Meter Farms
AEIC Measurement
Technologies Working Group
Prepared by Tom Lawton, TESCO
The Eastern Specialty Company
EEI
Tuesday, October 3, 2017
1:00 p.m.
Slide 2
• Define a Meter Farm
• Discuss how to size and format
a meter farm
– Discuss what features should be
included in your meter farm
• Discuss Uses of a Meter Farm
– Before deployment
– During deployment
– After deployment
– As a new way to do old tasks in a Post
AMI/AMR world
Panel Session Overview
Slide 3
• A Meter Farm is a representation of
your meter population in the field
• The Meter Farm is designed to be a tool
to measure base line performance of
your meters
• Meter farms are typically located
outside so meters are exposed to the
same temperatures, sun and elements
as your meter population.
• Meter Farms should include a
simulation of the entire communication
network back to the head end
What is a Meter Farm?
Slide 4
How big? How many? What forms?
Shop Testing
A Meter Farm needs to have a statistically significant representation of your meter
population in the field. This means a minimum of 30 meters regardless of
population. Typical farms have 50 to 100 meters for populations up to 50,000
meters and several thousand meters for populations over two million.
The breakdown of forms should be roughly representative of the breakdown of
meters within your population. 2S meters will typically have 85 to 90% of the spots
in a meter farm. Every polyphase meter is represented with a minimum of two to
three sockets if possible.
Slide 5
What features to build-in?
Shop Testing
Meter Farms will be used as a population
management tool as well as a diagnostic
tool and a certification/validation tool. To
accomplish all of these things various
features should be built in;
•Representation of all forms used in the field in
any volume in the meter farm;
•Ability to add load to certain meters
•Communication protocols so that firmware and
software updates to meters, collectors and the
head end system can all be tested and verified
Slide 6
Using a Meter Farm prior to deployment
Shop Testing
Prior to deployment you are still in Meter
Certification mode. Much of this work is done on
meter qualification boards, programming
stations and meter test boards.
Typically once the work in the meter lab is
completed utilities will jump directly to a pilot
program for a limited number of installations in
the field. The weakness with this is that the pilot
program is not dynamic.
The assumption had been made that the meters
used in full deployment would be static. What
was tested during the initial portion of the Meter
Certification phase would be representative of
what was eventually deployed.
Slide 7
Meter Farm’s prior to deployment (cont)
Shop Testing
Inaccurate assumption. Meters and
firmware change. Programs to be used in
the field change. Communication protocols
and information passed change. A meter
farm allows you to perform a mini-pilot and
to control and modify this pilot multiple
times during meter certification.
The meters in this meter farm also allow for
longer term observation of the new meters
performance in the field. Any anomalies
reported from the field during your pilot can
be more readily identified and diagnosed.
This is a precursor to some of the ways in
which you will use the meter farm after
deployment.
Slide 8
Meter Farm’s during deployment
Shop Testing
During deployment the meter services department is trying to manage
competing demands.
You are managing the largest metering related project in the company’s
history and you are also trying to maintain the integrity of the daily reading and
billing of every customer’s account.
Everything has to remain perfect while being completely changed.
Slide 9
Meter Farm’s during deployment
Shop Testing
The meter farm gives you a microcosm of
your population and as a result can be
used as a baseline to ensure the longer
term stability of the meters being delivered
and to ensure that they are not changing
over the course of the deployment.
Functional testing and accuracy testing
allow you to do this as well. The meter
farm allows longer term performance
comparison between delivered meters over
the course of the deployment.
Slide 10
Meter Farm’s after deployment
Shop Testing
This is where meter farms are the most valuable. The meter farm becomes your
most valuable tool in managing your AMI population.
Prior to a full scale AMI or AMR roll out you had a variety of meter types in the field
with meter vintages that often ranged over a fifty year time period and sometimes
longer.
To assess the performance of these meters and to look for potential systemic issues
within a particular family of meters statistic methods were used.
.
Slide 11
ANSI C12.1-2013 Section 5
Shop Testing
ANSI C12.1 Section 5 is dedicated to methods for statistically sampling your
meter population to determine as far in advance issues within a meter
population.
This methodology is typically used with the larger meter populations (e.g. self
contained) as they have the most statistically relevant populations and the ones
best managed in this way.
But with a single meter type this becomes problematic. A systemic issue within
a population would be found far too late. Too many false positives would be
found if trying to use this on the front end and too many other issues missed.
And metering issues are now just as likely to be a communication issue and not
a meter issue.
Slide 12
Meter Farms as base line performance
indicators
Shop Testing
How well is a meter type performing in the
field? Walk through the meter farm. That
is a pretty good initial indicator.
•Display issues? – You should see them.
•Power recovery issues? You can check
for them.
•Component failures? You should see
them.
In a perfect world you should see issues
before the field reports them or in the same
time frame.
Slide 13
Meter Farms as diagnostic tools
Shop Testing
Metering issues in the field are a constant
part of our lives. Most are readily dealt
with. Some are not.
Issues traditionally could be identified as
either a meter issue or an installation issue.
Now the issue can be a meter issue, an
installation issue, a communication issue
(which can be in the meter, can be site
specific or be further up the communication
chain), and even a customer equipment
issue.
And yet most utilities still send a meter tech
out to change a meter as the first line of
defense.
Slide 14
Meter Farms as diagnostic tools (cont)
Shop Testing
When a meter is brought back to the shop
a series of diagnostics can and are run in
the meter lab.
Programs are checked, alarm settings,
functional tests are performed, possibly
accuracy tests are performed. If that meter
passed these initial checks they might be
released back to the field. And that meter
might come back a second or even a third
time.
Now this meter can be put out onto the
meter farm and run against other meters of
a similar age or older and checked for any
anomaly over time. Acceptance protocols
can be run and performance checked one
meter against the others.
Slide 15
Meter Farms as acceptance testing
environments
Shop Testing
One against many. Newer against older. There is one thing for certain in
metering today. The meters we are purchasing today are not the same as the
meters we purchased last year. The meters we will purchase next year will not
be the same as the meters we purchase today.
•The components within the meter may change
•The firmware within the meter or within the collectors will change.
•We may elect to change settings.
•The software in the head end, the collectors or the meters may change
Slide 16
Meter Farms as acceptance testing
environments (cont)
Shop Testing
Develop protocols. Check for outage
management issues, surges and sags, load and
no load scenarios. Use what you learned during
your certification and acceptance testing (and
continue to learn) and incorporate this into your
protocols.
Put the meters through the ringer for the first
several days and longer.
What are we looking for? Nothing. Nothing
different. Different is bad. A difference in display
– bad. A difference in readings – much worse.
We want the new meters to perform, respond
and look exactly like the base line meters.
Slide 17
Meter Farms as acceptance testing
environments (cont)
Shop Testing
Use these same protocols when testing over the air upgrades or new
communication protocols of any sort.
Anything new – check before deploying to the field. This is your test
environment.
Slide 18
Meter Farms as Development tools
Meter farms can also be adapted
and used to test new technology.
This can range from new collectors
for a mesh system to new metering
applications that are brand new to
your utility.
Slide 19
• Define a Meter Farm
• Discuss how to size and format
a meter farm
– Discuss what features should be
included in your meter farm
• Discuss Uses of a Meter Farm
– Before deployment
– During deployment
– After deployment
– As a new way to do old tasks in a Post
AMI/AMR world
Summary
Slide 20
Gas Meter Farms
Slide 21
Gas Meter Farms
Slide 22
Meter Farms
Slide 23
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
1-800-762-8211
www.tesco-advent.com

More Related Content

What's hot

What's hot (14)

Meter Asset Tracking and the Power of Analytics in an AMI System
Meter Asset Tracking and the Power of Analytics in an AMI SystemMeter Asset Tracking and the Power of Analytics in an AMI System
Meter Asset Tracking and the Power of Analytics in an AMI System
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Managing Vendor Issues on AMI Design
Managing Vendor Issues on AMI DesignManaging Vendor Issues on AMI Design
Managing Vendor Issues on AMI Design
 
Tesco's AMI Specific Products and Services
Tesco's AMI Specific Products and ServicesTesco's AMI Specific Products and Services
Tesco's AMI Specific Products and Services
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
New Challenges for the Meter Shop
New Challenges for the Meter ShopNew Challenges for the Meter Shop
New Challenges for the Meter Shop
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni'sMeter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's and Muni's
 
Meter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni'sMeter Asset Management at Coop's, IOU's, & Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
 
Asset Tracking Systems for Meter Services
Asset Tracking Systems for Meter ServicesAsset Tracking Systems for Meter Services
Asset Tracking Systems for Meter Services
 
SEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the FutureSEMA 2016 - Managing Meter Shops of the Future
SEMA 2016 - Managing Meter Shops of the Future
 
Meter Shops of the Future
Meter Shops of the FutureMeter Shops of the Future
Meter Shops of the Future
 
Meter Operations In a Post AMI World
Meter Operations In a Post AMI WorldMeter Operations In a Post AMI World
Meter Operations In a Post AMI World
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 

Similar to Meter Farms: AEIC Measurement Technologies Working Group

Similar to Meter Farms: AEIC Measurement Technologies Working Group (20)

Fundamentals of AMI Testing
Fundamentals of AMI TestingFundamentals of AMI Testing
Fundamentals of AMI Testing
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and AfterMeter Testing and AMI Deployment - Before, During and After
Meter Testing and AMI Deployment - Before, During and After
 
New Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO SolutionsNew Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO Solutions
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
 
AMI Technology Overview
AMI Technology OverviewAMI Technology Overview
AMI Technology Overview
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
AMI Case Studies
AMI Case StudiesAMI Case Studies
AMI Case Studies
 
Advanced Metering Infrastructure (AMI) Overview
Advanced Metering Infrastructure (AMI) OverviewAdvanced Metering Infrastructure (AMI) Overview
Advanced Metering Infrastructure (AMI) Overview
 
ECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the FutureECNC 2016 - Managing Meter Shops of the Future
ECNC 2016 - Managing Meter Shops of the Future
 
AMI Case Studies
AMI Case StudiesAMI Case Studies
AMI Case Studies
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
Meter Operations in a Post AMI World
Meter Operations in a Post AMI WorldMeter Operations in a Post AMI World
Meter Operations in a Post AMI World
 
AMI Lessons Learned
AMI Lessons LearnedAMI Lessons Learned
AMI Lessons Learned
 
Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
 

Recently uploaded

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Recently uploaded (20)

WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 

Meter Farms: AEIC Measurement Technologies Working Group

  • 1. Slide 110/02/2012 Slide 1 Meter Farms AEIC Measurement Technologies Working Group Prepared by Tom Lawton, TESCO The Eastern Specialty Company EEI Tuesday, October 3, 2017 1:00 p.m.
  • 2. Slide 2 • Define a Meter Farm • Discuss how to size and format a meter farm – Discuss what features should be included in your meter farm • Discuss Uses of a Meter Farm – Before deployment – During deployment – After deployment – As a new way to do old tasks in a Post AMI/AMR world Panel Session Overview
  • 3. Slide 3 • A Meter Farm is a representation of your meter population in the field • The Meter Farm is designed to be a tool to measure base line performance of your meters • Meter farms are typically located outside so meters are exposed to the same temperatures, sun and elements as your meter population. • Meter Farms should include a simulation of the entire communication network back to the head end What is a Meter Farm?
  • 4. Slide 4 How big? How many? What forms? Shop Testing A Meter Farm needs to have a statistically significant representation of your meter population in the field. This means a minimum of 30 meters regardless of population. Typical farms have 50 to 100 meters for populations up to 50,000 meters and several thousand meters for populations over two million. The breakdown of forms should be roughly representative of the breakdown of meters within your population. 2S meters will typically have 85 to 90% of the spots in a meter farm. Every polyphase meter is represented with a minimum of two to three sockets if possible.
  • 5. Slide 5 What features to build-in? Shop Testing Meter Farms will be used as a population management tool as well as a diagnostic tool and a certification/validation tool. To accomplish all of these things various features should be built in; •Representation of all forms used in the field in any volume in the meter farm; •Ability to add load to certain meters •Communication protocols so that firmware and software updates to meters, collectors and the head end system can all be tested and verified
  • 6. Slide 6 Using a Meter Farm prior to deployment Shop Testing Prior to deployment you are still in Meter Certification mode. Much of this work is done on meter qualification boards, programming stations and meter test boards. Typically once the work in the meter lab is completed utilities will jump directly to a pilot program for a limited number of installations in the field. The weakness with this is that the pilot program is not dynamic. The assumption had been made that the meters used in full deployment would be static. What was tested during the initial portion of the Meter Certification phase would be representative of what was eventually deployed.
  • 7. Slide 7 Meter Farm’s prior to deployment (cont) Shop Testing Inaccurate assumption. Meters and firmware change. Programs to be used in the field change. Communication protocols and information passed change. A meter farm allows you to perform a mini-pilot and to control and modify this pilot multiple times during meter certification. The meters in this meter farm also allow for longer term observation of the new meters performance in the field. Any anomalies reported from the field during your pilot can be more readily identified and diagnosed. This is a precursor to some of the ways in which you will use the meter farm after deployment.
  • 8. Slide 8 Meter Farm’s during deployment Shop Testing During deployment the meter services department is trying to manage competing demands. You are managing the largest metering related project in the company’s history and you are also trying to maintain the integrity of the daily reading and billing of every customer’s account. Everything has to remain perfect while being completely changed.
  • 9. Slide 9 Meter Farm’s during deployment Shop Testing The meter farm gives you a microcosm of your population and as a result can be used as a baseline to ensure the longer term stability of the meters being delivered and to ensure that they are not changing over the course of the deployment. Functional testing and accuracy testing allow you to do this as well. The meter farm allows longer term performance comparison between delivered meters over the course of the deployment.
  • 10. Slide 10 Meter Farm’s after deployment Shop Testing This is where meter farms are the most valuable. The meter farm becomes your most valuable tool in managing your AMI population. Prior to a full scale AMI or AMR roll out you had a variety of meter types in the field with meter vintages that often ranged over a fifty year time period and sometimes longer. To assess the performance of these meters and to look for potential systemic issues within a particular family of meters statistic methods were used. .
  • 11. Slide 11 ANSI C12.1-2013 Section 5 Shop Testing ANSI C12.1 Section 5 is dedicated to methods for statistically sampling your meter population to determine as far in advance issues within a meter population. This methodology is typically used with the larger meter populations (e.g. self contained) as they have the most statistically relevant populations and the ones best managed in this way. But with a single meter type this becomes problematic. A systemic issue within a population would be found far too late. Too many false positives would be found if trying to use this on the front end and too many other issues missed. And metering issues are now just as likely to be a communication issue and not a meter issue.
  • 12. Slide 12 Meter Farms as base line performance indicators Shop Testing How well is a meter type performing in the field? Walk through the meter farm. That is a pretty good initial indicator. •Display issues? – You should see them. •Power recovery issues? You can check for them. •Component failures? You should see them. In a perfect world you should see issues before the field reports them or in the same time frame.
  • 13. Slide 13 Meter Farms as diagnostic tools Shop Testing Metering issues in the field are a constant part of our lives. Most are readily dealt with. Some are not. Issues traditionally could be identified as either a meter issue or an installation issue. Now the issue can be a meter issue, an installation issue, a communication issue (which can be in the meter, can be site specific or be further up the communication chain), and even a customer equipment issue. And yet most utilities still send a meter tech out to change a meter as the first line of defense.
  • 14. Slide 14 Meter Farms as diagnostic tools (cont) Shop Testing When a meter is brought back to the shop a series of diagnostics can and are run in the meter lab. Programs are checked, alarm settings, functional tests are performed, possibly accuracy tests are performed. If that meter passed these initial checks they might be released back to the field. And that meter might come back a second or even a third time. Now this meter can be put out onto the meter farm and run against other meters of a similar age or older and checked for any anomaly over time. Acceptance protocols can be run and performance checked one meter against the others.
  • 15. Slide 15 Meter Farms as acceptance testing environments Shop Testing One against many. Newer against older. There is one thing for certain in metering today. The meters we are purchasing today are not the same as the meters we purchased last year. The meters we will purchase next year will not be the same as the meters we purchase today. •The components within the meter may change •The firmware within the meter or within the collectors will change. •We may elect to change settings. •The software in the head end, the collectors or the meters may change
  • 16. Slide 16 Meter Farms as acceptance testing environments (cont) Shop Testing Develop protocols. Check for outage management issues, surges and sags, load and no load scenarios. Use what you learned during your certification and acceptance testing (and continue to learn) and incorporate this into your protocols. Put the meters through the ringer for the first several days and longer. What are we looking for? Nothing. Nothing different. Different is bad. A difference in display – bad. A difference in readings – much worse. We want the new meters to perform, respond and look exactly like the base line meters.
  • 17. Slide 17 Meter Farms as acceptance testing environments (cont) Shop Testing Use these same protocols when testing over the air upgrades or new communication protocols of any sort. Anything new – check before deploying to the field. This is your test environment.
  • 18. Slide 18 Meter Farms as Development tools Meter farms can also be adapted and used to test new technology. This can range from new collectors for a mesh system to new metering applications that are brand new to your utility.
  • 19. Slide 19 • Define a Meter Farm • Discuss how to size and format a meter farm – Discuss what features should be included in your meter farm • Discuss Uses of a Meter Farm – Before deployment – During deployment – After deployment – As a new way to do old tasks in a Post AMI/AMR world Summary
  • 23. Slide 23 Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 1-800-762-8211 www.tesco-advent.com