SlideShare a Scribd company logo
1 of 65
Download to read offline
Resources
         Management System
         (RMS)
         UAE (Building and Infrastructure) Overtime Review



                             Park Rotana, Abu Dhabi

                             02 October 2011
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 1
Presentation
I.   RMS (Version 1) – Concept Design
                             Presenter: Emad Elshorbagy, CPS, PMP, PS, RMP

II. RMS (Version 1) - Live Demo
                             Presenter: Maritess Eguia, Ph.D.




           Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 2
Presentation

I.   RMS (Version 1) – Concept Design




           Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 3
What is RMS
‘R’ ‘M’ ‘S’ stands for Resource Management System

RMS is an innovative approach of managing the
mobilization and demobilization of resources
between projects and HR.

RMS includes a Software, User Manual and Procedures

The software is web-based and linked with ERP



         Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 4
Resource Life Cycle:


Future Resource (Forecast)




                                                                         Baseline
 Planned Mobilization Date

Planned Demobilization Date
                                                                         Forecast
 Forecast Mobilization Date

Forecast Demobilization Date



            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 5
Resource Life Cycle:


Future Resource (Forecast)




 Planned Mobilization Date

Planned Demobilization Date

 Forecast Mobilization Date

Forecast Demobilization Date



            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 6
Resource Life Cycle:


   Requested Resource




                                         Mobilization
                                          Request



 Planned Mobilization Date

Planned Demobilization Date

Requested Mobilization Date
                                                                        2 Months for Labour
Forecast Demobilization Date
                                                                        3 Months for Staff
                                                                        4 Months for Senior Staff


            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 7
Resource Life Cycle:


      Actual Resource




 Planned Mobilization Date

Planned Demobilization Date

  Actual Mobilization Date

Forecast Demobilization Date



            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 8
Resource Life Cycle:


      Actual Resource




 Planned Mobilization Date

Planned Demobilization Date

  Actual Mobilization Date

Forecast Demobilization Date
                                                                                    Extension Request


            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 9
Resource Life Cycle:
                                                                 Notification of
                                                                 Demobilization

      Actual Resource




 Planned Mobilization Date

Planned Demobilization Date

  Actual Mobilization Date

Forecast Demobilization Date



           Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 10
Resource Life Cycle:


  Demobilized Resource




 Planned Mobilization Date

Planned Demobilization Date

  Actual Mobilization Date

Actual Demobilization Date



           Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 11
HLG Resources Management System
Welcome admin Change Password                                                Logout
                   Project Details

                                                                                                       Please Select
 UAE
   Abu Dhabi
                                                                              Baseline
       Building
                                                                              Forecast
         275
                                                                              Mobilization
         276

         278                                                 Non-HLG          Actual
         279
                                                                              Extension
         280

         281                                                                  Demobilization
         HMR 828
                                                                              Reports




                   Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 12
HLG Resources Management System
Welcome admin Change Password                                                Logout
                   Project Details

                                                                                                       Please Select
 UAE
   Abu Dhabi
                                                                              Baseline
       Building
                                                                              Forecast
         275
                                                                              Mobilization
         276

         278                                                                  Actual
         279
                                                                              Extension
         280

         281                         Staff Allocation                         Demobilization
         HMR 828
                                     Mobilization & Demobilization            Reports
                                     Histogram
                                     Look-ahead




                   Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 13
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 14
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 15
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 16
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 17
250

             Steel Fixers                                                                              Site XYZ

                                                                                                                                        3000
200




                                                                                                                                        2250
150




                                                                                                                                        1500
100




                                                                                                                                         750
50




 0

      Sep    Oct   Nov   Dec   Jan   Feb   Mar   Apr   May   Jun   Jul   Aug   Sep   Oct   Nov   Dec   Jan     Feb   Mar   Apr   May   Jun


            Baseline                                     Actual                                              Forecast



                    Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 18
300

            Steel Fixers                                                               All Sites
250




200




150




100




50




 0
      Aug     Sep    Oct    Nov     Dec     Jan      Feb    Mar     Apr     May     Jun     Jul      Aug    Sep

        Baseline                                  Actual                                  Forecast



                Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 19
The System Objectives

• Automating the Mobilization & Demobilization process.

• Monitoring & Controlling the process against Budget (Baseline)

• Optimizing Resource usage.

• Assisting in Long Term and Strategic Planning

• Allowing for What-If Scenarios

• Assisting indentifying proposed staff for projects under tendering




            Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 20
Presentation

II. RMS (Version 1) – Live Demo




          Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 21
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 22
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 23
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 24
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 25
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 26
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 27
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 28
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 29
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 30
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 31
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 32
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 33
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 34
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 35
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 36
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 37
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 38
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 39
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 40
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 41
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 42
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 43
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 44
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 45
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 46
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 47
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 48
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 49
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 50
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 51
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 52
Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 53
Thank you.




Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 54
Objective

 To ensure that on-going projects are equipped with pre-agreed
    budgeted resources to meet timetables and milestones in
    accordance with the stated contractual obligations and in
    compliance with organizational policies.
 To keep a record of resources for both deployed and released against
    each budget item/resources to eventually assess availability of
    resources and accurately plan staff and labor resource
    requirements.
 To standardize the process of communicating reports electronically on
    manpower requisitions on the basis of site mobilization and
    demobilization plan and maintain a consolidated database of the
    overall manpower data inclusive of the project sites, business units
    and corporate offices.
 Note: This has reference to the Manpower Deployment on RMS


                Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 55
RMS- Key Features



                                                                                Baseline
                                                                                Forecast
                                                                                Mobilization
                                                                                Actual
                                                                                Demobilization
                                                                                Extension
                                                                                Report

                                                                          Page 12 – RMS User Guide




        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 56
The Baseline


                                                                      The Baseline Plan will
                                                                       be maintained as the
                                                                       baseline for all
                                                                       Updated (Working)
                                                                       Contract Schedules.
                                                                      This shall be
                                                                       developed to
                                                                       accurately reflect the
                                                                       Contract requirement
                                                                       for each specific
                                                                       project.

                                                                          Page 13 – RMS User Guide




        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 57
The Forecast
         Page 13 – RMS User Guide


                                                                      Forecast Resources
                                                                       are based from the
                                                                       Project Completion
                                                                       Plan of a fully-
                                                                       resourced Clause 14
                                                                       program, to generate
                                                                       the 2-months/8-weeks
                                                                       look ahead.
                                                                      The Forecast shall be
                                                                       aligned with the
                                                                       Target Schedule
                                                                       which is a realistic
                                                                       and achievable
                                                                       improvement against
                                                                       the Contract/Baseline
                                                                       Schedule.


        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 58
The Mobilization Notifications
                                                                       Project Resources
                                                                        mobilization is a function
                                                                        provided in the form of
                                                                        new mobilization
                                                                        notifications pre-
                                                                        determined through
                                                                        Resource Calendar Start
                                                                        and End dates, for
                                                                        scheduling, tracking and
                                                                        resource allocation.
                                                                       The pull-down menu of
                                                                        Job Family and Master
                                                                        Trade are resources
                                                                        dictionary built-in the
                                                                        RMS are mapped on
                                                                        ERP-HR Trades List.

                                                                          Page 17 – RMS User Guide




         Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 59
The Actual Resources
                                                                      Actual Resources
                                                                       screen shows the
                                                                       actual number of
                                                                       resources on board
                                                                       for each project.


                                                                      The actual resources
                                                                       can also be viewed
                                                                       through the search
                                                                       engine from project
                                                                       start date up to the
                                                                       specified cut-off date.

                                                                          Page 18 – RMS User Guide




        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 60
The Demobilization Notifications
                                                                      The Demobilization
                                                                       Notifications portrays
                                                                       the staff and labor
                                                                       release plan, to enable
                                                                       the Operations Team
                                                                       to extract the
                                                                       necessary manpower
                                                                       required from
                                                                       alternate HLG projects
                                                                       in order to
                                                                       complement the
                                                                       existing manpower at
                                                                       critical location(s) so
                                                                       as to restore
                                                                       efficiency and
                                                                       increase productivity.
                                                                           Page 20 – RMS User Guide


         Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 61
The Extension Request
                                                                 The Extension Request
                                                                  feature provides an
                                                                  option to extend
                                                                  resources beyond the
                                                                  prescribed
                                                                  demobilization dates.
                                                                 Upon confirmation the
                                                                  selected resources shall
                                                                  be removed from the
                                                                  released list of the
                                                                  Demobilization Screen
                                                                  with the corresponding
                                                                  extension specified on
                                                                  the Calendar Dates.

                                                                       Page 24 – RMS User Guide




        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 62
The Reports
       Page 28 – RMS User Guide                               The Reports are classified as
                                                               Staff Allocation Report,
                                                               Mobilization & Demobilization
                                                               Report, Look Ahead Report
                                                               and Reports in Histograms.
                                                              Each report type can be
                                                               generated with the filters
                                                               provided such as the Resource
                                                               Type (All, HLG, Non-HLG),
                                                               Category (All, Staff, Labor), in
                                                               accordance with the Job
                                                               Family, Master Trade,
                                                               Employee Code, Employee
                                                               Name, Start Date, Roles etc.
                                                              Report Titles can also be
                                                               customized for each use.




         Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 63
Pilot Project
                               HLG 280
                        ARZANAH MEDICAL CENTRE




       Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 64
RMS Version 2
Phase II
                         Additional Features of the RMS


                                       Budget
                                       Actual Cost
                                       Budget At Completion
                                       Cost At Completion
                                       Estimate At Completion
                                       Contract Charges
                                       Variance




        Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 65

More Related Content

Featured

Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
 
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
 

Proposed Resources Management System

  • 1. Resources Management System (RMS) UAE (Building and Infrastructure) Overtime Review Park Rotana, Abu Dhabi 02 October 2011 Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 1
  • 2. Presentation I. RMS (Version 1) – Concept Design Presenter: Emad Elshorbagy, CPS, PMP, PS, RMP II. RMS (Version 1) - Live Demo Presenter: Maritess Eguia, Ph.D. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 2
  • 3. Presentation I. RMS (Version 1) – Concept Design Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 3
  • 4. What is RMS ‘R’ ‘M’ ‘S’ stands for Resource Management System RMS is an innovative approach of managing the mobilization and demobilization of resources between projects and HR. RMS includes a Software, User Manual and Procedures The software is web-based and linked with ERP Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 4
  • 5. Resource Life Cycle: Future Resource (Forecast) Baseline Planned Mobilization Date Planned Demobilization Date Forecast Forecast Mobilization Date Forecast Demobilization Date Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 5
  • 6. Resource Life Cycle: Future Resource (Forecast) Planned Mobilization Date Planned Demobilization Date Forecast Mobilization Date Forecast Demobilization Date Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 6
  • 7. Resource Life Cycle: Requested Resource Mobilization Request Planned Mobilization Date Planned Demobilization Date Requested Mobilization Date 2 Months for Labour Forecast Demobilization Date 3 Months for Staff 4 Months for Senior Staff Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 7
  • 8. Resource Life Cycle: Actual Resource Planned Mobilization Date Planned Demobilization Date Actual Mobilization Date Forecast Demobilization Date Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 8
  • 9. Resource Life Cycle: Actual Resource Planned Mobilization Date Planned Demobilization Date Actual Mobilization Date Forecast Demobilization Date Extension Request Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 9
  • 10. Resource Life Cycle: Notification of Demobilization Actual Resource Planned Mobilization Date Planned Demobilization Date Actual Mobilization Date Forecast Demobilization Date Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 10
  • 11. Resource Life Cycle: Demobilized Resource Planned Mobilization Date Planned Demobilization Date Actual Mobilization Date Actual Demobilization Date Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 11
  • 12. HLG Resources Management System Welcome admin Change Password Logout Project Details Please Select UAE Abu Dhabi Baseline Building Forecast 275 Mobilization 276 278 Non-HLG Actual 279 Extension 280 281 Demobilization HMR 828 Reports Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 12
  • 13. HLG Resources Management System Welcome admin Change Password Logout Project Details Please Select UAE Abu Dhabi Baseline Building Forecast 275 Mobilization 276 278 Actual 279 Extension 280 281 Staff Allocation Demobilization HMR 828 Mobilization & Demobilization Reports Histogram Look-ahead Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 13
  • 14. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 14
  • 15. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 15
  • 16. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 16
  • 17. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 17
  • 18. 250 Steel Fixers Site XYZ 3000 200 2250 150 1500 100 750 50 0 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Baseline Actual Forecast Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 18
  • 19. 300 Steel Fixers All Sites 250 200 150 100 50 0 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Baseline Actual Forecast Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 19
  • 20. The System Objectives • Automating the Mobilization & Demobilization process. • Monitoring & Controlling the process against Budget (Baseline) • Optimizing Resource usage. • Assisting in Long Term and Strategic Planning • Allowing for What-If Scenarios • Assisting indentifying proposed staff for projects under tendering Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 20
  • 21. Presentation II. RMS (Version 1) – Live Demo Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 21
  • 22. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 22
  • 23. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 23
  • 24. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 24
  • 25. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 25
  • 26. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 26
  • 27. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 27
  • 28. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 28
  • 29. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 29
  • 30. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 30
  • 31. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 31
  • 32. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 32
  • 33. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 33
  • 34. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 34
  • 35. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 35
  • 36. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 36
  • 37. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 37
  • 38. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 38
  • 39. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 39
  • 40. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 40
  • 41. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 41
  • 42. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 42
  • 43. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 43
  • 44. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 44
  • 45. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 45
  • 46. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 46
  • 47. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 47
  • 48. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 48
  • 49. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 49
  • 50. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 50
  • 51. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 51
  • 52. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 52
  • 53. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 53
  • 54. Thank you. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 54
  • 55. Objective To ensure that on-going projects are equipped with pre-agreed budgeted resources to meet timetables and milestones in accordance with the stated contractual obligations and in compliance with organizational policies. To keep a record of resources for both deployed and released against each budget item/resources to eventually assess availability of resources and accurately plan staff and labor resource requirements. To standardize the process of communicating reports electronically on manpower requisitions on the basis of site mobilization and demobilization plan and maintain a consolidated database of the overall manpower data inclusive of the project sites, business units and corporate offices. Note: This has reference to the Manpower Deployment on RMS Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 55
  • 56. RMS- Key Features  Baseline  Forecast  Mobilization  Actual  Demobilization  Extension  Report Page 12 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 56
  • 57. The Baseline  The Baseline Plan will be maintained as the baseline for all Updated (Working) Contract Schedules.  This shall be developed to accurately reflect the Contract requirement for each specific project. Page 13 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 57
  • 58. The Forecast Page 13 – RMS User Guide  Forecast Resources are based from the Project Completion Plan of a fully- resourced Clause 14 program, to generate the 2-months/8-weeks look ahead.  The Forecast shall be aligned with the Target Schedule which is a realistic and achievable improvement against the Contract/Baseline Schedule. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 58
  • 59. The Mobilization Notifications  Project Resources mobilization is a function provided in the form of new mobilization notifications pre- determined through Resource Calendar Start and End dates, for scheduling, tracking and resource allocation.  The pull-down menu of Job Family and Master Trade are resources dictionary built-in the RMS are mapped on ERP-HR Trades List. Page 17 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 59
  • 60. The Actual Resources  Actual Resources screen shows the actual number of resources on board for each project.  The actual resources can also be viewed through the search engine from project start date up to the specified cut-off date. Page 18 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 60
  • 61. The Demobilization Notifications  The Demobilization Notifications portrays the staff and labor release plan, to enable the Operations Team to extract the necessary manpower required from alternate HLG projects in order to complement the existing manpower at critical location(s) so as to restore efficiency and increase productivity. Page 20 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 61
  • 62. The Extension Request  The Extension Request feature provides an option to extend resources beyond the prescribed demobilization dates.  Upon confirmation the selected resources shall be removed from the released list of the Demobilization Screen with the corresponding extension specified on the Calendar Dates. Page 24 – RMS User Guide Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 62
  • 63. The Reports Page 28 – RMS User Guide  The Reports are classified as Staff Allocation Report, Mobilization & Demobilization Report, Look Ahead Report and Reports in Histograms.  Each report type can be generated with the filters provided such as the Resource Type (All, HLG, Non-HLG), Category (All, Staff, Labor), in accordance with the Job Family, Master Trade, Employee Code, Employee Name, Start Date, Roles etc.  Report Titles can also be customized for each use. Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 63
  • 64. Pilot Project HLG 280 ARZANAH MEDICAL CENTRE Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 64
  • 65. RMS Version 2 Phase II Additional Features of the RMS  Budget  Actual Cost  Budget At Completion  Cost At Completion  Estimate At Completion  Contract Charges  Variance Resources Management System (RMS) – UAE (Building and Infrastructure) Overtime Review| 02 October 2011 | 65