Why projects don’t fulfill
deadlines?
And how we can change this!

1	
  /	
  10	
  
What could happens?
•  If the average to get to your job is one hour and you
always leave your house just one hour before?
•  If the average fuel consumption from your car is 10
km / liter and your job is 40 km away from your
house, then you supplies it with exactly 4 liters?
1.  For these questions there are just one answer:
Sometimes you‘ll reach, sometimes you‘ll delay!

2.  But which is the probability of you‘ll reach deadline?

2	
  /	
  10	
  
You‘ll can be victim of the Bias of
Convergence.
•  Average means that there are higher values ​and
also lower values​​, and maybe not even there the
average value!
–  So, sometimes it took more than one hour to arrive at job.

•  Mathematically we would consider that there is a
50% chance to not be late.
•  But this isn‘t the correct answer for the second
question.
3	
  /	
  10	
  

3	
  
The right answer is 25%!

–	
  Delays

>	
  real	
  =	
  

0	
  

1	
  

> real =

Estimated
productivity

<	
  real	
  =	
  

0	
  

Delay

Delay

< real =1

Estimated duration

1	
  

Delay

Reach
Deadline

are mathematically expected!

– Deviations from targets are due to Parkinson's
Law.

4	
  /	
  10	
  

4	
  
And what does this have to do with
projects?
• 
• 
• 
• 

All!
There is nothing that doesn‘t have variations.
I gave a name to this: “Bias of Convergence”.
Even trying our best to meet the deadlines, we
almost always fail.
•  If you're thinking that no one ever goes to work
investing in the mean time and with minimum
fuel, maybe you're right, but in projects it
works so.
5	
  /	
  10	
  

5	
  
How are we trying to change that, and
why we're not succeeding?
•  We are trying of two ways:
–  We add time clearances.

–  We add clearance of resources.

•  Then, what is wrong?
–  The targets are the upper limit to be reached.
–  And we planned them as if they were the exact points to
be reached.
–  But we shouldn‘t do that, because, in the real life, points
don‘t exist.

•  And we know something about target‘s
centers…
6	
  /	
  10	
  

6	
  
Sometimes we‘ll reach, sometimes
won‘t!
•  You can think: we had increased clearances of time and
resources.
•  But if you focus just on the points to be reached, time
and resources keep being affected by variability.
•  Then you‘ll use all time and all resources and..
•  Sometimes you‘ll reach, sometimes won‘t.
•  This is bias of convergence.
7	
  /	
  10	
  

7	
  
How we can change this?
•  Clearances should be used to compensate
deviations, not to increase time or resources.
•  We must planning to reach goals earlier, then we will
have a buffer to use if necessary.
•  We should plan to meet all goals with clearance, so
when something don‘t occur, we will have some
additional job done to compensate.
•  We should consider the clearances just to put the
project back within its deadline.
8	
  /	
  10	
  

8	
  
Yep, the solution is counterintuitive.
•  You must be thinking that adding clearances will
derail the project.
•  I don‘t think so!
•  About 70% of projects end up late.
•  You know, this is better than our initial probability!
•  That‘s what can derail a project.
9	
  /	
  10	
  

9	
  
The source.
•  These slides are based on my two books:
–  Gestão por Modelagem Vetorial: Os segredos da curva S
(Management by Vectorial Modeling: The S curve secrets).

–  Viés de Convergência: Desvendando a causa raiz dos
atrasos (Bias of Convergence: Unraveling the root cause of the
delays).
Both in portuguese.
•  To contact: roberto@looplearn.com

10	
  /	
  10	
  

10	
  

Why projects do not fulfill deadlines? and how we can change this!

  • 1.
    Why projects don’tfulfill deadlines? And how we can change this! 1  /  10  
  • 2.
    What could happens? • If the average to get to your job is one hour and you always leave your house just one hour before? •  If the average fuel consumption from your car is 10 km / liter and your job is 40 km away from your house, then you supplies it with exactly 4 liters? 1.  For these questions there are just one answer: Sometimes you‘ll reach, sometimes you‘ll delay! 2.  But which is the probability of you‘ll reach deadline? 2  /  10  
  • 3.
    You‘ll can bevictim of the Bias of Convergence. •  Average means that there are higher values ​and also lower values​​, and maybe not even there the average value! –  So, sometimes it took more than one hour to arrive at job. •  Mathematically we would consider that there is a 50% chance to not be late. •  But this isn‘t the correct answer for the second question. 3  /  10   3  
  • 4.
    The right answeris 25%! –  Delays >  real  =   0   1   > real = Estimated productivity <  real  =   0   Delay Delay < real =1 Estimated duration 1   Delay Reach Deadline are mathematically expected! – Deviations from targets are due to Parkinson's Law. 4  /  10   4  
  • 5.
    And what doesthis have to do with projects? •  •  •  •  All! There is nothing that doesn‘t have variations. I gave a name to this: “Bias of Convergence”. Even trying our best to meet the deadlines, we almost always fail. •  If you're thinking that no one ever goes to work investing in the mean time and with minimum fuel, maybe you're right, but in projects it works so. 5  /  10   5  
  • 6.
    How are wetrying to change that, and why we're not succeeding? •  We are trying of two ways: –  We add time clearances. –  We add clearance of resources. •  Then, what is wrong? –  The targets are the upper limit to be reached. –  And we planned them as if they were the exact points to be reached. –  But we shouldn‘t do that, because, in the real life, points don‘t exist. •  And we know something about target‘s centers… 6  /  10   6  
  • 7.
    Sometimes we‘ll reach,sometimes won‘t! •  You can think: we had increased clearances of time and resources. •  But if you focus just on the points to be reached, time and resources keep being affected by variability. •  Then you‘ll use all time and all resources and.. •  Sometimes you‘ll reach, sometimes won‘t. •  This is bias of convergence. 7  /  10   7  
  • 8.
    How we canchange this? •  Clearances should be used to compensate deviations, not to increase time or resources. •  We must planning to reach goals earlier, then we will have a buffer to use if necessary. •  We should plan to meet all goals with clearance, so when something don‘t occur, we will have some additional job done to compensate. •  We should consider the clearances just to put the project back within its deadline. 8  /  10   8  
  • 9.
    Yep, the solutionis counterintuitive. •  You must be thinking that adding clearances will derail the project. •  I don‘t think so! •  About 70% of projects end up late. •  You know, this is better than our initial probability! •  That‘s what can derail a project. 9  /  10   9  
  • 10.
    The source. •  Theseslides are based on my two books: –  Gestão por Modelagem Vetorial: Os segredos da curva S (Management by Vectorial Modeling: The S curve secrets). –  Viés de Convergência: Desvendando a causa raiz dos atrasos (Bias of Convergence: Unraveling the root cause of the delays). Both in portuguese. •  To contact: roberto@looplearn.com 10  /  10   10