The project status document provides an update on the R+L Global Logistics Website Consolidation project. It reports that the marketing effort was considered and the project will continue moving forward, with the Bucket 1 transition date moved to September 12 assuming timely approvals. Stakeholder meetings were completed on July 28. Next steps include gathering requirements for chat and tracking and making modifications to internal pages in iRise. The project is 85% complete and on schedule.