SlideShare a Scribd company logo
1 of 2
Download to read offline
VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know:
After Prime Minister Nguyen Xuan Phuc’s notification No. 402/TB-VPCP on 22 November 2019 on FiT
2 and auction scheme, we would like to update some key policy progress as belows:
1. Most recent draft of MOIT on FiT 2
The draft only allows only a tiny proportion of already-approved solar projects may qualify for FiT
following MOIT document dated 22 November suggested that FiT 2 will only be available for projects with
signed PPAs that are “under construction” and provided they reach COD by end of 2020. The MOIT
document seeks to define what “under construction” means for this purpose. It takes a narrow view,
referring to Article 6.1.b of Decree 59/2015/ND-CP dated 18 June 2015 re management of construction
projects to suggest that for a project to be considered “under construction” the project must have completed
appraisal of detailed / technical construction designs prior to 22 November 2019. According to the MOIT’s
data contained in the draft, it appears that only 4 out of 23 projects having already-signed PPAs but not yet
reached COD would meet this criteria (some sources indicate there may be in excess of 30 such projects).
2. Document no.9608/BCT-DL on suspension of the approvals for solar power projects
Vietnam’s Ministry of Industry and Trade has issued OL 9608/BCT-DL, in which it urges provinces and
directly under the Central Government and the Electricity of Vietnam, on stopping proposals and
agreements for solar power projects (SPPs) under Feed in Tariff (FIT) mechanism. The ministry said that
only projects with signed FIT contracts that are scheduled for completion scheduled by the end of this year
will be able to secure subsidies, while all of the remaining projects will have to compete again in future
auctions. The Ministry of Industry and Trade is now working with ministries and agencies to complete the
draft of a new auction mechanism.
3. Respond from EVN to MOIT
EVN has sent letter no. 6774/EVN-TTD dated 12/12/2019 to MOIT to suggested FiT 2 to be applied to the
projects which have construction contracts before 22/11/2019 (of any part of the project) and have evidence
on the implementation of the project. In addition, EVN suggested that to the grid-connected projects under
COD before 1/7/2019, the remaining part which has not put under COD is entitled to FiT2.
4. Temporary accounting of FIT price for COD projects after 30/6/2019.
EVN has issued letter no.6909/EVN-TCKT, which instructs businesses to temporarily account FIT price of
1.916 VND/kWh (VAT excluded), unless any other guidance is issued.
*************
Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have
any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of
Duane Morris Vietnam LLC.
VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know:

More Related Content

What's hot

What's hot (9)

OECD, 7th Meeting on Public-Private Partnerships - Gisela LEHMER-KERKLOH
OECD, 7th Meeting on Public-Private Partnerships - Gisela LEHMER-KERKLOHOECD, 7th Meeting on Public-Private Partnerships - Gisela LEHMER-KERKLOH
OECD, 7th Meeting on Public-Private Partnerships - Gisela LEHMER-KERKLOH
 
Vietnam - Power Development Plan 8 - Finalizing the plan - what you must know:
Vietnam - Power Development Plan 8 - Finalizing the plan - what you must know:Vietnam - Power Development Plan 8 - Finalizing the plan - what you must know:
Vietnam - Power Development Plan 8 - Finalizing the plan - what you must know:
 
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
145-FUNDAMENTAL RULES – Amendment to FR 22-B – Orders – Issued
 
Simplified version IR Act comparision-23.08.2021
Simplified version IR Act comparision-23.08.2021Simplified version IR Act comparision-23.08.2021
Simplified version IR Act comparision-23.08.2021
 
Europese Commissie wil 2 miljard euro extra voor Turkije
Europese Commissie wil 2 miljard euro extra voor TurkijeEuropese Commissie wil 2 miljard euro extra voor Turkije
Europese Commissie wil 2 miljard euro extra voor Turkije
 
Things you should know about RERA Act by Hp Tripathi
Things you should know about RERA Act by Hp TripathiThings you should know about RERA Act by Hp Tripathi
Things you should know about RERA Act by Hp Tripathi
 
Income from house property - DR. MINAL BHANDARI
Income from house property - DR. MINAL BHANDARIIncome from house property - DR. MINAL BHANDARI
Income from house property - DR. MINAL BHANDARI
 
No penalty for non converted
No penalty for non convertedNo penalty for non converted
No penalty for non converted
 
Income from house property
Income from house propertyIncome from house property
Income from house property
 

Similar to VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know:

Similar to VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know: (20)

VIETNAM – SOLAR POWER – LATEST NEWS ON FEED IN TARIFF AND FIT-ELIGIBILITY – W...
VIETNAM – SOLAR POWER – LATEST NEWS ON FEED IN TARIFF AND FIT-ELIGIBILITY – W...VIETNAM – SOLAR POWER – LATEST NEWS ON FEED IN TARIFF AND FIT-ELIGIBILITY – W...
VIETNAM – SOLAR POWER – LATEST NEWS ON FEED IN TARIFF AND FIT-ELIGIBILITY – W...
 
VIETNAM – SOLAR POWER - FINAL DRAFT DECISION ON SOLAR POWER FEED-IN-TARIFFS (...
VIETNAM – SOLAR POWER - FINAL DRAFT DECISION ON SOLAR POWER FEED-IN-TARIFFS (...VIETNAM – SOLAR POWER - FINAL DRAFT DECISION ON SOLAR POWER FEED-IN-TARIFFS (...
VIETNAM – SOLAR POWER - FINAL DRAFT DECISION ON SOLAR POWER FEED-IN-TARIFFS (...
 
VIETNAM – MOIT IS REVIEWING NEW FEED IN TARIFFS (FiTs) FOR WIND POWER PROJECTS
VIETNAM – MOIT IS REVIEWING NEW FEED IN TARIFFS (FiTs) FOR WIND POWER PROJECTSVIETNAM – MOIT IS REVIEWING NEW FEED IN TARIFFS (FiTs) FOR WIND POWER PROJECTS
VIETNAM – MOIT IS REVIEWING NEW FEED IN TARIFFS (FiTs) FOR WIND POWER PROJECTS
 
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
 
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
VIETNAM - SOLAR POWER - NEW FEED IN TARIFFS - NEW GUIDANCE FOR SOLAR ENERGY D...
 
Asia Counsel Insights July 2022.pdf
Asia Counsel Insights July 2022.pdfAsia Counsel Insights July 2022.pdf
Asia Counsel Insights July 2022.pdf
 
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
 
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
VIETNAM - WIND ENERGY BREAKING NEWS - FEED IN TARIFF COULD BE EXTENDED - WHAT...
 
VIETNAM – MOIT PROPOSES EXTENSION OF CURRENT FiT RATE FOR WIND POWER PROJECTS
VIETNAM – MOIT PROPOSES EXTENSION OF CURRENT FiT RATE  FOR WIND POWER PROJECTSVIETNAM – MOIT PROPOSES EXTENSION OF CURRENT FiT RATE  FOR WIND POWER PROJECTS
VIETNAM – MOIT PROPOSES EXTENSION OF CURRENT FiT RATE FOR WIND POWER PROJECTS
 
VIETNAM – MOIT PROPOSES NEW FIT RATE FOR WIND POWER PROJECTS
VIETNAM – MOIT PROPOSES NEW FIT RATE FOR WIND POWER PROJECTSVIETNAM – MOIT PROPOSES NEW FIT RATE FOR WIND POWER PROJECTS
VIETNAM – MOIT PROPOSES NEW FIT RATE FOR WIND POWER PROJECTS
 
VIETNAM – SOLAR POWER AUCTION SYSTEM: WHAT YOU MUST KNOW
VIETNAM – SOLAR POWER AUCTION SYSTEM: WHAT YOU MUST KNOWVIETNAM – SOLAR POWER AUCTION SYSTEM: WHAT YOU MUST KNOW
VIETNAM – SOLAR POWER AUCTION SYSTEM: WHAT YOU MUST KNOW
 
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8VIETNAM –  LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
VIETNAM – LATEST UPDATE FROM MOIT REGARDING POWER MASTER PLAN 8
 
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTSVIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
VIETNAM – SOLAR POWER SECTOR NEW MODEL PPA FOR ROOFTOP SOLAR POWER PROJECTS
 
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
Lawyer in Vietnam Dr. Oliver Massmann - VIETNAM - SOLAR POWER - MOIT's PROPOS...
 
VIETNAM - SOLAR POWER FEED IN TARIFFS BREAKING NEWS - FINAL DRAFT DECISION ON...
VIETNAM - SOLAR POWER FEED IN TARIFFS BREAKING NEWS - FINAL DRAFT DECISION ON...VIETNAM - SOLAR POWER FEED IN TARIFFS BREAKING NEWS - FINAL DRAFT DECISION ON...
VIETNAM - SOLAR POWER FEED IN TARIFFS BREAKING NEWS - FINAL DRAFT DECISION ON...
 
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
 
VIETNAM – RENEWABLE ENERGY – NEW FEED IN TARIFFS FOR WIND ENERGY - AMAZING DE...
VIETNAM – RENEWABLE ENERGY – NEW FEED IN TARIFFS FOR WIND ENERGY - AMAZING DE...VIETNAM – RENEWABLE ENERGY – NEW FEED IN TARIFFS FOR WIND ENERGY - AMAZING DE...
VIETNAM – RENEWABLE ENERGY – NEW FEED IN TARIFFS FOR WIND ENERGY - AMAZING DE...
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
VIETNAM – THE GOVERNMENT REQUESTS MOIT TO CLARIFY POINTS ON DRAFT PDP 8 BEFO...
 VIETNAM – THE GOVERNMENT REQUESTS MOIT TO CLARIFY POINTS ON DRAFT PDP 8 BEFO... VIETNAM – THE GOVERNMENT REQUESTS MOIT TO CLARIFY POINTS ON DRAFT PDP 8 BEFO...
VIETNAM – THE GOVERNMENT REQUESTS MOIT TO CLARIFY POINTS ON DRAFT PDP 8 BEFO...
 
VIETNAM - New rules on Electricity Pricing and Power Purchase Agreements fro...
VIETNAM - New rules on Electricity Pricing  and Power Purchase Agreements fro...VIETNAM - New rules on Electricity Pricing  and Power Purchase Agreements fro...
VIETNAM - New rules on Electricity Pricing and Power Purchase Agreements fro...
 

More from Dr. Oliver Massmann

More from Dr. Oliver Massmann (20)

YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
YOU ARE WARMLY INVITED - Solar & Storage Live Vietnam 2024
 
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
 
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
 

Recently uploaded

一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
doypbe
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
acyefsa
 
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
acyefsa
 
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
ZurliaSoop
 
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
mefyqyn
 
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
afukemk
 
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
mefyqyn
 
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
mefyqyn
 

Recently uploaded (20)

HOW LAW FIRMS CAN SUPPORT MILITARY DIVORCE CASES
HOW LAW FIRMS CAN SUPPORT MILITARY DIVORCE CASESHOW LAW FIRMS CAN SUPPORT MILITARY DIVORCE CASES
HOW LAW FIRMS CAN SUPPORT MILITARY DIVORCE CASES
 
Asif_Sultan_Syeda_vs_UT_of_J_K.pdf op[ke[k
Asif_Sultan_Syeda_vs_UT_of_J_K.pdf op[ke[kAsif_Sultan_Syeda_vs_UT_of_J_K.pdf op[ke[k
Asif_Sultan_Syeda_vs_UT_of_J_K.pdf op[ke[k
 
一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
一比一原版(UC Berkeley毕业证书)加利福尼亚大学伯克利分校毕业证原件一模一样
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
 
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
官方认证新加坡国立大学毕业证(nus毕业证)成绩单电子版原版一模一样
 
Dabholkar-matter-Judgement-1.pdfrefp;sdPp;
Dabholkar-matter-Judgement-1.pdfrefp;sdPp;Dabholkar-matter-Judgement-1.pdfrefp;sdPp;
Dabholkar-matter-Judgement-1.pdfrefp;sdPp;
 
File Taxes Online Simple Steps for Efficient Filing.pdf
File Taxes Online Simple Steps for Efficient Filing.pdfFile Taxes Online Simple Steps for Efficient Filing.pdf
File Taxes Online Simple Steps for Efficient Filing.pdf
 
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
 
How to Protect Your Children During a Divorce?
How to Protect Your Children During a Divorce?How to Protect Your Children During a Divorce?
How to Protect Your Children During a Divorce?
 
2024 Managing Labor + Employee Relations Seminar
2024 Managing Labor + Employee Relations Seminar2024 Managing Labor + Employee Relations Seminar
2024 Managing Labor + Employee Relations Seminar
 
From Scratch to Strong: Introduction to Drafting of Criminal Cases and Applic...
From Scratch to Strong: Introduction to Drafting of Criminal Cases and Applic...From Scratch to Strong: Introduction to Drafting of Criminal Cases and Applic...
From Scratch to Strong: Introduction to Drafting of Criminal Cases and Applic...
 
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
一比一原版(TUOS毕业证书)谢菲尔德大学毕业证成绩单原件一模一样
 
Embed-3-2.pdfkp[k[odk[odk[d[ok[d[pkdkdkl
Embed-3-2.pdfkp[k[odk[odk[d[ok[d[pkdkdklEmbed-3-2.pdfkp[k[odk[odk[d[ok[d[pkdkdkl
Embed-3-2.pdfkp[k[odk[odk[d[ok[d[pkdkdkl
 
Mischief Rule of Interpretation of statutes
Mischief Rule of Interpretation of statutesMischief Rule of Interpretation of statutes
Mischief Rule of Interpretation of statutes
 
Comprehensive Guide on Drafting Directors' Report and its ROC Compliances und...
Comprehensive Guide on Drafting Directors' Report and its ROC Compliances und...Comprehensive Guide on Drafting Directors' Report and its ROC Compliances und...
Comprehensive Guide on Drafting Directors' Report and its ROC Compliances und...
 
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
一比一原版美国加州大学戴维斯分校毕业证(ucd毕业证书)学位证书仿制
 
Trending Topics in ITC Litigation with Knobbe Martens
Trending Topics in ITC Litigation with Knobbe MartensTrending Topics in ITC Litigation with Knobbe Martens
Trending Topics in ITC Litigation with Knobbe Martens
 
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
一比一原版(UOL毕业证书)利物浦大学毕业证成绩单原件一模一样
 
Respondent Moot Memorial including Charges and Argument Advanced.docx
Respondent Moot Memorial including Charges and Argument Advanced.docxRespondent Moot Memorial including Charges and Argument Advanced.docx
Respondent Moot Memorial including Charges and Argument Advanced.docx
 
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
一比一原版(UBC毕业证书)不列颠哥伦比亚大学毕业证成绩单原件一模一样
 

VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know:

  • 1. VIETNAM - SOLAR POWER - KEY POLICY NEWS - What you must know: After Prime Minister Nguyen Xuan Phuc’s notification No. 402/TB-VPCP on 22 November 2019 on FiT 2 and auction scheme, we would like to update some key policy progress as belows: 1. Most recent draft of MOIT on FiT 2 The draft only allows only a tiny proportion of already-approved solar projects may qualify for FiT following MOIT document dated 22 November suggested that FiT 2 will only be available for projects with signed PPAs that are “under construction” and provided they reach COD by end of 2020. The MOIT document seeks to define what “under construction” means for this purpose. It takes a narrow view, referring to Article 6.1.b of Decree 59/2015/ND-CP dated 18 June 2015 re management of construction projects to suggest that for a project to be considered “under construction” the project must have completed appraisal of detailed / technical construction designs prior to 22 November 2019. According to the MOIT’s data contained in the draft, it appears that only 4 out of 23 projects having already-signed PPAs but not yet reached COD would meet this criteria (some sources indicate there may be in excess of 30 such projects). 2. Document no.9608/BCT-DL on suspension of the approvals for solar power projects Vietnam’s Ministry of Industry and Trade has issued OL 9608/BCT-DL, in which it urges provinces and directly under the Central Government and the Electricity of Vietnam, on stopping proposals and agreements for solar power projects (SPPs) under Feed in Tariff (FIT) mechanism. The ministry said that only projects with signed FIT contracts that are scheduled for completion scheduled by the end of this year will be able to secure subsidies, while all of the remaining projects will have to compete again in future auctions. The Ministry of Industry and Trade is now working with ministries and agencies to complete the draft of a new auction mechanism. 3. Respond from EVN to MOIT EVN has sent letter no. 6774/EVN-TTD dated 12/12/2019 to MOIT to suggested FiT 2 to be applied to the projects which have construction contracts before 22/11/2019 (of any part of the project) and have evidence on the implementation of the project. In addition, EVN suggested that to the grid-connected projects under COD before 1/7/2019, the remaining part which has not put under COD is entitled to FiT2. 4. Temporary accounting of FIT price for COD projects after 30/6/2019. EVN has issued letter no.6909/EVN-TCKT, which instructs businesses to temporarily account FIT price of 1.916 VND/kWh (VAT excluded), unless any other guidance is issued. ************* Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.