolding2. CO3.ppt
Scaffolding2. CO3.pptScaffolding2. CO3.ppt
Scaffolding2. CO3.ppt
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Scaffolding awareness presentation
Scaffolding awareness presentationScaffolding awareness presentation
Scaffolding awareness presentation
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and Controls
 
Method Statement of precast pilie and its risk assessment
Method Statement of precast pilie and its risk assessmentMethod Statement of precast pilie and its risk assessment
Method Statement of precast pilie and its risk assessment
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Post tensioning company method statement | shivforce.in
Post tensioning company   method statement | shivforce.in Post tensioning company   method statement | shivforce.in
Post tensioning company method statement | shivforce.in
 
Various Load Cases In Pipe Stress Analysis
Various Load Cases In Pipe Stress AnalysisVarious Load Cases In Pipe Stress Analysis
Various Load Cases In Pipe Stress Analysis
 
Pipeline stress analysis with ceaser ii
Pipeline stress analysis with ceaser iiPipeline stress analysis with ceaser ii
Pipeline stress analysis with ceaser ii
 
Cross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guideCross country pipeline construction steps visual guide
Cross country pipeline construction steps visual guide
 
Column & beam
Column & beamColumn & beam
Column & beam
 

Similar to Stainless Steel Threaded&Welding Joint.docx

Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxharmanpnrgroup
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.pptMuhammed Sulfeek
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questionsKarthik Banari
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsThang Do Minh
 
Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1dhiaa ebadi
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Shop fabrication of structural steel
Shop fabrication of structural steelShop fabrication of structural steel
Shop fabrication of structural steelAhmed Allam
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Gensol Engineering Limited
 
244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdfmoumo1
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 

Similar to Stainless Steel Threaded&Welding Joint.docx (20)

Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptx
 
Mechanical
Mechanical Mechanical
Mechanical
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questions
 
Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Michael CV.
Michael CV.Michael CV.
Michael CV.
 
10334
1033410334
10334
 
Shop fabrication of structural steel
Shop fabrication of structural steelShop fabrication of structural steel
Shop fabrication of structural steel
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Mohammed Asif Hassan-cv
Mohammed Asif Hassan-cvMohammed Asif Hassan-cv
Mohammed Asif Hassan-cv
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf244737957-Piping-Question-and-Answer.pdf
244737957-Piping-Question-and-Answer.pdf
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Telescopic poles nea
Telescopic poles  neaTelescopic poles  nea
Telescopic poles nea
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Stainless Steel Threaded&Welding Joint.docx

  • 1. METHOD STATEMENT – COLD WATER PIPING WORK pg. 1 1.0 PURPOSE The purpose of this Method Statement is to establish a uniform procedure for: - a) Welding joint of stainless-steel pipe and fittings (Sch. 10) b) Threaded joint of stainless-steel pipe and fittings (Sch. 40) It aims to ensure that the work force involved to perform the operations have a complete understanding of the operating standards and safety practices associated with the use of machinery/equipment /tools. 2.0 SCOPE The scope of works shall not be limited to piping works only. It shall include supply, deliver, installation, testing, commissioning and defect liability maintenance for the entire Cold Water plumbing system. 3.0 HANDLING AND STORAGE OF MATERIALS Upon delivery at site, all pipes will be hoisted carefully and stored in a dry suitably designated area. Materials shall preferably be place on timber at both ends, stacked neatly. Fittings will be stored in a dry store. 4.0 INSPECTION OF MATERIALS Inspection is then carried out to ensure that materials delivered is new and without any damage. The materials will not be used for installations unless it has been inspected and verified for conformance to specifications. Only pipe that conforming to SPAN standard shall be approved and accepted. Inspection and verification will be carried out upon Supplier Delivery Order and documented in Material Inspection Checklist form This inspection will be carried out by Site Supervisors. The acceptance of material delivered shall be at the discretion of the consultant representatives with verification by his immediate superior, resident engineer. 5.0 SITE PLANNING AND PREPARATION a. All relevant documents shall be approved for execution. b. All the personnel involved in the job should attend the safety training. c. Ensure all workers are equipped with PPE (i.e., hard hat with chin strap, goggles, safety shoes, gloves, safety harness, etc.) relevant to the nature of work to be carried out. d. Determine manpower and delegation of task. e. Fully barricade the work area and restrict entry to authorized personnel only.
  • 2. METHOD STATEMENT – COLD WATER PIPING WORK pg. 2 f. Deliver to the site the required materials to be installed. g. All required machineries, tools and equipment shall be placed into the designated area. h. Prior to installation of the steel frames and bracket plates, the location should be cleaned and must be free from any obstructions. i. Prior to transferring of the Evaporator from yard to outside of building, the road must be checked and free from obstructions for the truck and mobile crane to have easy access. j. Prior to shifting of the evaporator from outside to inside of the building, ensure that the steel bed frame and railing are properly fixed, aligned and levelled. k. All qualified and authorized personnel shall be notified when commencing works. l. For night work, ensure that lightings are adequate. m. A proper line of communication throughout the job must be detailed. n. Anticipated problems shall be discussed and resolved immediately. o. Material catalogue and / or sample to be submitted early for approval prior to actual construction to avoid delay to physical construction. p. Daily checklist and measurement sheet for recording purpose and shall be established to provide information for claim and producing as-built drawing level. 6.0 ACTUAL WORK METHODOLOGY 6.1 WORK METHOD FOR WELDING JOINT – SCHEDULE 10, ASTM A312 TYPE 304 6.1.1 Materials  Stainless Steel Pipe and Fittings (Schedule 10) - 65mm till 150mm sizes 6.1.2 Tools & Machinery i) Magnetic drill machine, Drill machine, wrench, hammer, pliers, etc. ii) Level bar or Level hose iii) Mobile Crane or Boom Truck iv) Chain blocks, Slings, shackles, belts, chains, etc. v) Welding Machine, Electrodes and welding units vi) Measuring tape, pipe fitter’s wrap-around, marker pen, cleaning rags vii) Cutting/Grinding machine with carborundum cutting & sanding/grinding disc viii)Pie tape, Curve-o-mark, Angle Grinder, Emery disc ix) Electrical extension wires x) Level bar or Level hose
  • 3. METHOD STATEMENT – COLD WATER PIPING WORK pg. 3 6.1.3 Installation Procedure a) All the welding shall be as per the drawing or standard. b) Welding must be carried out by qualified and certified welder as per the below welding preparation and procedures: - i) Cutting and bevelling  Mark off the dimension of each pipe and fittings as per the approved drawing.  Proceed with cutting of Stainless-steel pipes and fittings, which shall be done by using cutting disc.  Once the pipes and fittings are cut, commence with the edge preparation.  the edge cleaning and bevelling shall be done using abrasive grinding disc/bevelling machines.  Line number, Spool Numbers and Joint Numbers are to be clearly identified and marked on the spool with the welder identification for each joint. ii) Purging arrangement  Before fit-up, arrange sponge/foam along with argon, gas, hoses from both sides of the joint.  Before start of welding open the purging gas in the joint, so we can get back purging gas during the welding. iii) Fit-Up and Tack Welding  Once the surface is bevelled and cleaned proceed for tack welding  Welders should put on proper safety equipment prior for welding.  Fit-up assembly shall be carried out by using locally prepared couplers. All the required pipe holdings work benches, assembling brackets’’ bolts etc. Would be made in house to suit the pipe size.  For Butt welds uniform root gap of 1.5-3mm shall be maintained.  Before commences the welding ensure that spool is aligned properly.  Once required levelness and alignment achieved proceed for welding.
  • 4. METHOD STATEMENT – COLD WATER PIPING WORK pg. 4  The pipe shall be tack welded in three equidistant positions, Tack welding shall as per approved drawing and standard by a qualified welder. iv) Welding  Ensure that edges are free from dust, rust, oil, grease, paint etc.  Welding shall be done as per approved drawing and by complying with the particular piping standard. Preheating and welding consumable shall be checked before starting of welding.  Each welding layer shall be cleaned before starting to weld next layer. The cleaned area shall be free from slags. Any visual defects like cracks, pores, spatters weld shall be removed by grinding before the next layer is applied. The ends of weld layer shall be removed by grinding in tack points of each weld. Any possible welds excess layer will be removed by grinding.  For the fabrication & welding of stainless-steel pipes and fittings only stainless-steel tools and consumables (Wire brush chipping, Hammer, and Abrasive disc) shall be used.  Appearance of finished weld shall be as even as possible and free from spatter, under cutting, cracks, excess reinforcement etc. 6.2 WORK METHOD FOR THREADED JOINT – SCHEDULE 40, ASTM A312 TYPE 304 6.2.1 Material Stainless Steel Pipe and Fittings (Schedule 10) - 20mm till 50mm sizes 6.2.2 Tools & Machinery i) Measuring tape, marker pen, cleaning rags and twine. ii) Scaffold iii) Threading machine iv) Fibre cutter v) Drill Machine
  • 5. METHOD STATEMENT – COLD WATER PIPING WORK pg. 5 6.2.3 Installation Procedure a) Check construction drawings and establish area or works that pipe to be installed. b) Determine the pipe route and measure pipe length to be cut. c) Employing the fibre cutting machine, cut required lengths of stainless- steel pipe necessary at the work shop. d) Set the threading machine die to the correct size of pipe to be threaded. e) Insert pipe into threading machine and thread with at least two passed. The first to obtain the basic pitch thread (BS 21) and the polish off the threads. These are termed the rough cut and the fine cut. Two passes are also necessary so as not to damage the high tensile die. f) Before removing the complete pipe, the completed threads need to be checked by screwing in a Stainless-Steel pipe socket of the same diameter into the threads. If the threaded pipe cannot penetrate at least four (4) revolutions into the socket it means that the threads are not good and needs to be redo. g) Upon completing the threading of all the pipes, apply sealing (Teflon) tape on to all the threaded joints. This should be done in a clock wise rotation with the roll of tape moving away from you. h) Sockets are next fixed onto one end of each completed pipe. This is achieved either by locking the pipe on a vice and wrenching tight the socket or by employing two wrenches in opposing directions. i) Deliver all the above completed pipes with sockets to the site where they are to be installed. j) Mark the start and end points of the pipe to be installed on the soft fit of the slab for horizontal installation or wall for vertical installation. k) Drill both points marked using the hand drill, insert drop-in anchor and set them. l) Screw in two length of stud bolts into the drop-in anchor and pull a twine from the first stud to the second stud. m) From the twine, mark the intermediate hangers that are required between the start and end points. n) Repeat procedures (10) and (11) to complete the intermediate pipe supports. o) The pipes are now hanged onto the supports, jointed and tightened together using pipe wrenches.
  • 6. METHOD STATEMENT – COLD WATER PIPING WORK pg. 6 p) When a significant section of pipes is completed or before it is to be installed in a plumbing shaft, the pipes have to be tested by means of hydrostatic pressure tests. 6.3 Work Flow Chart Installation of Stainless Steel PREPARE SHOP DRAWINGS FOR AREAS OF WORK SUBMIT TO CLIENT/CONSULTANT FOR APPROVAL ORDER MATERIALS TO BE INSTALLED MATERIALS INSPECTION BY RE/COW INSTALLED PIPING PRESSURE TEST PIPING TEST INSPECTION BY RE/COW TEST FAIL TEST PASS REPEAT TEST CLOSE INSPECTION BY RE/COW
  • 7. METHOD STATEMENT – COLD WATER PIPING WORK pg. 7 7.0 QUALITY CONTROL PROCEDURES 7.1 Verification Document  Request For Inspection Form (RFI)  Installation Checklist  Test Form 8.0 SAFETY Prior to work commencing all plant and equipment to be used will be inspected and confirmed for used by contractor's safety representative. Tool Box meeting shall be undertaken on a minimum weekly basis.