SlideShare a Scribd company logo
1 of 10
PROJECT PLANNING
      AND
  EVALUATION
PERT (Program Evaluation & Review Technique)

                            PERT was evolved by navy engineers James E. Casie &
Margan E. Walter, in charge of special projects of United States Navy. It was
formally applied to planning & control of missile program, in October 1958.

                   PERT deals with the problem of uncertain activities times by the
application of statistical analysis to determination of estimated time for each
activity concerning the project. In order to arrive at most reliable estimate of time,
“Three Time Estimates”.

   1. The Optimistic Time – It is the shortest time possible if everything goes
      perfectly with no complications, the chance of this optimum actually
      occurring might be in 1 in 100.
   2. The Pessimistic Time – It is the longest time considerable, it includes time
      for unusual delay and thus the change of its happening might be in 1 in 100.
   3. The Most Likely Time – It would be the best estimate of what normally
      would occur.



METHODOLOGY / STEPS OF PERT



           The steps involved in PERT are:-



   A. Preparing the network: - First of all a list of activities that constitute the
      project is prepared. The predecessor and successor activities are
      determined. A network diagram is prepared on the basis of dependence
      between different activities and events. This is project planning phase of
      PERT. Events are numbered in ascending order from left to right.
   B. Network Analysis: - Estimates of time required to perform each activities
      are made.
C. Scheduling: - Expected time for each activity is computed from the three
      time estimates. Earliest and latest start time and finished time for each
      activity are determined. Then the critical path through the network is
      determined. The slack times associated with the non critical activities are
      also computed.
   D. Time-Cost-Trade off: - If management wants to reduce the project
      completion time, crashing or compressing the project is done. The cost of
      reducing project completion time is computed.
   E. Resources Allocation: - The feasibility of each schedule is checked with
      respect to manpower and equipment requirements.
   F. Project Control: - The project is controlled by checking programs against the
      schedule, assigning and scheduling manpower and equipment and
      analysing the effects of delay. Whenever major changes are made in the
      schedule, the network is revised accordingly, and a new schedule is
      prepared. Thus, monitoring of program may require periodic updating of
      project and rescheduling to ensure completion of the project in time.




      Latest Finished Time (LFT)

                It is calculated by moving backward i.e. from last event to first
event of the network diagram.



      Latest Start Time (LST)

               It is the latest possible time by which an activity can start.



                        LST = LFT – Duration of that activity
Earliest Start Time (EST)

                It is the earliest possible time by which an activity can start.



  Earliest Finished Time (EFT)

              It is the earliest time of an activity.




     FLOAT / SLACK

          It means spare time, a margin of extra time over and above its duration
which a non-critical activity can consume without delaying the project.

         Float is the difference between the time available for completing an
activity and the time necessary to complete the same.




                                  Total Float = LST – EST

                                           OR

                                  Total Float = LFT - EFT




       Free Float  If all the non critical activities start as early as possible the
surplus time is the free flow. If an activity is delayed by the free flow period, the
succeeding activity will not be delayed.
Free Float = EST of tail event

                                          – EST of head event

                                          – Activity duration




Independent Float  The use of independent float of an activity does not change
the float in other activities.



                           Independent Float = EST of tail event

                                            - LFT of head event

                                             - Activity duration




 (*Note: - Independent float, if it turns out to be negative, it is taken as zero.)
NUMERICAL



Activity Optimistic Time   Most Expected Time   Pessimistic Time   Expected   Variance
         (to)              (tm)                 (tp)               Time
1-2      4                 8                    12                 8          1.78
2-3      1                 4                    7                  4          1.00
2-4      8                 12                   16                 12         1.78
3-5      3                 5                    7                  5          0.44
4-5      0                 0                    0                  0          0.00
4-6      3                 6                    9                  6          1.00
5-7      3                 6                    9                  6          1.00
5-8      4                 6                    8                  6          0.44
7-9      4                 8                    12                 8          1.78
8-9      2                 5                    8                  5          1.00
9-10     4                 10                   16                 10         4.00
6-10     4                 6                    8                  6          0.44




Expected Time=[(to+4tm+tp)/6]2

Varience=[(tp-to)%6]2

Q.Present the activity in the form of a PERT network and determine-

a.Critical path

b.Earliest and latest expected time

c.Probability of computing the project within schedule completion of 48 days.
SOLUTION

A.(i).




                                          3           5           4        8
                              1

                                                  2
                              5                                           16


                                                                                        2
                                  1
    1


    1         4
    1
                              2                           7           4            9
                                              0

0                         4
                          0
                                                      15                       19
                                                                               0




                          0                                                    0




                                                                                        4
                                  8




                              4                               6                    10
                                              3                       4


                          1                               15                   23
                          2




Critical Path=(1-2-4-5-7-9-10)
(ii).




                         3
                                      5         5         6            8


                    12           15       20        20            26            29




                                                     6                          5
                    4


                                      0

                8            2
    1                                           7                          9


0        0           8            8        26        26           34            34




                    2                                                                10




                             4                  6             6            10
                                      6



                                          26        38            44            44
                    20           20
Critical Path=(1-2-4-5-7-9-10)

B. The earliest expected time [E(U1)]=0

E (U2)=0+8=8

E (U3)=8+4=12

E (U4)=12+8=20

E (U5)=(12+5,20+0)=20

E (U6)=20+6=26

E (U7)=26

E (U8)=20+6=26

E (U9)=34

E (U10)=34

Latest expected time are-

E(L10)=44

E(L9)=34

E(L8)=29

E(L7)=20

E(L6)=38

E(L5)=20

E(L4)=20

E(L3)=15

E(L2)=8
E(L1)=0



C. Expected Project Completion time

8+12+0+6+8=44 days

Project variance=(∂T)2 =1.78+1.78+0+1+1.78+4=10.34

Varience=∂T=3.216

If due date of completion of the project is 48 days then=(48-44)/3.216=1.24

From the Standard normal table, probability of meeting the due date is 0.3925

More Related Content

Similar to Project

DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfssuserc9c6261
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfssuserc9c6261
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfssuserc9c6261
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfssuserc9c6261
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdfssuserc9c6261
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfssuserc9c6261
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdfssuserc9c6261
 
Example of Simple Network –.pdf
Example of Simple Network –.pdfExample of Simple Network –.pdf
Example of Simple Network –.pdfssuserc9c6261
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdfssuserc9c6261
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfssuserc9c6261
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfssuserc9c6261
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdfssuserc9c6261
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdfssuserc9c6261
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdfssuserc9c6261
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdfssuserc9c6261
 
Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdfssuserc9c6261
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Attention flow by tagging prediction
Attention flow by tagging predictionAttention flow by tagging prediction
Attention flow by tagging predictionYONG ZHENG
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 

Similar to Project (20)

Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdf
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdf
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdf
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdf
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdf
 
Example of Simple Network –.pdf
Example of Simple Network –.pdfExample of Simple Network –.pdf
Example of Simple Network –.pdf
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdf
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdf
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdf
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdf
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdf
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdf
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdf
 
Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdf
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Attention flow by tagging prediction
Attention flow by tagging predictionAttention flow by tagging prediction
Attention flow by tagging prediction
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 

Recently uploaded

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseribangash
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Recently uploaded (20)

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Project

  • 1. PROJECT PLANNING AND EVALUATION
  • 2. PERT (Program Evaluation & Review Technique) PERT was evolved by navy engineers James E. Casie & Margan E. Walter, in charge of special projects of United States Navy. It was formally applied to planning & control of missile program, in October 1958. PERT deals with the problem of uncertain activities times by the application of statistical analysis to determination of estimated time for each activity concerning the project. In order to arrive at most reliable estimate of time, “Three Time Estimates”. 1. The Optimistic Time – It is the shortest time possible if everything goes perfectly with no complications, the chance of this optimum actually occurring might be in 1 in 100. 2. The Pessimistic Time – It is the longest time considerable, it includes time for unusual delay and thus the change of its happening might be in 1 in 100. 3. The Most Likely Time – It would be the best estimate of what normally would occur. METHODOLOGY / STEPS OF PERT The steps involved in PERT are:- A. Preparing the network: - First of all a list of activities that constitute the project is prepared. The predecessor and successor activities are determined. A network diagram is prepared on the basis of dependence between different activities and events. This is project planning phase of PERT. Events are numbered in ascending order from left to right. B. Network Analysis: - Estimates of time required to perform each activities are made.
  • 3. C. Scheduling: - Expected time for each activity is computed from the three time estimates. Earliest and latest start time and finished time for each activity are determined. Then the critical path through the network is determined. The slack times associated with the non critical activities are also computed. D. Time-Cost-Trade off: - If management wants to reduce the project completion time, crashing or compressing the project is done. The cost of reducing project completion time is computed. E. Resources Allocation: - The feasibility of each schedule is checked with respect to manpower and equipment requirements. F. Project Control: - The project is controlled by checking programs against the schedule, assigning and scheduling manpower and equipment and analysing the effects of delay. Whenever major changes are made in the schedule, the network is revised accordingly, and a new schedule is prepared. Thus, monitoring of program may require periodic updating of project and rescheduling to ensure completion of the project in time. Latest Finished Time (LFT) It is calculated by moving backward i.e. from last event to first event of the network diagram. Latest Start Time (LST) It is the latest possible time by which an activity can start. LST = LFT – Duration of that activity
  • 4. Earliest Start Time (EST) It is the earliest possible time by which an activity can start. Earliest Finished Time (EFT) It is the earliest time of an activity. FLOAT / SLACK It means spare time, a margin of extra time over and above its duration which a non-critical activity can consume without delaying the project. Float is the difference between the time available for completing an activity and the time necessary to complete the same. Total Float = LST – EST OR Total Float = LFT - EFT Free Float  If all the non critical activities start as early as possible the surplus time is the free flow. If an activity is delayed by the free flow period, the succeeding activity will not be delayed.
  • 5. Free Float = EST of tail event – EST of head event – Activity duration Independent Float  The use of independent float of an activity does not change the float in other activities. Independent Float = EST of tail event - LFT of head event - Activity duration (*Note: - Independent float, if it turns out to be negative, it is taken as zero.)
  • 6. NUMERICAL Activity Optimistic Time Most Expected Time Pessimistic Time Expected Variance (to) (tm) (tp) Time 1-2 4 8 12 8 1.78 2-3 1 4 7 4 1.00 2-4 8 12 16 12 1.78 3-5 3 5 7 5 0.44 4-5 0 0 0 0 0.00 4-6 3 6 9 6 1.00 5-7 3 6 9 6 1.00 5-8 4 6 8 6 0.44 7-9 4 8 12 8 1.78 8-9 2 5 8 5 1.00 9-10 4 10 16 10 4.00 6-10 4 6 8 6 0.44 Expected Time=[(to+4tm+tp)/6]2 Varience=[(tp-to)%6]2 Q.Present the activity in the form of a PERT network and determine- a.Critical path b.Earliest and latest expected time c.Probability of computing the project within schedule completion of 48 days.
  • 7. SOLUTION A.(i). 3 5 4 8 1 2 5 16 2 1 1 1 4 1 2 7 4 9 0 0 4 0 15 19 0 0 0 4 8 4 6 10 3 4 1 15 23 2 Critical Path=(1-2-4-5-7-9-10)
  • 8. (ii). 3 5 5 6 8 12 15 20 20 26 29 6 5 4 0 8 2 1 7 9 0 0 8 8 26 26 34 34 2 10 4 6 6 10 6 26 38 44 44 20 20
  • 9. Critical Path=(1-2-4-5-7-9-10) B. The earliest expected time [E(U1)]=0 E (U2)=0+8=8 E (U3)=8+4=12 E (U4)=12+8=20 E (U5)=(12+5,20+0)=20 E (U6)=20+6=26 E (U7)=26 E (U8)=20+6=26 E (U9)=34 E (U10)=34 Latest expected time are- E(L10)=44 E(L9)=34 E(L8)=29 E(L7)=20 E(L6)=38 E(L5)=20 E(L4)=20 E(L3)=15 E(L2)=8
  • 10. E(L1)=0 C. Expected Project Completion time 8+12+0+6+8=44 days Project variance=(∂T)2 =1.78+1.78+0+1+1.78+4=10.34 Varience=∂T=3.216 If due date of completion of the project is 48 days then=(48-44)/3.216=1.24 From the Standard normal table, probability of meeting the due date is 0.3925